24
ELECTRICITY DISTRIBUTION OPERATORS VIEW Benin Electricity Distribution Company (BEDC)

Benin Electricity Distribution Company

Embed Size (px)

Citation preview

Page 1: Benin Electricity Distribution Company

ELECTRICITY DISTRIBUTION OPERATORS VIEW

Benin Electricity Distribution Company (BEDC)

Page 2: Benin Electricity Distribution Company

Presentation Flow

o Nigerian Power Landscape

o Power Sector Reform

o Investment Opportunities

2Benin Disco

o Way Forward- Critical Issues for Success

o Investment Opportunities

oActions taken so far

oAbout BEDC

Page 3: Benin Electricity Distribution Company

� Publicly-owned Utility

� Highly centralized vertically integrated ( Generation, Transmission and Distribution

under one structure)

� Poor Operational and Commercial Performance

Nigerian Power Sector – Pre 1999

� Dwindling FG funding from 1980 to year 2000

� No new electric power infrastructure commenced and completed between

1989-1999.

� The last transmission line built was in 1987 while distribution sector did not

receive any major investment

� Absence of a service delivery culture

� Significant Aggregate Technical Commercial and Collection levels in excess of 50%.

� Little impetus toward reform (significant resistance to change) despite the above3

Page 4: Benin Electricity Distribution Company

Nigeria’s Power Situation is particularly precarious…

Nigeria’s per capita electricity consumption is one of the lowest in the world

accounting for only 3% of South Africa’s.

•As at October 2013, the

peak generation supplied

by Nigeria’s PHCN was

4,500MW for an estimated

High Cost of Lost

GDP

High Self

Generation Cost

Low Generation

capacity

• Self-generation of

electricity (from diesel and

petrol generators) is

conservatively estimated at

• Stalled expansion in

Nigeria’s capacity

combined with high cost

of diesel and petrol 4,500MW for an estimated

population of 150 million

people

− South Africa has 40,000

MW of grid-based

generating capacity for a

population of 50 million

people

conservatively estimated at

a minimum of 6,000 MW

i.e. more than twice the

average output from the

grid during 2009.

− The poor pay N80/kWh

− Manufacturers pay in

excess of N60/kWh on

diesel or LPFO

generation

− The rest pay N50 –

70/kWh on self

generation

of diesel and petrol

generation has severely

crippled the growth in the

countries productive and

commercial industries..

• If situation were to

persist, the cost by 2020 in

terms of GDP would be

around USD 130 Bn 4

Page 5: Benin Electricity Distribution Company

� Passage of The Electricity (Amendment) Decree 1998 and the NEPA (Amendment)

Act 1998 , terminating the monopoly status of NEPA and inviting private sector

participation in the electricity sector.

� The Electric Power Reform Implementation Committee (EPIC) was inaugurated by

BPE and resulted in FEC approving the National Electric Power Policy in

September 2001, which recommended:

• Establishment of a sector regulator.

Nigerian Power Sector Reform

• Establishment of a sector regulator.

• Privatization of the electric power sector

• A market trading design and new rules, codes and processes

� In March 2005 the Federal legislature passed the Electric Power Sector Reform

Act. The Act outlined the framework of the reform as follows:

� Unbundle the state owned power entity into generation, transmission and

distribution

� Provide for the transfer of assets , liabilities and staff of NEPA to PHCN and

then to successor generation, transmission and distribution companies

� Create a competitive market for electricity services in Nigeria

� Set up an independent regulator

5

Page 6: Benin Electricity Distribution Company

Key reform activities for establishing an electricity market

Enabling Legislation2001-2005

Unbundling Process

Power Sector Reform: Reform Roadmap

6

Regulation Process

Market Structure

Privatisation

Page 7: Benin Electricity Distribution Company

� FGN privatisation of unbundled PHCN companies through core investor

sale of 60% of government equity in the 11 DisCos and 4 Therma GenCos

with granting of concessions to 2 Hydro GenCos.

� Multi Year (15) Tariff Order, MYTO 2, promulgated by the Regulator aimed

at:

Power Sector Reform: Privatisation So Far

� Incentives for rapid ATCC losses reduction

� Encouraging capital investment

� Cost recovery

� Return on Equity of 29%

� New owners took over on 1st Nov., 2013

7

Page 8: Benin Electricity Distribution Company

� Huge suppressed demand for electricity (as evidenced by the large amount of costly selfgeneration)

� Low Electricity production per capita (Currently at about 103.81kwk per capital

consumption)

Country Population Per Capital Consumption(kwh)

� South Africa 49 million 4,222.46

� Egypt 83.6million 1,383.71

� Ghana 24.6million 248.33

� Nigeria 170million 103.81

Growth Prospects of Nigerian Power Sector

� Nigeria 170million 103.81

8

The rule of thumb for any developed industrial nation is that at least

1 gigawatt (i.e. 1,000 megawatts) of electricity generation and consumption is required for every 1 million head of population

Page 9: Benin Electricity Distribution Company

� Investment in Generation

� Privatized 6 GenCos

� Privatized NIPP Assets

� IPPs

� Embedded Generation

� Renewable Energy

� Investment in Transmission

Power Sector: Investment Opportunities

� Investment in Transmission

� Strengthening of TCN network Infrastructure

� PPP Model – 5 major contract signed at the Power Finance Conference

� Investment in DisCos:

� Equity participation/Refinancing of the privatized 11 DisCos

� Investment in CAPEX for network rehabilitation and Refurbishment, network upgrade

and expansion

� IT Intervention and Automation

� Investment in Support Services like manufacturing of Poles, Transformers , Meters, etc.

Nigerian Local Content is being encouraged by the Regulator in these areas

9

Page 10: Benin Electricity Distribution Company

� DisCos are critical to the viability of the sector because revenue can only

be realized or collected through the distribution sub sectors .

� Issue of financial viability/ guaranteed income stream must therefore be

addressed at this level.

Distribution Sub Sector

� The investors are thus expected to ensure that the integrity of the

network is improved through maintenance and investment in

rehabilitation, reinforcement and expansion; invest in modernization and

technology upgrade especially Billing Systems, SCADA and GIS; expand

metering coverage as per agreed plan.

10

Page 11: Benin Electricity Distribution Company

Monthly Remittance to MO

• Eko

• Ikeja

• Ibadan

• Kano

• 97.65%

• 87.55%

• 65.37%

• 62.97%

DISCOBase Line Remittance

(% of MO Bill)% Power Allocation

� 11%

� 15%

� 13%

� 8%Kano

• Abuja

• PH

• Enugu

• Benin

• Kaduna

• Jos

• Yola

62.97%

• 53.5%

• 47.45%

• 41.24%

• 37.88%

• 33.16%

• 20.70%

• 0%

� 8%

� 11.5%

� 6.50%

� 9%

� 9%

� 8%

� 5.5%

� 3.5%

Page 12: Benin Electricity Distribution Company

Current Landscape & Reality

NIGERIA

BENIN ELECTRICITY

DISTRIBUTION COMPANY

States- 36 state +FCT

Local Govt- 774

Households- 32 million

Population- 160 million

Electricity Customers- 4 million

State Involved- 4 Edo, Delta, Ondo, Ekiti

Local Govts - 77

Households - 4.6 million

Population - 13.2 million

Electricity Customers- 770,600

12

Electricity Customers- 4 million

Access to power – 12.5 %

Energy Avail. – 2,500mw - 4,000 mw

24/7 Ideal Energy Avail - 160,000 mw

FGN Targeted 2020 Energy Avail- 20,000 mw

Current Average Daily Power

Avail. (hrs) – Less than 3hrs

Electricity Customers- 770,600

Access to power – 18.9 %

Energy Available- 625 mw

24/7 Ideal Energy Availability – 13,000 mw

Current Av. Daily Power Avail – 17hrs

ATTC Loss - 52%

Ave. Cost of Power - N13.86 per kwh

Ave Sale Price - N 7.89per kwh

Page 13: Benin Electricity Distribution Company

Licensed IPPs

• Azura Power West Africa Limited

License: Generation On-Grid 450MW

• Contour Global Solutions (Nig) Ltd

License: Generation Off-Grid 7MW

• Delta Electric Power Limited

License: Generation On-Grid 116MW

NIPP Power Plants

• Ihovbor Power Station (NIPP)

License: Generation On-Grid 450MW

• Ogorode Generation Co. Ltd (NIPP)License:

Generation On-Grid 450MW

• Omotosho Power Station (NIPP)

License: Generation On-Grid 500MW

POTENTIAL POWER SUPPLY TO BEDC - Power Stations within BEDC Geographical

Coverage

• Ethiope Energy Limited

License: Generation On-Grid 2,800MW

• Nigerian Agip Oil Co. Ltd

License: Generation On-Grid 480MW

TOTAL IPP – 3853MW

PHCN Successor Generation Companies

• Ughelli Power Plc

License: Generation On-Grid 942MW

• Sapele Power Plc (NIPP Expanded)

License: Generation On-Grid 1,020MW

TOTAL NIPP - 3362

13In addition, BEDC is a transmission hub

This is out of a total of 5153 mw from Govt initiatives

Page 14: Benin Electricity Distribution Company

� Located in Transmission Network Hub

� Allocated 9% but gets up to 12%

� Availability Uptime– Highest in the Country

BEDC Strategic Positioning

STATE 11KV FEEDER AVAILABILITY

DATE

STATE

AV. AVAIL.

(HRS)

EDO 12.17

� Largest Gas producing terrain- key source

of cheapest power- Delta State

� Has largest number of power plants –

Most Genco’s would prefer sales to closer

14

EDO 12.17

DELTA 10.09

ONDO 7.60

EKITI 11.52

STATE 33KV FEEDER

AVAILABILITY

DATE

AV. AVAIL.

(HRS)

STATE

EDO 19.52

DELTA 19.89

ONDO 10.48

EKITI 19.44

Most Genco’s would prefer sales to closer

distribution companies to reduce

technical losses

Page 15: Benin Electricity Distribution Company

• Network Condition:.– Aged, Undersized & over extended High Tension/Low Tension lines.– Overloaded Feeders and Transformers– Obsolete & faulty switchgears.– Poor maintenance practices– Poor Health and Safety Practice– High level of losses

• Customers issues:– Over Billing of customers– No service orientation to customers– Staff collecting money illegal from customers– Illegal Connection & stealing of power by customers– Inadequate metering

Status At Takeover

– Inadequate metering– Inadequate Power supply

• Technology & Automation intervention issues– Low level of Information Technology application.– Obsolete and non integrated ICT system in place.– Stand Alone Billing Centres – No Website, E-mail, Customer Information System, ICT tools available.– Absence of IT intervention like CRM, ERP, SCADA, DMS, OMS, GIS etc.

• Finance & Accounts:– Manual Accounting System– Decentralized Payroll System– Manual Audit & Internal Control System

Page 16: Benin Electricity Distribution Company

• Conclusion– Net work is in deplorable state– Customer are not being served– Public is expecting value for money– Investors are expected to change things massively and

dramatically

Massive investment of over N 45billion is required over a

BEDC Challenges and Issues Cont’d

Massive investment of over N 45billion is required over a sustained period before positive results can start to be visible

Page 17: Benin Electricity Distribution Company

� BEDC management focus is to address the rot in asset and to reposition the company in the path of :

� Providing good service to the customers

� Ensuring operational viability

� Ensuring financial viability

� Meeting the requirements of the regulators, especially NERC

� Having well trained, motivated and highly competent workforce

Management Focus

� However the problem of over 25years will take time to clear up

� This requires dedicated, honest, experience and competent staff who will put customer first and be ready to work hard.

� It is a journey that must show continuous improvement.

17

Page 18: Benin Electricity Distribution Company

� Customer Re-registration and Enumeration ( Know Your Customer- KYC) has commenced

� Call Centre and back-end complaint tracking solution currently being implemented.

� Website up with information to customers about BEDC an access to submit complaints

� The first publication of BEDC Digest, a fortnightly BEDC news already out

� The NERC Forum Office for lodging of complaints to the regulator currently being worked on and undergoing renovation

Action so far taken on Customer Care

� Customer Enlightenment program in major radio stations is ongoing

� Online Payment System to create payment convenience for customers on test run

� Improvement in power supply by monitoring of uptime and transmission related issues commenced; and setting turnaround benchmark on faults resolution also commenced

� Improvement in Safety Standards through better awareness for staff and public has commenced

� Regular line trace clearing and maintenance of injection substations to reduce power outage due feeder tripping has commenced

18

Page 19: Benin Electricity Distribution Company

� Technical Audit of High Value Customers has commenced

� Installation of Check meters and Boundary Metering commenced

� All Injection Stations in Edo States now metered

� Metering of Injection Stations in Delta States ongoing and expected to be completed this month

� Metering of Injection Stations in Ondo & Ekiti expected to commenced next month.

� Metering of Distribution 8000 Transformers is to commence in June, 2014

Actions taken on Technical & Commercial Loss Reduction

� Metering of Distribution 8000 Transformers is to commence in June, 2014

� Pilot Enumeration of Customers on a feeder along substations, Uprisers & Acct. Officers done. This will help reduce overloading and power theft

� Pilot Outsourcing of Revenue Drive ( Disconnection & Reconnection)has commenced

� Replacement parts and line materials identification for network maintenance and stocking up has commenced

� Intensify Preventive Maintenance for effectiveness and reduction in tripping is about to commence

19

Page 20: Benin Electricity Distribution Company

� Replacement and upgrade of overloaded power transformers and Installation/Commissioning of various power stations

� Out of 36 NIPPs projects existing, already commissioned 6 NIPP Projects within the network to improve supply availability and will soon commission another 3.

� Metering:

� HT Meter Replacement

Action on Loss Reduction Contd.

� HT Meter Replacement

� Selective Metering for Illegal Customers

� Mass Metering of Non MD customers to commence soon

� Criminalize Energy Theft with strict enforcement

� List of customers for name and shame currently being compiled and will be published

� Zero Tolerance for Non Payment of Bills & Vandalisation of Power Installations by any Community

20

Page 21: Benin Electricity Distribution Company

� In order to make progress customers need to pay for power used. Only 48% of power bill is currently being collected in Edo. High level of power theft and bypass is taking place.

� Over 8,000 backlog of meters paid by customers (in Edo, Delta, Ondo, Ekiti) under previous regime not serviced need to be sorted out

� Some Staff benefits existing without fund backing by previous management need to be sorted out

Challenges

� High volume (30%- 200000) of estimated billing need attention inherited need to be sorted out over time

� Contingent liabilities/ Judgment debts arising from pre takeover actions need to be sorted out

� Customer enlightenment on various issues need to be done eg,� Estimated billing

� Fixed Charge

� Obsolete meters

� AND MANY MORE…….

21

Page 22: Benin Electricity Distribution Company

� As at today:

� FGN /BPE have collected money- total of $ 2.6 billion from all investors (Gencos &

Discos) & is SMILING

� Most staff of PHCN have collected money- total of N 380 billion as severance pay & are

SMILING

� Union has collected N6billion to N7billion as their share of workers benefit & SMILING

� Core investors are out of money and paid for assets that they are only starting to know

about 9months after they should have had access. They are NOT SMILING

Conclusion

� Public is expecting drastic improvement in power availability overnight- They are NOT

SMILING

� Findings by all investors have indicated that several of the data given to the investors were

wrong and inflated (customer base, ATC&C Loss level

� The above applies that tariff structure was wrong and will eventually have to increase if

investment is to take place

� The current interim rule had to be introduced because several parameters for TEM is not yet

in place 22

Page 23: Benin Electricity Distribution Company

� 6MONTHS SHADOW MANAGEMENT THAT WAS NOT ALLOWED TO START BASED ON AGREED CONTRACT IN FEBRUARY 2013 ONLY JUST BEGONE ON 1ST

NOVEMBER 2013 FOR ALL GEMCOS AND DISCOS

� ROT OF OVER 25 YEARS CANNOT BE WIPED OUT WITHIN A SHORT TIME

� PUBLIC OUTCRY IS EXPECTED TO FIRST INCREASE AS WE ATTEMPT TO REARRANGE THE SYSTEM

Conclusion

REARRANGE THE SYSTEM

� WE ALL NEED UNDERSTANDING AND SUPPORTIVE STAKEHOLDERS FOR ALL OF US TO MAKE A DIFFERENCE

� PROCESS IS A JOURNEY NOT AN OVERNIGHT RACE !!!!!!!

23

Page 24: Benin Electricity Distribution Company

24