Capacity and Technology for the Snohvit LNG Plant

Embed Size (px)

Citation preview

  • 8/3/2019 Capacity and Technology for the Snohvit LNG Plant

    1/7

    PS7-Sp.1

    CAPACITY AND TECHNOLOGY FOR THE SNHVIT LNG PLANT

    CAPACIT ET TECHNOLOGIE DES INSTALLATIONSGNL DE SNHVIT

    R.S. HeierstedR. E. Jensen

    R. H. PettersenS. Lillesund

    Den norske stats oljeselskap a.s. (Statoil)Stavanger, Norway

    ABSTRACT

    The Statoil paper will give an insight into the selection of capacity and technology for

    the Snhvit LNG Plant development. The initial plant design was a single train of 3.4million tonnes of LNG per annum capacity. Recent screening studies indicate that LNG

    train capacity contributes significantly to the economy of scale. A decision on the Snhvit

    single train capacity will be balanced against specific risks related to the involved

    technology. The verification will particularly focus on technology exceeding present

    industrial practice when increasing train capacity into the range of 4.0 - 5.0 mtpa of LNG

    production.

    RESUME

    Lintervention de Statoil donnera un aperu de la slection effectue, quant la

    capacit et la technologie, pour le dveloppement des installations GNL de Snhvit.Initiellement, ces installations sont un train simple dune capacit de 3,4 millions de

    tonnes de GNL par an. Les tudes de dtail rcentes indiquent que la capacit du train de

    GNL a une incidence significative sur lconomie dchelle. Une dcision portant sur la

    capacit du train simple de Snhvit sera galement value en regard des risques

    spcifiques relatifs la technologie utilise. La vrification se penchera tout

    particulirement sur la technologie dpassant la pratique industrielle actuelle, puisque la

    capacit du train devrait tre augmente pour passer une production de GNL de lordre

    de 4,0 5,0 mt/an.

  • 8/3/2019 Capacity and Technology for the Snohvit LNG Plant

    2/7

    PS7-Sp.2

    CAPACITY AND TECHNOLOGY FOR THE SNHVIT LNG PLANT

    1 THE SNHVIT LNG CHAIN

    The gas reserves in the Barents Sea off the coast of Northern Norway were discovered

    in the early 1980s, and are located in three different fields, Askeladd, Albatross andSnhvit. The development of all three fields will be part of the Snhvit project. The fields

    are operated by Statoil. Other field owners are Norsk Hydro, TotalFinaElf, RWE-DEA,

    Amerada Hess and Svenska Petroleum.

    The Snhvit project aims at cost efficiency in all aspects of the development, being in

    the fore front of technology and execution methods to obtain the lowest unit production

    costs. Regarding the chain capacity, the project has balanced risks related to the reserves,

    the offshore and onshore technology and market potential. The reserves will be

    commercialised through a grass root LNG chain of 4.3 million tonnes per annum

    capacity.

    The gas fields are located 160 kilometres offshore in 300 to 350 metres water depth.

    The total reserves are in excess of 300 billion standard cubic metres of gas and 20 million

    cubic metres of condensate. The field development will comprise a subsea production

    system and the well stream will be transported to the onshore receiving facilities in a

    multiphase transportation pipeline. The offshore system and multiphase pipeline is

    designed to obtain reliable operations under the given conditions.

    The LNG plant will be situated on the Melkya Island in the vicinity of the city of

    Hammerfest. The plant development meets constraints, particularly on personnel air

    transport logistics and the fact that Norwegian labour regulations restrict personnel

    rotation options, all of which will have an impact on the investment costs. The LNG plantconstruction strategy is based on maximum prefabrication. The basic concept is to install

    a base load LNG process train and most of its utilities on a purpose built barge and ship it

    to site. Compared to other LNG plant executions, the Snhvit project has changed the

    philosophy from on-site, stick-built solutions to yard prefabrication, placing focus on

    maximum work executed in fabrication yards.

    Acquiring shipping capacity has been a focus area. Given the planned LNG

    production capacity and the sales portfolio, the Snhvit project will need four LNG

    carriers with a capacity of 145.000 m3

    each. The shipping distances from the Snhvit area

    to alternative markets balances with the current sales portfolio comprising southern ports

    of Continental Europe and terminals in USA. The Snhvit project is aiming at increasedcommercial robustness by selling its production capacity to markets with different pricing

    mechanisms.

    2 THE ENVIRONMENTAL EDGE OF SNHVIT

    The design of the overall thermal efficiency of the LNG plant must meet economic

    criteria and environmental constraints. The life cycle cost robustness of the technology

    versus future purchase of quota according to the Kyoto Protocol and criteria related to

    Best Available Technology is relevant in a Norwegian context. The cogeneration of

    power and heat production must meet stringent requirements on CO2 and NOx emissions.

    Therefore, the selection of energy optimised processes for the gas sweetening and gasliquefaction is important.

  • 8/3/2019 Capacity and Technology for the Snohvit LNG Plant

    3/7

    PS7-Sp.3

    As a significant measure in the environmental strategy of the project, the carbon

    dioxide will beseparated from the well stream gas at the onshore pretreatment facilities

    and pumped for transport and deposition in an offshore structure. This concept resembles

    the underground storage of carbon dioxide alreadyproven feasible by the Sleipner Field

    in the NorthSea.

    3 SCREENING PROCESS TECHNOLOGY FOR TRAIN SIZING

    In order to improve the economy of scale, by reducing unit cost of produced LNG and

    thus increase the net present value, the project performed a screening study on increasing

    the capacity of the LNG plant, involving the main engineering contractors, the technology

    licensors and the machinery vendors.

    The objectives of the screening were to select the optimum capacity increase and

    recommend the optimum technical solutions for the capacity increase based on high

    thermal efficiency, maximum economy of scale effect and lowest life cycle cost. This also

    included identification of the main technology qualification work for the recommendedsolution in order to reduce the risk with respect to increased capacity.

    The study was based on the initial concept of train capacity of 3.4 million tonnes

    LNG per annum. The contractors identified several potential schemes up to 150 %

    capacity. The short listed schemes were evaluated in more details taking into

    considerations given evaluation criteria such as life cycle cost, equipment size and

    duplication, availability, impact on barge size etc. These evaluations resulted in some

    recommended cases. Special consideration was given to equipment sizing for the carbon

    dioxide removal and liquefaction process design.

    The screening comprised several different driver options including industrial heavy

    duty gas turbines and aeroderivative machines. Both mechanical drive of refrigerant

    compressors as well as electrical motors as compressor drivers were considered. Both

    steam and hot oil were evaluated as waste heat recovery system.

    Relative investment (investment cost related to 100 % capacity) versus capacity,

    revealed a significant economy of scale effect by increasing the capacity up to 150 %. The

    scale up factor corresponded to an exponent of approximately 0.6 - 0.7. The best

    potential of combining reduced unit cost with moderate technology and plant complexity

    is a single LNG train capacity around 135 - 145 %. If capacity increases beyond 150 %

    this might trigger two LNG trains. Taking all relevant risks into consideration, the

    Snhvit project decided an LNG production capacity in the single train of 4.3 mtpa.

    Subsequently after having set the capacity based on screening results, the project

    initiated a feasibility study. The scope focused on process selection with high thermal

    efficiency. The contractors were specifically asked to develop two driver configurations,

    one based on steam and one based on hot oil as waste heat recovery system.

  • 8/3/2019 Capacity and Technology for the Snohvit LNG Plant

    4/7

    PS7-Sp.4

    4 SCREENING DRIVER/COMPRESSOR CONFIGURATIONS

    Statoil provided a list of pre-qualified drivers subject to the screening study. A

    prerequisite is all gas turbines to be equipped with low-NOx (DLE/DLN) combustors. The

    GE LM6000PD was not pre-qualified to be used in mechanical drive service on the basis

    of the present record of operation.

    The screening resulted in several alternative driver and compressor configurations,

    comprising both direct mechanical and indirect compressor drive by means of Gas

    Turbogenerators and electric VSD (Variable Speed Drive) motors.

    Combinations of gas turbines, helper motors, generators, steam turbines and electric

    VSD motors were selected to satisfy the power demands of the compressor drivers,

    process heat and electric power requirements of the LNG plant.

    To reach the most robust driver configuration design, the project is applying life cycle

    cost evaluations, taking the Norwegian offshore CO2 tax regime and BAT (Best Available

    Technology) recommendations into the screening/selection criteria. Driver designs arechecked versus fuel gas prices, reflecting upstream investments and carbon dioxide taxes

    of respectively 125 - 300 NOK per tonne.

    Under this regime, only the most energy efficient designs will be competitive. Plant

    availability is another selection criteria, especially with regards to increased on-stream

    days versus investments.

    5 AVAILABLE TECHNOLOGYLICENSED LNG PROCESSES

    In 1997 the Snhvit project requested three contractors ( Kellogg, Bechtel and Linde )

    to carry out conceptual designs for a baseload LNG plant located at Melkya in NorthernNorway.

    Kellogg selected the APCI propane pre-cooled process, C3/MCR Liquefaction

    Process, in their design. This is the far most utilised process for base load LNG plants,

    and have been utilised in virtually all base load LNG plants installed the last 20 years,

    with some few exceptions.

    Bechtel applied the Optimised Cascade Liquefaction Process based on Phillips

    technology.

    Linde based their design on a dual flow liquefaction process but proposed to change

    their design in eventual further stages of the project to a newly developed, proprietaryMixed Fluid Cascade Process, the MFC process.

    After evaluations of these three conceptual designs, the project decided to award an

    Extended Conceptual Engineering contract to Kellogg and Linde. The Bechel proposed

    technology was rejected for further studies, since it turned out that its overall energy

    efficiency was too low compared to the MFC process and the C3/MCR process, which

    virtually have the same efficiency.

  • 8/3/2019 Capacity and Technology for the Snohvit LNG Plant

    5/7

    PS7-Sp.5

    6 TECHNOLOGY QUALIFICATION

    The technology offered in the Extended Concept Engineering was qualified in

    accordance with Statoil Quality Control System. This technology qualification was based

    on a yearly LNG production capacity of 3.4 mtpa. The train capacity increase to 4.3 mtpa

    made it necessary to perform a new and more extensive technology qualification.

    The main purpose of technology evaluation is to get a firm basis for decision, where

    minimising risk is the main issue. A precondition for the use of any risk assessment

    techniques is that acceptance criteria is outlined. This naturally will shape the format of

    the evaluation, direct the focus to areas of importance and determine whether a risk is

    acceptable or not.

    Today no exact and broadly agreed set of criteria is available in the industry. For the

    purpose of this work the following acceptance criteria have been jointly drawn up by the

    licence partners in Snhvit.

    These overall guidelines were used, when performing the evaluation of the technologiesinvolved:

    When departing from known established technology, the stipulation of the acceptance

    criteria shall be based on the established technology, such as established, recognised

    standard. The new technology may be accepted, if the analysis demonstrate that specified

    characteristics such as risk contribution and unreliability do not increase in relation to the

    reference solution, the established and recognised standard.

    For rotating machinery, technical solutions are regarded as prototypes as long as

    machines in similar service have not successfully accumulated at least 10 000 hours on

    one machine and additional, the total fleet has accumulated 100 000 hours.

    If the above criteria are not fulfilled, and the proposed technical solution deviates

    from established technology, the gap shall be analysed. Quantities such as safety factors,

    experience in form of running time at similar service, testing and verification program etc.

    shall be used in the analysis. Together with any compensatory measures required, this

    shall form the basis for proofing that the risk level will be in line with the risk level for

    proven technology.

    6.1 APCI liquefaction technology

    APCI has delivered technology to the majority of LNG base load plants. Virtually all

    of these plants have been based on their C3/MCR technology. However, for the increased

    single train capacity of the Snhvit project, the Dual Mixed Refrigerant process was

    considered.

    The technology evaluation showed that either processes could be used, and that there

    are no identifiable advantages of DMR over C3/MCR for this specific case. APCI

    recommended to select the well proven C3/MCR technology.

    No technology stoppers were identified when assessing the technology selection.

  • 8/3/2019 Capacity and Technology for the Snohvit LNG Plant

    6/7

    PS7-Sp.6

    6.2 Linde liquefaction technology

    The MCP process proposed by Linde is in principle a cascade process, with the

    important difference that pure refrigerant cycles are replaced with mixed refrigerant

    cycles, and thereby improving efficiency and operational flexibility.

    Comparison work were performed between single flow, dual flow and mixed fluid cascade

    process options. Linde concluded that the MFC process was the most advantageous process.

    The following characteristics were found to apply to the MFC process:

    The process is new, and as a whole without any industrial references. However,

    theconcept is build up by well known elements.

    The liquefaction process utilizes a plate fin heat exchanger for pre-cooling, and two

    separate SWHE for liquefaction and sub-cooling.

    The size and complexity of the SWHE applied in the MFC process is considerably less

    when compared with todays dual flow LNG plants.

    The technology qualification has not revealed any technology stoppers in selection the

    Linde MFC process. The integrity and operability of the Linde SWHE has been proven by

    a test plant in Mossel Bay, South Africa. All critical elements of the liquefaction process

    have either references to plants in similar service, or have been qualified by extensive

    testing and verification calculations, based on sound engineering practice.

    7 LARGE LNG STORAGE CONCEPT

    The potential advantages of adopting one 220,000 m3

    LNG tank over the two times

    110,000 m3 option became apparent when judged on an economic and project executionbasis. These advantages included reduced labour and equipment requirements leading to a

    reduced effect on the local community and environment.

    In order to assess the viability of a 220,000 m3

    LNG storage tank, studies have been

    carried out based on a 9 % nickel inner tank and a pre-stressed concrete outer tank. Inner

    tank designs have been completed for both full height and partial hydro-test to identify the

    impact on shell thickness. Such large tank designs can be based on the rules of API 620

    which requires a partial height hydrostatic test. If the tank were to be subjected to a full

    height hydrostatic test, then the design of the inner tank would exceed the API 620 limit.

    BS 7777 requires that the tanks are hydro tested to the maximum design product leveland allows a maximum shell plate thickness of 30 mm. However, the code does allow

    thicknesses in excess of this figure with the purchaser's agreement. The new Eurocode

    under preparation will probably allow a maximum shell thickness for 9 % nickel steel of

    50 mm and partial height hydrotesting of the inner tank.

    A benefit of the partial hydro test design for the 220,000 m3

    tank is a material saving

    of more than 700 tonnes of 9 % nickel steel. Further associated savings would be made on

    labour and consumables due to the reduction in weld volumes.

    Considering the extreme conditions at the Hammerfest LNG plant site in winter, it is

    essential to have a weatherproof outer tank by the end of the construction window toallow work to continue inside the tank. In this case the steel roof would be exposed to the

  • 8/3/2019 Capacity and Technology for the Snohvit LNG Plant

    7/7

    PS7-Sp.7

    elements on the top of the tank and would be subjected to wind and snow loads. The

    schedule requirement is to progress tank construction during the first summer to achieve a

    weather tight envelope, permitting work to proceed inside the tank during the winter

    months. The target is to complete the outer tank concrete roof, however in order to

    mitigate for weather delays to the concreting, the steel roof should be designed to

    accommodate the potential snow load in the event that the concreting operation is notcomplete.

    8 CLOSING REMARKS

    In December 2000, the Snhvit LNG project has passed an important milestone. The

    license partners have selected the main engineering contractor and the LNG technology

    licensor, and agreed to enter into the next phase of the project development, namely the

    front-end design and engineering for the LNG plant.

    Start-up of LNG production from the Snhvit fields is scheduled for October 2006.