21
HUAWEI TECHNOLOGIES CO., LTD. TP48300/A V100R001 Quick Installation Guide Issue: 09 Part Number: 31504569 Date: 2011-07-28

Agisson TP48300 a Quick Installation Guide V100R001!09!2

Embed Size (px)

Citation preview

Page 1: Agisson TP48300 a Quick Installation Guide V100R001!09!2

8/20/2019 Agisson TP48300 a Quick Installation Guide V100R001!09!2

http://slidepdf.com/reader/full/agisson-tp48300-a-quick-installation-guide-v100r001092 1/21

HUAWEI TECHNOLOGIES CO., LTD.

TP48300/A V100R001

Quick Installation Guide

Issue: 09

Part Number: 31504569

Date: 2011-07-28

Page 2: Agisson TP48300 a Quick Installation Guide V100R001!09!2

8/20/2019 Agisson TP48300 a Quick Installation Guide V100R001!09!2

http://slidepdf.com/reader/full/agisson-tp48300-a-quick-installation-guide-v100r001092 2/211

Prepare the following tools before the installation:

Installing the Cabinet1

Installing the Cabinet on the Rack of Storage Batteries

 According to actual conditions, use one of the following modes to install the cabinet: installing the cabinet on the rack ofstorage batteries, installing the cabinet on the ground, installing the cabinet on the 19-inch open rack, installing the cabinet

on the BTS cabinet. The cabinet must be installed at the place which no more than 3 m distance from the DC load.

Move the cabinet to the installation position on the rack of storage batteries. Align the expansion bolt holes on the base in thefront of the cabinet with the installation holes for the bolt holes on the rack of storage batteries.Fix the bolts into the holes andfasten the bolts.

1

2

Install the rack-mounting ears to the cabinet.

Socket wrench Torque wrench

Insulating gloves

& ESD gloves

Copyright Huawei Technologies Co.,Ltd.2011.All rights reserved.Copyright Huawei Technologies Co.,Ltd.2011.All rights reserved.

Ф12 drill bitFlat-head screwdriver

(M3M4) Adjustable wrench

Key to cabinet

Percussion drill

Wire stripper Ratchet crimp tool Diagonal pliers Paint brush

 Nylon tie

Multimeter 

Insulating tape Marking pen Vacuum cleaner Hydraulic pliers Insulating handle Electric knife

Heat gun

Phillips screwdriver(M3M4)

A-shaped ladder (2 m)

 NOTE

Align thefirst bolt hole on the base with

the bolt hole on the storage rack, and then

install other bolts in the proper holes.

M8 x 16 (4 pcs)

 NOTE

The Flat-head screwdriver, Phillips screwdriver, Adjustable wrench, Torque wrench, and Inner hexagon wrench should be use insulating tape as a wrap.

Page 3: Agisson TP48300 a Quick Installation Guide V100R001!09!2

8/20/2019 Agisson TP48300 a Quick Installation Guide V100R001!09!2

http://slidepdf.com/reader/full/agisson-tp48300-a-quick-installation-guide-v100r001092 3/212

Installing the Cabinet on the Ground

Determine the installation position of the cabinet, and then mark the positions of the holes to be drilled with a marking pen.1

Unit: mm

Drill holes at the hole positions, feed expansion bolts into the holes, and then secure (hammer and then tighten) theexpansion bolts.

2

Install the rack-mounting ears to the cabinet. Place the cabinet on the expansion bolts, and then tighten the bolts.3

Cabinet outline

316

450

Installation hole

4- 10

Unit:mm

52-60

12

Ф8×60 mm

(4pcs)

Nut

Spring washer 

Flat washer 

Expansion tube

Expansiontrough

Cone-headbolt

Installation hole

Rack-mounting ears

Page 4: Agisson TP48300 a Quick Installation Guide V100R001!09!2

8/20/2019 Agisson TP48300 a Quick Installation Guide V100R001!09!2

http://slidepdf.com/reader/full/agisson-tp48300-a-quick-installation-guide-v100r001092 4/213

Installing the Cabinet on the 19-inch Open Rack (IMU)

Fix the rack-mounting ears into the bolt holes at both sides of the cabinet. Ensure that the base of the rack-mounting earsinstall direction faces the front of the cabinet

1

Determine the installation position of the cabinet on the 19-inch open rack, and then install the Ф6 floating nuts at the holesfor bolts. The recommended installation height of the cabinet is 1.5 m. The actual installation height of the cabinet must bedetermined according to the stature of installation personnel and installation requirements.

2

Move the cabinet to the installation position of the 19-inch open rack, and then install the cabinet on the open rack.3

CAUTION

A minimum of three persons are required for safe installation on the 19-inch open rack.

Otherwise, the cabinet may fall and cause injury.

Floating nut

3

Side of the cabinet

2

Ф6×12 mm

(4pcs)

3

Page 5: Agisson TP48300 a Quick Installation Guide V100R001!09!2

8/20/2019 Agisson TP48300 a Quick Installation Guide V100R001!09!2

http://slidepdf.com/reader/full/agisson-tp48300-a-quick-installation-guide-v100r001092 5/214

Installing the Cabinet on the BTS Cabinet

1

Install the conversion board on BTS cabinet.2

Install the rack-mounting ears to the cabinet.

 Align the expansion bolt holes on the base in the front of the cabinet with the installation holes for the bolt on the con-version board.

3

Fix the bolts into the holes and fasten the bolts.4

1

Rack-mounting ears

Operation side

2

Ф10×25 mm

(2pcs)

Ф6×12 mm

(4pcs)

Ф6×12mm(4pcs)

Installing PSU(Optional)2The TP48300/A is configured with two PSUs by default. The rated output current of each PSU is 30A or 50 A. The number ofPSUs depends on actual capacity requirements for the TP48300/A .

Page 6: Agisson TP48300 a Quick Installation Guide V100R001!09!2

8/20/2019 Agisson TP48300 a Quick Installation Guide V100R001!09!2

http://slidepdf.com/reader/full/agisson-tp48300-a-quick-installation-guide-v100r001092 6/215

 

Installing Sensor3Install indoor temperature and humidity sensor.1

Indoor temperature and humidity sensor 

  6  0   m  m

M4 X 35

Expansion Bolt Shelter 

Indoor temperature

and humidity sensor Main equipment

Install battery temperature sensor.2

Connect to battery

Connect to TP48300/A

 NOTE

Humidity and temperature sensor: Install it next to the air inlet of the main equipment and far from the air outlet. Install it at the same height of the air inlet of the

main equipment.

Page 7: Agisson TP48300 a Quick Installation Guide V100R001!09!2

8/20/2019 Agisson TP48300 a Quick Installation Guide V100R001!09!2

http://slidepdf.com/reader/full/agisson-tp48300-a-quick-installation-guide-v100r001092 7/216

 

Installing the PGND Cables4Unlock and open the cabinet door, and then remove the cover plate of the cable window on the top of the cabinet.1

Lead the PGND cables into the cabinet through the cable window, and then route the cables along the panels of the cabinet.2

DC output positive wiring busbar 

LLVD MCB

Monitoring module

Negative pole of the battery

BLVD MCB

 AC input MCB

PSU Ground busbar of the cabinet

 AC surge protector

Cover plate

 NOTE

 Please installing the cabinet according to actual conditions: load power-off tributary using fuse, load power-off tributary using MCB.

The outputs of the TP48300/A can be customized. The picture is for reference only.

Load power-off tributary using fuse

Load power-off tributary using MCB

DC output positive wiring busbar 

LLVD fuse

Monitoring module

Negative pole of the battery

BLVD MCB

 AC input MCB

PSU Ground busbar of the cabinet

 AC surge protector

Page 8: Agisson TP48300 a Quick Installation Guide V100R001!09!2

8/20/2019 Agisson TP48300 a Quick Installation Guide V100R001!09!2

http://slidepdf.com/reader/full/agisson-tp48300-a-quick-installation-guide-v100r001092 8/217

Connect the PGND cables to the ground busbar.3

Bind the PGND cables.4

4

4

33

The ground busbar

Use an insulating handle to remove battery fuses and load power-off fuses.5

  Use an insulating handle to remove battery fuses and set the load power-off MCB to

OFF .

CAUTION

The PGND cables, AC cables, DC cables, signal cables, and

communication cables must be bounded separately.

4

4

3

3

The ground busbar

Load power-off tributary using fuse

Load power-off tributary using MCB

 Load power-off tributary using fuse

Load power-off tributary using MCB

Page 9: Agisson TP48300 a Quick Installation Guide V100R001!09!2

8/20/2019 Agisson TP48300 a Quick Installation Guide V100R001!09!2

http://slidepdf.com/reader/full/agisson-tp48300-a-quick-installation-guide-v100r001092 9/218

Lead the dry contact signal cables and communication cables into the cabinet through the cable window, and then route thecables along the panels of the cabinet.

1

 According to the actual installation requirements, use a flat-head screwdriver to prop up the white contact plates to havethe metal dome sheets in the ports spring up. Insert the dry contact signal cable into the dry contact points, and pull out thescrewdriver to fasten the signal cable.

2

  Installing the Dry Contact Signal Cablesand Communication Cables (Optional)5

 NOTE

1. The use of the dry contact signal cables and communication cables is scenario-specific.According to actual requirements, determine the dry contact

signal cables and communication cables to be installed before installation.

2. Functions of dry contact points.

J13, J14, J4-J10 are nine dry contact sockets on the monitoring back plane. Status, Status1, Status2 are three circuits for the input of the detection signals

of the diesel generator. Ctrl1 and Ctrl2 are two circuits for the output of the control signals of the diesel generator. ALM1-ALM7 are seven circuits for the

output of the alarm signals of the diesel generator. Each circle represents the corresponding wiring terminal. The black circles are the common terminals

of the constant-enabled ports and constant-disabled ports on the relays.NC represents constant-disabled port and NO represents constant-enabled port.By

default, the output of the dry contact is set to OFF.

White contact plate

Dry contact point

1 2

 Alarm Type Default Function Description

 AC power-off alarm

DC input overvoltage and undervoltage

Power supply system fault alarm

Surge protector failure alarm

Fuse disconnectionalarm

Battery protection

Standby dry contact output 1

Control for the diesel generator 1

Control for the diesel generator 2

Detection for the runningstatus of the diesel generator Detection for the start/stopcontrol signals of diesel generator 1

Detection for the start/stopcontrol signals of diesel generator 2

 AC input power-cut alarm port (AC Fail)

DC input undervoltage alarm port (DC Low)

Rectifier module fault alarm port (PSU Fail)

Surge protector alarm port (SPD Fail)

Fuse disconnection alarm port (Fuse Alarm)

Battery low-voltage isolation disconnection alarm port (Batt.LVD)

Reserved dry contact 1 (Reserve 1)

Port for starting and stopping the Generator 1

Port for detecting the running status of the diesel generator 

Port for starting and stopping the Generator 2

Port for detecting the start.stop signals of diesel generator 1

Port for detecting the start.stop signals of diesel generator 2

 ALM1

 ALM2

 ALM3

 ALM4

 ALM5

 ALM6

 ALM7

Ctrl1

Ctrl2

Status

Status1

Status2

12

Page 10: Agisson TP48300 a Quick Installation Guide V100R001!09!2

8/20/2019 Agisson TP48300 a Quick Installation Guide V100R001!09!2

http://slidepdf.com/reader/full/agisson-tp48300-a-quick-installation-guide-v100r001092 10/219

insert the signal cables of the temperature & humidity sensor and the battery temperature sensor.3

Bind the dry contact signal cables and communication cables on the cable window separately, and then route all thecables to the distribution frame.

5

 

Installing the DC Output Cables6

Insert the –48 V DC output cable into the output port on the BLVD MCBs.1

Loosen the bolt on the top of the load power-off fuse, connect the –48 V output cable to the bolt, use torque wrench to tightenthe bolt, force moment as 10 Nm.

2

Connect the 0 V output cable to the DC output positive wiring busbar.3

Bind the DC output cables on the cable window. Ensure that the DC output cables are separated from other cables.4

Load power-off tributary using fuse

DC output distribution can be customized.

Load power-off tributary using fuse

CAUTION

Do not connect the power system and the BBU with an Ethernet cable or RJ45 communication cable. If the customer requires in-band NMS

management of the power system, the NMS management requires setting of the storage battery capacity. For the details of NMS setting,

 please see theNMS User Guide .

Communication cable

RJ45

12

 According to the actual installation requirements, Insert the temperature and humidity sensor signal cable and batterytemperature sensor signal cable.

4

Indoor temperature

and humidity sensor 

Battery temperature sensor  

Page 11: Agisson TP48300 a Quick Installation Guide V100R001!09!2

8/20/2019 Agisson TP48300 a Quick Installation Guide V100R001!09!2

http://slidepdf.com/reader/full/agisson-tp48300-a-quick-installation-guide-v100r001092 11/2110

Insert the –48 V DC output cable into the output port on the BLVD and LLVD MCBs .1

Connect the 0 V output cable to the DC output positive wiring busbar.2

Bind the DC output cables on the cable window. Ensure that the DC output cables are separated from other cables.3

Load power-off tributary using fuse机柜负载下电支路采用熔丝Load power-off tributary using MCB

CAUTION

1. The force moment of tightening the bolt must less than 10 Nm.

2. The signal cables must be installed in the front of the –48 V cables.

1

2

3

1

2

Page 12: Agisson TP48300 a Quick Installation Guide V100R001!09!2

8/20/2019 Agisson TP48300 a Quick Installation Guide V100R001!09!2

http://slidepdf.com/reader/full/agisson-tp48300-a-quick-installation-guide-v100r001092 12/2111

Loosen the bolt on the top of the base of the battery negative-pole access fuse, connect the –48 V input cables to the bolt,and use torque wrench to tighten the bolt, force moment as 10 Nm.

2

Connect the positive-pole of the storage battery to the DC output positive wiring busbar.1

 Arrange the output cables, and then use a nylon bundling tape to bind the cables to the bundling tie at the rear of the cablewindow.

3

 

Installing the Power Cables of the Storage Battery7

Load power-off tributary using fuse

Loosen the bolt on the top of the base of the battery negative-pole access fuse, connect the –48 V input cables to the bolt,and use torque wrench to tighten the bolt, force moment as 10 Nm.

2

Connect the positive-pole of the storage battery to the DC output positive wiring busbar.1

 Arrange the output cables, and then use a nylon bundling tape to bind the cables to the bundling tie at the rear of the cablewindow.

3

Load power-off tributary using fuse机柜负载下电支路采用熔丝Load power-off tributary using fuse

Load power-off tributary using fuse机柜负载下电支路采用熔丝Load power-off tributary using MCB

Battery negative-pole

1   2

BF1-   BF2-

Battery positive-pole

If the MCB for batteries is available, Set the MCB of thebattery rack or battery cabinet to OFF.

If the MCB for batteries is not available, disconnect one of thecables between two batteries.

CAUTION

1. Ensure that the signal cables are installed in the front of the battery negative-pole input cable and that the BLVD MCBs is set to OFF.

2. When installing a fuse for the load storage batteries, ensure that the bare metal part of the screwdriver does not touch the positive bus and the fuse

wiring terminal, otherwise a short circuit may be caused.

3. The force moment of tightening the bolt must less than 10 Nm.

4. If only one group of batteries is connected ,it should be connected to BF1.

CAUTION

1. Ensure that the signal cables are installed in the front of the battery negative-pole input cable and that the BLVD MCBs is set to OFF.

2. When installing a fuse for the load storage batteries, ensure that the bare metal part of the screwdriver does not touch the positive bus and the

fuse wiring terminal, otherwise a short circuit may be caused.

3.The force moment of tightening the bolt must less than 10 Nm

4. If only one group of batteries is connected ,it should be connected to BF1.

Battery negative-pole

1 2

BF1 BF2

BF1-   BF2-

Battery positive-pole

Page 13: Agisson TP48300 a Quick Installation Guide V100R001!09!2

8/20/2019 Agisson TP48300 a Quick Installation Guide V100R001!09!2

http://slidepdf.com/reader/full/agisson-tp48300-a-quick-installation-guide-v100r001092 13/2112

The cabinet supports the single-phase and three-phase AC input cables, which must be installed in different ways.Mode 1: To install the single-phase AC input cables, perform the following steps:

a) Connect the neutral cable to the N-terminal. b) Install the copper bar on the AC input MCB. c) Connect live cable to thecopper bar.

1

Mode 2: To install the three-phase AC input cables, perform the following steps:a) Connect the neutral cable to the N-terminal.b) Connect the U-phase, V-phase, and W-phase cables to the AC input MCB.

AC input MCB using 3-pole MCB

Input copper bar  Live cableNeutral cable

N-terminal

Phillips screwdriver 

a cb

Neutral cable

N-terminal

ba

Phillips screwdriver 

 

Installing the AC Input Cables8

Install the plastic protection plate.2

Bind the AC input cable to the nearest bundling tie.3

2 3

Plastic protection plate

 220V AC Input

Page 14: Agisson TP48300 a Quick Installation Guide V100R001!09!2

8/20/2019 Agisson TP48300 a Quick Installation Guide V100R001!09!2

http://slidepdf.com/reader/full/agisson-tp48300-a-quick-installation-guide-v100r001092 14/2113

机柜负载下电支路采用熔丝AC input MCB using 4-pole MCB

To install the three-phase AC input cables, perform the following steps: Connect the N-phase, U-phase, V-phase, andW-phase cables to the AC input MCB.

U V W N

Phillips screwdriver

1

Install the plastic protection plate.2

Bind the AC input cable to the nearest bundling tie.3

 

110V AC Input

Plastic protection plate

L1 L2

b ca

Phillips screwdriver 

The cabinet supports the single-phase and three-phase AC input cables, which must be installed in different ways.Mode 1: To install the single-phase AC input cables, perform the following steps:a) Connect the L1, L2, cables to the AC input MCB.b) Install the plastic protection plate.c) Bind the AC input cable to the nearest bundling tie.

Mode 2: To install the three-phase AC input cables, perform the following steps:a) Connect the L1, L2, and L3 cables to the AC input MCB.b) Install the plastic protection plate.c) Bind the AC input cable to the nearest bundling tie.

Plastic protection plate

L2 L3L1

b ca

Phillips screwdriver 

Page 15: Agisson TP48300 a Quick Installation Guide V100R001!09!2

8/20/2019 Agisson TP48300 a Quick Installation Guide V100R001!09!2

http://slidepdf.com/reader/full/agisson-tp48300-a-quick-installation-guide-v100r001092 15/2114

 

Cabling guide9

-

-

+

+

-

+

-

+

-

+

-

-

+

-

+

3

76

83

4

45

68

2

5

1

2

The power cable of the storage battery

DC output cable

PGND cable

 AC input cableDry contact signal cable

1

2

3

45

Battery temperature sensor 

6 Temperature and humidity sensor signal cable

7

Communication cable8

The scenario with Cabling Rack

 NOTE

The AC input cables and signal cables must be bound

and routed separately.

a

a

b

c

c

Cutaway view:

Cable

Rack Rack Rack

Cable Cable Cable

b

1

7

Page 16: Agisson TP48300 a Quick Installation Guide V100R001!09!2

8/20/2019 Agisson TP48300 a Quick Installation Guide V100R001!09!2

http://slidepdf.com/reader/full/agisson-tp48300-a-quick-installation-guide-v100r001092 16/2115

The scenario without Cabling Rack

-

-

+

+

-

+

-

+

-+

-1

2

2

34

34

5

78

6

568The power cable of the storage battery

DC output cable

PGND cable

 AC input cable

Dry contact signal cable

1

2

3

4

5

Battery temperature sensor 

6 Temperature and humidity sensor signal cable

7Communication cable8

-

+

-

+

 NOTE

The AC input cables and signal cables must be bound

and routed separately.

1

a

a

b

c

c

Cutaway view:

b

17

CableRack Rack Rack

Cable Cable Cable

Page 17: Agisson TP48300 a Quick Installation Guide V100R001!09!2

8/20/2019 Agisson TP48300 a Quick Installation Guide V100R001!09!2

http://slidepdf.com/reader/full/agisson-tp48300-a-quick-installation-guide-v100r001092 17/2116

 

Power-on Testing11a Connecting the Battery Branch and Setting PMU Parameters

Ensure that System type is set to TP48300/A.1

Set temperature alarm parameters.3

Set time and date.4

 

Verifying the Installation10Ensure that the cabinet and cables are secure.1

 According to the connecting diagram, ensure that the cables are installed properly by sight or with a multimeter and that thelive cable, ground cable, and neutral cable are not short-circuited.Ensure that the 0 V cable and –48 V cable are not short-cir-cuited.

2

Insert the removed battry fuses into the corresponding positions.3

 

- -

Connect the battery branch:If the MCB for batteries is available, set the MCB for thebattery rack or battery cabinet to ON.

If the MCB for batteries is not available, connect thecables Removed between two batteries.

Then set PMU parameters.

Set the number, capacity and Install time of battery groups.2

 NOTE

1. The position of the CPMU01 monitoring module, operating keyboard, and status indicator are shown in the following figure.

2. When the TP48300/A power system is working properly and communicate with the main equipment, the ALM indicator on the CPMU01 does not light and the

RUNflash slowly. When the TP48300/A power system is working properly and the TP48300/A power system does not communicate with the main equipment,the ALM indicator on the CPMU01 does not work and the RUN indicator is ON.

When the TP48300/A power system has serious alarms, the ALM indicator on the CPMU01 is ON and the buzzer sounds. For details, see the TP48300/A power

system Maintenance Guide.

3. When the system is in standby mode, press "↓" and "Enter" at the same time to reduce the contrast of the LCD or press "↑" and "Enter" at the same time to

increase the contrast of the LCD.

4. Before setting the CPMU01 menu, press "↓" or "↑" to select options and configure values.Press "Enter" to enter the main menu when the system is standby. On

the main menu, press "Enter" to view the submenu, and save the configuration by pressing "Enter" on the submenu.Press Cancel to undo the operation and return

to the upper menu without saving the configuration.

5. The PMU does not generate any alarm. When the current interface is not the main menu, the LCD goes dark five minutes later if you do not press any button,

and the main menu is displayed eight minutes later if you do not press any button.

6. On the System Control interface, you can access the system with the user password, or engineer password. On the Engineer Advanced Setting interface, you can

access the system with the engineer password. The user password and engineer password are 0# and 11# respectively and can be reset on the menu.

 NOTE

The number of the battery group can be set as 0, 1 or 2. Please set the number of the battery group and capacity according to actual configuration. If you face to

the door, the fuse at the leftside is BF1- and the fuse at the rightside is BF2- .

1. If only one group of batteries is connected, please connect to BF1- , set the number of the battery group as 1, and set "battery capacity 1" according to actual

configuration.

2. If two groups of batteries are connected, please separately connect to BF1- and BF2- , set the number of the battery group as 2, and set "battery capacity 1",

"battery capacity 2" according to actual configuration.

3. If four groups of batteries are connected, two battery groups connect to BF1- and the other two battery groups connect to BF2- , set the number of the batterygroup as 2, and set "battery capacity 1", "battery capacity 2" according to total actual capacity of every two battery groups.

4. This guide take two groups of 300Ah batteries as an example.

Load power-off tributary using fuse Load power-off tributary using MCB

Page 18: Agisson TP48300 a Quick Installation Guide V100R001!09!2

8/20/2019 Agisson TP48300 a Quick Installation Guide V100R001!09!2

http://slidepdf.com/reader/full/agisson-tp48300-a-quick-installation-guide-v100r001092 18/2117

English中 文

2001-01-01

53.6VDC 227VAC

Load:0.2A

Batt:0.0A

MAIN MENU

StatusMaintenance

Settings

SettingsSystem Settings

 Alarm Setting s

 AC Setting s

ENT

ENT

ENT 0# ENT ENT 0# ENT ENT 0# ENT ENT 0# ENT

ENT

 Add ress:0Text:EnglishComm Mode: RS232

Band:9600

Batt2Shunt: YesDisp Contrast:3

System Type:

TP48300/A

ENT

English中 文

2001-01-01

53.6VDC 227VAC

Load:0.2A

Batt:0.0A

ENT

ENT

ENT

Batt SettingsBatt SelectionLVD Settings

Charge

ENT

ENT ENT

Batt SelectionBatt String :1

Cap 1:400AhCap:0Ah

ENT

ENT

ENT

ENT

English中 文

2001-01-01

53.6VDC 227VAC

Load:0.2A

Batt:0.0A

ENT

ENT

ENT

Batt SettingsBatt Test

Temp Coeff 

ENT

Temp Comp Basis:Batt 1

Temp Comp:80mV/°C

ENT

Low Temp Alarm:

0°C

High Temp Alarm:

50°CENT

English中 文

2001-01-01

53.6VDC 227VAC

Load:0.2A

Batt:0.0A

ENT

ENT

ENT

ENT

Date:2001-01-01

Time:

09:10

ENT

MAIN MENU

StatusMaintenance

Settings

MAIN MENU

StatusMaintenance

Settings

MAIN MENU

StatusMaintenance

Settings

SettingsSystem Settings

 Alarm Setting s

 AC Setting s

SettingsDC Settings

Batt Settings

 AMB. Setting s

SettingsDC Settings

Batt Settings

 AMB. Setting s

Batt2Shunt: Yes

Disp Contrast:3System Type:

TP48300/A

Batt Selection

Batt String :2Cap 1:400Ah

Cap 2:30Ah

Batt Selection

Batt String :2Cap 1:400Ah

Cap 2:30Ah

Batt SelectionBatt String :2

Cap 1:300AhCap 2:30Ah

Batt SelectionBatt String :2

Cap 1:300Ah

Cap 2:30Ah

Batt SelectionBatt String :2

Cap 1:300AhCap 2:300Ah

Low Temp Alarm:

0°CHigh Temp Alarm:

50°C

 Add ress:0Text:EnglishComm Mode: RS232

Band:9600

Date:

2001-01-01Time:

09:10

ENT

Batt SelectionInstall Date:

2001-01-01

1 2 3 4

Page 19: Agisson TP48300 a Quick Installation Guide V100R001!09!2

8/20/2019 Agisson TP48300 a Quick Installation Guide V100R001!09!2

http://slidepdf.com/reader/full/agisson-tp48300-a-quick-installation-guide-v100r001092 19/2118

b Power-on Check

CAUTION

Do not power on the DC load before the storage batteries parameter is correctly

set on the CPMU01 , otherwise, it will cause damage to storage batteries.

Check whether the voltage of the LLVD fuse or MCB, battery fuse, and BLVD MCB is proper using a multimeter. The ratevoltage is 53.5 V and the range is between 43.2 V and 57.6 V. Check whether the panel display of the PMU is functional. Ifthe voltage is improper or the panel display fails, contact professional personnel for troubleshooting or handle the problem

by referring to the TP48300/A Maintenance Guide .

1

Set the AC MCB to ON and repeat step 1.2

ON

OFF

Set the LLVD MCBs to ON or insert the removed battery LLVD fuses into the corresponding positions, set the BLVD MCBsto ON and repeat step 1.

3

ON   ON ON

OFF   OFF OFF

Set the AC input MCB, LLVD MCB, and BLVD MCB according to actual conditions.4

Cut the cabling holes on the top of the cabinet according to the cabling conditions. Clear up the site, close and lock the cabinetdoor, and return the key to the administrator.5

Page 20: Agisson TP48300 a Quick Installation Guide V100R001!09!2

8/20/2019 Agisson TP48300 a Quick Installation Guide V100R001!09!2

http://slidepdf.com/reader/full/agisson-tp48300-a-quick-installation-guide-v100r001092 20/2119

TP48300/A Power System Parameter List

Date Sign 2st Rev Date

Environment

High Alarm

0.10.05~0.25Current LimitCoefficient

56.5V43.2V~57.6VBattery Boost

43.0V35V~LLVDBLVD

44.0VBLVD~DC Under 

Volt

LLVD

53.5V43.2V~57.6VBattery Float

Sign1st RevFactory SettingSetting BoundItem

50°C

50°C

-50°C~100°CBattery High

Temp Alarm

YesYes/NoBLVD Ena ble

YesYes/NoLLVD Enable

NoYes/NoRect Sleep

00:0000:00~23:59Time

2001-01-010000-00-00~9999-

12-31

Date

0Ah30~1000★Battery Cap 2

400Ah30~1000★Battery Cap 1

10~2★Battery String

TP48300/A Parameter Settings

Date Sign 2st Rev Date Sign1st RevDefault ValueValue RangeParameter 

-

-50°C~100°C-

CAUTION

Please set the number of the battery group, battery capacity, battery temperature and environment temperature according to actual configuration.

Page 21: Agisson TP48300 a Quick Installation Guide V100R001!09!2

8/20/2019 Agisson TP48300 a Quick Installation Guide V100R001!09!2

http://slidepdf.com/reader/full/agisson-tp48300-a-quick-installation-guide-v100r001092 21/21

HUAWEI TECHNOLOGIES CO., LTD.Huawei Industrial Base Bantian Longgang

Shenzhen 518129

People’s Republic of China