61
3-09339 09339 00 91 13 Addendum No. 1 2017.06.06 Page 1 of 2 ADDENDUM NO. 1 TO THE PLANS, SPECIFICATIONS AND CONTRACT DOCUMENTS FOR SENIOR CITIZEN CENTER CDBG NO. 1132-16-172-PF-01 & 1133-16-172-PF-01 FOR CITY OF DURANT HOLMES COUNTY, MISSISSIPPI This Addendum No. 1 supersedes and takes precedence over the “CONSTRUCTION PLANS,” “SPECIFICATIONS” and “CONTRACT DOCUMENTS” for SENIOR CITIZEN CENTER , CDBG NO. 1132-16-172-PF-01 & 1133-16-172-PF-01 dated MAY 2017, and shall remain in full force except as herein amended. CONTRACTS 1. REPLACE bound pages 23-28, “00 41 43 Bid Form – Proposal” Contract with attached Contract called “00 41 43 Bid Form – Proposal” Contract marked “REVISED by Addendum No. 1”. Item Description No. 2 changed and Number of Days of Construction changed from 120 to 150 consecutive calendar days. SPECIFICATIONS 1. ADD “23 07 13 Duct Insulation” Specification, marked “ADDED Addendum No. 1”. 2. ADD “23 34 16 Centrifugal Fans” Specification, marked “ADDED Addendum No. 1”.

ADDENDUM NO. 1 · Project #3-09339 BID SCHEDULE Item Estimate No. Item Description Quantity Unit 1 ... insurance, and other costs necessary to cover the finished work of the several

  • Upload
    others

  • View
    0

  • Download
    0

Embed Size (px)

Citation preview

Page 1: ADDENDUM NO. 1 · Project #3-09339 BID SCHEDULE Item Estimate No. Item Description Quantity Unit 1 ... insurance, and other costs necessary to cover the finished work of the several

3-09339

09339 00 91 13 Addendum No. 1 2017.06.06 Page 1 of 2

ADDENDUM NO. 1

TO THE

PLANS, SPECIFICATIONS AND CONTRACT DOCUMENTS

FOR

SENIOR CITIZEN CENTER

CDBG NO. 1132-16-172-PF-01 & 1133-16-172-PF-01

FOR

CITY OF DURANT

HOLMES COUNTY, MISSISSIPPI

This Addendum No. 1 supersedes and takes precedence over the “CONSTRUCTION PLANS,” “SPECIFICATIONS” and “CONTRACT DOCUMENTS” for SENIOR CITIZEN CENTER, CDBG NO. 1132-16-172-PF-01 & 1133-16-172-PF-01 dated MAY 2017, and shall remain in full force except as herein amended.

CONTRACTS 1. REPLACE bound pages 23-28, “00 41 43 Bid Form – Proposal” Contract with attached Contract called “00 41 43 Bid Form – Proposal” Contract marked “REVISED by Addendum No. 1”. Item Description No. 2 changed and Number of Days of Construction changed from 120 to 150 consecutive calendar days.

SPECIFICATIONS 1. ADD “23 07 13 Duct Insulation” Specification, marked “ADDED Addendum No. 1”. 2. ADD “23 34 16 Centrifugal Fans” Specification, marked “ADDED Addendum No. 1”.

Page 2: ADDENDUM NO. 1 · Project #3-09339 BID SCHEDULE Item Estimate No. Item Description Quantity Unit 1 ... insurance, and other costs necessary to cover the finished work of the several
Page 3: ADDENDUM NO. 1 · Project #3-09339 BID SCHEDULE Item Estimate No. Item Description Quantity Unit 1 ... insurance, and other costs necessary to cover the finished work of the several

REVISED by Addendum No. 1 09339 00 41 43 Bid Form 2017.06.06 Page 1 of 6

BID PROPOSAL Proposal of (hereinafter called "Bidder"), organized and existing under the laws of the State of , doing business as * to CITY OF DURANT (hereinafter called "Owner"). In compliance with your Advertisement for Bids, Bidder hereby proposes to perform all work for SENIOR CITIZEN CENTER, in strict accordance with the Contract Documents, within the time set forth herein, and at the prices stated below. By submission of this Bid, each Bidder certifies, and in the case of a joint bid, each party thereto certifies as to his own organization that this Bid has been arrived at independently, without consultation, communication, or agreement as to any matter relating to this bid with any other Bidder or with any competitor. Bidder hereby agrees to commence work under this contract on the date to be specified in the Notice to Proceed and to fully complete the project within 150 consecutive calendar days. Bidder further agrees to pay as liquidated damages, the sum of $500.00 for each consecutive calendar day thereafter as provided in Article 14 of the General Conditions, said amount to cover the cost of additional resident inspection. Bidder acknowledges receipt of the following addendum: *Insert "a corporation", "a partnership", or "an individual" as applicable. Bidder agrees to perform all work described in the Contract Documents for the following unit prices or lump sum:

Page 4: ADDENDUM NO. 1 · Project #3-09339 BID SCHEDULE Item Estimate No. Item Description Quantity Unit 1 ... insurance, and other costs necessary to cover the finished work of the several

Project #3-09339 BID SCHEDULE

Item EstimateNo. Item Description Quantity Unit

1

Clearing & Grubbing (Includes Demoltion & Removal of Existing Site Material (Concrete, Brick, Stone & Soil) and Saw Cutting of Existing Concrete 1 LS $ $

2

Unclassified Excavation (P.M.) Complete Site, Includes Removal of Existing Drain Line 1 LS $ $

3Select Borrow Material (P.M.) Building & Parking Area 200 CuYd $ $

4

Senior Citizen Center Building Complete with but not Limited to Termite Treatment with NPCA - 99A & 99B Certification Crushed Limestone Base Building & Sidewalks (Crusher Run) Foundation, Masonry, Electrical, Lighting, Plumbing, Carpentry, HVAC, Fixtures, Doors, Windows, Sidewalks, Top Soiling, Telephone, Computer Service and all other Appurtenances Necessary for a Complete Building Ready for Use and Occupancy. 1 LS $ $

5

Granular Material (Crusher Limestone Parking) (Crusher Run) (P.M.) Includes 30% Shrinkage Includes Area Under Asphalt & Crushed Stone Parking. 324 Ton $ $

6 Asphalt Prime Coat (EA-I) or (AE-P) 170 Gal $ $

7Hot Bituminous Pavement Surface Course (9.5 mm, ST) 55 Ton $ $

SENIOR CITIZEN CENTER

Each bid item unit price shall include sales tax and all other applicable taxes and fees.

* Items that can possibly be subcontracted to MBE/WBE firms.g ( ) y

adequate to cover Contractor's overhead and profit for each separately identified item, (2) estimated quantities are not guaranteed and are solely for the purpose of comparison of Bids, and (3) final

payment for all Unit Price Bid Items will be based on actual quantities, determined as provided in the Contract Documents.

BASE BID

Write/Type unit prices and bid prices, as clearly as possible, in number format.

Bid Unit BidPrice Price

2017.06.06 00 41 43

REVISED by Addendum No. 1Bid Form - Proposal

Page 2 of 624

Page 5: ADDENDUM NO. 1 · Project #3-09339 BID SCHEDULE Item Estimate No. Item Description Quantity Unit 1 ... insurance, and other costs necessary to cover the finished work of the several

Project #3-09339 BID SCHEDULE

Item EstimateNo. Item Description Quantity Unit

Bid Unit BidPrice Price

8Parking & Handicap Striping & Concrete Wheel Stops 1 LS $ $

9 Solid Sod 550 SqYd $ $

10 Landscaping Shrubs 1 LS $ $

11 Temporary Silt Fence 250 LinFt $ $

12 CDBG Project Sign 1 LS $ $

$

13

Kitchen Fixtures (Electric Range & Refrigerator) Includes Installation Complete In Place Ready for Use 1 LS $ $

$

14 Temporary Erosion Checks 6 Bales $ $

15 Seeding 0.25 Acres $ $

16 Vegetative Material for Mulch 0.50 Ton $ $

17 Ammonium Nitrate 0.06 Ton $ $

18 Agricultural Limestone 0.50 Ton $ $

19 Commercial Fertilizer (13x13x13) 0.25 Ton $ $

$TOTAL ADDITIVE ALTERNATE NO. 2

ADDITIVE ALTERNATE NO. 2

ADDITIVE ALTERNATE NO. 1

TOTAL BASE BID

TOTAL ADDITIVE ALTERNATE NO. 1

2017.06.06 00 41 43

REVISED by Addendum No. 1Bid Form - Proposal

Page 3 of 625

Page 6: ADDENDUM NO. 1 · Project #3-09339 BID SCHEDULE Item Estimate No. Item Description Quantity Unit 1 ... insurance, and other costs necessary to cover the finished work of the several

Project #3-09339 BID SCHEDULE

Item EstimateNo. Item Description Quantity Unit

Bid Unit BidPrice Price

5

Granular Material (Crusher Limestone Parking) (Crusher Run) (P.M.) Includes 30% Shrinkage, Includes Area Under Asphalt ONLY. 75 Ton $ $

6 Asphalt Prime Coat (EA-I) or (AE-P) 170 Gal $ $

7Hot Bituminous Pavement Surface Course (9.5 mm, ST) 55 Ton $ $

8Parking & Handicap Striping & Concrete Wheel Stops 1 LS $ $

$

9 Solid Sod 550 SqYd $ $

10 Landscaping Shrubs 1 LS $ $

20Deduction for Replacing all Top Soil with Select Borrow Material 1 LS $ $

$

21

Deduction for Replacing all Exterior Masonry Brick with Metal Sheeting. This Includes Removal of Brick Back-up Stud Wall & 5/8" OSB Board, and all Other Items Necessary for an Exterior Brick Wall. 1 LS $ $

22 Remove the Structural Building Façade (Stantions, Outriggers, Sheeting, Etc.) 1 LS $ $

$

DEDUCTIVE ALTERNATE NO. 1

TOTAL DEDUCTIVE ALTERNATE NO. 1

DEDUCTIVE ALTERNATE NO. 2

TOTAL DEDUCTIVE ALTERNATE NO. 2

DEDUCTIVE ALTERNATE NO. 3

TOTAL DEDUCTIVE ALTERNATE NO. 3

2017.06.06 00 41 43

REVISED by Addendum No. 1Bid Form - Proposal

Page 4 of 626

Page 7: ADDENDUM NO. 1 · Project #3-09339 BID SCHEDULE Item Estimate No. Item Description Quantity Unit 1 ... insurance, and other costs necessary to cover the finished work of the several

REVISED by Addendum No. 1 09339 00 41 43 Bid Form 2017.06.06 Page 5 of 6

PROPOSED SUBCONTRACTORS

In accordance with General Condition 6.15.4, the Contractor shall not award to Subcontractors in excess of fifty (50%) percent of the contract value, without prior approval of the Owner.

Subcontractor Address Work to be

Subcontracted Amount

All of the above prices shall include all labor, materials, taxes, overhead, profit, bonds, insurance, and other costs necessary to cover the finished work of the several kinds called for. Bidder understands that the Owner reserves the right to reject any or all bids and to waive any informality in the bidding. The Bidder agrees that this Bid shall be good and may not be withdrawn for a period of 90 calendar days after the scheduled closing time for receiving bids. Upon receipt of written notice of the acceptance of this Bid, Bidder will execute the formal contract attached within 10 calendar days and deliver a Surety Bond or Bonds as required by Article 5 of the General Conditions. The bid security attached in the sum of Dollars, ($ ) (5% of the Total Bid) is to become the property of the Owner in the event the contract and bond are not executed within the time set forth, as liquidated damages for the delay and additional expense to the Owner caused thereby. Bidder hereby certifies that he is a: Resident Contractor Non-Resident Contractor (See Information for Bidders)

27

Page 8: ADDENDUM NO. 1 · Project #3-09339 BID SCHEDULE Item Estimate No. Item Description Quantity Unit 1 ... insurance, and other costs necessary to cover the finished work of the several

REVISED by Addendum No. 1 09339 00 41 43 Bid Form

2017.06.06 Page 6 of 6

Respectfully submitted this the day of , 20 .

By Title

Company

Address

Phone

Employer Identification No.

SEAL (If bid is by a corporation.)

28

Page 9: ADDENDUM NO. 1 · Project #3-09339 BID SCHEDULE Item Estimate No. Item Description Quantity Unit 1 ... insurance, and other costs necessary to cover the finished work of the several

Added Addendum No. 1 23 07 13 Duct Insulation 2014.05.20 Page 1 of 8

DUCT INSULATION

PART 1 - GENERAL

1.01 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General Conditions, apply to this Section.

1.02 SUMMARY

A. This Section includes semi rigid and flexible duct, plenum, and breeching insulation; insulating cements; field-applied jackets; accessories and attachments; and sealing compounds.

B. Related Sections include the following: 1. Division 7 Section "Firestopping" for firestopping materials and requirements

for penetrations through fire and smoke barriers. 2. Division 15 Section "Pipe Insulation" for insulation for piping systems.

1.03 SUBMITTALS

A. Product Data: Identify thermal conductivity, thickness, and jackets (both factory and field applied, if any), for each type of product indicated.

1.04 QUALITY ASSURANCE

A. Installer Qualifications: Skilled mechanics who have successfully completed an apprenticeship program or another craft training program certified by the U.S. Department of Labor, Bureau of Apprenticeship and Training.

B. Fire-Test-Response Characteristics: As determined by testing materials identical to those specified in this Section according to ASTM E 84, by a testing and inspecting agency acceptable to authorities having jurisdiction. Factory label insulation and jacket materials and sealer and cement material containers with appropriate markings of applicable testing and inspecting agency.

1. Insulation Installed Indoors: Flame-spread rating of 25 or less, and smoke-developed rating of 50 or less.

1.05 DELIVERY, STORAGE, AND HANDLING

A. Packaging: Ship insulation materials in containers marked by manufacturer with appropriate ASTM specification designation, type and grade, and maximum use temperature.

Page 10: ADDENDUM NO. 1 · Project #3-09339 BID SCHEDULE Item Estimate No. Item Description Quantity Unit 1 ... insurance, and other costs necessary to cover the finished work of the several

Added Addendum No. 1 23 07 13 Duct Insulation 2014.05.20 Page 2 of 8

1.06 COORDINATION

A. Coordinate clearance requirements with duct Installer for insulation application.

1.07 SCHEDULING

A. Schedule insulation application after testing duct systems. Insulation application may begin on segments of ducts that have satisfactory test results.

PART 2: MATERIALS

2.01 MANUFACTURERS

A. Manufacturers: Subject to compliance with requirements, provide products by one of the following:

2. Mineral-Fiber Insulation: a. CertainTeed Manson. b. Knauf FiberGlass GmbH. c. Owens-Corning Fiberglas Corp.

2.02 INSULATION MATERIALS

A. Mineral-Fiber Board Thermal Insulation: Glass fibers bonded with a thermosetting resin. Comply with ASTM C 612, Type IB, without facing and with all-service jacket manufactured from kraft paper, reinforcing scrim, aluminum foil, and vinyl film.

B. Mineral-Fiber Blanket Thermal Insulation: Glass fibers bonded with a thermosetting resin. Comply with ASTM C 553, Type II, without facing and with all-service jacket manufactured from kraft paper, reinforcing scrim, aluminum foil, and vinyl film.

2.03 FIELD-APPLIED JACKETS

A. General: ASTM C 921, Type 1, unless otherwise indicated.

B. Foil and Paper Jacket: Laminated, glass-fiber-reinforced, flame-retardant kraft paper and aluminum foil.

2.04 ACCESSORIES AND ATTACHMENTS

A. Glass Cloth and Tape: Comply with MIL-C-20079H, Type I for cloth and Type II for tape. Woven glass-fiber fabrics, plain weave, presized a minimum of 8 oz./sq. yd. (270 g/sq. m).

1. Tape Width: 4 inches (100 mm).

Page 11: ADDENDUM NO. 1 · Project #3-09339 BID SCHEDULE Item Estimate No. Item Description Quantity Unit 1 ... insurance, and other costs necessary to cover the finished work of the several

Added Addendum No. 1 23 07 13 Duct Insulation 2014.05.20 Page 3 of 8

B. Weld-Attached Anchor Pins and Washers: Copper-coated steel pin for capacitor-discharge welding and galvanized speed washer. Pin length sufficient for insulation thickness indicated.

1. Welded Pin Holding Capacity: 100 lb (45 kg) for direct pull perpendicular to the attached surface.

C. Adhesive-Attached Anchor Pins and Speed Washers: Galvanized steel plate, pin, and washer manufactured for attachment to duct and plenum with adhesive. Pin length sufficient for insulation thickness indicated.

1. Adhesive: Recommended by the anchor pin manufacturer as appropriate for surface temperatures of ducts, plenums, and breechings; and to achieve a holding capacity of 100 lb (45 kg) for direct pull perpendicular to the adhered surface.

D. Self-Adhesive Anchor Pins and Speed Washers: Galvanized steel plate, pin, and washer manufactured for attachment to duct and plenum with adhesive. Pin length sufficient for insulation thickness indicated.

2.05 VAPOR RETARDERS

A. Mastics: Materials recommended by insulation material manufacturer that are compatible with insulation materials, jackets, and substrates.

PART 3: EXECUTION

3.01 EXAMINATION

A. Examine substrates and conditions for compliance with requirements for installation and other conditions affecting performance of insulation application.

B. Proceed with installation only after unsatisfactory conditions have been corrected.

3.02 PREPARATION

A. Surface Preparation: Clean and dry surfaces to receive insulation. Remove materials that will adversely affect insulation application.

3.03 GENERAL APPLICATION REQUIREMENTS

A. Apply insulation materials, accessories, and finishes according to the manufacturer's written instructions; with smooth, straight, and even surfaces; and free of voids throughout the length of ducts and fittings.

B. Refer to schedules at the end of this Section for materials, forms, jackets, and thicknesses required for each duct system.

Page 12: ADDENDUM NO. 1 · Project #3-09339 BID SCHEDULE Item Estimate No. Item Description Quantity Unit 1 ... insurance, and other costs necessary to cover the finished work of the several

Added Addendum No. 1 23 07 13 Duct Insulation 2014.05.20 Page 4 of 8

C. Use accessories compatible with insulation materials and suitable for the service. Use accessories that do not corrode, soften, or otherwise attack insulation or jacket in either wet or dry state.

D. Apply multiple layers of insulation with longitudinal and end seams staggered.

E. Seal joints and seams with vapor-retarder mastic on insulation indicated to receive a vapor retarder.

F. Keep insulation materials dry during application and finishing.

G. Apply insulation with tight longitudinal seams and end joints. Bond seams and joints with adhesive recommended by the insulation material manufacturer.

H. Apply insulation with the least number of joints practical.

I. Apply insulation over fittings and specialties, with continuous thermal and vapor-retarder integrity, unless otherwise indicated.

J. Hangers and Anchors: Where vapor retarder is indicated, seal penetrations in insulation at hangers, supports, anchors, and other projections with vapor-retarder mastic. Apply insulation continuously through hangers and around anchor attachments.

K. Insulation Terminations: For insulation application where vapor retarders are indicated, seal ends with a compound recommended by the insulation material manufacturer to maintain vapor retarder.

L. Apply insulation with integral jackets as follows: 1. Pull jacket tight and smooth. 2. Joints and Seams: Cover with tape and vapor retarder as recommended

by insulation material manufacturer to maintain vapor seal. 3. Vapor-Retarder Mastics: Where vapor retarders are indicated, apply

mastic on seams and joints and at ends adjacent to duct flanges and fittings.

M. Cut insulation according to manufacturer's written instructions to prevent compressing insulation to less than 75 percent of its nominal thickness.

N. Install vapor-retarder mastic on ducts and plenums scheduled to receive vapor retarders.

1. Ducts with Vapor Retarders: Overlap insulation facing at seams and seal with vapor-retarder mastic and pressure-sensitive tape having same facing as insulation. Repair punctures, tears, and penetrations with tape or mastic to maintain vapor-retarder seal.

2. Ducts without Vapor Retarders: Overlap insulation facing at seams and secure with outward clinching staples and pressure-sensitive tape having same facing as insulation.

Page 13: ADDENDUM NO. 1 · Project #3-09339 BID SCHEDULE Item Estimate No. Item Description Quantity Unit 1 ... insurance, and other costs necessary to cover the finished work of the several

Added Addendum No. 1 23 07 13 Duct Insulation 2014.05.20 Page 5 of 8

O. Interior Wall and Partition Penetrations: Apply insulation continuously through walls and partitions, except fire-rated walls and partitions.

P. Fire-Rated Wall and Partition Penetrations: Terminate insulation at fire/smoke damper sleeves for fire-rated wall and partition penetrations.

Q. Floor Penetrations: Terminate insulation at underside of floor assembly and at floor support at top of floor.

1. For insulation indicated to have vapor retarders, taper termination and seal insulation ends with vapor-retarder mastic.

3.04 MINERAL-FIBER INSULATION APPLICATION

A. Blanket Applications for Ducts and Plenums: Secure blanket insulation with adhesive and anchor pins and speed washers.

1. Apply adhesives according to manufacturer's recommended coverage rates per square foot, for 100 percent coverage of duct and plenum surfaces.

2. Apply adhesive to entire circumference of ducts and to all surfaces of fittings and transitions.

3. Install anchor pins and speed washers on sides and bottom of horizontal ducts and sides of vertical ducts as follows: a. On duct sides with dimensions 18 inches (450 mm) and smaller,

along longitudinal centerline of duct. Space 3 inches (75 mm) maximum from insulation end joints, and 16 inches (400 mm) o.c.

b. On duct sides with dimensions larger than 18 inches (450 mm). Space 16 inches (400 mm) o.c. each way, and 3 inches (75 mm) maximum from insulation joints. Apply additional pins and clips to hold insulation tightly against surface at cross bracing.

c. Anchor pins may be omitted from top surface of horizontal, rectangular ducts and plenums.

d. Do not overcompress insulation during installation. 4. Impale insulation over anchors and attach speed washers. 5. Cut excess portion of pins extending beyond speed washers or bend

parallel with insulation surface. Cover exposed pins and washers with tape matching insulation facing.

6. Create a facing lap for longitudinal seams and end joints with insulation by removing 2 inches (50 mm) from one edge and one end of insulation segment. Secure laps to adjacent insulation segment with 1/2-inch (13-mm) staples, 1 inch (25 mm) o.c., and cover with pressure-sensitive tape having same facing as insulation.

7. Overlap unfaced blankets a minimum of 2 inches (50 mm) on longitudinal seams and end joints. Secure with steel band at end joints and spaced a maximum of 18 inches (450 mm) o.c.

Page 14: ADDENDUM NO. 1 · Project #3-09339 BID SCHEDULE Item Estimate No. Item Description Quantity Unit 1 ... insurance, and other costs necessary to cover the finished work of the several

Added Addendum No. 1 23 07 13 Duct Insulation 2014.05.20 Page 6 of 8

8. Apply insulation on rectangular duct elbows and transitions with a full insulation segment for each surface. Apply insulation on round and flat-oval duct elbows with individually mitered gores cut to fit the elbow.

9. Insulate duct stiffeners, hangers, and flanges that protrude beyond the insulation surface with 6-inch- (150-mm-) wide strips of the same material used to insulate duct. Secure on alternating sides of stiffener, hanger, and flange with anchor pins spaced 6 inches (150 mm) o.c.

10. Apply vapor-retarder mastic to open joints, breaks, and punctures for insulation indicated to receive vapor retarder.

B. Board Applications for Ducts and Plenums: Secure board insulation with adhesive and anchor pins and speed washers.

1. Apply adhesives according to manufacturer's recommended coverage rates per square foot, for 100 percent coverage of duct and plenum surfaces.

2. Apply adhesive to entire circumference of ducts and to all surfaces of fittings and transitions.

3. Space anchor pins as follows: a. On duct sides with dimensions 18 inches (450 mm) and smaller,

along longitudinal centerline of duct. Space 3 inches (75 mm) maximum from insulation end joints, and 16 inches (400 mm) o.c.

b. On duct sides with dimensions larger than 18 inches (450 mm). Space 16 inches (400 mm) o.c. each way, and 3 inches (75 mm) maximum from insulation joints. Apply additional pins and clips to hold insulation tightly against surface at cross bracing.

c. Anchor pins may be omitted from top surface of horizontal, rectangular ducts and plenums.

d. Do not overcompress insulation during installation. 4. Cut excess portion of pins extending beyond speed washers or bend

parallel with insulation surface. Cover exposed pins and washers with tape matching insulation facing.

5. Create a facing lap for longitudinal seams and end joints with insulation by removing 2 inches (50 mm) from one edge and one end of insulation segment. Secure laps to adjacent insulation segment with 1/2-inch (13-mm) staples, 1 inch (25 mm) o.c., and cover with pressure-sensitive tape having same facing as insulation.

6. Apply insulation on rectangular duct elbows and transitions with a full insulation segment for each surface. Groove and score insulation to fit as closely as possible to outside and inside radius of elbows. Apply insulation on round and flat-oval duct elbows with individually mitered gores cut to fit the elbow.

7. Insulate duct stiffeners, hangers, and flanges that protrude beyond the insulation surface with 6-inch- (150-mm-) wide strips of the same material used to insulate duct. Secure on alternating sides of stiffener, hanger, and flange with anchor pins spaced 6 inches (150 mm) o.c.

8. Apply vapor-retarder mastic to open joints, breaks, and punctures for insulation indicated to receive vapor retarder.

Page 15: ADDENDUM NO. 1 · Project #3-09339 BID SCHEDULE Item Estimate No. Item Description Quantity Unit 1 ... insurance, and other costs necessary to cover the finished work of the several

Added Addendum No. 1 23 07 13 Duct Insulation 2014.05.20 Page 7 of 8

3.05 FIELD-APPLIED JACKET APPLICATION

A. Apply glass-cloth jacket, where indicated, directly over bare insulation or insulation with factory-applied jackets.

1. Apply jacket smooth and tight to surface with 2-inch (50-mm) overlap at seams and joints.

2. Embed glass cloth between two 0.062-inch- (1.6-mm-) thick coats of jacket manufacturer's recommended adhesive.

3. Completely encapsulate insulation with jacket, leaving no exposed raw insulation.

3.06 FINISHES

A. Glass-Cloth Jacketed Insulation: Paint insulation finished with glass-cloth jacket as specified in Division 9 Section "Painting."

3.07 DUCT SYSTEM APPLICATIONS

A. Insulation materials and thicknesses are specified in schedules at the end of this Section.

B. Materials and thicknesses for systems listed below are specified in schedules at the end of this Section.

C. Insulate the following plenums and duct systems: 1. Indoor concealed supply-, return-, and outside-air ductwork. 2. Indoor exposed supply-, return-, and outside-air ductwork.

D. Items Not Insulated: Unless otherwise indicated, do not apply insulation to the following systems, materials, and equipment:

1. Factory-insulated flexible ducts. 2. Factory-insulated plenums, casings, terminal boxes, and filter boxes and

sections. 3. Flexible connectors. 4. Vibration-control devices. 5. Insulated access panels and doors in air-distribution systems.

3.08 INDOOR DUCT AND PLENUM APPLICATION SCHEDULE

E. Service: Supply-air ducts. 1. Material: Mineral-fiber blanket. 2. Thickness: 2 inches (50 mm) at ceiling cavity Layers: One. 3. Field-Applied Jacket: Glass cloth or Foil and paper. 4. Vapor Retarder Required: Yes.

Page 16: ADDENDUM NO. 1 · Project #3-09339 BID SCHEDULE Item Estimate No. Item Description Quantity Unit 1 ... insurance, and other costs necessary to cover the finished work of the several

Added Addendum No. 1 23 07 13 Duct Insulation 2014.05.20 Page 8 of 8

3.09 BASIS OF PAYMENT

A. The cost of materials and material installation required to meet the scope of work and the drawings is included as part of the lump sum bid.

Page 17: ADDENDUM NO. 1 · Project #3-09339 BID SCHEDULE Item Estimate No. Item Description Quantity Unit 1 ... insurance, and other costs necessary to cover the finished work of the several

Added Addendum No. 1 23 34 16 Centrifugal Fans 2014.05.20 Page 1 of 7

CENTRIFUGAL FANS PART 1: GENERAL 1.01 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General Conditions, apply to this Section.

1.02 SUMMARY

A. This Section includes centrifugal fans.

1.03 PERFORMANCE REQUIREMENTS A. Project Altitude: Base air ratings on sea-level conditions. B. Operating Limits: Classify according to AMCA 99.

1.04 SUBMITTALS

A. Product Data: Include rated capacities, furnished specialties, and accessories

for each type of product indicated and include the following:

1. Certified fan performance curves with system operating conditions indicated. 2. Certified fan sound-power ratings. 3. Motor ratings and electrical characteristics, plus motor and electrical

accessories. 4. Material gages and finishes, including color charts. 5. Dampers, including housings, linkages, and operators.

B. Maintenance Data: For centrifugal fans to include in maintenance manuals

specified in Division 1. C. Comply with General Conditions: Shop Drawings and Samples.

1.05 QUALITY ASSURANCE

A. Electrical Components, Devices, and Accessories: Listed and labeled as defined

in NFPA 70, Article 100, by a testing agency acceptable to authorities having jurisdiction, and marked for intended use.

B. AMCA Compliance: Products shall comply with performance requirements and

shall be licensed to use the AMCA-Certified Ratings Seal.

Page 18: ADDENDUM NO. 1 · Project #3-09339 BID SCHEDULE Item Estimate No. Item Description Quantity Unit 1 ... insurance, and other costs necessary to cover the finished work of the several

Added Addendum No. 1 23 34 16 Centrifugal Fans 2014.05.20 Page 2 of 7

C. NEMA Compliance: Motors and electrical accessories shall comply with NEMA standards.

1.06 DELIVERY, STORAGE, AND HANDLING

A. Deliver fans as factory-assembled units, to the extent allowable by shipping

limitations, with protective crating and covering.

B. Disassemble and reassemble units, as required for moving to the final location, according to manufacturer's written instructions.

C. Lift and support units with manufacturer's designated lifting or supporting points.

1.07 COORDINATION

A. Coordinate installation of roof curbs, equipment supports, and roof penetrations.

These items are specified in Division 7 Section "Roof Accessories." 1.08 EXTRA MATERIALS

A. Furnish extra materials described below that match products installed and that

are packaged with protective covering for storage and identified with labels describing contents. 1. Belts: One set for each belt-driven unit.

1.09 OPERATION AND MAINTENANCE MANUAL

A. Comply with Operations and Maintenance Manual specification.

PART 2: MATERIALS 2.01 MANUFACTURERS

A. Manufacturers: Subject to compliance with requirements, provide products by one of the following:

1. Acme Engineering & Mfg. Corp. 2. Greenheck. 3. Cook, Loren Company.

2.02 MANUFACTURED UNITS

A. Description: Factory-fabricated, -assembled, -tested, and -finished, belt-driven centrifugal fans consisting of housing, wheel, fan shaft, bearings, motor and disconnect switch, drive assembly, and support structure, suitable for exterior installation.

Page 19: ADDENDUM NO. 1 · Project #3-09339 BID SCHEDULE Item Estimate No. Item Description Quantity Unit 1 ... insurance, and other costs necessary to cover the finished work of the several

Added Addendum No. 1 23 34 16 Centrifugal Fans 2014.05.20 Page 3 of 7

2.03 HOUSINGS

A. Materials and Fabrication: Formed and reinforced steel panels to make curved scroll housings with shaped cutoff, spun-metal inlet bell, and doors or panels to allow access to internal parts and components. 1. Panel Bracing: Steel angle- or channel-iron member supports for mounting

and supporting fan scroll, wheel, motor, and accessories. 2. Fabrication Class: AMCA 99, Class I.

3. Horizontal Flanged Split Housing: Bolted construction.

2.04 WHEELS

A. Backward-Inclined Fan Wheels: Steel construction with curved inlet flange, back plate, backward-inclined blades and fastened to shaft with set screws. 2.05 SHAFTS

A. Statically and dynamically balanced and selected for continuous operation at

maximum rated fan speed and motor horsepower, with final alignment and belt adjustment made after installation.

B. Turned, ground, and polished hot-rolled steel with keyway. Ship with a protective coating of lubricating oil.

C. Designed to operate at no more than 70 percent of first critical speed at top of

fan's speed range.

2.06 BEARINGS

A. Prelubricated and Sealed Shaft Bearings: Self-aligning, pillow-block-type ball bearings.

1. Ball-Bearing Rating Life: ABMA 9, L10 of 120,000 hours. 2. Roller-Bearing Rating Life: ABMA 11, L10 of 120,000 hours.

2.07 BELT DRIVES

A. Description: Factory mounted, with final alignment and belt adjustment made

after installation. 1. Service Factor Based on Fan Motor: 1.5.

B. Fan Pulleys: Cast iron or cast steel with split, tapered bushing; dynamically balanced at factory.

Page 20: ADDENDUM NO. 1 · Project #3-09339 BID SCHEDULE Item Estimate No. Item Description Quantity Unit 1 ... insurance, and other costs necessary to cover the finished work of the several

Added Addendum No. 1 23 34 16 Centrifugal Fans 2014.05.20 Page 4 of 7

C. Motor Pulleys: Adjustable pitch for use with motors through 5 hp; fixed pitch for use with motors larger than 5 hp. Select pulley so pitch adjustment is at the middle of adjustment range at fan design conditions.

D. Belts: Oil resistant, nonsparking, and nonstatic; matched sets for multiple belt drives. 1. Belt Guards: Fabricate to comply with OSHA and SMACNA requirements;

0.1046-inch- (2.7-mm-) thick, 3/4-inch (20-mm) diamond-mesh wire screen welded to steel angle frame or equivalent, prime coated. Secure to fan or fan supports without short circuiting vibration isolation. Include provisions for adjustment of belt tension, lubrication, and use of tachometer with guard in place.

E. Motor Mount: Adjustable for belt tensioning.

2.08 ACCESSORIES

A. Companion Flanges: Galvanized steel, for duct connections.

B. Weatherproof enclosure for motor and drive.

2.09 MOTORS

A. Motor Construction: NEMA MG 1, general purpose, continuous duty, premium efficiency, Design B.

B. Enclosure Type: Open dripproof. 2.10 SOURCE QUALITY CONTROL

A. Sound-Power Level Ratings: Comply with AMCA 301, "Methods for Calculating Fan Sound Ratings from Laboratory Test Data." Factory test fans according to AMCA 300, "Reverberant Room Method for Sound Testing of Fans." Label fans with the AMCA-Certified Ratings Seal.

B. Fan Performance Ratings: Establish flow rate, pressure, power, air density, speed of rotation, and efficiency by factory tests and ratings according to AMCA 210, "Laboratory Methods of Testing Fans for Rating."

2.11 IN-LINE CENTRIFUGAL FANS

A. Manufacturers: Subject to compliance with requirements, provide products by one of the following:

1. Acme Engineering & Mfg. Corp. 2. Bayley Fans; a division of Lau Industries, Inc. 3. Carnes Company HVAC.

Page 21: ADDENDUM NO. 1 · Project #3-09339 BID SCHEDULE Item Estimate No. Item Description Quantity Unit 1 ... insurance, and other costs necessary to cover the finished work of the several

Added Addendum No. 1 23 34 16 Centrifugal Fans 2014.05.20 Page 5 of 7

4. Greenheck. 5. Loren Cook Company.

B. Description: In-line, belt-driven centrifugal fans consisting of housing, wheel, outlet guide vanes, fan shaft, bearings, motor and disconnect switch, drive assembly, mounting brackets, and accessories.

C. Housing: Split, spun aluminum with aluminum straightening vanes, inlet and outlet flanges, and support bracket adaptable to floor, side wall, or ceiling mounting.

D. Belt-Driven Units: Motor mounted on adjustable base, with adjustable sheaves,

enclosure around belts within fan housing, and lubricating tubes from fan bearings extended to outside of fan housing.

E. Fan Wheels: Aluminum, airfoil blades welded to aluminum hub.

F. Accessories: 1. Companion Flanges: For inlet and outlet duct connections. 2. Motor and Drive Cover (Belt Guard): Epoxy-coated steel.

G. Capacities and Characteristics: 1. Wheel Type: Backward inclined. 2. Class: I. 3. Vibration Isolators:

a. Type: [Elastomeric hangers b. Static Deflection: 1 inch.

2.12 CEILING-MOUNTING VENTILATORS

A. Description: Centrifugal fans designed for installing in ceiling or wall or for concealed in-line applications.

B. Housing: Steel, lined with acoustical insulation.

C. Fan Wheel: Centrifugal wheels directly mounted on motor shaft. Fan shrouds, motor, and fan wheel shall be removable for service.

D. Grille: Stainless-steel louvered grille with flange on intake and thumbscrew attachment to fan housing.

E. Electrical Requirements: Junction box for electrical connection on housing and receptacle for motor plug-in.

F. Accessories:

Page 22: ADDENDUM NO. 1 · Project #3-09339 BID SCHEDULE Item Estimate No. Item Description Quantity Unit 1 ... insurance, and other costs necessary to cover the finished work of the several

Added Addendum No. 1 23 34 16 Centrifugal Fans 2014.05.20 Page 6 of 7

1. Variable-Speed Controller: Solid-state control to reduce speed from 100 percent to less than 50 percent.

2. Manual Starter Switch: Single-pole rocker switch assembly with cover and pilot light.

3. Time-Delay Switch: Assembly with single-pole rocker switch, timer, and cover plate.

4. Motion Sensor: Motion detector with adjustable shutoff timer. 5. Filter: Washable aluminum to fit between fan and grille. 6. Isolation: Rubber-in-shear vibration isolators. 7. Manufacturer’s standard roof jacket, or wall louver, and transition fittings.

PART 3: EXECUTION 3.01 INSTALLATION

A. Install centrifugal fans level and plumb.

B. Label fans according to requirements specified in Division 15 Section "Mechanical Identification."

3.02 CONNECTIONS

A. Duct installation and connection requirements are specified in other Division 15 Sections. Drawings indicate general arrangement of ducts and duct accessories. Make final duct connections with flexible connectors. Flexible connectors are specified in Division 15 Section "Duct Accessories."

B. Install ducts adjacent to fans to allow service and maintenance.

C. Ground equipment.

D. Tighten electrical connectors and terminals according to manufacturer's published torque-tightening values. If manufacturer's torque values are not indicated, use those specified in UL 486A and UL 486B.

3.03 FIELD QUALITY CONTROL

A. Equipment Startup Checks: 1. Verify that shipping, blocking, and bracing are removed. 2. Verify that unit is secure on mountings and supporting devices and that

connections to ducts and electrical components are complete. Verify that proper thermal-overload protection is installed in motors, starters, and disconnect switches.

3. Verify that cleaning and adjusting are complete.

Page 23: ADDENDUM NO. 1 · Project #3-09339 BID SCHEDULE Item Estimate No. Item Description Quantity Unit 1 ... insurance, and other costs necessary to cover the finished work of the several

Added Addendum No. 1 23 34 16 Centrifugal Fans 2014.05.20 Page 7 of 7

4. Disconnect fan drive from motor, verify proper motor rotation direction, and verify fan wheel free rotation and smooth bearing operation. Reconnect fan drive system, align and adjust belts, and install belt guards.

5. Verify lubrication for bearings and other moving parts. 6. Verify that manual and automatic volume control and fire and smoke

dampers in connected ductwork systems are in fully open position.

B. Starting Procedures: 7. Energize motor and adjust fan to indicated rpm. 8. Measure and record motor voltage and amperage.

C. Operational Test: After electrical circuitry has been energized, start units to confirm proper motor rotation and unit operation. Remove malfunctioning units, replace with new units, and retest.

D. Refer to Division 15 Section "Testing, Adjusting, and Balancing" for testing, adjusting, and balancing procedures.

E. Replace fan and motor pulleys as required to achieve design airflow.

F. Repair or replace malfunctioning units. Retest as specified above after repairs or replacements are made.

3.04 ADJUSTING

A. Adjust damper linkages for proper damper operation.

B. Adjust belt tension.

C. Lubricate bearings. 3.05 CLEANING

A. On completion of installation, internally clean fans according to manufacturer's written instructions. Remove foreign material and construction debris. Vacuum fan wheel and cabinet.

B. After completing system installation, including outlet fitting and devices, inspect exposed finish. Remove burrs, dirt, and construction debris and repair damaged finishes.

3.06 BASIS OF PAYMENT

A. The cost of materials and material installation required to meet the scope of work and the drawings is included as part of the lump sum bid.

Page 24: ADDENDUM NO. 1 · Project #3-09339 BID SCHEDULE Item Estimate No. Item Description Quantity Unit 1 ... insurance, and other costs necessary to cover the finished work of the several

CCE Project No. 3-09339-16P Senior Citizens Center City of Durant, MS April 25, 2017

ELECTRICAL GENERAL 16010 - 1

SECTION 16010- ELECTRICAL GENERAL

PART I- GENERAL

1.1 GENERAL

A. The Division 16000 Contractor shall provide all supervision, labor, material, tools,equipment, supplies, items, articles, and conduct or perform into operation satisfactory to theOwner and Engineers, the system described herein and shown or reasonably implied on theplans.

B. All work shall conform to the latest editions of the National Electrical Code (NEC) [NationalFire Protection Association (NFPA) 70], the Life-Safety Code (NFPA 101), the StandardBuilding Code, the International Building Code (IBC2012), the Americans with DisabilitiesAct (ADA), and all other applicable federal, state, and local codes and regulations.

C. The General Conditions, Supplementary Conditions, General Requirements, Information toBidders, and all other parts of this set of Contract Documents are hereby adopted and areapplicable to the Division 16000 Contractor.

1.2 DRAWINGS

A. The Contract Drawings and Documents are schematic in nature and are intended to conveythe intent of the electrical work to be performed on this project. The drawings are intended toindicate general arrangement of equipment, ducts, piping, conduit, and approximate sizes andlocations of equipment and outlets. Follow these drawings in laying out work. Consultgeneral construction drawings for general conditions affecting this work, and verify spaces inwhich work will be installed. Items not shown or specified which are required to produce acomplete, operative and finished system shall be provided. Provide all material, labor,equipment, etc., necessary to provide complete and operable electrical systems.

B. The drawings and specifications shall be considered as supplementary, one to the other, sothat materials and workmanship indicated, called for, or implied by one and not the othershall be supplied and installed as though specifically called for by both.

C. The drawings indicate the extent and general arrangement of the various systems. If anydepartures from these drawings are deemed necessary by the Contractor, detailed drawingsand descriptions of these departures and a statement of the reasons therefor shall be submittedto the Engineer for approval as soon as practicable. No departures from the arrangementsshown on the drawings shall be made without the prior written approval of the Engineer.

D. The drawings showing the extent and arrangement of the work of this particular trade must beused together with the drawings showing the extent and arrangement of the work of othertrades and shall be responsible for calling to the attention of the Engineer any interferencesencountered. Such interferences shall be investigated and called to the attention of theEngineer before any equipment is installed and before any material is fabricated. Relocationresulting from interferences shall be made at no additional cost to the Owner.

1.3 SCOPE OF WORK

09339 26 00 16010-16801 REPLACED by Addendum No. 1 Page 1 of 35

Page 25: ADDENDUM NO. 1 · Project #3-09339 BID SCHEDULE Item Estimate No. Item Description Quantity Unit 1 ... insurance, and other costs necessary to cover the finished work of the several

CCE Project No. 3-09339-16P Senior Citizens Center City of Durant, MS April 25, 2017

ELECTRICAL GENERAL 16010 - 2

A. Visit site prior to bid. Devise a plan for installation of complete and operable electrical systems meeting the requirements and intent of the Contract Documents. Submission of Bid stands as evidence that the Contractor accepts the Contract Documents as sufficient and complete for the work to be performed. Notify the engineer at least two weeks prior to bid of any discrepancies between the Contract Documents and actual field conditions. No change orders will be granted due to existing conditions that could have been observed during a site visit.

B. Provide temporary power and lighting during construction. Coordinate with the General Contractor for the exact requirements. C. Relocate, or recircuit, all electrical equipment, conduit, and circuitry conflicting with or obstructing work on this project. Where the electrical systems are owned by other entities,

pay them to relocate, or recircuit, their facilities. D. Arrange for connection of service to all electrical systems by the appropriate utility company.

Coordinate completely with all utility company requirements even if they are different than the contract documents. If utility company requirements are different from the contract documents, notify the engineer at least ten days prior to bid. Pay all utility company charges necessary for installation and connection of service. If the cost of the service is unavailable at the time of bid, submit a letter to the General Contractor, signed by the appropriate utility company official, stating that the cost has not been determined. The General Contractor shall submit this letter with his bid. The cost will then become the Owner's responsibility.

E. Provide all necessary equipment, raceway, circuitry, fittings, lugs, terminations, labor, etc.

and connect to all equipment and appliances requiring electrical connections furnished herein, by the Owner, or by other Contractors. Prior to ordering electrical equipment and roughing in for equipment furnished by the Owner or other Contractors, verify all connection types, connection locations, connection heights, voltages, number of phases, conductor sizes, disconnecting means, breaker sizes, etc. Furnish the proper electrical equipment for the equipment actually being supplied.

1.3 SUBMITTALS AND SHOP DRAWINGS

A. Within 30 days after award of Contract and prior to beginning work, provide six bound copies of manufacturers' cut sheets containing information concerning each article of electrical equipment to be finished on this project. These cut sheets shall contain sufficient information to prove compliance with the contract documents. In addition to cut sheets, the contractor shall provide a Bill-Of-Materials, listing each article of electrical equipment, including description and catalog number(s), and the quantity of each, to be furnished on this project. Information addressing the requirements of the contract documents shall be highlighted. Each bound set shall bear the stamp of the Electrical Contractor as well as the General Contractor.

B. Within 30 days after award of Contract and prior to beginning work, provide six sets of full

size shop drawings showing exact equipment locations with all equipment drawn to scale. Show all raceways with their junction boxes and pull boxes. Show all connection types, locations, and heights to equipment. Provide mounting and support details for all raceways and equipment.

C. Coordinate with all other trades to ensure that there are no conflicts between systems. Each

set of shop drawings shall bear the stamp of the Electrical Contractor, the General Contractor, and all Project Sub-Contractors. Failure to submit these Shop Drawings will render the

09339 26 00 16010-16801 REPLACED by Addendum No. 1 Page 2 of 35

Page 26: ADDENDUM NO. 1 · Project #3-09339 BID SCHEDULE Item Estimate No. Item Description Quantity Unit 1 ... insurance, and other costs necessary to cover the finished work of the several

CCE Project No. 3-09339-16P Senior Citizens Center City of Durant, MS April 25, 2017

ELECTRICAL GENERAL 16010 - 3

Electrical Contractor responsible for resolving all conflicts between trades at his own expense.

D. Submittals and Shop Drawings are reviewed to determine quality of materials. Approval of submittals and shop drawings does not relieve the Contractor of meeting the requirements

and intent of the Contract Documents. E. Outlet, light fixture, and device locations are shown in their approximate locations on the

drawings. Coordinate with Architectural drawings to get final locations. The Owner reserves the right to relocate outlets, light fixtures, and devices a distance not to exceed twenty feet prior to the installation of outlet boxes.

PART 2- PRODUCTS 2.1 All electrical equipment and materials shall be new. All equipment and materials shall be stored

on the job site in weatherproof enclosures. Electronic equipment shall be stored in facilities where the temperature and humidity are controlled. In addition, comply completely with all manufacturers' requirements for storage and handling.

2.2 All equipment shall be UL listed for the application in which it is used and shall be labeled as evidence of its UL listing. PART 3- EXECUTION 3.1 WORKMANSHIP

A. All work shall be performed with an emphasis on neatness. The Engineer, Architect, and Owner retain the right to reject work that is, in their judgment, unsatisfactory.

B. This Contractor shall co-operate with all other Contractors on the project and shall install his

work as fast as the progress of the balance of the work will permit.

C. This Contractor shall do all cutting and repairing of walls, floors, and ceilings necessary for the installation of his work, but no cutting of work of other Contractors will be permitted without the consent of the Engineer or his representative.

D. All cutting and repairing of walls, floors and ceilings shall be subject to the supervision and

approval of the General Contractor.

E. This Contractor shall keep the building clean of his own rubbish and scrap materials at all times.

3.2 EXPERIENCE AND LICENSING

A. The Electrical Contractor shall have completed at least two jobs of similar size and scope within the past five years. The Engineer reserves the right to reject Contractors based on their inability to submit evidence of their experience, or based on experience with the Contractor on previous projects.

B. The Electrical Contractor shall be a Licensed Electrician, and certified to perform electrical construction work in the State of Mississippi. The Electrical Contractor shall be responsible

09339 26 00 16010-16801 REPLACED by Addendum No. 1 Page 3 of 35

Page 27: ADDENDUM NO. 1 · Project #3-09339 BID SCHEDULE Item Estimate No. Item Description Quantity Unit 1 ... insurance, and other costs necessary to cover the finished work of the several

CCE Project No. 3-09339-16P Senior Citizens Center City of Durant, MS April 25, 2017

ELECTRICAL GENERAL 16010 - 4

for obtaining his/her own licensing and permitting at the local level, in which this project is located, and for coordinating work and inspections with all authorities having jurisdiction.

3.3 PERMITS

Obtain and pay for all permits required for work. Furnish the owner with Certificate of Inspection from all authorities having jurisdiction.

3.4 FIREPROOFING A. Fireproof all penetrations through firewalls with a fireproofing compound listed to maintain

the rating of the wall through which the raceway passes. B. The firestopping caulk shall be a one-part, intumescent, latex elastomer. The caulk shall be

capable of expanding a minimum of 3 times at 1000°F. The material shall be thixotropic and be applicable to overhead, vertical and horizontal firestops. The caulk shall be listed by independent test agencies such as IJL or FM and be tested to, and pass the criteria of ASTM B 814 Fire Test, tested under positive pressure. It shall comply with the requirements of the NEC (NFPA-70, BOCA, ICBO, SBCCI and NFPA Code 101. Firestopping caulk shall be paintable, but shall be non-hardening. Firestopping caullc shall be 3M Firebarrier CF or approved equal.

C. (Where applicable) - Where cable trays are shown crossing firewalls, terminate the cable tray

on each side of the wall and run the conductors through conduits installed in the wall. Fireproof around the conductors after installation.

D. Provide mineral wool packing and all other materials recommended by the manufacturer for a

complete installation. 3.5 FLASHING Provide all necessary equipment and flash all roof penetrations in such a manner to ensure that all

penetrations are completely sealed and all roof warranties remain in effect. Where there are no roof warranties, the Electrical Contractor shall guarantee the electrical penetrations against leaking for a period of one year from project completion. Employ a professional roofing contractor to perform all flashing.

3.6 PROTECTION A. Keep energized equipment covered during all phases of construction. Use enclosures, doors, covers, etc., to ensure that neither personnel nor machinery contact live electrical equipment. B. Replace electrical equipment that is damaged during construction.

3.7 DAMAGED FACILITIES

Locate all existing site equipment and utilities prior to beginning construction. Repair all equipment and utilities damaged during construction, or pay for the repair of the equipment and utilities where required by the Owner of the damaged facilities.

09339 26 00 16010-16801 REPLACED by Addendum No. 1 Page 4 of 35

Page 28: ADDENDUM NO. 1 · Project #3-09339 BID SCHEDULE Item Estimate No. Item Description Quantity Unit 1 ... insurance, and other costs necessary to cover the finished work of the several

CCE Project No. 3-09339-16P Senior Citizens Center City of Durant, MS April 25, 2017

ELECTRICAL GENERAL 16010 - 5

3.8 EXCAVATION AND BACKFILL A. Excavate in such a manner as to minimize erosion of the soil. Backfill trenches around

conduits with fine sand that is free of rocks, clods, and debris. Fill sand a minimum of 4" over conduits. Backfill the Test of the trench in six-inch increments, wetted, and tamped. Final compaction shall be a minimum of 95% of that of the adjacent earth. Resurface the grade with the same material as that excavated from the grade whether it be paving, concrete, sod, etc. Repair work shall be comparable to the quality of the original site prior to excavation.

B. Provide a 3" wide plastic labeled marker tape 12" below grade over all electrical conduits

buried underground. Tapes for power circuits shall have a warning such as "Caution: Buried Electrical Line Below." Labels on tapes for telephone, data, cable television, and other facilities shall adequately describe the line over which they are buried.

3.9 IDENTIFICATION A. Label all switchboards, panelboards, motor starters, disconnects, and motor control centers furnished under Division 16000 and other divisions of this contract with engraved rigid

plastic nameplates having letters at least 1/4 inch high. Nameplates shall be bolted to the enclosure. All labels shall indicate the voltage, number of phases, the AIC rating, and the panelboard and circuit number from which the device is fed.

B. All circuit breakers in Switchboards, Motor Control Centers, Power Distribution Type

Panelboards, such as Square D I-Line, and similar panelboards shall be labeled with plastic nameplates (as described in Part A) providing the name of the load served and the ampacity and number of poles of the breaker.

C. All Lighting and Appliance Type panelboards, and similar panelboards shall have typewritten

circuit directories. D. Label all conductors at all junction boxes, pull boxes, and terminations with typewritten

adhesive markers indicating the panelboard or switchboard name and circuit number of the conductor. Labels shall be Brady Datatab or approved equal.

E. Label all junction boxes and pull boxes with stenciled painted letters containing the name of

the panelboard and circuit numbers of the circuits contained within. Use black paint for normal circuits, red paint for emergency circuits, and orange paint for fire alarm circuits. The Contractor may select other colors for junction boxes and pull boxes for auxiliary systems.

F. Label all conduits in the most likely direction of access and view every 50' and on both ends

of each bend with stenciled painted letters containing the name of the panelboard and circuit numbers of the circuits contained within. Use black paint for normal circuits, red paint for emergency circuits, and orange paint for fire alarm circuits. The Contractor may select other colors for conduits for auxiliary systems. 3.10 AS-BUILT DRAWINGS Maintain one set of drawings during construction for as-built markings. Mark these drawings in red to indicate field changes. Provide these drawings to the Engineer at the end of the construction process. Where required under the General Conditions, Special Conditions, or other portions of this contract, provide revised computer drawn as-built drawings to the Engineer at the

09339 26 00 16010-16801 REPLACED by Addendum No. 1 Page 5 of 35

Page 29: ADDENDUM NO. 1 · Project #3-09339 BID SCHEDULE Item Estimate No. Item Description Quantity Unit 1 ... insurance, and other costs necessary to cover the finished work of the several

CCE Project No. 3-09339-16P Senior Citizens Center City of Durant, MS April 25, 2017

ELECTRICAL GENERAL 16010 - 6

end of construction. 3.11 TESTING A. Test all systems, or pay testing agencies as required, for compliance with the requirements of

all regulatory agencies. B. Test the electrical power service ground using a Biddle Three-Terminal Ground Resistance

Tester, or approved equal. Grounds shall meet the requirements of the NEC, or of Specification 16250, whichever is more stringent. Test grounds only when the earth is dry. Provide additional ground rods as necessary to achieve the required results.

C. Prior to making final equipment connections, test all service, feeder, and branch circuit conductors for continuity, phase-to-phase faults, and phase-to-ground faults using a Megger BM100 or approved equal test instrument generating 500 Vdc. Insulation resistance shall be a

minimum of 500,000 Ohms between any conductor and ground and 1,000,000 Ohms between any two conductors.

D. Test other systems as required in their respective specifications. E. Provide three bound copies of all test results to the Engineer at the end of the construction

process. No Recommendation of Substantial Completion will be granted until all testing reports have been submitted.

3.12 WARRANTY Provide the Owner a written guarantee to repair, or replace, all faulty equipment and systems for a period of one year from date of Substantial Completion. During this one-year period, a representative of the Contractor shall be on the site actively working on the repairs within 24 hours of the Owner's telephone call. During this period of time, the Owner shall not be charged for any repair work or expenses related with the repair work unless the Contractor can prove that the Owner has damaged the equipment or system.

END OF SECTION

09339 26 00 16010-16801 REPLACED by Addendum No. 1 Page 6 of 35

Page 30: ADDENDUM NO. 1 · Project #3-09339 BID SCHEDULE Item Estimate No. Item Description Quantity Unit 1 ... insurance, and other costs necessary to cover the finished work of the several

CCE Project No. 3-09339-16P Senior Citizens Center City of Durant, MS April 25, 2017

RACEWAYS 16110 - 1

SECTION 16110 - RACEWAYS PART 1 - GENERAL 1.1 GENERAL All electrical systems circuitry shall be contained in raceways unless expressly listed in the

specification for that system. All raceways shall be embedded in walls, concealed above ceiling, or as otherwise directed by project drawings.

1.2 SCOPE OF WORK A. Provide all raceways, fittings, couplings, anchors, supports, hangers, etc. for complete raceway systems. B. Use Schedule 40 (Gray) polyvinyl chloride (PVC) conduit for circuits run underground and

in slabs on grade level. Provide PVC-Coated Galvanized Rigid Steel elbows and PVC- Coated Galvanized Rigid Steel Conduit (GRSC) for all vertical runs extending to a point at least 6" above grade, or as directed by plans. Galvanized Rigid Steel Conduit coated with two complete coats of asphaltum or bituminous paint may be used in lieu of PVC-coated galvanized rigid steel conduit.

C. Use Galvanized Rigid Steel Conduit (GRSC) conduit for all applications where circuits are

run above ground exposed to the weather. D. Use Intermediate Metal Conduit (IMC) for all branch circuits, feeders, and auxiliary circuits requiring conduit 1 1/4" nominal trade size or larger in dry locations. E. Use Electrical Metallic Tubing (EMT) for all branch circuits and feeders less than 1-1/4"

nominal trade size in dry locations and in slabs above grade level. PART 2 - PRODUCTS 2.1 PVC conduits, fittings, couplings, adapters, and accessories shall be UL listed and approved for use with 90 degree Celsius conductors. The UL label shall be affixed to each ten foot length of conduit and each fitting. Conduits shall comply with NEMA Specification TC-2 and UL 651. Fittings shall comply with NEMA TC-3 and UL 514b. 2.2 PVC-coated conduits, fittings, couplings, adapters, and accessories shall be UL listed with PVC as the primary corrosion protection. They shall be hot dipped galvanized rigid steel conduit with threads hot galvanized after cutting. The conduit shall meet UL 6. The fittings shall meet UL 51413. The PVC coating shall be uniformly applied to the interior and exterior

of all conduit and fittings. The coating shall be nominally 2 mils thick. The PVC coating shall extend one pipe diameter or two inches, whichever is less, at every male fitting except unions to fit over the joining female connection. Couplings shall contain a series of longitudinal ribs, 40 mils in thickness, to protect the coating from damage by tools during installation. PVC-coated conduit shall be Robroy Plastibond or approved equal.

2.3 GRSC conduits, fittings, couplings, adapters, and accessories shall be UL listed. They shall be hot-dipped galvanized steel. They shall meet the safety standards of UL 6, and shall be manufactured to ANSI C80.1. Threads shall be hot galvanized after cutting.

09339 26 00 16010-16801 REPLACED by Addendum No. 1 Page 7 of 35

Page 31: ADDENDUM NO. 1 · Project #3-09339 BID SCHEDULE Item Estimate No. Item Description Quantity Unit 1 ... insurance, and other costs necessary to cover the finished work of the several

CCE Project No. 3-09339-16P Senior Citizens Center City of Durant, MS April 25, 2017

RACEWAYS 16110 - 2

2.4 IMC conduits, fittings, couplings, adapters, and accessories shall be UL listed. They shall be hot-galvanized steel. Fittings, couplings, adapters, and accessories shall be the same as those for GRS conduit described above. IMC shall meet UL 1242 and ANSI C80.6. Threads shall be hot galvanized after cutting. The inside of the conduit shall be finished with a corrosion-resistant coating. 2.5 EMT conduits, fittings, couplings, adapters, and accessories shall be UL listed. They shall be hot galvanized steel and shall be produced in accordance with UL 797 and ANSI C80.3. The inside shall be finished with a corrosion-resistant lubricating coating. 2.6 Conduit fittings used with EMT conduits may be set screw indenter type or compression type. All metallic fittings for IMC and Rigid conduit shall be compression type fittings. 2.7 Flexible metallic conduit shall be constructed of galvanized steel and shall be UL listed as compliant with UL I and UL 1479. 2.8 Liquidtight flexible conduit shall be constructed of galvanized steel and shall be coated with a PVC jacket to resist liquids, dirt, grease, and oils. All fittings shall be designed, constructed, and installed to maintain the integrity of the liquidtight connections. Liquidtight flexible conduit shall comply with UL 360. 2.9 Conduit straps used shall be metal two-hole straps. One-hole straps shall not be allowed. PART 3 - EXECUTION 3.1 Conduits run underground shall be buried no less than 24" deep. Services and primary conduits feeding transformers shall be buried no less than 48" deep, or as directed on plans. 3.2 Do not install conduits with outside diameters larger than 1/3 of the slab thickness in slabs. Space conduits a minimum of 6 conduit diameters apart in slabs. Conduit crossings shall occur no closer than 12" apart. Conduits shall be run in the center, not the bottom, of the slab. 3.3 Support and install all conduits per the latest edition of the National Electrical Code. Support groups of conduits with electrical strut supported by threaded rods anchored to the building structure. Supports shall be designed to hold no less than twice the weight of the conduit and conductors to be supported plus an additional 250 pounds at midspan. 3.4 All conduits shall be grouped and run parallel to each other and to building walls. 3.5 All conduits shall be assembled according to the manufacturer's instructions. 3.6 Conduits run underground shall be assembled to be watertight. 3.7 Low-voltage wiring, including control, instrumentation, and monitoring wiring, shall not be run

in the same conduit with power wiring. 3.8 Wiring from circuits of different voltages shall not be run together in the same conduit. 3.9 DC wiring shall not be run in same conduit with AC wiring. 3.10 Analog Signal wiring shall not be run in same conduit with digital signal wiring. 3.11 Cap all conduits during installation. Pull a mandrel sized for that conduit and a cleaning

09339 26 00 16010-16801 REPLACED by Addendum No. 1 Page 8 of 35

Page 32: ADDENDUM NO. 1 · Project #3-09339 BID SCHEDULE Item Estimate No. Item Description Quantity Unit 1 ... insurance, and other costs necessary to cover the finished work of the several

CCE Project No. 3-09339-16P Senior Citizens Center City of Durant, MS April 25, 2017

RACEWAYS 16110 - 3

brush through each conduit before installation of any conductors. 3.12 Conduits that are obviously damaged and field bends that are obviously out of round shall be replaced. 3.13 Use strap wrenches in the installation of PVC-coated conduit in order to prevent or minimize

damage to the conduit coating during installation. 3.14 Provide final connections to equipment with flexible metallic conduit, or as directed on plans. In

wet or damp locations, use liquidtight flexible metallic conduit, or as directed on plans. Flexible conduit shall not exceed six (6) feet in total conduit length.

3.15 Terminate conduits entering boxes with a locknut inside the box and a locknut outside the

box. Provide protective bushings on all conduit threads. Use watertight hubs, with grounding screw, where conduit terminations are exposed to moisture - Myers or equal.

3.16 Use grounding bushings where required by the National Electrical Code. 3.17 Conduits shall be run no closer than 12" to hot water pipes. 3.18 Where conduits are run through the ceiling and are required to make connections to equipment within the room that is not located near a wall, support the conduit from the structural ceiling and provide a flange bolted to the floor. Install a tee conduit fitting in the vertical run of conduit, and make the connection to the equipment with a piece of flexible conduit extending from the tee conduit fitting to the equipment. 3.19 Provide expansion fittings where conduits cross building expansion joints. Provide grounding jumpers between the conduits. 3.20. Provide EMT conduit sleeves where conduits pass through walls, floors, or footings sized a minimum of two nominal trade sizes larger than the conduit that must pass through the sleeve.

END OF SECTION

09339 26 00 16010-16801 REPLACED by Addendum No. 1 Page 9 of 35

Page 33: ADDENDUM NO. 1 · Project #3-09339 BID SCHEDULE Item Estimate No. Item Description Quantity Unit 1 ... insurance, and other costs necessary to cover the finished work of the several

CCE Project No. 3-09339-16P Senior Citizens Center City of Durant, MS April 25, 2017

OUTLET & JUNCTION BOXES 16150 - 1

SECTION 16150 - OUTLET BOXES AND JUNCTION BOXES PART 1 - GENERAL 1.1 Furnish and install all outlet boxes and junction boxes in accordance with this specification and the requirements of the NEC. 1.2 Provide outlet boxes for all switches, receptacles, luminaires, telephone jacks, cable jacks, data jacks and other devices furnished in this Contract. Provide all necessary hardware including, but not limited to, additional structural support, support brackets, screws, bolts, fixture studs, etc. PART 2 - PRODUCTS 2.1 ACCEPTABLE MANUFACTURERS Outlet boxes and junction boxes shall be manufactured by Raco, Steel City, Crouse Hinds, or Appleton. 2.2 GENERAL A. Outlet boxes and junction boxes in dry locations shall be galvanized stamped steel boxes sized per the latest edition of the National Electrical Code (NEC), but no less than 4" x 4" x 2 1/8" deep. The thickness of the steel shall be in compliance with the requirements of the NEC. Provide stamped steel covers for all junction boxes manufactured to fit the particular box on which it is used. B. Outlet boxes used in concrete and masonry walls and ceilings shall be of the concrete type manufactured for such applications. C. Outlet boxes and junction boxes in wet locations shall be of cast metal construction with gasketed waterproof covers. All conduit connections to the boxes shall be made watertight. D. Wall outlet boxes shall be 4" x 4" x 2 1/8", or larger as required, with plaster rings provided for final flush installation. E. Floor boxes in slabs on grade shall be deep rectangular, cast iron, fully adjustable boxes with brass rings. Covers shall be made of brass and shall provide flip top access to the power or data jacks inside. Screw-on covers are not acceptable unless a flip-top cover is unavailable for the device installed in the floor box. Provide the box sized as required for the number of devices shown installed. Boxes shall be as follows, or equal: 1. Single-Gang Boxes: Hubbell B2436 2. Single-Gang Cover Plates: Hubbell 53825 3. Double-Gang Boxes: Hubbell 64233 4. Double-Gang Cover Plates: Two Hubbell S3825 Cover Plates 5. Triple-Gang Boxes: Hubbell 134333 6. Triple-Gang Cover Plates: Three Hubbell S3825 Cover Plates

09339 26 00 16010-16801 REPLACED by Addendum No. 1 Page 10 of 35

Page 34: ADDENDUM NO. 1 · Project #3-09339 BID SCHEDULE Item Estimate No. Item Description Quantity Unit 1 ... insurance, and other costs necessary to cover the finished work of the several

CCE Project No. 3-09339-16P Senior Citizens Center City of Durant, MS April 25, 2017

OUTLET & JUNCTION BOXES 16150 - 2

In slabs above grade, use cast iron, semi-adjustable shallow boxes as follows, or equal:

1. Single-Gang Boxes: Hubbell 1324142. Two-Gang Boxes: Hubbell B42143. Three-Gang Boxes: Hubbell 134314

Receptacles installed in floor boxes shall be as described in Specification 16460, Switches and Receptacles. Data, Telephone, or Combination Data and Telephone Outlets shall consist of Category 5 rated RJ45 jacks mounted in a Hubbell DJOI strap for use under a 53825 flip top cover plate.

F. Size all boxes per the requirements of the latest NEC.

PART 3 - EXECUTION

3.1 All devices shall be flush mounted unless specific written permission is obtained from the Engineer for a particular device in a particular location.

3.2 Install outlet boxes in walls, and provide plaster rings such that wall finish contractors finish is flush against the edge of the plaster ring. Workmanship will not be accepted where the hole in the wall shows behind the cover plate, or the wall finish is uneven or unpainted at the edge of the cover plate.

3.3 Use round or square ceiling outlet boxes as required for the device being installed. The ceiling shall be finished flush against the box; the fixture shall completely cover the box and mount tight against the ceiling. Coordinate the requirements of the fixture prior to installing the box.

3.4 Provide junction boxes, pull boxes, and conduit fittings where required by the NEC to limit the number of bends in the raceway, and where required to prevent damage to conductors due to long runs.

3.5 Junction boxes and pull boxes installed in the ground outside shall be Quazite Composolite or approved equal. Mount the boxes over 24" of washed gravel fill. If splices are to be made inside the boxes, the boxes shall be of the type furnished with a bottom, and all conduit connections shall be watertight. In addition, all conductor splices shall be made watertight using an appropriate splice kit as manufactured by 3M, or an approved equal.

END OF SECTION

09339 26 00 16010-16801 REPLACED by Addendum No. 1 Page 11 of 35

Page 35: ADDENDUM NO. 1 · Project #3-09339 BID SCHEDULE Item Estimate No. Item Description Quantity Unit 1 ... insurance, and other costs necessary to cover the finished work of the several

CCE Project No. 3-09339-16P Senior Citizens Center City of Durant, MS April 25, 2017

GROUNDING 16250 - 1

SECTION 16250 - GROUNDING

PART 1 - GENERAL

1.1 GENERAL

Ground all equipment, systems, structures, etc., per the latest edition of the National Electrical Code (NEC).

PART 2 - PRODUCTS

2.1 Use mechanical bolted connections in dry locations that are accessible.

2.2 Use exothermic welds in wet locations and locations that will be inaccessible at the end of construction.

2.3 Ground rods shall be UL Listed 3/4" x 10' copper-clad steel ground rods with a minimum copper cladding thickness of 10 mils.

PART 3 - EXECUTION

3.1 Ground rods shall be installed with their tops no less than 6" below grade, and in the arrangement as shown on plans.

3.2 Bond ground connections to metal raceways at each end of the conduit run. Provide grounding bushings where required by the NEC. Where cable trays are used, bond the ground conductor to each section and fitting of the tray.

3.3 Provide all circuits with an equipment grounding conductor sized per the NEC, or as shown on the drawings. Circuitry shown on drawings does not include the required equipment grounding conductor. Where multiple circuits are run with a common neutral, only one equipment grounding conductor is needed. The equipment grounding conductor shall be furnished with green insulation for conductors #8 AWG and smaller; where larger than #8, the equipment grounding conductor shall be taped green for its entire exposed length.

3.4 The grounding electrode conductor(s) shall be bare or shall be colored green for its entire exposed length.

3.5 Individual grounding conductors shall be installed in PVC conduit sized per the NEC.

3.6 Provide receptacles, luminaires, and other devices with a green conductor that bonds the receptacle grounding screw or pigtail, the outlet box grounding screw, and the equipment grounding conductor together.

3.7 Telephone, cable television, and other auxiliary systems shall be bonded to the building electrical service entrance ground using a conductor no smaller than #6 AWG.

END OF SECTION

09339 26 00 16010-16801 REPLACED by Addendum No. 1 Page 12 of 35

Page 36: ADDENDUM NO. 1 · Project #3-09339 BID SCHEDULE Item Estimate No. Item Description Quantity Unit 1 ... insurance, and other costs necessary to cover the finished work of the several

CCE Project No. 3-09339-16P Senior Citizens Center City of Durant, MS April 25, 2017

CONDUCTORS 16410 - 1

SECTION 16410 - CONDUCTORS PART 1 - GENERAL Provide all circuitry, terminations, splices, connectors, lugs, and other equipment necessary for connection of all equipment requiring electrical connections. PART 2 - PRODUCTS 2.1 All electrical conductors shall be soft-drawn annealed copper having 98% conductivity and an insulation rating of 600V. 2.2 Conductors shall be UL listed for installation in the raceway in which they are to be installed. 2.3 Conductors shall be rated 75 degrees C minimum for use in residential, commercial, industrial,

and institutional facilities, and shall be listed as 105 degrees C appliance wire. Conductors shall be listed under UL 83, UL 1063, and UL 758. If XLP or EPR insulation is used, conductors shall be listed under UL 44 and NEMA WC7. 2.4 Conductors used for branch circuits, feeders, auxiliary systems, and controls run in dry

locations and where temperatures shall not exceed 75 degrees Celsius, shall have PVC insulation and a Nylon outerjacket. Conductors shall be THHW, THWN, XHHW, or THHN, THHW, THWN-2, XHHW-2. Other conductor types such as multi-conductor cable shall be as directed on the project drawings.

2.5 Conductors used for branch circuits, feeders, auxiliary systems, and controls run in wet locations shall have XLP or EPR insulation and be type XHHW or XHHW-2. 2.6 Conductors used for services shall be type XHHW-2 or RHW-2 for aerial services and type USE-

2 or XHHW-2 for underground services, or each as indicated on project drawings. 2.7 Sizes #10 and #12 shall be solid conductors except where used for controls. All controls conductors shall be stranded. 2.8 Conductors for branch and feeder circuits shall not be less than #12 AWG. Conductors for

controls and auxiliary circuits shall not be less than #16 AWG, or as indicated on plans. Size conductors as required, using larger conductors as required to compensate for voltage drops exceeding 3% of the system voltage, or as shown on the project drawings.

2.9 Conductors shall be furnished in the colors described below unless local ordinances require different colors. Conductors #8 and smaller shall be furnished with colored insulation; conductors larger than #8 shall be taped with the appropriately colored tape for a length of at least 2" at each panelboard, junction box, pull box, load, or other exposed location. Grounding conductors shall be taped green for their entire exposed length.

09339 26 00 16010-16801 REPLACED by Addendum No. 1 Page 13 of 35

Page 37: ADDENDUM NO. 1 · Project #3-09339 BID SCHEDULE Item Estimate No. Item Description Quantity Unit 1 ... insurance, and other costs necessary to cover the finished work of the several

CCE Project No. 3-09339-16P Senior Citizens Center City of Durant, MS April 25, 2017

CONDUCTORS 16410 - 2

System Voltage 208Y/120V, 3-Phase, 120/240V, 3-Phase, 480Y/277V, 3-Phase, 4-Wire 4-Wire 4-Wire Phase A Black Black Brown Phase B Red Orange Orange Phase C Blue Purple Yellow Neutral White White Gray Ground Green Green Green Table-1. Conductor Color Code PART 3 - EXECUTION 3.1 Install conductors carefully using a minimum of two tradesmen - one feeding the conductors into the conduit, and the other pulling the conductors into the conduit. 3.2 Install conductors in cable trays per NEC and NEMA standards, and as directed in project

drawings. 3.3 Join stranded conductors with appropriate mechanical or compression lugs. Wire nuts may be used for solid conductors only. 3.3 Splices in feeder and branch conductors shall not be made. 3.4 Provide cable supports and strain relief connectors as required by the NEC. 3.5 Furnish junction boxes, pull boxes, handholes, manholes, etc. as required to ensure that the maximum number of bends allowed by the NEC are not exceeded and to ensure that the cables are not damaged during installation. 3.6 All conductors shall be tested after conductor is installed in raceway but before termination on

ends. Conductors shall be tested by the following methods: 1. Conductive Continuity Test (Ohm-meter) 2. Conductor Insulation Resistance Test (Megger) a) The Megger test shall conform to ANSI/NETA ATS-2009 Standards for test voltages (Vdc) and minimum acceptable resistance values (Ohms).

END OF SECTION

09339 26 00 16010-16801 REPLACED by Addendum No. 1 Page 14 of 35

Page 38: ADDENDUM NO. 1 · Project #3-09339 BID SCHEDULE Item Estimate No. Item Description Quantity Unit 1 ... insurance, and other costs necessary to cover the finished work of the several

CCE Project No. 3-09339-16P Senior Citizens Center City of Durant, MS April 25, 2017

PANELBOARDS 16420 - 1

SECTION 16420 - PANELBOARDS PART 1 - GENERAL Furnish and install all panelboards, complete with their circuit breakers, phase buses, neutral buses, ground buses, structural supports, and other equipment necessary for complete systems. PART 2 - PRODUCTS 2.1 GENERAL A. Panelboards shall be designed, manufactured, and tested to be in compliance with NEMA PB 1, UL 50, UL 67, UL 489, NFPA 70, and the ASTM. B. Circuit breakers shall be designed, manufactured, and tested to be in compliance with NEMA AB 1, UL 489, and Federal Specification W-C-375B/GEN. C. Panelboards shall be UL listed for service entrance where used for that purpose. D. Panelboard ampere interrupting current (AIC) ratings shall equal the lowest rated device in the panelboard. Provide panelboards with the AIC ratings shown on the

Contract Drawings. Short Circuit Current Ratings (SCCR) of panelboard buses shall be braced to withstand the AIC rating shown on the drawings.

E. All panelboards shall be furnished with dead-front, door-in-door construction, unless

otherwise noted on plans or elsewhere in these specifications. F. Lug locations shall be determined during the creation of shop drawings for proper arrangement with the raceway system. G. Buses shall be constructed of 98% conductivity copper or equivalently rated aluminum. H. Panelboard enclosures shall be NEMA-1 when they are to be mounted indoors, and NEMA-3R when they are to be mounted outdoors. Provide special enclosures where shown on the Contract Drawings. 2.2 ACCEPTABLE MANUFACTURERS Panelboards shall be manufactured by Eaton, Square D, or Siemens. 2.3 PANELBOARD CLASSES A. Power distribution panelboards shall be available with mains and branch devices up

to 1200 amperes. AIC ratings shall be available up to 200,000 Amperes. Power distribution panelboards shall be equipped with a nameplate containing the appropriate system voltage, number of wires, and number of phases for the system on which they are installed.

09339 26 00 16010-16801 REPLACED by Addendum No. 1 Page 15 of 35

Page 39: ADDENDUM NO. 1 · Project #3-09339 BID SCHEDULE Item Estimate No. Item Description Quantity Unit 1 ... insurance, and other costs necessary to cover the finished work of the several

CCE Project No. 3-09339-16P Senior Citizens Center City of Durant, MS April 25, 2017

PANELBOARDS 16420 - 2

B. In 48OVac and less applications where a main breaker not exceeding 600 Amperes is required, the AIC rating does not exceed 65,000 Amperes, and no branch breakers exceed 125 amperes, Square D NF and equivalent panelboards may be used. C. In 24OVac and less applications where a main breaker not exceeding 400 Amperes or main

lugs not exceeding 600 Amperes is required, the AIC rating does not exceed 22,000 Amperes, and no branch breakers exceed 125 Amperes, Square D NQ and equivalent panelboards may be used.

D. Residential-Type Load Center panelboards shall not be used. 2.4 CIRCUIT BREAKERS A. Circuit breakers shall be thermal magnetic, molded-case with quick-make, quick- break contact action. They shall have thermal and magnetic tripping elements on each pole. Breakers with multiple poles shall have common tripping of all poles. Circuit breaker ampere ratings shall be stamped on the handle. Interrupting ratings of the circuit breakers shall be equivalent to the specified AIC rating of the panelboard. Breakers handles shall reside in a position between "ON" and "OFF" after a trip condition. Breakers shall be rated HACR when used for heating, air- conditioning, and refrigeration: HID when used with High Intensity Discharge fixtures; and shall be rated SWD when used for switching duty. PART 3 - EXECUTION 3.1 Install panelboards in complete compliance with all manufacturers' installation instructions. 3.2 Install conductors neatly in panelboards. Group and tie-wrap circuits that share a common neutral. 3.3 Provide a typewritten circuit schedule on the inside of the panel door for each panelboard.

Switchboards shall have their circuits labeled at each circuit breaker with a permanent thermal imprinted, heat and UV-resistant label. In no case shall hand-written labels be allowed, nor shall any hand writing be allowed on the equipment.

3.3 Number circuits exactly as shown on the contract drawings. Deviations from the circuit

schedule(s) shall make the electrical contractor completely responsible for ensuring the proper balancing of loads on the phases and/or legs of the electrical system.

END OF SECTION

09339 26 00 16010-16801 REPLACED by Addendum No. 1 Page 16 of 35

Page 40: ADDENDUM NO. 1 · Project #3-09339 BID SCHEDULE Item Estimate No. Item Description Quantity Unit 1 ... insurance, and other costs necessary to cover the finished work of the several

CCE Project No. 3-09339-16P Senior Citizens Center City of Durant, MS April 25, 2017

DISCONNECTS & SEPARATELY-MOUNTED CIRCUIT BREAKERS 16430 - 1

SECTION 16430 - DISCONNECTS & SEPARATELY-MOUNTED CIRCUIT BREAKERS PART 1 - GENERAL Furnish and install all disconnects and separately mounted circuit breakers as shown on the drawings, specified herein, and required by the NEC. PART 2 - PRODUCTS 2.1 GENERAL

A. Unless noted otherwise on project drawings and schedules, Disconnects shall be of the heavy-duty type, and shall be UL listed for service entrance use. They shall meet or exceed the requirements of NEMA Standard KS1. For fused disconnects, provide fuses sized to appropriately protect the load served, or as shown on project drawings. Equipment manufacturer's recommendations shall take precedence over the Contract Drawings.

B. Fuses shall be dual element, time-delay, Class RK-1, and have an Interrupting Rating of

200,000 Amps. Fuses shall be Bussman Low-Peak, Ferraz Shawmut, Littlefuse or approved equal. Other fuse types, if used, shall be as shown on the project drawings.

C. Circuit breakers shall be thermal magnetic, molded-case with quick-make, quick-break

contact action. They shall have thermal and magnetic tripping elements on each pole. Breakers with multiple poles shall have common tripping of all poles. Circuit breaker ampere ratings shall be stamped on the handle. Interrupting ratings of the circuit breakers shall be equivalent to the specified AIC rating of the paneIboard. Breakers handles shall reside in a position between ON" and "OFF" after a trip condition. Breakers shall be rated HACR when used for heating, air-conditioning, and refrigeration; HID when used with High Intensity Discharge fixtures; and shall be rated SWD when used for switching duty.

D. Disconnects and individually-mounted circuit breaker ampere interrupting current (AIC)

ratings shall equal the rating of the panelboard from which they are fed unless otherwise noted.

E. Disconnects used as service-entrance equipment shall have a short circuit current rating (SCCR) sufficient to withstand the available short circuit current, as shown on the project drawings, or elsewhere in these specifications, or as provided by others. Equipment manufacturer’s recommendations shall take precedence over the contract documents. Disconnects used as service entrance equipment shall be service-entrance-rated, and shall contain grounding lugs and apparatus for NEC-required grounding.

F. Buses shall be constructed of 98% conductivity copper or equivalently rated aluminum. G. Switches shall be horsepower rated where used to serve motors. H. Unless noted otherwise on the project drawings, enclosures shall be NEMA-1 when they are

to be mounted indoors, NEMA-3R when they are to be mounted outdoors, and NEMA-4X where they are subject to washdown or corrosive materials. Provide special enclosures where shown on the Contract Drawings.

09339 26 00 16010-16801 REPLACED by Addendum No. 1 Page 17 of 35

Page 41: ADDENDUM NO. 1 · Project #3-09339 BID SCHEDULE Item Estimate No. Item Description Quantity Unit 1 ... insurance, and other costs necessary to cover the finished work of the several

CCE Project No. 3-09339-16P Senior Citizens Center City of Durant, MS April 25, 2017

DISCONNECTS & SEPARATELY-MOUNTED CIRCUIT BREAKERS 16430 - 2

2.2 ACCEPTABLE MANUFACTURERS

Disconnects and separately-mounted circuit breakers shall be manufactured by Square D, Eaton, or Siemens.

PART 3 - EXECUTION 3.1 Install disconnects and individually-mounted circuit breakers in complete compliance with all manufacturers' installation instructions. Where necessary, provide structural supports and bracing for installation. 3.2 Disconnects are to be surface-mounted. 3.3 Individually-mounted circuit breakers are to be flush-mounted unless otherwise shown.

END OF SECTION

09339 26 00 16010-16801 REPLACED by Addendum No. 1 Page 18 of 35

Page 42: ADDENDUM NO. 1 · Project #3-09339 BID SCHEDULE Item Estimate No. Item Description Quantity Unit 1 ... insurance, and other costs necessary to cover the finished work of the several

CCE Project No. 3-09339-16P Senior Citizens Center City of Durant, MS April 25, 2017

SURGE PROTECTIVE DEVICES 16440 - 1

SECTION 16440 - SURGE PROTECTIVE DEVICES

PART 1 - SUMMARY

This section describes the quality, performance, and installation of Parallel Connected, AC Power, Panel Type, Surge Protective Devices (SPDs).

PART 2 - QUALITY ASSURANCE

All Surge Protective Devices (SPDs) shall be tested and listed to ANSI/UL 1449-2006 (UL 1449 3rd Edition) and Complimentary Listed to UL 1283 by an independent testing agency, with the experience and capability to conduct the testing indicated, that is a member company of the International Electrical Testing Association or is a Nationally Recognized Testing Laboratory (NRTL) as defined by OSHA in 29 CFR 1910.7, and that is acceptable to authorities having jurisdiction. This agency must comply with NSI/IEEE C62.45 test procedures for all categories established in C62.41 (1991). “Manufactured in accordance with UL 1449” is not equivalent to being listed to ANSI/UL 1449-2006 and does not meet the intention of this specification.

PART 3 - CODES AND STANDARDS

3.1 ANSI/IEEE Std C62.41.1™-2002, IEEE Guide on the Surge Environment in Low- Voltage (1000 V and Less) AC Power Circuits.

3.2 ANSI/IEEE Std C62.41.2™-2002, IEEE Recommended Practice on Characterization of Surges in Low-Voltage (1000 V and Less) AC Power Circuits.

3.3 ANSI/IEEE Std C62.45™ -2002, IEEE Recommended Practice on Surge Testing for Equipment Connected to Low-Voltage (1000 V and Less) AC Power Circuits.

3.4 ANSI C84.1, American National Standard for Electric Power Systems and Equipment – Voltage Ratings 60 Hertz).

3.5 ANSI/IEEE Standard 1100-2005, IEEE Recommended Practice for Power and Grounding Electronic Equipment (Emerald Book) - Clause 8.6.1.

3.6 National Fire Protection Association (NFPA) 70 (N.E.C.) – 2002 - Article 285.

3.7 ANSI/UL Standards 1449-2006 Listed (UL 1449 Third Edition), UL 1283 Listed,CUL Listed & CE compliant “low-voltage directive.”

3.8 IEEE Standard C62.72™ - 2007 – IEEE Guide for the Application of Surge-Protective Devices for Low-Voltage (1000 V or less) AC Power Circuits.

3.9 IEEE Standard 1100-1999, IEEE Recommended Practice for Power and Grounding Electronic Equipment.

09339 26 00 16010-16801 REPLACED by Addendum No. 1 Page 19 of 35

Page 43: ADDENDUM NO. 1 · Project #3-09339 BID SCHEDULE Item Estimate No. Item Description Quantity Unit 1 ... insurance, and other costs necessary to cover the finished work of the several

CCE Project No. 3-09339-16P Senior Citizens Center City of Durant, MS April 25, 2017

SURGE PROTECTIVE DEVICES 16440 - 2

PART 4 - MANUFACTURER QUALIFICATIONS 4.1 All surge suppression devices shall be manufactured by an ISO 9001-2000 certified

company normally engaged in the design, development, and manufacture of such equipment, with at least 10 years of engineering experience in the design and manufacture of permanently connected SPD devices.

4.2 The surge suppressor manufacturer shall provide unlimited free replacement of the entire

SPD for all inoperable SPD units during the warranty period. 4.3 The listing of a manufacturer as “acceptable” does not imply automatic approval. It is

the sole responsibility of the Contractor to ensure that any submittals made are for products that meet or exceed the specifications included herein. Subject to compliance with requirements, provide products by the following:

• Surge Suppression Incorporated (888-212-2728) • Liebert Corporation 614-888-0246 • Square-D • Eaton • APT • Or Pre-approved equal.

A. Pre-Approval submittals for products by manufacturers not listed above must be

submitted not less than ten (10) business days prior to bid date to allow ample engineering time for review of submitted products.

B. Submit proper documentation showing detailed (line-by-line) compliance with this

specification. Prior approvals not received by the deadline date defined above will not be considered.

C. Along with the line-by-line comparison from manufacturers not listed herein, pre-

approval surge suppression submittals shall include all of the items listed in Part 5, below.

PART 5 – SUBMITTALS 5.1 Surge suppression submittals shall include, but shall not be limited to the following

items: A. Complete schematic data for all suppressors indicating part numbers, conductor

sizes, etc. B. Dimensioned drawing of each suppressor type indicating mounting arrangement.

C. Manufacturer’s ANSI/UL 1449-2006 Third Edition listing classification page and listing number(s).

09339 26 00 16010-16801 REPLACED by Addendum No. 1 Page 20 of 35

Page 44: ADDENDUM NO. 1 · Project #3-09339 BID SCHEDULE Item Estimate No. Item Description Quantity Unit 1 ... insurance, and other costs necessary to cover the finished work of the several

CCE Project No. 3-09339-16P Senior Citizens Center City of Durant, MS April 25, 2017

SURGE PROTECTIVE DEVICES 16440 - 3

D. Manufacturer’s UL 1283 listing classification page and listing number(s).

E. Certified test data documenting ANSI/IEEE C62.41-2002 performance and the

ability of the device to meet or exceed all requirements of this specification. Include complete let-through voltage/measured limiting voltage test data (not Voltage Protection Rating), test graphs, and scope traces for each mode for each product submitted for Category’s C, B, A (including Cat A, 2 kV, 67 A, 100 kHz ring wave at both 90 & 270 degree electrical phase angles).

F. Letter from manufacturer stating products are in strict compliance with the recommendations of IEEE Standard 1100-2005, Clause 8.6.1 and incorporate 10 individual dedicated discrete modes of protection for three-phase Wye systems, including direct line-to-line components. (Reduced-mode variations will not be accepted).

G. Certificate of declaration that product is CE low voltage directive compliant.

H. Statement of manufacturer’s warranty duration and replacement policy.

PART 6 – REQUIREMENTS 6.1 The Surge Protective Devices (SPDs) shall be of a parallel-connected design using fast-

acting transient energy protection components that will divert and dissipate the surge energy.

6.2 All SPDs shall be tested and listed to ANSI/UL 1449-2006 (UL 1449 3rd Edition) &

Complimentary Listed to UL 1283 by a Nationally Recognized Testing Laboratory (NRTL) (i.e. CSA, UL, etc).

6.3 SPDs shall be Type 1 or Type 2 SPDs, as application dictates; Type 4 SPDs are not

permitted. 6.4 The SPD shall be tested and listed by an NRTL as a complete assembly to a

symmetrical fault current rating greater than or equal to the available fault current at the location of installation at the connected panel, in accordance with NEC Article 285 and shall be marked with the Short Circuit Current Rating (SCCR). If the available fault current is unknown, then the SCCR of the SPD shall be 200 kAIC.

6.5 Permanently connected devices mounted parallel to the service, distribution, and sub

panels are required. SPD device drawings shall be made available upon request. 6.6 The SPD shall have a Nominal Discharge Current (In) of 10 kA. ((The Nominal

Discharge Current Test was designed to establish that the SPD remains functional after

09339 26 00 16010-16801 REPLACED by Addendum No. 1 Page 21 of 35

Page 45: ADDENDUM NO. 1 · Project #3-09339 BID SCHEDULE Item Estimate No. Item Description Quantity Unit 1 ... insurance, and other costs necessary to cover the finished work of the several

CCE Project No. 3-09339-16P Senior Citizens Center City of Durant, MS April 25, 2017

SURGE PROTECTIVE DEVICES 16440 - 4

15 surges at various currents (3 kA, 5 kA, 10 kA, and 20 kA) using the test procedure described in ANSI/UL 1449-2006.))

6.7 FUSING:

A. The SPD shall provide as a minimum, over-current, over temperature protectionin the form of component-level thermal fusing to ensure safe failure and preventthermal runaway. This component-level fusing shall be an integral part of theMOV itself and not silver wire (or other) independently laid across each MOV.SPDs without thermal fuses or disconnects, or SPDs with shared thermaldevices that disconnect more than one MOV are not acceptable.

B. Surge protective devices shall contain integral short circuit current safety fusingwithin each device for over-current requirements of the NEC. This fusing willbe independent of the “component-level” fusing and be specifically for over-current protection and shall be constructed utilizing surge rated, cartridge fusesand not rated ‘silver-fuse-wire’ (or other).

C. The use of any mechanical or electro-mechanical thermal/over-currentprotection (i.e. moving parts and/or springs and shutters) in combination with orfor the protection of the suppression elements is expressly prohibited and willbe rejected.

D. The fusing mechanisms employed must effectively coordinate theirperformance in conjunction with the high current abnormal over-voltage testingunder ANSI/UL 1449-2006 (a.k.a. UL 1449 3rd Edition).

6.8 MCOV:

The SPD shall have a maximum continuous operating voltage (MCOV) capable of sustaining 115% of nominal RMS voltage continuously without degrading.

6.9 COMPONENT LIMITATIONS: The SPD shall only use solid-state clamping components to limit the surge voltage and divert the surge current. SPD components that “crowbar” short-circuit the AC power system (e.g. spark gaps, gas tubes, selenium cells, or SCR’s) shall not be acceptable. Device circuitry shall be bi-directional, enclosed in a UL listed encapsulated thermal stress reducing compound, and be of a parallel design.

6.10 PROTECTION MODES: The SPD system shall provide (per IEEE Std. 1100-1999 8.6.1) dedicated, independent, distinct, individual protection circuitry for every possible mode in the electrical distribution system at the point of SPD application. For example, a 277/480V, 3-phase Wye, 4-wire plus ground system has 10 distinct modes that require independent and dedicated protection (i.e., L1-L2, L2-L3, L3-L1, L1-N, L2-N, L3-N, L1-G, L2-G, L3-G, N-G). None of these modes of protection depend on protection elements purposed for other protection modes. Reduced mode

SPD with only 3, 4, or 7 dedicated, distinct, independent protection modes are not acceptable and are not to be submitted. For 6 mode delta systems, 6 dedicated, independent, distinct protection modes are required (L1-L2, L2-L3, L3-L1, L1-G, L2-G, L3-G). When a mode of

09339 26 00 16010-16801 REPLACED by Addendum No. 1 Page 22 of 35

Page 46: ADDENDUM NO. 1 · Project #3-09339 BID SCHEDULE Item Estimate No. Item Description Quantity Unit 1 ... insurance, and other costs necessary to cover the finished work of the several

CCE Project No. 3-09339-16P Senior Citizens Center City of Durant, MS April 25, 2017

SURGE PROTECTIVE DEVICES 16440 - 5

protection is specified, the protective mode must be specifically included. Thus, Line-to-Neutral-to-Line is not acceptable where Line-to-Line is specified. 6.11 SINEWAVE TRACKING CAPABILITY: Power panels and MCCs serving sensitive electronic equipment shall utilize voltage independent, dedicated Sinewave Tracking circuitry. EMI/RFI filtering specifically will not be considered as equal to sinewave tracking! To demonstrate the sinewave tracking capability of the submitted devices, manufacturers shall submit 3rd party, independent tests results for units claiming sinewave tracking capability. Such tests shall include testing under the standards of ANSI/IEEE C62.41 and C62.45 category A1 (2kV, 67A, 100kHz ring wave) applied at the 270 degree phase angle, positive polarity, on a 120/208Vrms, 3 phase Wye device, on each of the following modes: line-to-neutral, line-to-ground, and line-to-line (dynamic tests with normal voltage applied to the unit under test), and neutral-to-ground (static test with no normal voltage applied to unit under test). The “let-through voltage” derived from each of these tests shall have a maximum amplitude of less than 50V peak deviation from the insertion point of the surge on the sine wave to the peak of the transient. Measurement of the let-through voltage shall be made with six-inches of lead length external to the SPD housing in accordance with ANSI/UL 1449-2006. Performance requirements are as stated in the table in Section VIII below (ANSI/IEEE C62.41 Let-Through Voltage) at Test Category A1. 6.12 STATUS INDICATORS: SPD UNITS SHALL HAVE PANEL FRONT STATUS MONITORS AS A MINIMUM TO INDICATE A CONTINUOUS POSITIVE STATUS OF EACH PROTECTED PHASE. A REMOTE AUDIBLE ALARM OPTION MUST BE SUPPLIED WHERE THE SPECIFYING ENGINEER DEEMS IT NECESSARY AND COST EFFECTIVE UNDER THE CIRCUMSTANCES. REFER TO THE APPROPRIATE DRAWINGS AND SCHEDULES FOR THESE DETAILS. 6.13 EQUIPMENT CERTIFICATION: Items shall be listed to ANSI/UL 1449-2006, shall bear the seal of the NRTL, shall bear the Marking “Listed to UL 1449”, shall have been tested under ANSI/UL 1449-2006, and shall be marked in accordance with the referenced standard. SPD units shall be UL 1283 Listed as an Electromagnetic Interference Filter and marked accordingly. All surge suppression devices shall be manufactured by an ISO 9001-2001 certified company normally engaged in the design, development, and manufacture of such equipment. 6.14 CIRCUIT CONFIGURATION: The circuit configuration of the suppression units shall be bi-directional, thermal stress reducing, encapsulated, custom parallel connected, and solid state. (Series units or units equipped with “load carrying” components are expressly prohibited due to the possibility of single point series failures causing power interruption to protected loads.) 6.15 ENCLOSURES: Unless otherwise noted, provide NEMA 1 or better enclosure for indoor mounting and NEMA 4 enclosure or better for all outdoor locations. All units will contain Form C, N/O or N/C, dry relay contacts, if so specified, and weatherproof fittings to maintain the required NEMA integrity. 6.16 MAINTENANCE RESTRICTIONS:

09339 26 00 16010-16801 REPLACED by Addendum No. 1 Page 23 of 35

Page 47: ADDENDUM NO. 1 · Project #3-09339 BID SCHEDULE Item Estimate No. Item Description Quantity Unit 1 ... insurance, and other costs necessary to cover the finished work of the several

CCE Project No. 3-09339-16P Senior Citizens Center City of Durant, MS April 25, 2017

SURGE PROTECTIVE DEVICES 16440 - 6

No suppression unit shall be supplied which requires scheduled preventive maintenance or replacement parts. Units requiring functional testing, special test equipment, or special training to monitor surge protection device (SPD) status are not acceptable. SPD shall require NO routine maintenance. SPD devices are considered non-repairable items and shall be fully replaced upon failure. 6.17 COMMONALITY: All SPDs at the service entrance, distribution panels, and sub-panels shall be from the same manufacturer. 6.18 All SPDs shall meet or exceed the following performance criteria:

A. Service Entrance (Category C): Service Entrance (Category C): The SPD shall provide a minimum protection of 480 kA or 240 kA per phase – (REFER TO CONTRACT DRAWINGS FOR SPECIFIC RATING), (three-phase Wye) and be capable of meeting the Category C-High Let-Through Voltage criteria as shown in the Section VII, below.

B. Building Distribution Panels (Category B): The SPD shall provide a minimum protection of 240 kA per phase and be capable of meeting the Category B3-High Let-Through Voltage criteria as shown in the Section VII, below.

C. Branch Panels/Panelboards (Non-Electronics) (Category A): The SPD shall provide a minimum protection of 120kA per phase and be capable of meeting the Category B-High Let-Through Voltage criteria as shown in the Section VII, below.

6.19 BRANCH PANELS/PANELBOARDS (ELECTRONICS) (CATEGORY A): The SPD shall provide a minimum protection of 120kA per phase, be of sinewave tracking design, and be capable of meeting the Category A Let-Through Voltage criteria as shown in Part 7, below.

PART 7 - ANSI/IEEE C62.41 LET-THROUGH VOLTAGE 7.1 The SPD shall meet the Let-Through Voltage requirements shown in the tables below for voltage and locations specified. All voltages shall be peak (±10%) Positive Polarity, Time base = 10μS, Sampling Rate = 500 Megasamples per second to ensure maximum transient capture. [These settings assure Let-through Voltage test results are accurate]. Surge voltages shall be measured from the insertion of the surge on the sine wave to the peak of the surge. All tests are Static (unpowered), except for the 120V circuits that are Dynamic (powered). Let-through voltages on static tests calculated by subtracting sine wave peak from let-through measured from zero. All tests shall be performed in accordance with UL 1449 Third Edition with measurements performed at a point on the leads 15.24 cm (6 inches) outside of the device enclosure. No data measured at a module, lugs, component, or undefined location will be accepted. These settings assure Let-through Voltage test results are accurate. SPDs shall meet the following criteria:

A. Service Entrance ANSI/IEEE Cat. C Impulse Wave

09339 26 00 16010-16801 REPLACED by Addendum No. 1 Page 24 of 35

Page 48: ADDENDUM NO. 1 · Project #3-09339 BID SCHEDULE Item Estimate No. Item Description Quantity Unit 1 ... insurance, and other costs necessary to cover the finished work of the several

CCE Project No. 3-09339-16P Senior Citizens Center City of Durant, MS April 25, 2017

SURGE PROTECTIVE DEVICES 16440 - 7

The let-through voltage based on ANSI/IEEE C62.41 and C62.45 recommended procedures for the ANSI/IEEE Cat. C Impulse Wave (20kV, 10,000 amps) at the 90 degree phase angle, shall be less than (values are total let-through voltage (LTV) measured from the insertion point of the transient on the sine wave to the peak of the transient):

Mode / Voltage 120/208Y 277/480Y 480V, 3Ø∆ L-N 950V 1075V N/A L-L 1175V 1350V 1375V L-G 1040V 1275V 1375V N-G 1200V 1585V N/A

B. Distribution and Branch Panels/Panelboards (Non-Electronics)ANSI/IEEE Cat. B Combination Wave Impulse Let-Through Voltage:

The let-through voltage based on ANSI/IEEE C62.41 and C62.45 recommended procedures for the ANSI/IEEE Cat. B Combination Wave Impulse (6kV, 3000 amps) at the 90 degree phase angle, shall be less than; (values are total let-through voltage (LTV) measured from the insertion point of the transient on the sine wave to the peak of the transient):

Mode / Voltage 120/208Y 277/480Y 480V, 3Ø∆ L-N 390V 560V N/A L-L 580V 900V 900V L-G 400V 600V 900V N-G 575V 985V N/A

C. Branch Panels/Panelboards (Electronics) ANSI/IEEE Cat. A Ring WaveLet-through-Voltage:

The let-through voltage based on ANSI/IEEE C62.41 and C62.45 recommended procedures for the ANSI/IEEE Cat. A Ring Wave (2kV, 67 amps, 100kHz ring wave) at the 270 degree phase angle, shall be less than; (values are total let-through voltage (LTV) measured from the insertion point of the transient on the sinewave to the peak of the transient):

Mode / Voltage

120/208Y 277/480Y 480V, 3Ø∆

L-N 50V 65V N/A L-L 60V 135V 65V L-G 65V 85V 65V N-G 60V 60V N/A

PART 8 - ANSI/UL 1449-2006 VOLTAGE PROTECTIVE RATING

09339 26 00 16010-16801 REPLACED by Addendum No. 1 Page 25 of 35

Page 49: ADDENDUM NO. 1 · Project #3-09339 BID SCHEDULE Item Estimate No. Item Description Quantity Unit 1 ... insurance, and other costs necessary to cover the finished work of the several

CCE Project No. 3-09339-16P Senior Citizens Center City of Durant, MS April 25, 2017

SURGE PROTECTIVE DEVICES 16440 - 8

8.1 Voltage Protection Rating (VPR) is a rating selected from a list of preferred values as detailed in ANSI/UL 1449-2006 and assigned to each mode of protection. The value of VPR is determined as the nearest highest value taken from a list of preferred values (as detailed in ANSI/UL 1449-2006) compared to the measured limiting voltage determined during the transient voltage surge suppression test using the combination wave generator at a setting of 6 kV, 3 kA.

8.2 The SPD shall have Voltage Protection Ratings (VPRs) no greater than those shown

below:

Nominal System Voltage Mode VPR

120/240 Single-Phase

L-N L-L L-G N-G

500 V 1000 V 500 V 500 V

120/240 Three-Phase

L-N HL-N L-L L-G

HL-G N-G

500 V 1000 V 1000 V 500 V

1000 V 500 V

120/208 Wye

L-N L-L L-G N-G

500 V 1000 V 500 V 500 V

277/480 Wye

L-N L-L L-G N-G

1000 V 1800 V 1000 V 1200 V

480 Delta L-L L-G

1800 V 1800 V

PART 9 - WARRANTY 9.1 All SPD devices shall be warranted to be free from defects in materials and workmanship under

normal use in accordance with the instructions provided for a period of twenty-five (25) years from date of substantial completion.

9.2 Any SPD device that shows evidence of failure or incorrect operation, including damage as the

result of lightning strikes, during the warranty period shall be replaced as a complete unit (not just modules, subassemblies, or components) by the manufacturer at no charge to the owner. Warranty will provide for multiple exchanges of any inoperable devices at any time during the warranty period that starts at the date of substantial completion of the system to which the surge suppressor is installed.

9.3 SPD manufacturers whose warranty does not meet the requirements listed above standard

shall submit a letter extending the warranty to meet these standards with the product submittal

PART 10 - INSTALLATION 10.1 Provide surge suppressor at each building service entrance and at other distribution and

panelboard locations as indicated on the drawings. The SPD shall be located immediately adjacent to the switchboard or panelboard being protected (close-nipple to panel-boards). The SPD may be located integral (switchgear manufacturer installed)

09339 26 00 16010-16801 REPLACED by Addendum No. 1 Page 26 of 35

Page 50: ADDENDUM NO. 1 · Project #3-09339 BID SCHEDULE Item Estimate No. Item Description Quantity Unit 1 ... insurance, and other costs necessary to cover the finished work of the several

CCE Project No. 3-09339-16P Senior Citizens Center City of Durant, MS April 25, 2017

SURGE PROTECTIVE DEVICES 16440 - 9

within a switchboard if the switchgear manufacturer providing such SPD products expressly meets or exceeds ALL parameters of this specification for the SPD. These SPDs shall be individually tested and Listed to ANSI/UL 1449-2006 according to their type and not be listed solely as part of the larger assembly. SPD devices not meeting or exceeding the performance of this specification will be deemed unacceptable.

10.2 Do not energize or connect service entrance equipment and panelboards to their sources until TVSS devices are properly installed and connected.

10.3 Do not perform insulation resistance tests of the distribution wiring equipment with the TVSS installed. Disconnect before conducting insulation resistance tests, and reconnect immediately after the testing is over.

10.4 Install the SPD with #10 AWG minimum conductors to dedicated 30-amp breaker(s) in panel per manufacturer’s installation instructions and close to the Neutral Bus. The dedicated breaker shall serve as a means of service disconnect for the SPD so that the electrical panel remains energized during SPD servicing. The installer may rearrange breaker locations to ensure the shortest and straightest leads to the SPD. If a dedicated breaker is not provided, an SPD with internal 30-amp fuse or a UL Listed fused disconnect switch shall be installed as a minimum. The conductors serving the SPD shall be twisted together (one twist per 12” of wire) to reduce the SPD system input impedance and shall be kept at the minimum length. The SPD shall be installed in strict accordance with the manufacturer’s recommended practices and in compliance with N.E.C. requirements, State, and Local Codes.

10.5 If any lead lengths exceed 18”, the Contractor responsible for installation must contact the specifying electrical engineer and the surge suppression manufacturer or distributor (888-212-2728) for installation assistance.

10.6 The electrical contractor shall verify the proper application of the SPD (i.e., voltage, phases, etc.). The electrical contractor shall ensure that all Neutral conductors are bonded to the system Ground at the service entrance or the serving isolation transformer prior to installation of the associated SPD. The electrical contractor will ensure that neutral-to-ground bonds do not exist at locations that are not service entrances or newly derived power sources.

10.7 The electrical contractor shall furnish all labor, materials, equipment, and services necessary for and incidental to the installation of the SPD system components as specified herein.

10.8 The electrical contractor shall coordinate with other electrical work as necessary to interface installation of the transient voltage surge suppression systems with other work on the site.

10.9 The SPD installation shall be certified by a licensed electrician that the installation is in accordance with the manufacturer’s recommendations, applicable electrical code requirements and the requirements of the specification above. Any deficiencies noted shall be corrected by the Contractor. Provide written documentation of this inspection as part of the closeout documentation

END OF SECTION

09339 26 00 16010-16801 REPLACED by Addendum No. 1 Page 27 of 35

Page 51: ADDENDUM NO. 1 · Project #3-09339 BID SCHEDULE Item Estimate No. Item Description Quantity Unit 1 ... insurance, and other costs necessary to cover the finished work of the several

CCE Project No. 3-09339-16P Senior Citizens Center City of Durant, MS April 25, 2017

WIRING DEVICES – SWITCHES & RECEPTACLES 16460 - 1

SECTION 16460- WIRING DEVICES - SWITCHES AND RECEPTACLES

PART 1 - GENERAL

Furnish and install all switches and receptacles in accordance with this specification and the requirements of the NEC.

PART 2- PRODUCTS

2.1 ACCEPTABLE MANUFACTURERS: Switches and receptacles shall be manufactured by Hubbell, Cooper Wiring Devices, Leviton, or Pass & Seymour.

2.2 GENERAL

A. Switches and receptacles shall be specification grade. They shall have ampacityand voltage ratings suitable for the application in which they are used.

B. Consult architect or engineer for device colors prior to ordering devices.

C. Provide brushed stainless steel cover plates for all devices. A single cover plateshall cover all devices in one box.

D. Light switches shall be minimum 15 Ampere, 120-277V back-wired and side-wired toggleswitches. They shall be rated up to 2 HP at 240V. Each switch shall be equipped with agrounding screw. Switches shall be Hubbell CSB series or approved equal.

E. Wall Switch Occupancy Sensors

1. Wall Switch Occupancy Sensors shall be of the Passive Infrared (PIR) type, capable ofdetecting infrared emissions from human presence and responding by switchingincandescent, low-voltage, and fluorescent lighting loads on. If the occupancy sensorswitch does not detect movement after a pre-set period of time, it will respond byswitching its assigned load off. The unit shall switch at the zero crossing point of the ACpower curve to ensure maximum relay contact life and compatibility with electronicballasts.

2. The wall switch occupancy sensor shall be equipped with a push-button to providemanual on/off switching. The unit shall feature adjustable delayed-OFF time and ambientlight override capabilities. The unit shall also provide sensitivity adjustment and integralsliding blinders to customize the horizontal field of view. The unit shall be capable ofproviding optional manual-on/automatic-off operation.

3. Wall Switch Occupancy Sensors shall be line-voltage, 120/277VAC, 60Hz, with aminimum load rating of 1200VA at 120V and 2700VA at 277V for fluorescent loads, and800W at 120V for incandescent loads, and shall be capable of switching motor loads ofup to 1/4HP at 120V.

09339 26 00 16010-16801 REPLACED by Addendum No. 1 Page 28 of 35

Page 52: ADDENDUM NO. 1 · Project #3-09339 BID SCHEDULE Item Estimate No. Item Description Quantity Unit 1 ... insurance, and other costs necessary to cover the finished work of the several

CCE Project No. 3-09339-16P Senior Citizens Center City of Durant, MS April 25, 2017

WIRING DEVICES – SWITCHES & RECEPTACLES 16460 - 2

F. Power receptacles shall be 20 Ampere, 125V, Duplex NEMA 5-20R, Hubbell HBL5362 or approved equal.

G. Duplex GFI NEMA 5-20R receptacles shall be Hubbell GFR5362 or approved equal. H. Other receptacles and wiring devices not listed in this section shall be of type and

specifications shown on the project drawings. I. Devices furnished in this Contract, but not listed above, shall be of the same standard of quality as those items listed. PART 3 - EXECUTION 3.1 Flush mount all devices unless shown otherwise on the project drawings, or specific written

permission is obtained from the Engineer for a particular device in a particular location. 3.2 Install all devices vertically unless the drawings specifically state that the particular device should be mounted horizontally.

END OF SECTION

09339 26 00 16010-16801 REPLACED by Addendum No. 1 Page 29 of 35

Page 53: ADDENDUM NO. 1 · Project #3-09339 BID SCHEDULE Item Estimate No. Item Description Quantity Unit 1 ... insurance, and other costs necessary to cover the finished work of the several

CCE Project No. 3-09339-16P Senior Citizens Center City of Durant, MS April 25, 2017

LIGHTING 16500 - 1

SECTION 16500 - LIGHTING PART 1- GENERAL Provide all lighting fixtures (luminaires), lamps, end caps, connectors, fittings, structural support members, supports, brackets, etc., for a complete and operable lighting system. PART 2-PRODUCTS 2.1 LUMINAIRES A. Luminaires are shown in the Lighting Fixture Schedule on the drawings to establish a

standard of quality, and to provide the IES recommended lighting levels, color rendering, and energy efficiency as designed by the engineer. The lighting fixtures listed in the Lighting Fixture Schedule were used in the design and calculations of light levels (fc). Consult with General Contractor for any fixture types unavailable. Substitutions made must demonstrate the same IES design levels, color rendering, ratings, wattage levels, and energy efficiency as the fixtures in the Lighting Fixture Schedule. Notify the General Contractor at least two weeks prior to bid if an equivalent for a fixture listed in the schedule is not readily available.

B. Provide the appropriate lamps, trim types, lenses, and accessories for proper installation in the area shown on the drawing. Coordinate with the ceiling contractor during the creation of shop drawings to ensure that fixtures are appropriate for the type of ceiling being installed. 2.2 LAMPS A. Incandescent lamps shall be rated 130V and shall be of the appropriate size with the appropriate base configuration for installation in the fixture specified. Incandescent lamps shall be clear unless otherwise specified. B. Fluorescent lamps shall be T8, rapid-start with a Color Rendering Index (CR1) of 75 and a

color temperature of 3500K, or as shown in the Lighting Fixture Schedule. Other types of fluorescent lamps for specific fixtures shall be as shown in the Lighting Fixture Schedule.

C. HID Lamps shall be clear unless otherwise noted. They shall have a color temperature of

3500K, or as shown in the Lighting Fixture Schedule. Coordinate base size with fixture socket prior to ordering lamps.

2.3 BALLASTS A. Fluorescent luminaires shall be Furnished with energy-saving, high power factor (0.9 or greater), electronic ballasts. Ballasts shall operate lamps without noticeable flicker and shall operate within the JES recommended noise levels. Ballasts shall operate at a frequency no less than 20,000 Hz. Total harmonic distortion shall be less than 10%. Ballasts shall be able to withstand voltage transients in accordance with IEEE C62.41, Category A for normal and common modes. Ballasts shall be compatible with the lamps furnished. Furnish number and size of ballasts as required to operate the number of lamps indicated with the control schemes

shown.

09339 26 00 16010-16801 REPLACED by Addendum No. 1 Page 30 of 35

Page 54: ADDENDUM NO. 1 · Project #3-09339 BID SCHEDULE Item Estimate No. Item Description Quantity Unit 1 ... insurance, and other costs necessary to cover the finished work of the several

CCE Project No. 3-09339-16P Senior Citizens Center City of Durant, MS April 25, 2017

LIGHTING 16500 - 2

B. Emergency Ballasts: Emergency Ballasts in fluorescent fixtures shall consist of an automaticpower failure device, a test switch, and a pilot light that is visible from outside of the fixture.They shall contain a fully automatic solid-state charger in a self-contained power pack. Thefixture shall be factory wired in a manner that will allow the emergency lamps to be switchedwhile still maintaining charging power to the battery. Wiring Diagrams shall he furnishedwith the fixture showing switching connections. The battery shall be of the sealed electrolytetype with the capacity to provide power to the lamps provided for a minimum of 90 minutesat a minimum output as indicated below:

Linear and U-Tube T-8 and T-l2 Lamps 1100 Lumens 26W DTT 970 Lumens 26W TRT 450 Lumens 32W TRT 575 Lumens 42W TRT 1000 Lumens

The battery shall be able to operate unattended with no maintenance for a period of no less than five years. Emergency ballasts shall be fully compatible with solid state ballasts. Battery packs shall be mounted inside the fixture unless remotely mounted ballasts are shown on the drawings, or unless the fixture is of a type that does not have room for internally mounted battery packs.

C. HID ballasts shall be of the high power factor type (0.9 or greater).

D. Where quartz restrike fixtures are fed at voltages different than 120V, they shall be furnishedwith integral transformers and all equipment necessary to feed the quartz fixtures at 120V.

2.4 SUPPORTS

A. Provide all structural members necessary to support fixtures in locations shown on thecontract drawings. Submit mounting and support details to the Architect or Engineer forapproval with the project shop drawings. Notify the General Contractor prior to bid of anystructural work that will be required to support the fixtures.

B. Provide hangers, cords, stems, etc., where required. Coordinate with the Architect orEngineer for proper stem lengths prior to ordering fixtures.

C. Support the ceiling grid at all four corners of recessed light fixtures.

PART 3- EXECUTION

3.1 Raceways for lighting systems in accessible ceilings shall be run to junction boxes mounted in locations that do not interfere with the ceiling installation, the luminaire installation, or other building systems. Provide final connections to fixtures using conductors in flexible conduit. Flexible conduit whips shall not exceed six feet in length.

3.2 All recessed fixtures shall be mounted with their trims flush against the ceiling.

09339 26 00 16010-16801 REPLACED by Addendum No. 1 Page 31 of 35

Page 55: ADDENDUM NO. 1 · Project #3-09339 BID SCHEDULE Item Estimate No. Item Description Quantity Unit 1 ... insurance, and other costs necessary to cover the finished work of the several

CCE Project No. 3-09339-16P Senior Citizens Center City of Durant, MS April 25, 2017

LIGHTING 16500 - 3

3.3 Comply completely with all manufacturers' installation instructions. 3.4 Fixtures shall be warranted for a period of one year after beneficial occupancy. Incandescent

lamps shall be warranted for 90 days after beneficial occupancy. Fluorescent and HID lamps shall be warranted for 180 days after beneficial occupancy.

END OF SECTION

09339 26 00 16010-16801 REPLACED by Addendum No. 1 Page 32 of 35

Page 56: ADDENDUM NO. 1 · Project #3-09339 BID SCHEDULE Item Estimate No. Item Description Quantity Unit 1 ... insurance, and other costs necessary to cover the finished work of the several

CCE Project No. 3-09339-16P Senior Citizens Center City of Durant, MS April 25, 2017

TV CABLE SYSTEM 16781 - 1

SECTION 16781 -TELEVISION CABLE SYSTEM

PART 1 - GENERAL

Provide a complete system of raceways, outlet boxes, cable, and receptacles for a television service system in accordance with this specification and the contract drawings.

PART 2- PRODUCTS

2.1 Outlet boxes shall be furnished per Specification Section 16150 and shall be flush mounted.

2.2 Raceways shall be furnished per Specification Section 16110. Minimum conduit size shall be 1" nominal trade size.

2.3 Television Cable for distribution to outlet receptacles shall be plenum-rated, double-shielded RG6/U, #18 AWG copper with an aluminum polyester aluminum tape with 100% coverage and an aluminum braid with 45% coverage.

2.4 Receptacles/Covers: Each outlet box shall contain a brushed stainless steel cover plate containing a Type-F female coaxial connector.

2.5 Terminal Board: Television service equipment shall be mounted on the Communications Backboard (CBB), and grounded to the copper ground bar with #6 minimum copper ground conductor.

2.6 Service Conduits: Unless directed otherwise, the service entrance for television service shall utilize the same service conduit as the telephone service, as specified in section 16801, and shall terminate at the CBB. Satellite Systems may require otherwise. Provide and install any conduit(s) required for Satellite TV Systems. Consult with owner for direction.

2.7 Television Service and Service Equipment shall be furnished by service provider, in accordance with provider’s policies and directions, unless directed otherwise by television service provider, or owner.

PART 3-EXECUTION

3.1 Extend a 1” EMT conduit from each outlet box to a point above the nearest accessible ceiling. Turn the conduit horizontal and terminate it with a protective bushing. Provide any conduits left empty with a nylon pull string.

3.2 Homerun one cable from each Type-F receptacle in each outlet box to the CBB for termination. Terminate coax cable onto each Type-F connector in each TV cable receptacle.

3.3 Provide/Install EMT conduit(s) as required, 1” minimum nominal trade size, from CBB at television service equipment to accessible ceiling, for consolidation of cable homeruns to service equipment. Provide conduit with protective bushings.

3.4 Test all cable runs and complete TV cable installation for proper operation.

3.4 Comply completely with all Television Service Provider company requirements.

END OF SECTION

09339 26 00 16010-16801 REPLACED by Addendum No. 1 Page 33 of 35

Page 57: ADDENDUM NO. 1 · Project #3-09339 BID SCHEDULE Item Estimate No. Item Description Quantity Unit 1 ... insurance, and other costs necessary to cover the finished work of the several

CCE Project No. 3-09339-16P Senior Citizens Center City of Durant, MS April 25, 2017

TELEPHONE & DATA SYSTEMS 16801 - 1

SECTION 16801 -TELEPHONE AND DATA SYSTEMS

PART 1 - GENERAL

Provide a complete system of raceways, outlet boxes, cable, and receptacles for the telephone and data systems in accordance with this specification and the contract drawings.

PART 2- PRODUCTS

2.1 Outlet boxes shall be furnished per Specification Section 16150.

2.2 Raceways shall be furnished per Specification Section 16110. Minimum conduit size shall be 1" nominal trade size.

2.3 Provide all outlets with blank, brushed stainless steel cover plates.

2.4 Communications Backboard (CBB) for Telephone and Data cabling: Wall mount a 3/4" x 4' x 8' sheet of plywood, primed and painted with two coats of fire-resistant black enamel paint, or of the color and finish selected by the Architect. Mount securely to wall framing members. Orient CBB per General Contractor, or owner, or as described on plans. The bottom of the backboard shall be a minimum of 6” above the finished floor.

2.5 Provide a 1/4”T x 2"W x 12"L Copper Ground Bar (Erico Eritech EGBA14212TES or approved equal) on each backboard.

2.6 Service Conduits: Provide one (1) 1½” IMC or GRSC sleeve - from the Main Communications Backboard (CBB), through the exterior wall, for communications service cable entrance.

2.7 Tele/Data Receptacles and cables shall be furnished and installed by this contractor. Contractor shall furnish and install one (1) outlet box at each outlet location, as shown on the drawings.

2.8 Receptacles shall consist of: One (1) single-gang metal device box with a 2-port stainless steel faceplate. Provide and install (1) RJ45 CAT-5e Modular Jack for solid conductor in the top port, and (1) RJ11 Modular Jack for solid conductor in the bottom port.

2.9 Cable shall be: CAT-5e, 4-Pair, UTP, Plenum-Rated CMP, 24 AWG Solid.Belden 1213F Series, or equal.

PART 3-EXECUTION

3.1 On the Main Communications Backboard, bond a #6 AWG copper conductor to the Copper Ground Bar with a two hole compression lug and run the #6 AWG ground wire to the electrical power system grounding electrode. Bond the #6 AWG ground wire to the power system grounding electrode using an exothermic weld.

09339 26 00 16010-16801 REPLACED by Addendum No. 1 Page 34 of 35

Page 58: ADDENDUM NO. 1 · Project #3-09339 BID SCHEDULE Item Estimate No. Item Description Quantity Unit 1 ... insurance, and other costs necessary to cover the finished work of the several

CCE Project No. 3-09339-16P Senior Citizens Center City of Durant, MS April 25, 2017

TELEPHONE & DATA SYSTEMS 16801 - 2

3.2 Extend a 1” EMT conduit from each outlet box to a point above the nearest accessible ceiling. Turn the conduit horizontal and terminate it with a protective bushing. Provide any empty conduits with a pullstring.

3.3 Provide and install (2) CAT-5e 4-Pair UTP cables from each receptacle to the CBB cabling hub. Terminate (1) CAT-5e cable to the RJ45 jack, via Straight-Through wiring protocol, using Ethernet Cable Pin-Out Wiring Standard T568A. Terminate (1) CAT-5e cable to the RJ11 jack for land-line telephone. Coordinate with owner for telephone details. Typical for all voice/data receptacles.

3.4 Service Conduits: Seal exterior end of sleeve with silicone sealant, after service cables installation. Provide temporary cap or seal, at each end, to prevent entrance of water, dirt, etc., during construction.

END OF SECTION

09339 26 00 16010-16801 REPLACED by Addendum No. 1 Page 35 of 35

Page 59: ADDENDUM NO. 1 · Project #3-09339 BID SCHEDULE Item Estimate No. Item Description Quantity Unit 1 ... insurance, and other costs necessary to cover the finished work of the several

REVISED by Addendum No. 1 09339 31 23 18 Unclassified Excavation

2017.06.06 Page 1 of 3

UNCLASSIFIED EXCAVATION

1. SCOPE OF WORK Work under this item shallconsist of the excavation of all materials encountered within the limits of the work and thedisposal of excavated materials by hauling to embankment or waste. Excavation shall becarried to the section and grade shown on the plans. Excavation for storm sewers anddrainage structures is covered elsewhere.

2. GENERAL The area shall be clearedand grubbed prior to the start of excavation. The Contractor shall inform himself as to theproper movements of haul and disposal of materials.

All suitable materials excavated shall be used in the formation of embankments and backfill as directed. During the process of excavation, the grade shall be maintained in such condition that it will be well drained at all times, and temporary ditches shall be cut to divert surface water which may affect the prosecution of the work. Prior to acceptance, then entire area shall be machined and bladed for proper drainage.

The rough excavation shall be carried to such depth that sufficient material will be left above the designated subgrade to allow for compaction of this grade. Likewise, on embankments, sufficient material shall be placed above the designated subgrade to allow for both compaction and settlement. Should the Contractor, through negligence, excavate below the designated line, he shall replace at his own expense such excavation with approved materials.

3. DISPOSAL OF UNSUITABLE ANDSURPLUS MATERIALS Any material encountered

which, in the opinion of the Engineers, is unsuitable for use in the work, shall be removed and disposed of as directed. No excavation shall be wasted without permission of the Engineers. Surplus excavation shall be disposed of as directed - some in uniformity widening embankments or flattening slopes. Waste excavation shall be left presenting a neat appearance well drained and smoothed suitable for mowing. Excavation material in excess of on-the-site requirements shall be hauled and deposited at a site provided by the Contractor unless a site si designated on the plans. Spoils from ditch excavation shall be spread and leveled to blend with the well-drained, pleasing appearance.

4. EMBANKMENTS Embankments shall be formed of satisfactory materials placed in successive horizontal layers of not more than 12 inches in loose depth for the full width of the cross-section. The Contractor shall route his equipment at all times over the layers so as to distribute evenly the travel over the entire width.

5. BORROW EXCAVATIONSAND CLAY TOPPING The borrow excavation and

sand clay topping materials shall be a mixture of clay and mineral aggregate. This mixture

174

Page 60: ADDENDUM NO. 1 · Project #3-09339 BID SCHEDULE Item Estimate No. Item Description Quantity Unit 1 ... insurance, and other costs necessary to cover the finished work of the several

REVISED by Addendum No. 1 09339 31 23 18 Unclassified Excavation

2017.06.06 Page 2 of 3

shall consist of topsoil, sand-clay gravel, disintegrated granite, or other approved selected aggregate, and it shall contain sufficient binder material so blended or processed as to produce a uniform mixture complying with the requirements of these specifications.

The materials shall be uniform and free of organic matter such as leaves, grass, roots and other objectionable or foreign substances.

The gradation of the blended or processed material shall meet the requirements of the Select Borrow Material section contained within the Granular Materials specification.

6. SUBGRADE PREPARATION FOR BASE COURSE After all storm sewers, drainage structures and curbs and gutters have been completed, backfilled and compacted, the top portion of the subgrade, both cut and fill sections, shall be shaped correctly and brought to a firm, unyielding layer. The top 6 inches under the base course shall be compacted to a least 95% Standard Proctor Method density at optimum moisture content.

Rolling and compaction of the entire area shall done with equipment which will attain maximum results. Sheepsfoot, rubber-tired, or flat rollers shall be used as, in the opinion of the Engineers, conditions require. Any portion of the area which is not accessible to a roller shall be compacted to the required density by other approved means.

Any irregularities or depressions that develop under rolling shall be corrected by loosening the material at those places and adding, removing, or replacing material until the surface is smooth and uniform. All soft and yielding material which will not compact readily when rolled or tamped shall be removed as directed by the Engineers and replaced with suitable material.

During all compacting operations, the water content of the material shall be constantly adjusted, if necessary, by sprinkling or loosening and subsequent evaporation to within 2% by weight of the optimum moisture content.

At all times the top of the subgrade shall be kept in such condition that it will drain readily and effectively. The Contractor shall protect the subgrade from damage, and in no case will vehicles be allowed to travel in a single track. If ruts are formed, the subgrade shall be reshaped and rolled.

The top of the subgrade shall be of such smoothness that when tested with the parabolic roadway template, it shall not show any deviation in excess of ½-inch nor shall it be more than 0.05 foot from the true established grade.

Where material is encountered that will not permit satisfactory compaction for subgrade, excavation, disposal and replacement of this material will be required and will be considered as incidental to subgrade preparation. No extra pay will be allowed for this item.

175

Page 61: ADDENDUM NO. 1 · Project #3-09339 BID SCHEDULE Item Estimate No. Item Description Quantity Unit 1 ... insurance, and other costs necessary to cover the finished work of the several

REVISED by Addendum No. 1 09339 31 23 18 Unclassified Excavation

2017.06.06 Page 3 of 3

7. HAUL All materials shall behauled from the original position to embankment or waste to the final position as directed.All haul shall be “free haul”, and no payment will be made therefor.

8. METHOD OF MEASUREMENT When, in the opinionof the Engineers, the unclassified excavation is completed in accordance with the plans,the quantities shown on the plans will be considered the measurement for final payment.If it is found necessary during construction, in the opinion of the Engineers, to makeconstruction changes, the original plans will be revised to incorporate such changes andthe change will be measured to neat lines of the change.

9. BASIS OF PAYMENT UnclassifiedExcavation, when not a Lump Sum pay Item, will be paid for at the contract unit price percubic yard for unclassified excavation; plan measure, which price shall be fullcompensation for the removal and satisfactory disposal of all excavated materialsregardless of material encountered; for haul to embankment areas; for the formation ofembankments; for compaction; and for subgrade preparation under areas to be coveredwith the base course.

Borrow Excavation and Sand Clay Topping will be paid for at the contract unit price per cubic yard, plan measure - which payment will be full compensation for locating, acquiring, and furnishing the material, haul and the formation of embankments. The yardage to be paid for shall be the number of cubic yards hauled to the job site as directed by the Engineer in the presence of the Engineer’s Representative. Any material hauled to the job site without notifying the Engineer will not be paid for. The quantity includes a 50 percent shrinkage factor.

No compensation shall be made for the haul to embankments or for the formation of embankments. Embankments are considered a necessary part of the roadway and incidental to the Unclassified Excavation item.

176