License #765851 6/28/2011 Fax: 323-233-3557 PROPOSAL SUBMITTED TO: JOB ADDRESS: Underwood Construction 114 E.61 st Street 816 W. 47th Street Los Angeles, CA 90037 Los Angeles, CA Attn: Lindval Underwood We are pleased to submit a quote for the legal removal and disposal of the following Lead Based Painted items as described in the Barr & Clark survey provided dated 3/4/11: Lead Based Paint Removal / Disposal Scope: L- 1. Remove Windows & Frames - $3,972.27 L- 2. Remove Doors & Frames - $2,648.18 L- 3. Remove Exterior Loose/ Flaky Paint - $2,648.18 L- 4. Remove Exterior Components - $1,986.14 L- 5. Remove Foundation Door, Frame & Vents - $662.05 L- 6. Remove Interior Wood Components - $2,648.18 Total Cost Of Above Work: $14,565.00 Fourteen Thousand Five Hundred Sixty Five Dollars. Note: Repair or Replacement of building items removed as a result of our work is excluded. Standard Terms: All salvage rights are ours. Only one (1) equipment mobilization has been included in this estimate. This proposal is valid for 30 days from above date. Upon acceptance of this proposal a mutually acceptable contract must be executed by both parties prior to start of work. 1536 West 25 th Street #248 • San Pedro, CA 90732 • Tel: 310.732.1991 • Fax: 310.832.4989

Basic Template Proposal

  • Upload
    russt2

  • View
    2

  • Download
    0

Embed Size (px)

DESCRIPTION

Proposal form

Citation preview

Page 1: Basic Template Proposal

License #765851

6/28/2011Fax: 323-233-3557 PROPOSAL

SUBMITTED TO: JOB ADDRESS:Underwood Construction 114 E.61st Street816 W. 47th Street Los Angeles, CA 90037

Los Angeles, CA

Attn: Lindval Underwood

We are pleased to submit a quote for the legal removal and disposal of the following Lead Based Painted items as described in the Barr & Clark survey provided dated 3/4/11:

Lead Based Paint Removal / Disposal Scope:

L- 1. Remove Windows & Frames - $3,972.27

L- 2. Remove Doors & Frames - $2,648.18

L- 3. Remove Exterior Loose/ Flaky Paint - $2,648.18

L- 4. Remove Exterior Components - $1,986.14

L- 5. Remove Foundation Door, Frame & Vents - $662.05

L- 6. Remove Interior Wood Components - $2,648.18

Total Cost Of Above Work: $14,565.00 Fourteen Thousand Five Hundred Sixty Five Dollars. Note: Repair or Replacement of building items removed as a result of our work is excluded.

Standard Terms: All salvage rights are ours. Only one (1) equipment mobilization has been included in this estimate. This proposal is valid for 30 days from above date. Upon acceptance of this proposal a mutually acceptable contract must be executed by both parties prior to start of work.

Submitted By:

Russell Taylor . Authorized Representative, National Demolition

1536 West 25th Street #248 • San Pedro, CA 90732 • Tel: 310.732.1991 • Fax: 310.832.4989