15
PRESENTED BY: VASANTH BHAT, SINGAPORE REFINING CO. PTE. LTD. JIM DEMETRIOU, CHEVRON ENERGY TECHNOLOGY CO. DRY GAS SEAL FAILURES IN A RECYCLE GAS CENTRIFUGAL COMPRESSOR, CAUSES & REMEDIAL ACTIONS

Case Study T14: Dry Gas Seal Failures in a Recycle Gas

  • Upload
    others

  • View
    10

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Case Study T14: Dry Gas Seal Failures in a Recycle Gas

PRESENTED BY: VASANTH BHAT, SINGAPORE REFINING CO. PTE. LTD.

JIM DEMETRIOU, CHEVRON ENERGY TECHNOLOGY CO.

DRY GAS SEAL FAILURES IN A RECYCLE GAS CENTRIFUGAL COMPRESSOR,

CAUSES & REMEDIAL ACTIONS

Page 2: Case Study T14: Dry Gas Seal Failures in a Recycle Gas

Presenters Vasanth Bhat is a Reliability Manager at Singapore Refining Company ( A joint venture refinery between Chevron & Petro China ). During his last 6 years with SRC, his main role has been support all technical and asset management issues with regards to rotating machinery in the refinery. Prior to this, Mr.Vasanth has over 19 years of experience in various roles as consultant , Sales , Reliability & Maintenance engineer in organizations in India , Middle east and Singapore. Mr. Vasanth has a B.E. degree (Mechanical Engineering, 1989) from Manipal Institute of technology – India and is a certified Category IV Vibration specialist by Vibration Institute USA .

Jim Demetriou is a Consulting Engineer with Chevron Energy Technology Company in Richmond, California. During his 14 years with Chevron, he has provided machinery technical support for refining, chemicals and upstream business units including specification, selection, operation, root cause analysis and optimization of machinery systems. Prior to this, Mr. Demetriou was a machinery engineer with Exxon for 20 years, including assignments in corporate engineering in New Jersey and refining assignments in Texas and California. Mr. Demetriou has a B.E. degree (Mechanical Engineering, 1980) from Stevens Institute of Technology and is a registered Professional Engineer in the state of California. He is presently task force vice-chair on API 692 (Dry Gas Seal Systems) and on the API SOME steering committee.

Page 3: Case Study T14: Dry Gas Seal Failures in a Recycle Gas

Contents • Introduction • Machine & System Details • First Failure • Cause of First Failure • Second Failure • Cause of Second Failure • Solutions • Lessons Learned

Page 4: Case Study T14: Dry Gas Seal Failures in a Recycle Gas

Introduction The recycle gas train is part of the Hydro-desulphurization Plant main reactor loop. The steam turbine driven, single section barrel-type centrifugal compressor uses a dry gas seal system.

Compressor was commissioned in 1995 and had no failures prior to 2011.

LC

FC

FLARE

FG

FC

LC

PC

LC

7204-C

M 7204-J/JA

M

7202-F

7202-C

TC

7203-C

PC

TC

FLARE

FG7209-F

7201-B

7201-D

FC

T7205-J

MP STEAM

TO 7202-E

FLARE

7212-F

FC

PC

M

SR

-C

7206-JA/JB/JC(2ND STAGE)

FW

PC

LC

MP STEAM ATMOS

SR

7201-L

7205-F

LC

7204-F

7203-F

LSS

FC

7201-E FC

M

ANTIFOAMER

7211-J

#1

#16

7201-C

PC

LC

LC

FW

7214-F

FC

TC

SR

TC

TCFC

340354

329315

299283

293291

222223

240240

133134

160160

137137

4343

55.8

140140

9.2

175177

4848

128128

4343

58

Page 5: Case Study T14: Dry Gas Seal Failures in a Recycle Gas

Machine Details • 8 stage compressor • ~11,000 rpm • Ps = 50 barg (725 psig) • Pd = 80 barg (1160 psig) • Tandem arrangement dry gas

seals • External seal gas from

Hydrogen Make-up compressors (lubricated recips) as primary source, with the compressor discharge as back up in case of Make-up compressor trip.

Page 6: Case Study T14: Dry Gas Seal Failures in a Recycle Gas

First Failure

• Compressor was started post turnaround.

• No compressor work was done during turnaround.

• After about 13 hours of running the compressor tripped on high primary vent pressure on the suction-side seal.

Page 7: Case Study T14: Dry Gas Seal Failures in a Recycle Gas

Causes of Failure

• Seal system found heavily contaminated with water-like liquid.

• Suction drum steaming for vessel entry during turnaround done with compressor suction and discharge ESVs left open resulting in condensate building up in the compressor and seal gas system.

• Seal gas take-off from casing bottom allowed for additional condensate to reach the dry gas seal, shattering the faces.

Page 8: Case Study T14: Dry Gas Seal Failures in a Recycle Gas

Compressor Flow Scheme

8

FI

PDCV ESV

Filter

ESV

Primary Dry Gas From Hydrogen Make up Compressor Discharge Header

Comp

Back-up Dry Gas From Compressor Suct

ion

Dis

char

ge

Suction Drum

Recycle Gas To System

(Piping pocket)

(Piping pocket)

To Compressor Dry Gas Seal

To Drain

To Dry Gas Seal

Page 9: Case Study T14: Dry Gas Seal Failures in a Recycle Gas

Challenges in restoration • Dry gas seal rotating face

fragments (WC) caused damage that impeded compressor disassembly.

• OEM’s previous experience with similar failure: 4 weeks to grind out the stuck sleeve with pencil grinder.

• Spare rotor allowed for partially destructive drilling method for sleeve removal. Rotor was removed within two days and compressor was restarted in 11 days.

Page 10: Case Study T14: Dry Gas Seal Failures in a Recycle Gas

Second Failure • Compressor tripped

on high primary vent pressure on suction side exactly one month after the first post-failure start up.

• Damage similar to first failure with shattered faces and seal stuck on the rotor.

• No liquid found.

NDE Primary Seal

NDE Secondary Seal

Page 11: Case Study T14: Dry Gas Seal Failures in a Recycle Gas

Causes of the Failure

• Presence of particulate contamination in the system due to improper cleaning following first failure.

• Seal gas system high flow excursion due to DP transmitter failure.

• Dry gas seal system vulnerabilities to contamination (both solids and liquids).

Heat Check Cracks

Deep Groove at Seal Dam

Page 12: Case Study T14: Dry Gas Seal Failures in a Recycle Gas

Restoration Challenges • No spare rotor & no spare seals. • Sleeve was drilled using same technique as the last

time but with added precaution to prevent damage to rotor.

• Rotor was repaired at the seal seating area using API recommended rotor repair techniques.

• The seal vendor was able to re groove the discharge end seal from first failure, test and return the seals within 4 days.

• Ensure the root cause is identified and mitigate risks by completing as many recommendations as practical.

• Compressor was restarted in 13 days from date of failure.

Page 13: Case Study T14: Dry Gas Seal Failures in a Recycle Gas

Post Failure Work

• Complete review of the compressor and dry gas seal system identified major gaps from evolving industry and company practices. New gas seal panel and system changes provide improvements and new capabilities: – Gas treating (separation, heating) – Filtration, coalescing, drainage – Seal gas supply availability (booster)

Page 14: Case Study T14: Dry Gas Seal Failures in a Recycle Gas

Post Failure Work

• Dry gas seal rotating face material changed to silicon carbide with bi-directional grooves to reduce post-failure damage and repair time, and also make spare seals compatible with either end of compressor.

Page 15: Case Study T14: Dry Gas Seal Failures in a Recycle Gas

Key Lessons Learned

• A machine without failures does not mean it has no gaps. Constant review of systems and latest industry practices helps to ensure equipment reliability. Dry gas seal system design has evolved to consider off-design and unanticipated conditions.

• Challenging situations like these are best overcome with strong partnerships with vendors who can provide unique and timely solutions.

• The need to ensure cleanliness of dry gas seal systems to the highest possible degree, especially during maintenance, is emphasized in these failures.

• Success can be our worst enemy…if we allow it.