Upload
nguyenquynh
View
217
Download
0
Embed Size (px)
Citation preview
www.enterpriseis.com.au
CASE STUDY Process De-‐Bottlenecking
CLIENT: Major Pipe Manufacturer
LOCATION: NSW, Australia
THE CHALLENGE:
The client was Australia’s largest manufacturer of Oil and Gas pipe.
Market pressures and delivery timeframes for some specific customers meant that increased throughput without additional production shifts was required.
THE SOLUTION:
To understand the process and its performance, 12 months of production data was analysed, with initial analysis showing that there was a significant bottleneck in the production line.
More detailed analysis using the Six Sigma DMAIC toolset, in particular, Failure Modes and Effects Analysis (FMEA) and statistical analysis of cycle-‐by-‐cycle production data showed that there were a number of factors that were contributing to the area being the bottleneck:
1. Component reliability in the production equipment
2. Errors in the equipment control systems that meant that product was processed multiple times
3. Product specification inconsistencies that forced processing of product through the bottleneck that did not require processing.
THE RESULT:
Dependent on the product mix, an increase of between 15% and 30% throughput was achieved.
The analysis also quantified the throughput through the production steps and enabled an understanding of the movement of the constraint areas, through the plant, as product mix changed. This facilitated a heightened awareness, by production personnel, of plant bottleneck areas and their effect on overall performance. This awareness then changed the shift tactics used in the operation of the equipment.
This work also enabled more efficient and effective maintenance of equipment in the bottleneck area, as the critical components had been identified.
Having greater knowledge of the bottleneck area and the inter-‐relationship with other equipment in the production line, more appropriate plant throughput measures and targets were developed and implemented.