19
AHCAL Electronics. Status Commissioning Mathias Reinecke for the AHCAL developers HCAL main meeting Hamburg, Dec. 10th, 2009

AHCAL Electronics. Status Commissioning Mathias Reinecke for the AHCAL developers HCAL main meeting Hamburg, Dec. 10th, 2009

Embed Size (px)

Citation preview

Page 1: AHCAL Electronics. Status Commissioning Mathias Reinecke for the AHCAL developers HCAL main meeting Hamburg, Dec. 10th, 2009

AHCAL Electronics.Status Commissioning

Mathias Reinecke for the AHCAL developersHCAL main meetingHamburg, Dec. 10th, 2009

Page 2: AHCAL Electronics. Status Commissioning Mathias Reinecke for the AHCAL developers HCAL main meeting Hamburg, Dec. 10th, 2009

Mathias Reinecke | HCAL main meeting - Hamburg | Dec. 10th, 2009 | Page 2

Outline

> System Commissioning

Labview DAQ operation

First Results

> Testbeam Preparation

> The Next Generation

> Conclusions and Outlook

Page 3: AHCAL Electronics. Status Commissioning Mathias Reinecke for the AHCAL developers HCAL main meeting Hamburg, Dec. 10th, 2009

Mathias Reinecke | HCAL main meeting - Hamburg | Dec. 10th, 2009 | Page 3

HCAL Base Unit (HBU) and system setup

2 setups in operation

Page 4: AHCAL Electronics. Status Commissioning Mathias Reinecke for the AHCAL developers HCAL main meeting Hamburg, Dec. 10th, 2009

Mathias Reinecke | HCAL main meeting - Hamburg | Dec. 10th, 2009 | Page 4

Tile Assembly – HBUII SPIROC2 area

Alignment ‘Reflector Foil – HBU’

Some positions cannot be assembled(tiles do not fit in)

“mechanics tiles”(cassette construction)

Reflector foil:without cover (blank)still with cover

Page 5: AHCAL Electronics. Status Commissioning Mathias Reinecke for the AHCAL developers HCAL main meeting Hamburg, Dec. 10th, 2009

Mathias Reinecke | HCAL main meeting - Hamburg | Dec. 10th, 2009 | Page 5

Single-Photon Peaks I

100fF PA feedback,50ns shaping, no ‘hold’ sent,ext. trig., SiPM at nom. bias,~9000 entries per curve,one SPIROC2 memory cell used.VCALIB ~ LED light ampl.

Prelim

inary

Page 6: AHCAL Electronics. Status Commissioning Mathias Reinecke for the AHCAL developers HCAL main meeting Hamburg, Dec. 10th, 2009

Mathias Reinecke | HCAL main meeting - Hamburg | Dec. 10th, 2009 | Page 6

Single-Photon Peaks II (reduced SiPM bias)

Gain blue curve: ~70%

100fF PA feedback,50ns shaping,ext. trig., no ‘hold’,~9000 entries per curveone mem-cell used

Prelim

inary

Page 7: AHCAL Electronics. Status Commissioning Mathias Reinecke for the AHCAL developers HCAL main meeting Hamburg, Dec. 10th, 2009

Mathias Reinecke | HCAL main meeting - Hamburg | Dec. 10th, 2009 | Page 7

Single-Photon Peaks III (SPIROC2 SCA test)

Prelim

inary

time between LED triggers: ~40µs

Page 8: AHCAL Electronics. Status Commissioning Mathias Reinecke for the AHCAL developers HCAL main meeting Hamburg, Dec. 10th, 2009

Mathias Reinecke | HCAL main meeting - Hamburg | Dec. 10th, 2009 | Page 8

Single-Photon Peaks III (SPIROC2 SCA test)

Prelim

inary

> Different light amplitudes due to integrated LED system, but reason unknown (no level shifts of GND or VCALIB observed).

> Offset may be due to SCA cells, or due to GND level shifts.

> Without correction, sum of SCA cell results (black curve) should not be used.

Page 9: AHCAL Electronics. Status Commissioning Mathias Reinecke for the AHCAL developers HCAL main meeting Hamburg, Dec. 10th, 2009

Mathias Reinecke | HCAL main meeting - Hamburg | Dec. 10th, 2009 | Page 9

integrated LED system – dynamic range

SPIROC2: 400fF PA feedback, 50ns shaping, results for 18 assembled channels shown

Zoom of Fig. on the left

> LED comp-to-comp spread is large => preselection necessary.

> Dynamic range: Change LED capacitor? VCALIB max = 10V.

Page 10: AHCAL Electronics. Status Commissioning Mathias Reinecke for the AHCAL developers HCAL main meeting Hamburg, Dec. 10th, 2009

Mathias Reinecke | HCAL main meeting - Hamburg | Dec. 10th, 2009 | Page 10

Testbench Labviews – Histogram Building

Choose:Channel 0..35 or all

Memory cell0..15 or all

SPIROC2_2

SPIROC2_1

Result file

Page 11: AHCAL Electronics. Status Commissioning Mathias Reinecke for the AHCAL developers HCAL main meeting Hamburg, Dec. 10th, 2009

Mathias Reinecke | HCAL main meeting - Hamburg | Dec. 10th, 2009 | Page 11

Testbench Labviews – Coherent Noise Analysis

meanvalues(whitepoints)

now:rip offblock capacit.

no coh.noise:circularshape

Page 12: AHCAL Electronics. Status Commissioning Mathias Reinecke for the AHCAL developers HCAL main meeting Hamburg, Dec. 10th, 2009

Mathias Reinecke | HCAL main meeting - Hamburg | Dec. 10th, 2009 | Page 12

Testbeam Synchronization (CALICE DAQ setup)

Concept: M. Wing et al.,hopefully extended correctly

> All timing critical signals are distributed from central DAQ (via CCC).

> All detector units (+DIFs) run synchronously.

Page 13: AHCAL Electronics. Status Commissioning Mathias Reinecke for the AHCAL developers HCAL main meeting Hamburg, Dec. 10th, 2009

Mathias Reinecke | HCAL main meeting - Hamburg | Dec. 10th, 2009 | Page 13

Testbeam Data Taking: Internal Trigger

AHCAL timing scheme for common CALICE testbeam

> Internal Trigger with “Validate_Event”. Pink boxes: deadtime!

> Do we need “Internal trigger mode” without Val_Evt in TB (full clock rate)?

> CALICE DAQ: Synchronize Val_Evt on global clock (multi-DIF synchron.).

Page 14: AHCAL Electronics. Status Commissioning Mathias Reinecke for the AHCAL developers HCAL main meeting Hamburg, Dec. 10th, 2009

Mathias Reinecke | HCAL main meeting - Hamburg | Dec. 10th, 2009 | Page 14

DESY Testbeam Synchronization (Labview setup)

> Synchronization done by temporary hardware signals to/from DIF.

> First: Only one DIF/HBU used. With two HBUs the CCC is needed.

> Readout Speed limited due to USB/Serial Interface.

Page 15: AHCAL Electronics. Status Commissioning Mathias Reinecke for the AHCAL developers HCAL main meeting Hamburg, Dec. 10th, 2009

Mathias Reinecke | HCAL main meeting - Hamburg | Dec. 10th, 2009 | Page 15

DESY Testbeam Synchronization (Labview setup)

LV: LabviewTB: Testbeam ElectronicsHW: Hardware

> Due to shutdown of DESYII: HBU testbeam tests end of Feb 2010.

> External and Internal trigger will be tested.

Page 16: AHCAL Electronics. Status Commissioning Mathias Reinecke for the AHCAL developers HCAL main meeting Hamburg, Dec. 10th, 2009

Mathias Reinecke | HCAL main meeting - Hamburg | Dec. 10th, 2009 | Page 16

The Next Generation (‘final’ ILC setup concept)

Mechanical concept: K. Gadow

Not in scale!

Page 17: AHCAL Electronics. Status Commissioning Mathias Reinecke for the AHCAL developers HCAL main meeting Hamburg, Dec. 10th, 2009

Mathias Reinecke | HCAL main meeting - Hamburg | Dec. 10th, 2009 | Page 17

The Next Generation

Sector Connecting Plate

Cassette (=slab)

HBU

SPIROC

Central Interface Boardwith DIF, CALIB and POWER

Not in scale!!

Page 18: AHCAL Electronics. Status Commissioning Mathias Reinecke for the AHCAL developers HCAL main meeting Hamburg, Dec. 10th, 2009

Mathias Reinecke | HCAL main meeting - Hamburg | Dec. 10th, 2009 | Page 18

The Next Generation

SPIROC LED Flexlead+ tiny connector

Central Interface Board with DIF, CALIB and POWER

Cooling PipeTile with SiPM

Reflector FoilCassette Bottom PlateNot in scale!!

HBU

Height pitchof 20mm possible:

HCAL-W, under invest.

Page 19: AHCAL Electronics. Status Commissioning Mathias Reinecke for the AHCAL developers HCAL main meeting Hamburg, Dec. 10th, 2009

Mathias Reinecke | HCAL main meeting - Hamburg | Dec. 10th, 2009 | Page 19

Conclusions and Outlook

> AHCAL prototype in full operation! 2 setups realized!

> CALICE DAQ (hardware, DIF firmware) still has to be implemented.

we expect a first system Feb/March 2010. Till then: Labview operation.

> SPIROC2a submission Jan2010. Changes under discussion.

> DESY electron-testbeam preparation ongoing.

> Redesigns of AHCAL modules are prepared now.

> Fibre based calibration system in operation as well! (see Ivo’s talk)

> A lot of system’s and SPIROC analogue and digital tests ahead.

all shown analysis have not been completed.

status only demonstrates readiness of the system and system’s tools.