1
www.enterpriseis.com.au CASE STUDY Process DeBottlenecking CLIENT: Major Pipe Manufacturer LOCATION: NSW, Australia THE CHALLENGE: The client was Australia’s largest manufacturer of Oil and Gas pipe. Market pressures and delivery timeframes for some specific customers meant that increased throughput without additional production shifts was required. THE SOLUTION: To understand the process and its performance, 12 months of production data was analysed, with initial analysis showing that there was a significant bottleneck in the production line. More detailed analysis using the Six Sigma DMAIC toolset, in particular, Failure Modes and Effects Analysis (FMEA) and statistical analysis of cycle bycycle production data showed that there were a number of factors that were contributing to the area being the bottleneck: 1. Component reliability in the production equipment 2. Errors in the equipment control systems that meant that product was processed multiple times 3. Product specification inconsistencies that forced processing of product through the bottleneck that did not require processing. THE RESULT: Dependent on the product mix, an increase of between 15% and 30% throughput was achieved. The analysis also quantified the throughput through the production steps and enabled an understanding of the movement of the constraint areas, through the plant, as product mix changed. This facilitated a heightened awareness, by production personnel, of plant bottleneck areas and their effect on overall performance. This awareness then changed the shift tactics used in the operation of the equipment. This work also enabled more efficient and effective maintenance of equipment in the bottleneck area, as the critical components had been identified. Having greater knowledge of the bottleneck area and the interrelationship with other equipment in the production line, more appropriate plant throughput measures and targets were developed and implemented.

Case Study - Process DeBottlenecking - Pipe … analysis! also! quantified! the! throughput! through!the!production steps! andenabled! an! understanding!of!the!movement!of!the!constraint!

Embed Size (px)

Citation preview

           

 www.enterpriseis.com.au  

 

CASE  STUDY  Process  De-­‐Bottlenecking

CLIENT:  Major  Pipe  Manufacturer  

LOCATION:  NSW,  Australia  

 

   

THE  CHALLENGE:    

The  client  was  Australia’s  largest  manufacturer  of  Oil  and  Gas  pipe.  

Market   pressures   and   delivery   timeframes   for  some   specific   customers   meant   that   increased  throughput   without   additional   production   shifts  was  required.  

THE  SOLUTION:  

To  understand   the  process   and   its   performance,  12  months  of  production  data  was  analysed,  with  initial   analysis   showing   that   there   was   a  significant  bottleneck  in  the  production  line.  

More  detailed  analysis  using  the  Six  Sigma  DMAIC  toolset,   in   particular,   Failure   Modes   and   Effects  Analysis   (FMEA)   and   statistical   analysis   of   cycle-­‐by-­‐cycle  production  data  showed  that  there  were  a  number  of  factors  that  were  contributing  to  the  area  being  the  bottleneck:  

1. Component   reliability   in   the   production  equipment  

2. Errors  in  the  equipment  control  systems  that  meant   that   product  was  processed  multiple  times  

3. Product   specification   inconsistencies   that  forced   processing   of   product   through   the  bottleneck  that  did  not  require  processing.  

     

THE  RESULT:  

Dependent   on   the   product   mix,   an   increase   of  between  15%  and  30%  throughput  was  achieved.  

The   analysis   also   quantified   the   throughput  through   the   production   steps   and   enabled   an  understanding  of  the  movement  of  the  constraint  areas,  through  the  plant,  as  product  mix  changed.    This   facilitated   a   heightened   awareness,   by  production   personnel,   of   plant   bottleneck   areas  and   their   effect   on   overall   performance.     This  awareness  then  changed  the  shift  tactics  used   in  the  operation  of  the  equipment.      

This   work   also   enabled   more   efficient   and  effective   maintenance   of   equipment   in   the  bottleneck   area,   as   the   critical   components   had  been  identified.  

Having  greater  knowledge  of  the  bottleneck  area  and   the   inter-­‐relationship  with   other   equipment  in   the   production   line,   more   appropriate   plant  throughput   measures   and   targets   were  developed  and  implemented.