1 BIM 1.0, BIM 2.0, BIM 3.0 2010 Update I gave a presentation at the 2010 AIA National Convention earlier this year. That Power Point presentation with audio is available from the AIA. This Power Point is a modified version of that presentation designed to stand alone. Text (Italic and blue) has been added to the slides to provide information on what the firms are doing with BIM. Dennis Neeley, AIA

BIM 1.0, BIM 2.0, BIM 3.0 2010 Update. BIM 1.0, BIM 2.0, BIM 3.0 2010 Update. I gave a presentation at the 2010 AIA National Convention earlier this year. That Power Point presentation

  • Upload
    vuthuan

  • View
    226

  • Download
    7

Embed Size (px)

Citation preview

Page 1: BIM 1.0, BIM 2.0, BIM 3.0 2010 Update. BIM 1.0, BIM 2.0, BIM 3.0 2010 Update. I gave a presentation at the 2010 AIA National Convention earlier this year. That Power Point presentation

1

BIM 1.0, BIM 2.0, BIM 3.0 2010 Update

I gave a presentation at the 2010 AIA National Convention earlier this year.  

That Power Point presentation with audio is available from the AIA.

This Power Point is a modified version of that presentation designed to 

stand alone.  Text (Italic and blue) has been added to the slides to provide 

information on what the firms are doing with BIM. 

Dennis Neeley, AIA

Page 2: BIM 1.0, BIM 2.0, BIM 3.0 2010 Update. BIM 1.0, BIM 2.0, BIM 3.0 2010 Update. I gave a presentation at the 2010 AIA National Convention earlier this year. That Power Point presentation

Acknowledgements/Credits

10 Miles Wide - Jeffrey McGrewDPR - Rob Leicht, PhDDOC - Diego Torres-Palma Hathaway Dinwiddie – Darin PetersFriedmutter Group – Lonnie CumptonRaymond Group - Ashish PetersTME - Mark MergenschroerWATG - James J. Balding, AIA

The presentation looks at what is being done 

with BIM by architects, engineers and 

contractors.  The following individuals 

contributed the information that made this 

presentation possible.

2

Page 3: BIM 1.0, BIM 2.0, BIM 3.0 2010 Update. BIM 1.0, BIM 2.0, BIM 3.0 2010 Update. I gave a presentation at the 2010 AIA National Convention earlier this year. That Power Point presentation

Bad News, You are at the Start of a New Era

Good News, You are Part of a New Era

BIM 1.0, BIM 2.0, BIM 3.0 2010 Update

BIM will change everything for everybody dealing with 

buildings

BIM will change the roles, responsibilities, 

education and training for everyone dealing 

with the built environment.

3

Page 4: BIM 1.0, BIM 2.0, BIM 3.0 2010 Update. BIM 1.0, BIM 2.0, BIM 3.0 2010 Update. I gave a presentation at the 2010 AIA National Convention earlier this year. That Power Point presentation

BIM 1.0 –

Visualization & Drawings 

BIM 2.0 – Analysis

BIM 3.0 –

Simulation

BIM 1.0, BIM 2.0, BIM 3.0, BIM 4.0 2010 Update

I have divided BIM into three categories, and each year 

take a look at what AEC professionals are doing.  BIM 1.0 

is the level that most are using BIM, the creation of 

paper drawings, renderings and animations.  BIM 2.0  

looks at how BIM can be linked to analysis.  BIM 3.0 

deals with simulation based upon the BIM project.

4

Page 5: BIM 1.0, BIM 2.0, BIM 3.0 2010 Update. BIM 1.0, BIM 2.0, BIM 3.0 2010 Update. I gave a presentation at the 2010 AIA National Convention earlier this year. That Power Point presentation

BIM Adoption

BIM Products: Revit, ArchiCAD, Digital Project (Catia), Bentley, VectorWorks, Tekla

CAD took 15‐20 years to replace hand drawing.  BIM will 

replace CAD in 1/3 that time, amazing.  The blue circles 

indicate when the charts were created, the blue circle, 

current adoption is tracking the prediction.

5

Page 6: BIM 1.0, BIM 2.0, BIM 3.0 2010 Update. BIM 1.0, BIM 2.0, BIM 3.0 2010 Update. I gave a presentation at the 2010 AIA National Convention earlier this year. That Power Point presentation

Architect/Engineer

Building Product Manufacturer /Supplier / DistributorContractor

BuildingOwner

From Fragmented to an  Integrated Process 

The next few slides will show how BIM is going to 

change the roles and activities of these involved with 

the design, construction, manufacturing and facilities 

management process.

6

Page 7: BIM 1.0, BIM 2.0, BIM 3.0 2010 Update. BIM 1.0, BIM 2.0, BIM 3.0 2010 Update. I gave a presentation at the 2010 AIA National Convention earlier this year. That Power Point presentation

Mfg. Product Library

Virtual Library,Select a Product

Architect/Engineer

Building Product Manufacturer /Supplier / DistributorContractor

BuildingOwner

Paper DrawingsSchedulesRenderings

BIM Project Models&Data

Objects & Assemblies

AssemblyBuilder, Create an Assembly

Most designers are using BIM to create paper drawings, 

schedules and renderings.  They need libraries of objects 

and assemblies (both generic and manufacturer 

specific).

7

Page 8: BIM 1.0, BIM 2.0, BIM 3.0 2010 Update. BIM 1.0, BIM 2.0, BIM 3.0 2010 Update. I gave a presentation at the 2010 AIA National Convention earlier this year. That Power Point presentation

Mfg. Product Library

Virtual Library,Select a Product

Architect/Engineer

Building Product Manufacturer /Supplier / DistributorContractor

BuildingOwner

DrawingsSchedulesRenderings

Export BIM Data

AssemblyBuilder, Create an Assembly

BIM Project Models&Data

BuildingInformationServices, DataManagement

Sharing of Data

The exporting of the BIM model to those that can take 

advantage of the information is critical.  Many 

designers are uncomfortable with this step, they need to 

share their BIM models, it will be demanded by owners.

8

Page 9: BIM 1.0, BIM 2.0, BIM 3.0 2010 Update. BIM 1.0, BIM 2.0, BIM 3.0 2010 Update. I gave a presentation at the 2010 AIA National Convention earlier this year. That Power Point presentation

Mfg. Product Library

Virtual Library,Select a Product

Architect/Engineer

Building Product Manufacturer /Supplier / DistributorContractor

BuildingOwner

DrawingsSchedulesRenderings

Calculated Data

Analysis

AssemblyBuilder, Create an Assembly

BIM Project Models&Data

Masterformat

Cross Reference Database

BuildingInformationServices, DataManagement

QuantityReports

Products & Assembly Builder Database

Simulate

Active BIM Data

Analysis & Simulation

Internal to the architectural and engineering process 

there are multiple software programs that will lead to 

better designed and performing buildings. 

9

Page 10: BIM 1.0, BIM 2.0, BIM 3.0 2010 Update. BIM 1.0, BIM 2.0, BIM 3.0 2010 Update. I gave a presentation at the 2010 AIA National Convention earlier this year. That Power Point presentation

Mfg. Product Library

Virtual Library,Select a Product

Architect/Engineer

Building Product Manufacturer /Supplier / DistributorContractor

BuildingOwner

DrawingsSchedulesRenderings

EstimatedConstruction

Prices Database

Analysis

AssemblyBuilder, Create an Assembly

BIM Project Models&Data

BuildingInformationServices, DataManagement

QuantityReports Cost

Reports

Simulate

Active BIM Data

Preliminary Costs

Quantity take‐off calculations can be aligned with 

databases of preliminary costs for labor, material and 

equipment to quickly calculate anticipated construction 

costs.

Calculated Data

Masterformat

Cross Reference Database

Products & Assembly Builder Database

10

Page 11: BIM 1.0, BIM 2.0, BIM 3.0 2010 Update. BIM 1.0, BIM 2.0, BIM 3.0 2010 Update. I gave a presentation at the 2010 AIA National Convention earlier this year. That Power Point presentation

Mfg. Product Library

BiddingService

Virtual Library,Select a Product

Architect/Engineer

Building Product Manufacturer /Supplier / DistributorContractor

BuildingOwner

DrawingsSchedulesRenderings

EstimatedConstruction

Prices Database

Analysis

AssemblyBuilder, Create an Assembly

BIM Project Models&Data

Product Specific Pricing

BuildingInformationServices, DataManagement

QuantityReports

Simulate

Labor, Equipment Specific Pricing

Active BIM Data

Accurate Costs

The BIM project (graphics and data) is used by the 

contractors to calculate accurate costing.  Manufacturer 

and supplier costs are electronically accessed.  

Calculated Data

Masterformat

Cross Reference Database

Products & Assembly Builder Database

CostReports

11

Page 12: BIM 1.0, BIM 2.0, BIM 3.0 2010 Update. BIM 1.0, BIM 2.0, BIM 3.0 2010 Update. I gave a presentation at the 2010 AIA National Convention earlier this year. That Power Point presentation

Mfg. Product Library

BiddingService

Virtual Library,Select a Product

Architect/Engineer

Building Product Manufacturer /Supplier / DistributorContractor

BuildingOwner

DrawingsSchedulesRenderings

EstimatedConstruction

Prices Database

Analysis

AssemblyBuilder, Create an Assembly

BIM Project Models&Data

Product Specific Pricing

BuildingInformationServices, DataManagement

QuantityReports

Simulate

Labor, Equipment Specific Pricing

Active BIM Data

Construction

The BIM project is shared with the contractors and 

manufacturers and they add their work to the model.  

Conflicts are discovered and resolved prior to the start 

of construction. These models will lead to the simulation 

of the construction project.

Calculated Data

Masterformat

Cross Reference Database

Products & Assembly Builder Database

CostReports

BIM Project Models&Data

12

Page 13: BIM 1.0, BIM 2.0, BIM 3.0 2010 Update. BIM 1.0, BIM 2.0, BIM 3.0 2010 Update. I gave a presentation at the 2010 AIA National Convention earlier this year. That Power Point presentation

Mfg. Product Library

BiddingService

Virtual Product Library,Select a Product

Architect/Engineer

Building Product Manufacturer /Supplier / DistributorContractor

FacilityMgmt.Service

BuildingOwner

DrawingsSchedulesRenderings

EstimatedConstruction

Prices Database

Analysis

AssemblyBuilder, Create an Assembly

BIM Project Models&Data

Asset Database

BuildingInformationServices, DataManagement

QuantityReports

Simulate

Active BIM Data

Product Specific Pricing

Facilities & Asset Management

The owner is provided the BIM project for use in 

operations, facility management and asset 

management.  The BIM project is constantly maintained 

for accuracy .

Calculated Data

Masterformat

Cross Reference Database

Products & Assembly Builder Database

CostReports

Labor, Equipment Specific Pricing

BIM Project Models&Data

13

Page 14: BIM 1.0, BIM 2.0, BIM 3.0 2010 Update. BIM 1.0, BIM 2.0, BIM 3.0 2010 Update. I gave a presentation at the 2010 AIA National Convention earlier this year. That Power Point presentation

BIM 1.0 –

Visualization & DrawingsTME

MEP Engineers

Little RockTucson

FayettevilleOklahoma City

St. Louis

At a time when many A&E firms are 

downsizing, or closing, TME 

business is increasing.  They have 

added  over 20 BIM workstations 

this year.  They use BIM for 

marketing, production and post 

construction services.

14

Page 15: BIM 1.0, BIM 2.0, BIM 3.0 2010 Update. BIM 1.0, BIM 2.0, BIM 3.0 2010 Update. I gave a presentation at the 2010 AIA National Convention earlier this year. That Power Point presentation

BIM 1.0 –

Visualization & DrawingsTME

MEP Engineers

Little RockTucson

FayettevilleOklahoma City

St. Louis

At a time when many A&E firms are 

downsizing, or closing, TME 

business is increasing.  They have 

added  over 20 BIM workstations 

this year.  They use BIM for 

marketing, production and post 

construction services.

14

Page 16: BIM 1.0, BIM 2.0, BIM 3.0 2010 Update. BIM 1.0, BIM 2.0, BIM 3.0 2010 Update. I gave a presentation at the 2010 AIA National Convention earlier this year. That Power Point presentation

BIM 1.0 –

Visualization & DrawingsTME

MEP Engineers

Little RockTucson

FayettevilleOklahoma City

St. Louis

At a time when many A&E firms are 

downsizing, or closing, TME 

business is increasing.  They have 

added  over 20 BIM workstations 

this year.  They use BIM for 

marketing, production and post 

construction services.

14

Page 17: BIM 1.0, BIM 2.0, BIM 3.0 2010 Update. BIM 1.0, BIM 2.0, BIM 3.0 2010 Update. I gave a presentation at the 2010 AIA National Convention earlier this year. That Power Point presentation

BIM 1.0 –

Visualization & DrawingsTME

MEP Engineers

Little RockTucson

FayettevilleOklahoma City

St. Louis

At a time when many A&E firms are 

downsizing, or closing, TME 

business is increasing.  They have 

added  over 20 BIM workstations 

this year.  They use BIM for 

marketing, production and post 

construction services.

14

Page 18: BIM 1.0, BIM 2.0, BIM 3.0 2010 Update. BIM 1.0, BIM 2.0, BIM 3.0 2010 Update. I gave a presentation at the 2010 AIA National Convention earlier this year. That Power Point presentation

BIM 1.0 –

Visualization & DrawingsTME

MEP Engineers

Little RockTucson

FayettevilleOklahoma City

St. Louis

At a time when many A&E firms are 

downsizing, or closing, TME 

business is increasing.  They have 

added  over 20 BIM workstations 

this year.  They use BIM for 

marketing, production and post 

construction services.

14

Page 19: BIM 1.0, BIM 2.0, BIM 3.0 2010 Update. BIM 1.0, BIM 2.0, BIM 3.0 2010 Update. I gave a presentation at the 2010 AIA National Convention earlier this year. That Power Point presentation

BIM 1.0 –

Visualization & DrawingsTME

MEP Engineers

Little RockTucson

FayettevilleOklahoma City

St. Louis

At a time when many A&E firms are 

downsizing, or closing, TME 

business is increasing.  They have 

added  over 20 BIM workstations 

this year.  They use BIM for 

marketing, production and post 

construction services.

14

Page 20: BIM 1.0, BIM 2.0, BIM 3.0 2010 Update. BIM 1.0, BIM 2.0, BIM 3.0 2010 Update. I gave a presentation at the 2010 AIA National Convention earlier this year. That Power Point presentation

BIM 1.0 –

Visualization & DrawingsTME

MEP Engineers

Little RockTucson

FayettevilleOklahoma City

St. Louis

At a time when many A&E firms are 

downsizing, or closing, TME 

business is increasing.  They have 

added  over 20 BIM workstations 

this year.  They use BIM for 

marketing, production and post 

construction services.

14

Page 21: BIM 1.0, BIM 2.0, BIM 3.0 2010 Update. BIM 1.0, BIM 2.0, BIM 3.0 2010 Update. I gave a presentation at the 2010 AIA National Convention earlier this year. That Power Point presentation

BIM 1.0 –

Visualization & DrawingsFriedmutter

Group

Architects

Las VegasNew York

Newport BeachHong Kong

Big Projects

Friedmutter

Group 

works on massive 

projects measured in 

millions of square feet 

and billions of dollars. 

15

Page 22: BIM 1.0, BIM 2.0, BIM 3.0 2010 Update. BIM 1.0, BIM 2.0, BIM 3.0 2010 Update. I gave a presentation at the 2010 AIA National Convention earlier this year. That Power Point presentation

BIM 1.0 –

Visualization & DrawingsFriedmutter

Group

Object Design

Multi‐Billion Dollar Projects

Millions of Square Feet

6700 Drawings

Multiple Sub Projects

Consultant Coordination

Computer Speed / Storage/ Backup Their challenges include addressing 

and solving the management of the 

items listed to the right.  They have 

learned how to use BIM on their 

massive projects.

16

Page 23: BIM 1.0, BIM 2.0, BIM 3.0 2010 Update. BIM 1.0, BIM 2.0, BIM 3.0 2010 Update. I gave a presentation at the 2010 AIA National Convention earlier this year. That Power Point presentation

Jeffrey McGrewOakland

BIM 1.0 –

Visualization & Drawings

Jeffrey is a single person firm.  He is a talented designer who is also a mater user of BIM.  He 

is also using his BIM models to fabricate components of his projects.

17

Page 24: BIM 1.0, BIM 2.0, BIM 3.0 2010 Update. BIM 1.0, BIM 2.0, BIM 3.0 2010 Update. I gave a presentation at the 2010 AIA National Convention earlier this year. That Power Point presentation

Jeffrey McGrewOakland

BIM 1.0 –

Visualization & Drawings

Jeffrey is a single person firm.  He is a talented designer who is also a mater user of BIM.  He 

is also using his BIM models to fabricate components of his projects.

17

Page 25: BIM 1.0, BIM 2.0, BIM 3.0 2010 Update. BIM 1.0, BIM 2.0, BIM 3.0 2010 Update. I gave a presentation at the 2010 AIA National Convention earlier this year. That Power Point presentation

Jeffrey McGrewOakland

BIM 1.0 –

Visualization & Drawings

Jeffrey is a single person firm.  He is a talented designer who is also a mater user of BIM.  He 

is also using his BIM models to fabricate components of his projects.

17

Page 26: BIM 1.0, BIM 2.0, BIM 3.0 2010 Update. BIM 1.0, BIM 2.0, BIM 3.0 2010 Update. I gave a presentation at the 2010 AIA National Convention earlier this year. That Power Point presentation

Jeffrey McGrewOakland

BIM 1.0 –

Visualization & Drawings

Jeffrey is a single person firm.  He is a talented designer who is also a mater user of BIM.  He 

is also using his BIM models to fabricate components of his projects.

17

Page 27: BIM 1.0, BIM 2.0, BIM 3.0 2010 Update. BIM 1.0, BIM 2.0, BIM 3.0 2010 Update. I gave a presentation at the 2010 AIA National Convention earlier this year. That Power Point presentation

Jeffrey McGrewOakland

BIM 1.0 –

Visualization & Drawings

Jeffrey is a single person firm.  He is a talented designer who is also a mater user of BIM.  He 

is also using his BIM models to fabricate components of his projects.

17

Page 28: BIM 1.0, BIM 2.0, BIM 3.0 2010 Update. BIM 1.0, BIM 2.0, BIM 3.0 2010 Update. I gave a presentation at the 2010 AIA National Convention earlier this year. That Power Point presentation

Jeffrey McGrewOakland

BIM 1.0 –

Visualization & Drawings

Jeffrey is a single person firm.  He is a talented designer who is also a mater user of BIM.  He 

is also using his BIM models to fabricate components of his projects.

17

Page 29: BIM 1.0, BIM 2.0, BIM 3.0 2010 Update. BIM 1.0, BIM 2.0, BIM 3.0 2010 Update. I gave a presentation at the 2010 AIA National Convention earlier this year. That Power Point presentation

Jeffrey McGrewOakland

BIM 1.0 –

Visualization & Drawings

Jeffrey is a single person firm.  He is a talented designer who is also a mater user of BIM.  He 

is also using his BIM models to fabricate components of his projects.

17

Page 30: BIM 1.0, BIM 2.0, BIM 3.0 2010 Update. BIM 1.0, BIM 2.0, BIM 3.0 2010 Update. I gave a presentation at the 2010 AIA National Convention earlier this year. That Power Point presentation

BIM 1.0 –

Visualization & DrawingsGuidelines

BIM is moving faster that the guidelines and standards can help guide the users.  Many of the 

organizations working on guidelines are volunteer operations that move very slowly.  

Conflicts between guidelines will make life difficult.  Owners are just realizing they must set 

guidelines if they are to get ‘downstream”

value from their BIM projects.

18

Page 31: BIM 1.0, BIM 2.0, BIM 3.0 2010 Update. BIM 1.0, BIM 2.0, BIM 3.0 2010 Update. I gave a presentation at the 2010 AIA National Convention earlier this year. That Power Point presentation

BIM 1.0 –

Visualization & DrawingsGuidelines

BIM is moving faster that the guidelines and standards can help guide the users.  Many of the 

organizations working on guidelines are volunteer operations that move very slowly.  

Conflicts between guidelines will make life difficult.  Owners are just realizing they must set 

guidelines if they are to get ‘downstream”

value from their BIM projects.

18

Page 32: BIM 1.0, BIM 2.0, BIM 3.0 2010 Update. BIM 1.0, BIM 2.0, BIM 3.0 2010 Update. I gave a presentation at the 2010 AIA National Convention earlier this year. That Power Point presentation

BIM 1.0 –

Visualization & DrawingsGuidelines

BIM is moving faster that the guidelines and standards can help guide the users.  Many of the 

organizations working on guidelines are volunteer operations that move very slowly.  

Conflicts between guidelines will make life difficult.  Owners are just realizing they must set 

guidelines if they are to get ‘downstream”

value from their BIM projects.

18

Page 33: BIM 1.0, BIM 2.0, BIM 3.0 2010 Update. BIM 1.0, BIM 2.0, BIM 3.0 2010 Update. I gave a presentation at the 2010 AIA National Convention earlier this year. That Power Point presentation

BIM 1.0 –

Visualization & DrawingsGuidelines

BIM is moving faster that the guidelines and standards can help guide the users.  Many of the 

organizations working on guidelines are volunteer operations that move very slowly.  

Conflicts between guidelines will make life difficult.  Owners are just realizing they must set 

guidelines if they are to get ‘downstream”

value from their BIM projects.

18

Page 34: BIM 1.0, BIM 2.0, BIM 3.0 2010 Update. BIM 1.0, BIM 2.0, BIM 3.0 2010 Update. I gave a presentation at the 2010 AIA National Convention earlier this year. That Power Point presentation

BIM 1.0 –

Visualization & DrawingsGuidelines

BIM is moving faster that the guidelines and standards can help guide the users.  Many of the 

organizations working on guidelines are volunteer operations that move very slowly.  

Conflicts between guidelines will make life difficult.  Owners are just realizing they must set 

guidelines if they are to get ‘downstream”

value from their BIM projects.

18

Page 35: BIM 1.0, BIM 2.0, BIM 3.0 2010 Update. BIM 1.0, BIM 2.0, BIM 3.0 2010 Update. I gave a presentation at the 2010 AIA National Convention earlier this year. That Power Point presentation

BIM 1.0 –

Visualization & DrawingsGuidelines

BIM is moving faster that the guidelines and standards can help guide the users.  Many of the 

organizations working on guidelines are volunteer operations that move very slowly.  

Conflicts between guidelines will make life difficult.  Owners are just realizing they must set 

guidelines if they are to get ‘downstream”

value from their BIM projects.

18

Page 36: BIM 1.0, BIM 2.0, BIM 3.0 2010 Update. BIM 1.0, BIM 2.0, BIM 3.0 2010 Update. I gave a presentation at the 2010 AIA National Convention earlier this year. That Power Point presentation

BIM 1.0 –

Visualization & DrawingsGuidelines

BIM is moving faster that the guidelines and standards can help guide the users.  Many of the 

organizations working on guidelines are volunteer operations that move very slowly.  

Conflicts between guidelines will make life difficult.  Owners are just realizing they must set 

guidelines if they are to get ‘downstream”

value from their BIM projects.

18

Page 37: BIM 1.0, BIM 2.0, BIM 3.0 2010 Update. BIM 1.0, BIM 2.0, BIM 3.0 2010 Update. I gave a presentation at the 2010 AIA National Convention earlier this year. That Power Point presentation

BIM 1.0 –

2009 & 2010 Recap

2009 • Reduces Errors & Omissions• Reduces Paper Drawing Creation 

Time ( Not a Goal )

• Training• Lack of Objects –

Generic and 

Manufacturers

2010 • Expected by Owners• May, or may not increase 

architectural fees• More manufacturers 

understanding they need to 

provide objects

• May redefine the role and 

responsibilities of the architect

Year                                 Positives

Concerns                

19

Page 38: BIM 1.0, BIM 2.0, BIM 3.0 2010 Update. BIM 1.0, BIM 2.0, BIM 3.0 2010 Update. I gave a presentation at the 2010 AIA National Convention earlier this year. That Power Point presentation

Massing

Acoustic Structural

Shading & Shadows

Wind & Air Flow

Radiance

Artificial Lighting

Costing

Energy

Quantity Take Off

BIM 2.0 –

Analysis

Last year I looked at what each of these categories would mean as BIM and analysis 

seamlessly work together.  This year I look a some specific examples of what firms are doing.

20

Page 39: BIM 1.0, BIM 2.0, BIM 3.0 2010 Update. BIM 1.0, BIM 2.0, BIM 3.0 2010 Update. I gave a presentation at the 2010 AIA National Convention earlier this year. That Power Point presentation

BIM 2.0 –

AnalysisTME

MEP Engineers

Little RockTucson

FayettevilleOklahoma City

St. Louis

When objects are inserted in the project that were 

modeled with correct and extensive data the creation of 

the footcandle

and watts/sq.ft. calculations take seconds.  

21

Page 40: BIM 1.0, BIM 2.0, BIM 3.0 2010 Update. BIM 1.0, BIM 2.0, BIM 3.0 2010 Update. I gave a presentation at the 2010 AIA National Convention earlier this year. That Power Point presentation

BIM 2.0 –

AnalysisHathawayDinwiddie

Contractors

San Francisco, CASanta Clara, CALos Angeles, CA

Logistics / Scheduling

Hathaway Dinwiddie  

works on negotiated 

projects.  They use 

BIM from the start 

of the project for 

planning, costing, 

conflict resolution, 

and presentations

They use the BIM 

project to plan their 

construction process 

as shown on this 

sequence of images.

22

Page 41: BIM 1.0, BIM 2.0, BIM 3.0 2010 Update. BIM 1.0, BIM 2.0, BIM 3.0 2010 Update. I gave a presentation at the 2010 AIA National Convention earlier this year. That Power Point presentation

BIM 2.0 –

AnalysisHathawayDinwiddie

Contractors

San Francisco, CASanta Clara, CALos Angeles, CA

Logistics / Scheduling

Hathaway Dinwiddie  

works on negotiated 

projects.  They use 

BIM from the start 

of the project for 

planning, costing, 

conflict resolution, 

and presentations

They use the BIM 

project to plan their 

construction process 

as shown on this 

sequence of images.

22

Page 42: BIM 1.0, BIM 2.0, BIM 3.0 2010 Update. BIM 1.0, BIM 2.0, BIM 3.0 2010 Update. I gave a presentation at the 2010 AIA National Convention earlier this year. That Power Point presentation

BIM 2.0 –

AnalysisHathawayDinwiddie

Contractors

San Francisco, CASanta Clara, CALos Angeles, CA

Logistics / Scheduling

Hathaway Dinwiddie  

works on negotiated 

projects.  They use 

BIM from the start 

of the project for 

planning, costing, 

conflict resolution, 

and presentations

They use the BIM 

project to plan their 

construction process 

as shown on this 

sequence of images.

22

Page 43: BIM 1.0, BIM 2.0, BIM 3.0 2010 Update. BIM 1.0, BIM 2.0, BIM 3.0 2010 Update. I gave a presentation at the 2010 AIA National Convention earlier this year. That Power Point presentation

BIM 2.0 –

AnalysisHathawayDinwiddie

Contractors

San Francisco, CASanta Clara, CALos Angeles, CA

Logistics / Scheduling

Hathaway Dinwiddie  

works on negotiated 

projects.  They use 

BIM from the start 

of the project for 

planning, costing, 

conflict resolution, 

and presentations

They use the BIM 

project to plan their 

construction process 

as shown on this 

sequence of images.

22

Page 44: BIM 1.0, BIM 2.0, BIM 3.0 2010 Update. BIM 1.0, BIM 2.0, BIM 3.0 2010 Update. I gave a presentation at the 2010 AIA National Convention earlier this year. That Power Point presentation

BIM 2.0 –

AnalysisHathawayDinwiddie

Contractors

San Francisco, CASanta Clara, CALos Angeles, CA

Logistics / Scheduling

Hathaway Dinwiddie  

works on negotiated 

projects.  They use 

BIM from the start 

of the project for 

planning, costing, 

conflict resolution, 

and presentations

They use the BIM 

project to plan their 

construction process 

as shown on this 

sequence of images.

22

Page 45: BIM 1.0, BIM 2.0, BIM 3.0 2010 Update. BIM 1.0, BIM 2.0, BIM 3.0 2010 Update. I gave a presentation at the 2010 AIA National Convention earlier this year. That Power Point presentation

BIM 2.0 –

AnalysisTrade Coordination 

HathawayDinwiddie

The BIM modeling starts immediately and progresses throughout the life of the project.  As 

more information is added the model becomes more complex and valuable as they move to 

construction.

23

Page 46: BIM 1.0, BIM 2.0, BIM 3.0 2010 Update. BIM 1.0, BIM 2.0, BIM 3.0 2010 Update. I gave a presentation at the 2010 AIA National Convention earlier this year. That Power Point presentation

BIM 2.0 –

AnalysisTrade Coordination 

HathawayDinwiddie

The BIM modeling starts immediately and progresses throughout the life of the project.  As 

more information is added the model becomes more complex and valuable as they move to 

construction.

23

Page 47: BIM 1.0, BIM 2.0, BIM 3.0 2010 Update. BIM 1.0, BIM 2.0, BIM 3.0 2010 Update. I gave a presentation at the 2010 AIA National Convention earlier this year. That Power Point presentation

BIM 2.0 –

AnalysisTrade Coordination 

HathawayDinwiddie

The BIM modeling starts immediately and progresses throughout the life of the project.  As 

more information is added the model becomes more complex and valuable as they move to 

construction.

23

Page 48: BIM 1.0, BIM 2.0, BIM 3.0 2010 Update. BIM 1.0, BIM 2.0, BIM 3.0 2010 Update. I gave a presentation at the 2010 AIA National Convention earlier this year. That Power Point presentation

BIM 2.0 –

AnalysisEstimating

Cost Range of Study ‐

$52.1M to $29.6M

HathawayDinwiddie

They do extensive design/costing studies.  The designs above meet the customer program 

requirements, the cost variations are dramatic.  This type of study is clearly valuable 

information to show the owner. 

24

Page 49: BIM 1.0, BIM 2.0, BIM 3.0 2010 Update. BIM 1.0, BIM 2.0, BIM 3.0 2010 Update. I gave a presentation at the 2010 AIA National Convention earlier this year. That Power Point presentation

BIM 2.0 –

AnalysisEstimating

Cost Range of Study ‐

$52.1M to $29.6M

HathawayDinwiddie

They do extensive design/costing studies.  The designs above meet the customer program 

requirements, the cost variations are dramatic.  This type of study is clearly valuable 

information to show the owner. 

24

Page 50: BIM 1.0, BIM 2.0, BIM 3.0 2010 Update. BIM 1.0, BIM 2.0, BIM 3.0 2010 Update. I gave a presentation at the 2010 AIA National Convention earlier this year. That Power Point presentation

BIM 2.0 –

AnalysisEstimating

Cost Range of Study ‐

$52.1M to $29.6M

HathawayDinwiddie

They do extensive design/costing studies.  The designs above meet the customer program 

requirements, the cost variations are dramatic.  This type of study is clearly valuable 

information to show the owner. 

24

Page 51: BIM 1.0, BIM 2.0, BIM 3.0 2010 Update. BIM 1.0, BIM 2.0, BIM 3.0 2010 Update. I gave a presentation at the 2010 AIA National Convention earlier this year. That Power Point presentation

BIM 2.0 –

AnalysisEstimating

Cost Range of Study ‐

$52.1M to $29.6M

HathawayDinwiddie

They do extensive design/costing studies.  The designs above meet the customer program 

requirements, the cost variations are dramatic.  This type of study is clearly valuable 

information to show the owner. 

24

Page 52: BIM 1.0, BIM 2.0, BIM 3.0 2010 Update. BIM 1.0, BIM 2.0, BIM 3.0 2010 Update. I gave a presentation at the 2010 AIA National Convention earlier this year. That Power Point presentation

BIM 2.0 –

AnalysisEstimating

Cost Range of Study ‐

$52.1M to $29.6M

HathawayDinwiddie

They do extensive design/costing studies.  The designs above meet the customer program 

requirements, the cost variations are dramatic.  This type of study is clearly valuable 

information to show the owner. 

24

Page 53: BIM 1.0, BIM 2.0, BIM 3.0 2010 Update. BIM 1.0, BIM 2.0, BIM 3.0 2010 Update. I gave a presentation at the 2010 AIA National Convention earlier this year. That Power Point presentation

BIM 2.0 –

AnalysisEstimating

Cost Range of Study ‐

$52.1M to $29.6M

HathawayDinwiddie

They do extensive design/costing studies.  The designs above meet the customer program 

requirements, the cost variations are dramatic.  This type of study is clearly valuable 

information to show the owner. 

24

Page 54: BIM 1.0, BIM 2.0, BIM 3.0 2010 Update. BIM 1.0, BIM 2.0, BIM 3.0 2010 Update. I gave a presentation at the 2010 AIA National Convention earlier this year. That Power Point presentation

Contractor

DrywallMetal Framing

PaintingMillworkCeilings

BIM 2.0 –

AnalysisRaymond Group

Orange, CAConcord, CALas Vegas, NVSan Diego, CA

The work of the Raymond Group clearly shows how BIM is changing approaches, roles and 

responsibilities within the AEC professions.  

25

Page 55: BIM 1.0, BIM 2.0, BIM 3.0 2010 Update. BIM 1.0, BIM 2.0, BIM 3.0 2010 Update. I gave a presentation at the 2010 AIA National Convention earlier this year. That Power Point presentation

BIM 2.0 –

Analysis

Disney Concert Hall –

Founders Room ‐

2003

Raymond Group

This space presented a challenge for creating the contract documents necessary for the workers 

to build the space.  They turned to BIM and now have a 20+ person modeling operation.

26

Page 56: BIM 1.0, BIM 2.0, BIM 3.0 2010 Update. BIM 1.0, BIM 2.0, BIM 3.0 2010 Update. I gave a presentation at the 2010 AIA National Convention earlier this year. That Power Point presentation

BIM 2.0 –

Analysis

Disney Concert Hall –

Founders Room ‐

2003

Raymond Group

This space presented a challenge for creating the contract documents necessary for the workers 

to build the space.  They turned to BIM and now have a 20+ person modeling operation.

26

Page 57: BIM 1.0, BIM 2.0, BIM 3.0 2010 Update. BIM 1.0, BIM 2.0, BIM 3.0 2010 Update. I gave a presentation at the 2010 AIA National Convention earlier this year. That Power Point presentation

BIM 2.0 –

Analysis

City Center – Crystals ‐

2010

Raymond Group

They recently completed this space in Las Vegas.  They used BIM to create the contract 

documents necessary to plan, cost, and inform their workers.

27

Page 58: BIM 1.0, BIM 2.0, BIM 3.0 2010 Update. BIM 1.0, BIM 2.0, BIM 3.0 2010 Update. I gave a presentation at the 2010 AIA National Convention earlier this year. That Power Point presentation

BIM 2.0 –

AnalysisRaymond Group

The green mass model was created by the architect, Raymond created  the BIM model based 

upon this sketch and the structural components.  They added the “architecture”, discovered 

conflicts and eventually added in other trades elements (lighting, railings, access panels, etc.)

28

Page 59: BIM 1.0, BIM 2.0, BIM 3.0 2010 Update. BIM 1.0, BIM 2.0, BIM 3.0 2010 Update. I gave a presentation at the 2010 AIA National Convention earlier this year. That Power Point presentation

BIM 2.0 –

AnalysisRaymond Group

The green mass model was created by the architect, Raymond created  the BIM model based 

upon this sketch and the structural components.  They added the “architecture”, discovered 

conflicts and eventually added in other trades elements (lighting, railings, access panels, etc.)

28

Page 60: BIM 1.0, BIM 2.0, BIM 3.0 2010 Update. BIM 1.0, BIM 2.0, BIM 3.0 2010 Update. I gave a presentation at the 2010 AIA National Convention earlier this year. That Power Point presentation

BIM 2.0 –

AnalysisRaymond Group

The green mass model was created by the architect, Raymond created  the BIM model based 

upon this sketch and the structural components.  They added the “architecture”, discovered 

conflicts and eventually added in other trades elements (lighting, railings, access panels, etc.)

28

Page 61: BIM 1.0, BIM 2.0, BIM 3.0 2010 Update. BIM 1.0, BIM 2.0, BIM 3.0 2010 Update. I gave a presentation at the 2010 AIA National Convention earlier this year. That Power Point presentation

Exposed Steel

BIM 2.0 –

AnalysisTheir model became “the 

model”

Coordination

Lighting Analysis

Visualization

Raymond Group

Their model became the most 

complete and accurate model 

of the space, the model 

became the foundation for 

coordination, lighting and 

visualization.

29

Page 62: BIM 1.0, BIM 2.0, BIM 3.0 2010 Update. BIM 1.0, BIM 2.0, BIM 3.0 2010 Update. I gave a presentation at the 2010 AIA National Convention earlier this year. That Power Point presentation

Exposed Steel

BIM 2.0 –

AnalysisTheir model became “the 

model”

Coordination

Lighting Analysis

Visualization

Raymond Group

Their model became the most 

complete and accurate model 

of the space, the model 

became the foundation for 

coordination, lighting and 

visualization.

29

Page 63: BIM 1.0, BIM 2.0, BIM 3.0 2010 Update. BIM 1.0, BIM 2.0, BIM 3.0 2010 Update. I gave a presentation at the 2010 AIA National Convention earlier this year. That Power Point presentation

Exposed Steel

BIM 2.0 –

AnalysisTheir model became “the 

model”

Coordination

Lighting Analysis

Visualization

Raymond Group

Their model became the most 

complete and accurate model 

of the space, the model 

became the foundation for 

coordination, lighting and 

visualization.

29

Page 64: BIM 1.0, BIM 2.0, BIM 3.0 2010 Update. BIM 1.0, BIM 2.0, BIM 3.0 2010 Update. I gave a presentation at the 2010 AIA National Convention earlier this year. That Power Point presentation

Exposed Steel

BIM 2.0 –

AnalysisTheir model became “the 

model”

Coordination

Lighting Analysis

Visualization

Raymond Group

Their model became the most 

complete and accurate model 

of the space, the model 

became the foundation for 

coordination, lighting and 

visualization.

29

Page 65: BIM 1.0, BIM 2.0, BIM 3.0 2010 Update. BIM 1.0, BIM 2.0, BIM 3.0 2010 Update. I gave a presentation at the 2010 AIA National Convention earlier this year. That Power Point presentation

Exposed Steel

BIM 2.0 –

AnalysisTheir model became “the 

model”

Coordination

Lighting Analysis

Visualization

Raymond Group

Their model became the most 

complete and accurate model 

of the space, the model 

became the foundation for 

coordination, lighting and 

visualization.

29

Page 66: BIM 1.0, BIM 2.0, BIM 3.0 2010 Update. BIM 1.0, BIM 2.0, BIM 3.0 2010 Update. I gave a presentation at the 2010 AIA National Convention earlier this year. That Power Point presentation

BIM 2.0 –

AnalysisRaymond Group

The contract 

documents 

include 

perspectives, 

and extensive 

details for 

construction.  

The BIM 

model 

supports 

prefabrication 

of many wall 

sections.  

30

Page 67: BIM 1.0, BIM 2.0, BIM 3.0 2010 Update. BIM 1.0, BIM 2.0, BIM 3.0 2010 Update. I gave a presentation at the 2010 AIA National Convention earlier this year. That Power Point presentation

BIM 2.0 –

AnalysisRaymond Group

The contract 

documents 

include 

perspectives, 

and extensive 

details for 

construction.  

The BIM 

model 

supports 

prefabrication 

of many wall 

sections.  

30

Page 68: BIM 1.0, BIM 2.0, BIM 3.0 2010 Update. BIM 1.0, BIM 2.0, BIM 3.0 2010 Update. I gave a presentation at the 2010 AIA National Convention earlier this year. That Power Point presentation

BIM 2.0 –

AnalysisRaymond Group

The contract 

documents 

include 

perspectives, 

and extensive 

details for 

construction.  

The BIM 

model 

supports 

prefabrication 

of many wall 

sections.  

30

Page 69: BIM 1.0, BIM 2.0, BIM 3.0 2010 Update. BIM 1.0, BIM 2.0, BIM 3.0 2010 Update. I gave a presentation at the 2010 AIA National Convention earlier this year. That Power Point presentation

BIM 2.0 –

AnalysisRaymond Group

The contract 

documents 

include 

perspectives, 

and extensive 

details for 

construction.  

The BIM 

model 

supports 

prefabrication 

of many wall 

sections.  

30

Page 70: BIM 1.0, BIM 2.0, BIM 3.0 2010 Update. BIM 1.0, BIM 2.0, BIM 3.0 2010 Update. I gave a presentation at the 2010 AIA National Convention earlier this year. That Power Point presentation

BIM 2.0 –

AnalysisRaymond Group

The contract 

documents 

include 

perspectives, 

and extensive 

details for 

construction.  

The BIM 

model 

supports 

prefabrication 

of many wall 

sections.  

30

Page 71: BIM 1.0, BIM 2.0, BIM 3.0 2010 Update. BIM 1.0, BIM 2.0, BIM 3.0 2010 Update. I gave a presentation at the 2010 AIA National Convention earlier this year. That Power Point presentation

BIM 2.0 –

AnalysisRaymond Group

The contract 

documents 

include 

perspectives, 

and extensive 

details for 

construction.  

The BIM 

model 

supports 

prefabrication 

of many wall 

sections.  

30

Page 72: BIM 1.0, BIM 2.0, BIM 3.0 2010 Update. BIM 1.0, BIM 2.0, BIM 3.0 2010 Update. I gave a presentation at the 2010 AIA National Convention earlier this year. That Power Point presentation

DPR Construction

CATXAZNCVADCFL

BIM 2.0 –

AnalysisIPD – Integrated Project Delivery

Architect/Engineer

Building Product Manufacturer /Supplier / Distributor

Contractor & Sub-Contractors

BuildingOwner

Pre‐Construction Detailed BIM ModelsRelationships and Responsibilities

Conflict Resolution

Substantial Cost Savings

Prefabrication Scheduling and Sequencing

DPR has multiple BIM projects.  They use the “big room”

concept during the contract 

document phase where the owner, architect, engineers, general contractor and main trade 

contractors work collaboratively to improve the project, reduce costs and resolve conflicts. 

31

Page 73: BIM 1.0, BIM 2.0, BIM 3.0 2010 Update. BIM 1.0, BIM 2.0, BIM 3.0 2010 Update. I gave a presentation at the 2010 AIA National Convention earlier this year. That Power Point presentation

BIM 2.0 –

2009 & 2010 Recap

2009 • Integrates with BIM • Reduces analysis time

• A&E’s

just starting to use• Integration to BIM software• Accuracy of Results

2010 • Integration is getting better• More use of the BIM project• IPD

• Adoption Speed• Redefine Roles

Year                                 Value

Concerns                

32

Page 74: BIM 1.0, BIM 2.0, BIM 3.0 2010 Update. BIM 1.0, BIM 2.0, BIM 3.0 2010 Update. I gave a presentation at the 2010 AIA National Convention earlier this year. That Power Point presentation

BIM 3.0 –

Simulation

My Definitions

1. Simultaneous display of 

multiple data results when the 

model is changed

2. User controlled realtime 3D movement

3. Highly graphicalanalytical results

Information DashboardConstruction Cost      $7,234,000Energy Cost/yr           $343,000Time to Construct       28 MonthsCode Issues               12Conflicts                     474

33

It could be debated that there is no difference between analysis

and simulation.  The 

definitions above separate analysis from simulation.  The “dashboard”

example predicts a 

future where the designer is provided real time information as they work.

Page 75: BIM 1.0, BIM 2.0, BIM 3.0 2010 Update. BIM 1.0, BIM 2.0, BIM 3.0 2010 Update. I gave a presentation at the 2010 AIA National Convention earlier this year. That Power Point presentation

DOC

Construction

Project 

Management

Estimating

MACT

BIM 3.0 –

Simulation

34

The slides show how the construction company uses the BIM project to plan their construction.  

Notice that the information at the top is tracking against their

spreadsheet of activities.

Page 76: BIM 1.0, BIM 2.0, BIM 3.0 2010 Update. BIM 1.0, BIM 2.0, BIM 3.0 2010 Update. I gave a presentation at the 2010 AIA National Convention earlier this year. That Power Point presentation

DOC

Construction

Project 

Management

Estimating

MACT

BIM 3.0 –

Simulation

34

The slides show how the construction company uses the BIM project to plan their construction.  

Notice that the information at the top is tracking against their

spreadsheet of activities.

Page 77: BIM 1.0, BIM 2.0, BIM 3.0 2010 Update. BIM 1.0, BIM 2.0, BIM 3.0 2010 Update. I gave a presentation at the 2010 AIA National Convention earlier this year. That Power Point presentation

DOC

Construction

Project 

Management

Estimating

MACT

BIM 3.0 –

Simulation

34

The slides show how the construction company uses the BIM project to plan their construction.  

Notice that the information at the top is tracking against their

spreadsheet of activities.

Page 78: BIM 1.0, BIM 2.0, BIM 3.0 2010 Update. BIM 1.0, BIM 2.0, BIM 3.0 2010 Update. I gave a presentation at the 2010 AIA National Convention earlier this year. That Power Point presentation

DOC

Construction

Project 

Management

Estimating

MACT

BIM 3.0 –

Simulation

34

The slides show how the construction company uses the BIM project to plan their construction.  

Notice that the information at the top is tracking against their

spreadsheet of activities.

Page 79: BIM 1.0, BIM 2.0, BIM 3.0 2010 Update. BIM 1.0, BIM 2.0, BIM 3.0 2010 Update. I gave a presentation at the 2010 AIA National Convention earlier this year. That Power Point presentation

DOC

Construction

Project 

Management

Estimating

MACT

BIM 3.0 –

Simulation

34

The slides show how the construction company uses the BIM project to plan their construction.  

Notice that the information at the top is tracking against their

spreadsheet of activities.

Page 80: BIM 1.0, BIM 2.0, BIM 3.0 2010 Update. BIM 1.0, BIM 2.0, BIM 3.0 2010 Update. I gave a presentation at the 2010 AIA National Convention earlier this year. That Power Point presentation

DOC

Construction

Project 

Management

Estimating

MACT

BIM 3.0 –

Simulation

34

The slides show how the construction company uses the BIM project to plan their construction.  

Notice that the information at the top is tracking against their

spreadsheet of activities.

Page 81: BIM 1.0, BIM 2.0, BIM 3.0 2010 Update. BIM 1.0, BIM 2.0, BIM 3.0 2010 Update. I gave a presentation at the 2010 AIA National Convention earlier this year. That Power Point presentation

WATG

Architects

HonoluluIrvineLondonOrlandoSeattle

Singapore

BIM 3.0 –

Simulation

35

This firm designs massive projects throughout 

the world and examples of their work could be 

shown throughout this presentation, but the 

following slides look a how they are simulating 

the environments they are designing in real 

time.

Page 82: BIM 1.0, BIM 2.0, BIM 3.0 2010 Update. BIM 1.0, BIM 2.0, BIM 3.0 2010 Update. I gave a presentation at the 2010 AIA National Convention earlier this year. That Power Point presentation

BIM 3.0 –

SimulationWATG

Immersive Box

36

The viewer stands in a 

space with walls, floor and 

ceiling upon which the 

images of the space are 

projected.  The viewer is 

able to look and move 

around the space.  The 

images are in 3D to add 

realism.

Page 83: BIM 1.0, BIM 2.0, BIM 3.0 2010 Update. BIM 1.0, BIM 2.0, BIM 3.0 2010 Update. I gave a presentation at the 2010 AIA National Convention earlier this year. That Power Point presentation

BIM 3.0 –

SimulationWATG

Video Game

37

Gamming software can now convert the BIM model into the game environment.  The viewer 

can move around the space as desired.  The software is inexpensive and the import process 

relatively quick.

Page 84: BIM 1.0, BIM 2.0, BIM 3.0 2010 Update. BIM 1.0, BIM 2.0, BIM 3.0 2010 Update. I gave a presentation at the 2010 AIA National Convention earlier this year. That Power Point presentation

BIM 3.0 –

SimulationWATG

Video Game

37

Gamming software can now convert the BIM model into the game environment.  The viewer 

can move around the space as desired.  The software is inexpensive and the import process 

relatively quick.

Page 85: BIM 1.0, BIM 2.0, BIM 3.0 2010 Update. BIM 1.0, BIM 2.0, BIM 3.0 2010 Update. I gave a presentation at the 2010 AIA National Convention earlier this year. That Power Point presentation

BIM 3.0 –

SimulationWATG

Video Game

37

Gamming software can now convert the BIM model into the game environment.  The viewer 

can move around the space as desired.  The software is inexpensive and the import process 

relatively quick.

Page 86: BIM 1.0, BIM 2.0, BIM 3.0 2010 Update. BIM 1.0, BIM 2.0, BIM 3.0 2010 Update. I gave a presentation at the 2010 AIA National Convention earlier this year. That Power Point presentation

BIM 3.0 –

SimulationWATG

Video Game

37

Gamming software can now convert the BIM model into the game environment.  The viewer 

can move around the space as desired.  The software is inexpensive and the import process 

relatively quick.

Page 87: BIM 1.0, BIM 2.0, BIM 3.0 2010 Update. BIM 1.0, BIM 2.0, BIM 3.0 2010 Update. I gave a presentation at the 2010 AIA National Convention earlier this year. That Power Point presentation

BIM 3.0 –

2009 & 2010 Recap

2009 • Little to show • Little to show

2010 • A view into the future• Getting exciting

• Manual and time consuming 

Year                                 Value

Concerns                

38

Page 88: BIM 1.0, BIM 2.0, BIM 3.0 2010 Update. BIM 1.0, BIM 2.0, BIM 3.0 2010 Update. I gave a presentation at the 2010 AIA National Convention earlier this year. That Power Point presentation

Conclusion – BIM Changes EverythingThe BIM model is the index to all Data (attached or linked)

Data is power

BIM Will Change Everything

How professionals work

How we interact with each other

How we interact with BPM’s

How we interact with contractors

How we interact with the owner

How Facility Managers get and maintain data

How building operators get and maintain data

The education of AEC Professionals

39

The “standard of practice”

for architects has changed throughout the decades, they used to

do the engineering, their contract documents used to only include a few sheets.  We are at 

the threshold of a new era.  The next few years will redefine the “Standard of Practice”