24
ELECTRICITY DISTRIBUTION OPERATORS VIEW Benin Electricity Distribution Company (BEDC)

Electricity Distribution - An Operator's View

Embed Size (px)

DESCRIPTION

the details on power system distribution using port harcourt, Nigeria as a case study

Citation preview

  • ELECTRICITY DISTRIBUTION OPERATORS VIEW

    Benin Electricity Distribution Company (BEDC)

  • Presentation Flow

    o Nigerian Power Landscape

    o Power Sector Reform

    o Investment Opportunities

    2Benin Disco

    o Way Forward- Critical Issues for Success

    o Investment Opportunities

    oActions taken so far

    oAbout BEDC

  • Publicly-owned Utility

    Highly centralized vertically integrated ( Generation, Transmission and Distribution

    under one structure)

    Poor Operational and Commercial Performance

    Nigerian Power Sector Pre 1999

    Dwindling FG funding from 1980 to year 2000

    No new electric power infrastructure commenced and completed between

    1989-1999.

    The last transmission line built was in 1987 while distribution sector did not

    receive any major investment

    Absence of a service delivery culture

    Significant Aggregate Technical Commercial and Collection levels in excess of 50%.

    Little impetus toward reform (significant resistance to change) despite the above3

  • Nigerias Power Situation is particularly precarious

    Nigerias per capita electricity consumption is one of the lowest in the world

    accounting for only 3% of South Africas.

    As at October 2013, the

    peak generation supplied

    by Nigerias PHCN was

    4,500MW for an estimated

    High Cost of Lost

    GDP

    High Self

    Generation Cost

    Low Generation

    capacity

    Self-generation of

    electricity (from diesel and

    petrol generators) is

    conservatively estimated at

    Stalled expansion in

    Nigerias capacity

    combined with high cost

    of diesel and petrol 4,500MW for an estimated

    population of 150 million

    people

    South Africa has 40,000

    MW of grid-based

    generating capacity for a

    population of 50 million

    people

    conservatively estimated at

    a minimum of 6,000 MW

    i.e. more than twice the

    average output from the

    grid during 2009.

    The poor pay N80/kWh

    Manufacturers pay in

    excess of N60/kWh on

    diesel or LPFO

    generation

    The rest pay N50

    70/kWh on self

    generation

    of diesel and petrol

    generation has severely

    crippled the growth in the

    countries productive and

    commercial industries..

    If situation were to

    persist, the cost by 2020 in

    terms of GDP would be

    around USD 130 Bn 4

  • Passage of The Electricity (Amendment) Decree 1998 and the NEPA (Amendment)

    Act 1998 , terminating the monopoly status of NEPA and inviting private sector

    participation in the electricity sector.

    The Electric Power Reform Implementation Committee (EPIC) was inaugurated by

    BPE and resulted in FEC approving the National Electric Power Policy in

    September 2001, which recommended:

    Establishment of a sector regulator.

    Nigerian Power Sector Reform

    Establishment of a sector regulator.

    Privatization of the electric power sector

    A market trading design and new rules, codes and processes

    In March 2005 the Federal legislature passed the Electric Power Sector Reform

    Act. The Act outlined the framework of the reform as follows:

    Unbundle the state owned power entity into generation, transmission and

    distribution

    Provide for the transfer of assets , liabilities and staff of NEPA to PHCN and

    then to successor generation, transmission and distribution companies

    Create a competitive market for electricity services in Nigeria

    Set up an independent regulator

    5

  • Key reform activities for establishing an electricity market

    Enabling Legislation2001-2005

    Unbundling Process

    Power Sector Reform: Reform Roadmap

    6

    Regulation Process

    Market Structure

    Privatisation

  • FGN privatisation of unbundled PHCN companies through core investor

    sale of 60% of government equity in the 11 DisCos and 4 Therma GenCos

    with granting of concessions to 2 Hydro GenCos.

    Multi Year (15) Tariff Order, MYTO 2, promulgated by the Regulator aimed

    at:

    Power Sector Reform: Privatisation So Far

    Incentives for rapid ATCC losses reduction

    Encouraging capital investment

    Cost recovery

    Return on Equity of 29%

    New owners took over on 1st Nov., 2013

    7

  • Huge suppressed demand for electricity (as evidenced by the large amount of costly selfgeneration)

    Low Electricity production per capita (Currently at about 103.81kwk per capital

    consumption)

    Country Population Per Capital Consumption(kwh)

    South Africa 49 million 4,222.46

    Egypt 83.6million 1,383.71

    Ghana 24.6million 248.33

    Nigeria 170million 103.81

    Growth Prospects of Nigerian Power Sector

    Nigeria 170million 103.81

    8

    The rule of thumb for any developed industrial nation is that at least

    1 gigawatt (i.e. 1,000 megawatts) of electricity generation and consumption is required for every 1 million head of population

  • Investment in Generation

    Privatized 6 GenCos

    Privatized NIPP Assets

    IPPs

    Embedded Generation

    Renewable Energy

    Investment in Transmission

    Power Sector: Investment Opportunities

    Investment in Transmission

    Strengthening of TCN network Infrastructure

    PPP Model 5 major contract signed at the Power Finance Conference

    Investment in DisCos:

    Equity participation/Refinancing of the privatized 11 DisCos

    Investment in CAPEX for network rehabilitation and Refurbishment, network upgrade

    and expansion

    IT Intervention and Automation

    Investment in Support Services like manufacturing of Poles, Transformers , Meters, etc.

    Nigerian Local Content is being encouraged by the Regulator in these areas

    9

  • DisCos are critical to the viability of the sector because revenue can only

    be realized or collected through the distribution sub sectors .

    Issue of financial viability/ guaranteed income stream must therefore be

    addressed at this level.

    Distribution Sub Sector

    The investors are thus expected to ensure that the integrity of the

    network is improved through maintenance and investment in

    rehabilitation, reinforcement and expansion; invest in modernization and

    technology upgrade especially Billing Systems, SCADA and GIS; expand

    metering coverage as per agreed plan.

    10

  • Monthly Remittance to MO

    Eko

    Ikeja

    Ibadan

    Kano

    97.65%

    87.55%

    65.37%

    62.97%

    DISCOBase Line Remittance

    (% of MO Bill)% Power Allocation

    11%

    15%

    13%

    8%Kano

    Abuja

    PH

    Enugu

    Benin

    Kaduna

    Jos

    Yola

    62.97%

    53.5%

    47.45%

    41.24%

    37.88%

    33.16%

    20.70%

    0%

    8%

    11.5%

    6.50%

    9%

    9%

    8%

    5.5%

    3.5%

  • Current Landscape & Reality

    NIGERIA

    BENIN ELECTRICITY

    DISTRIBUTION COMPANY

    States- 36 state +FCT

    Local Govt- 774

    Households- 32 million

    Population- 160 million

    Electricity Customers- 4 million

    State Involved- 4 Edo, Delta, Ondo, Ekiti

    Local Govts - 77

    Households - 4.6 million

    Population - 13.2 million

    Electricity Customers- 770,600

    12

    Electricity Customers- 4 million

    Access to power 12.5 %

    Energy Avail. 2,500mw - 4,000 mw

    24/7 Ideal Energy Avail - 160,000 mw

    FGN Targeted 2020 Energy Avail- 20,000 mw

    Current Average Daily Power

    Avail. (hrs) Less than 3hrs

    Electricity Customers- 770,600

    Access to power 18.9 %

    Energy Available- 625 mw

    24/7 Ideal Energy Availability 13,000 mw

    Current Av. Daily Power Avail 17hrs

    ATTC Loss - 52%

    Ave. Cost of Power - N13.86 per kwh

    Ave Sale Price - N 7.89per kwh

  • Licensed IPPs

    Azura Power West Africa Limited

    License: Generation On-Grid 450MW

    Contour Global Solutions (Nig) Ltd

    License: Generation Off-Grid 7MW

    Delta Electric Power Limited

    License: Generation On-Grid 116MW

    NIPP Power Plants

    Ihovbor Power Station (NIPP)

    License: Generation On-Grid 450MW

    Ogorode Generation Co. Ltd (NIPP)License:

    Generation On-Grid 450MW

    Omotosho Power Station (NIPP)

    License: Generation On-Grid 500MW

    POTENTIAL POWER SUPPLY TO BEDC - Power Stations within BEDC Geographical

    Coverage

    Ethiope Energy Limited

    License: Generation On-Grid 2,800MW

    Nigerian Agip Oil Co. Ltd

    License: Generation On-Grid 480MW

    TOTAL IPP 3853MW

    PHCN Successor Generation Companies

    Ughelli Power Plc

    License: Generation On-Grid 942MW

    Sapele Power Plc (NIPP Expanded)

    License: Generation On-Grid 1,020MW

    TOTAL NIPP - 3362

    13In addition, BEDC is a transmission hub

    This is out of a total of 5153 mw from Govt initiatives

  • Located in Transmission Network Hub

    Allocated 9% but gets up to 12%

    Availability Uptime Highest in the Country

    BEDC Strategic Positioning

    STATE 11KV FEEDER AVAILABILITY

    DATE

    STATE

    AV. AVAIL.

    (HRS)

    EDO 12.17

    Largest Gas producing terrain- key source

    of cheapest power- Delta State

    Has largest number of power plants

    Most Gencos would prefer sales to closer

    14

    EDO 12.17

    DELTA 10.09

    ONDO 7.60

    EKITI 11.52

    STATE 33KV FEEDER

    AVAILABILITY

    DATE

    AV. AVAIL.

    (HRS)

    STATE

    EDO 19.52

    DELTA 19.89

    ONDO 10.48

    EKITI 19.44

    Most Gencos would prefer sales to closer

    distribution companies to reduce

    technical losses

  • Network Condition:. Aged, Undersized & over extended High Tension/Low Tension lines. Overloaded Feeders and Transformers Obsolete & faulty switchgears. Poor maintenance practices Poor Health and Safety Practice High level of losses

    Customers issues: Over Billing of customers No service orientation to customers Staff collecting money illegal from customers Illegal Connection & stealing of power by customers Inadequate metering

    Status At Takeover

    Inadequate metering Inadequate Power supply

    Technology & Automation intervention issues Low level of Information Technology application. Obsolete and non integrated ICT system in place. Stand Alone Billing Centres No Website, E-mail, Customer Information System, ICT tools available. Absence of IT intervention like CRM, ERP, SCADA, DMS, OMS, GIS etc.

    Finance & Accounts: Manual Accounting System Decentralized Payroll System Manual Audit & Internal Control System

  • Conclusion Net work is in deplorable state Customer are not being served Public is expecting value for money Investors are expected to change things massively and

    dramatically

    Massive investment of over N 45billion is required over a

    BEDC Challenges and Issues Contd

    Massive investment of over N 45billion is required over a sustained period before positive results can start to be visible

  • BEDC management focus is to address the rot in asset and to reposition the company in the path of :

    Providing good service to the customers

    Ensuring operational viability

    Ensuring financial viability

    Meeting the requirements of the regulators, especially NERC

    Having well trained, motivated and highly competent workforce

    Management Focus

    However the problem of over 25years will take time to clear up

    This requires dedicated, honest, experience and competent staff who will put customer first and be ready to work hard.

    It is a journey that must show continuous improvement.

    17

  • Customer Re-registration and Enumeration ( Know Your Customer- KYC) has commenced

    Call Centre and back-end complaint tracking solution currently being implemented.

    Website up with information to customers about BEDC an access to submit complaints

    The first publication of BEDC Digest, a fortnightly BEDC news already out

    The NERC Forum Office for lodging of complaints to the regulator currently being worked on and undergoing renovation

    Action so far taken on Customer Care

    Customer Enlightenment program in major radio stations is ongoing

    Online Payment System to create payment convenience for customers on test run

    Improvement in power supply by monitoring of uptime and transmission related issues commenced; and setting turnaround benchmark on faults resolution also commenced

    Improvement in Safety Standards through better awareness for staff and public has commenced

    Regular line trace clearing and maintenance of injection substations to reduce power outage due feeder tripping has commenced

    18

  • Technical Audit of High Value Customers has commenced

    Installation of Check meters and Boundary Metering commenced

    All Injection Stations in Edo States now metered

    Metering of Injection Stations in Delta States ongoing and expected to be completed this month

    Metering of Injection Stations in Ondo & Ekiti expected to commenced next month.

    Metering of Distribution 8000 Transformers is to commence in June, 2014

    Actions taken on Technical & Commercial Loss Reduction

    Metering of Distribution 8000 Transformers is to commence in June, 2014

    Pilot Enumeration of Customers on a feeder along substations, Uprisers & Acct. Officers done. This will help reduce overloading and power theft

    Pilot Outsourcing of Revenue Drive ( Disconnection & Reconnection)has commenced

    Replacement parts and line materials identification for network maintenance and stocking up has commenced

    Intensify Preventive Maintenance for effectiveness and reduction in tripping is about to commence

    19

  • Replacement and upgrade of overloaded power transformers and Installation/Commissioning of various power stations

    Out of 36 NIPPs projects existing, already commissioned 6 NIPP Projects within the network to improve supply availability and will soon commission another 3.

    Metering:

    HT Meter Replacement

    Action on Loss Reduction Contd.

    HT Meter Replacement

    Selective Metering for Illegal Customers

    Mass Metering of Non MD customers to commence soon

    Criminalize Energy Theft with strict enforcement

    List of customers for name and shame currently being compiled and will be published

    Zero Tolerance for Non Payment of Bills & Vandalisation of Power Installations by any Community

    20

  • In order to make progress customers need to pay for power used. Only 48% of power bill is currently being collected in Edo. High level of power theft and bypass is taking place.

    Over 8,000 backlog of meters paid by customers (in Edo, Delta, Ondo, Ekiti) under previous regime not serviced need to be sorted out

    Some Staff benefits existing without fund backing by previous management need to be sorted out

    Challenges

    High volume (30%- 200000) of estimated billing need attention inherited need to be sorted out over time

    Contingent liabilities/ Judgment debts arising from pre takeover actions need to be sorted out

    Customer enlightenment on various issues need to be done eg, Estimated billing

    Fixed Charge

    Obsolete meters

    AND MANY MORE.

    21

  • As at today:

    FGN /BPE have collected money- total of $ 2.6 billion from all investors (Gencos &

    Discos) & is SMILING

    Most staff of PHCN have collected money- total of N 380 billion as severance pay & are

    SMILING

    Union has collected N6billion to N7billion as their share of workers benefit & SMILING

    Core investors are out of money and paid for assets that they are only starting to know

    about 9months after they should have had access. They are NOT SMILING

    Conclusion

    Public is expecting drastic improvement in power availability overnight- They are NOT

    SMILING

    Findings by all investors have indicated that several of the data given to the investors were

    wrong and inflated (customer base, ATC&C Loss level

    The above applies that tariff structure was wrong and will eventually have to increase if

    investment is to take place

    The current interim rule had to be introduced because several parameters for TEM is not yet

    in place 22

  • 6MONTHS SHADOW MANAGEMENT THAT WAS NOT ALLOWED TO START BASED ON AGREED CONTRACT IN FEBRUARY 2013 ONLY JUST BEGONE ON 1ST

    NOVEMBER 2013 FOR ALL GEMCOS AND DISCOS

    ROT OF OVER 25 YEARS CANNOT BE WIPED OUT WITHIN A SHORT TIME

    PUBLIC OUTCRY IS EXPECTED TO FIRST INCREASE AS WE ATTEMPT TO REARRANGE THE SYSTEM

    Conclusion

    REARRANGE THE SYSTEM

    WE ALL NEED UNDERSTANDING AND SUPPORTIVE STAKEHOLDERS FOR ALL OF US TO MAKE A DIFFERENCE

    PROCESS IS A JOURNEY NOT AN OVERNIGHT RACE !!!!!!!

    23

  • 24