26
University of Akron Addendum No. 3 December 30, 2014 Project No.: UAK140011 Project Title: Research Lab Renovations - Olson Research Center The University of Akron Office of Capital Planning & Facilities Management Lincoln Building Akron, Ohio 44325-0405 v: 330.972.8316 f: 330.972.5838 web: www.uakron.edu

University of Akron Addendum No. 3€¦ · to specification 262923 “Variable Frequency Motor Controllers”. Item D7: Sheet E2.1; ... Item Q1: There is no mention of temperature

  • Upload
    others

  • View
    1

  • Download
    0

Embed Size (px)

Citation preview

Page 1: University of Akron Addendum No. 3€¦ · to specification 262923 “Variable Frequency Motor Controllers”. Item D7: Sheet E2.1; ... Item Q1: There is no mention of temperature

University of Akron

Addendum No. 3 December 30, 2014

Project No.: UAK140011 Project Title: Research Lab Renovations - Olson Research Center The University of Akron Office of Capital Planning & Facilities Management Lincoln Building Akron, Ohio 44325-0405 v: 330.972.8316 f: 330.972.5838

web: www.uakron.edu

Page 2: University of Akron Addendum No. 3€¦ · to specification 262923 “Variable Frequency Motor Controllers”. Item D7: Sheet E2.1; ... Item Q1: There is no mention of temperature

TO ALL BIDDERS:

This addendum supplements and amends the original drawings and specifications, and shall be taken

into account in the preparing proposals, and shall become part of the contract documents by

reference. Receipt of this addendum must be acknowledged on the bid form.

Addendum consists of the following:

General Clarifications:

Item G1: Substitution Request; Multiple substitution requests for the fume hoods have been

received, including Mott Manufacturing, Hamilton Scientific LLC and Hanson Lab

Furniture, Inc. While these manufacturers and those currently listed in the specification

are generally acceptable as fume hood manufacturers, all manufacturers must

demonstrate that their product meets the performance specifications of the Basis-of-

Design fume hoods and the stringent CFM and face velocity requirements for which the

HVAC system was designed. Per Addendum 1, if during the submittal review it is

determined that an alternate product submitted does not meet the specified

requirements; the Contractor shall provide the specified product at no additional cost to

the University.

Item G2: Existing Roof; The existing roof membrane is Firestone Ultraply TPO and was originally

installed by Cardinal Maintenance Roofing. All roof work shall be performed by a

contractor certified by Firestone that will allow for the current warranties to remain in

effect.

Drawings:

Item D1: Sheet AD1.2; ADD notation “GENERAL TRADES CONTRACTOR TO REMOVE FLAMMABLE

STORAGE CABINET FROM WEST WALL OF LAB 323 AND RETURN TO UNIVERSITY.”

Item D2: Sheet AD1.2; ADD notation “GENERAL TRADES CONTRACTOR TO REMOVE BASE

CABINET FROM WEST WALL OF LAB 323.”

Item D3: Sheet AD1.2; ADD notation “MECHANICAL CONTRACTOR TO REMOVE WATER

FILTRATION SYSTEM FROM WEST WALL OF LAB 323.”

Item D4: Sheet A1.1; ADD notation “GENERAL TRADES CONTRACTOR TO CONSTRUCT PARTITION

TYPE “B” FROM TOP OF WALL TO UNDERSIDE OF DECK BEHIND FUME HOOD.”

Item D5: Sheet A4.1; ADD notation “EXTEND GYPSUM BOARD TO UNDERSIDE OF DECK WHERE

EXPOSED CEILINGS OCCUR” to Wall Type “B”.

Item D6: Sheet H6.1; ADD to remark 6 of Fan Schedule that the Mechanical Contractor shall refer

to specification 262923 “Variable Frequency Motor Controllers”.

Item D7: Sheet E2.1; REVISE note 11 to read “NEW VFD FOR EXHAUST FAN EF8A FURNISHED BY

MECHANICAL CONTRACTOR, INSTALLED BY ELECTRICAL CONTRACTOR. CONTROLS,

PILOT LIGHTS AND DIGITAL READ OUT SHALL BE INSTALLED IN FRONT COVER OF VFD.”

Page 3: University of Akron Addendum No. 3€¦ · to specification 262923 “Variable Frequency Motor Controllers”. Item D7: Sheet E2.1; ... Item Q1: There is no mention of temperature

Item D8: Sheet E3.1; ADD fire alarm strobe devices in rooms 313, 314A and 323A.

Item D9: Sheet E4.1; ADD notation to riser diagram for surge protectors for panels P-314, LEM

and P-322.

Item D10: Sheet E4.2; ADD 60 amp, 3 pole circuit breaker to panel P-314 for surge protection

device and wire per manufacturer’s instruction.

Item D11: Sheet E4.2; ADD 60 amp, 3 pole circuit breaker to panel P-322 for surge protection

device and wire per manufacturer’s instruction.

Item D12: Sheet E4.2; ADD 60 amp, 3 pole circuit breaker to panel LEM for surge protection device

and wire per manufacturer’s instruction.

Specifications:

Item S1: Table of Contents: DELETE Specification 283111 “Digital, Addressable Fire-Alarm

System”. Refer to sheet E4.1 for system requirements and Sheet E3.1 for device

quantities and locations.

Item S2: Specification 020702; ADD specification for “Asbestos Abatement”.

Item S3: Specification 115313; Section 2.1.A; ADD the following to the list of manufacturers,

which subject to compliance with the Basis-of-Design product may provide products.

5. Hamilton Scientific LLC

6. Hanson Lab Furniture, Inc.

7. Mott Manufacturing

Item S4: Specification 123553; Section 2.1.A; ADD the following to the list of manufacturers:

5. Hamilton Scientific LLC

6. Hanson Lab Furniture, Inc.

Item S5: Specification 262913; Section 2.1.B; DELETE entire section for “Motor-Starting

Switches”.

Item S6: Specification 262913; Section 2.1.C; DELETE entire section for “Fractional Horsepower

Manual Controllers”.

Item S7: Specification 262923; Section 2.1.G; DELETE “32”.

Item S8: Specification 264313; Specification Reissued. See Attachments.

Questions:

Item Q1: There is no mention of temperature controls?

Temperature control is by wall-mounted thermostat. See Specification 238146,

paragraph 2.2. Each of the existing heat pumps serving these labs (WSHP-28A, WSHP-30

and WSHP-31)is also to receive a new wall-mounted thermostat.

Page 4: University of Akron Addendum No. 3€¦ · to specification 262923 “Variable Frequency Motor Controllers”. Item D7: Sheet E2.1; ... Item Q1: There is no mention of temperature

Attachments:

Sheet A3.1

Specification 020702 “Asbestos Abatement”

Specification 264313 “Surge Protection for Low-Voltage Electrical Power Circuits”

Page 5: University of Akron Addendum No. 3€¦ · to specification 262923 “Variable Frequency Motor Controllers”. Item D7: Sheet E2.1; ... Item Q1: There is no mention of temperature

THE UNIVERSITY OF AKRON

LABORATORY RENOVATION PROJECT

ASBESTOS ABATEMENT 020702-1

SECTION 020702 – ASBESTOS ABATEMENT

PART 1 - GENERAL

1.1 DESCRIPTION OF ASBESTOS ABATEMENT

A. Asbestos abatement includes demolition or salvage of structures where asbestos is present;

removal, encapsulation or enclosure of materials containing asbestos; alteration, repair,

maintenance or renovation of structures, substrates or portions thereof, that contain asbestos;

asbestos spill/emergency cleanup; and transportation, disposal, storage, containment of and

housekeeping activities involving asbestos or products containing asbestos.

B. This Contract entails removal and disposal of asbestos-containing materials (ACM) from the

University of Akron’s Olson Research Center, Rooms 313, 314, 322 and 323, Akron, Summit

County, Ohio (the Facility).

C. The CONTRACTOR refers to the General Trades Contractor responsible for performing the

asbestos abatement put forth in this specification.

1.2 SUMMARY OF WORK

A. This Section includes the removal, handling, and disposal of asbestos-containing materials and

asbestos-contaminated waste to support the renovation effort at the Facility. All asbestos hazard

abatement work shall be conducted in compliance with all applicable federal, state, and local

regulations and "state of the art" technology.

B. Building materials identified as containing asbestos and which are required to be abated by the

CONTRACTOR are itemized below:

Location Asbestos-Containing Material Quantity

Rooms 313, 322 and

323 Cementitious Countertops 50 sq.ft.

Room 323 Cementitious Panel – Associated

with Hood Vent

30 sq.ft.

Assumed

Rooms 313, 314, 322

and 323 Fire Door Insulation

10 Doors

Assumed

C. The work to be performed is classified as Class II Asbestos Work by OSHA. All abatement

activities performed by the CONTRACTOR will be conducted in accordance with OSHA’s Class

II work requirements.

D. This Specification is based on the findings of HzW Environmental Consultants, LLC asbestos

sampling activities conducted in August 2014. Laboratory test results are on file and may be

obtained for review if requested in writing.

Page 6: University of Akron Addendum No. 3€¦ · to specification 262923 “Variable Frequency Motor Controllers”. Item D7: Sheet E2.1; ... Item Q1: There is no mention of temperature

THE UNIVERSITY OF AKRON

LABORATORY RENOVATION PROJECT

ASBESTOS ABATEMENT 020702-2

E. DLZ will retain an on-site representative (ENVIRONMENTAL REPRESENTATIVE) to verify

compliance with governing regulations and Contract Documents. The furnishing of this

representative shall not make DLZ responsible for CONTRACTOR’S failure to perform work in

accordance with regulations and/or the Contract Documents.

F. The CONTRACTOR shall provide all items and services in accordance with this Paragraph.

1. The CONTRACTOR shall provide all labor, equipment, materials, appurtenances, and

incidentals required for the complete removal, containment, transportation, and disposal of

the ACMs as listed in this section, and to include the cleaning/decontamination and/or

collection and disposal of adjacent materials which may become contaminated during the

removal process.

2. The CONTRACTOR shall secure the immediate work area(s) for the duration of the Work

as required by the Contract Documents and all federal, state and local regulations. Only

authorized personnel directly involved with the abatement work may enter the work area(s).

The CONTRACTOR is totally responsible for all safety and security of

CONTRACTOR’S employees and equipment, respectively.

3. The CONTRACTOR shall conduct personal air monitoring for CONTRACTOR’S

employees in compliance with OSHA regulations. It is the CONTRACTOR’S

responsibility to furnish and maintain air-monitoring equipment required to determine

worker exposure. The CONTRACTOR shall bear costs in connection with exposure

monitoring and reporting required.

4. The CONTRACTOR shall be responsible for providing temporary water as follows:

a. The CONTRACTOR shall make whatever connections or arrangements for water

deemed necessary for its operations. A backflow preventer at the initial connection

point is mandatory and shall be provided by the CONTRACTOR. All items required

for the connection, including hoses, etc., shall be provided by the CONTRACTOR.

The CONTRACTOR shall be responsible for the shutdown of all water sources when

not in use.

1.3 CONTRACTOR'S SUBMITTALS

A. All submittals shall conform completely to the requirements of the Contract Documents, including

all requirements set forth in this Section.

B. The CONTRACTOR shall submit the following documentation prior to start of project:

1. Proof of Ohio Asbestos Hazard Abatement Contractor’s License.

2. Documentation of any regulatory violations and associated penalties within the last five

years.

3. Employee medical examination documentation.

Page 7: University of Akron Addendum No. 3€¦ · to specification 262923 “Variable Frequency Motor Controllers”. Item D7: Sheet E2.1; ... Item Q1: There is no mention of temperature

THE UNIVERSITY OF AKRON

LABORATORY RENOVATION PROJECT

ASBESTOS ABATEMENT 020702-3

4. Employee current Ohio Department of Health asbestos licenses and training certifications.

5. Employee fit test documentation.

C. Prior to commencing work and as a condition under the Contract, the CONTRACTOR shall

secure all necessary licenses and permits associated with asbestos abatement, transportation and

disposal as required by Federal, State and local regulations. These documents may include, but

are not limited to, the Ohio Department of Health Prior Notification of Asbestos Hazard

Abatement Project form, and the Ohio Environmental Protection Agency Notification of

Demolition and Renovation form.

D. Prior to commencing work and as a condition under the Contract, the CONTRACTOR shall

provide copies of state and local licenses for the waste hauler, USEPA identification number of the

waste hauler, name and address of the waste disposal facility, and copies of the disposal facility’s

licenses and permits.

E. Plan of Work Procedure

1. The CONTRACTOR shall submit to the UNIVERSITY OF AKRON prior to

commencement of Work, a detailed plan of the Work procedures to be used in the

abatement of the ACMs.

F. Project Log

1. The CONTRACTOR will maintain a daily Project Log. The log will be used each day of

the project to record the following information:

a. Name of Superintendent and actual time physically on job.

b. Brief description of daily Work accomplishments.

c. Listing of all employees on the job.

d. Description of any significant events, incidents, or unusual occurrences, including

but not limited to, deviations from plans, contract requirements, or specifications;

emergencies, accidents or dangerous conditions; and steps taken to assure continued

security of the Work area.

2. The log will also include copies of routine inspection reports, results of air monitoring and

analysis, project minutes, chain-of-custody forms and any other routine documents relating

to project activities. The log for the project will be made immediately available for

inspection by the UNIVERSITY OF AKRON.

3. At the completion of the project, the CONTRACTOR shall forward one copy of the Project

Log to DLZ.

G. Contractor’s Compliance Data

Page 8: University of Akron Addendum No. 3€¦ · to specification 262923 “Variable Frequency Motor Controllers”. Item D7: Sheet E2.1; ... Item Q1: There is no mention of temperature

THE UNIVERSITY OF AKRON

LABORATORY RENOVATION PROJECT

ASBESTOS ABATEMENT 020702-4

1. The CONTRACTOR shall submit to the UNIVERSITY OF AKRON within 30 days after

waste load-out, an original copy of the chain-of-custody forms signed by the disposal site

operator, evidencing acceptance of the waste ACM.

2. The CONTRACTOR shall maintain a log of all personal air monitoring data gathered

during the Work. The log format shall be: air monitoring form, air sampling log,

laboratory results, summary of equipment used, and calibration data all bound in a complete

packet. A complete log of air samples and results shall be submitted to the UNIVERSITY

OF AKRON at the completion of Work.

1.4 JOB CONDITIONS

A. The asbestos work area(s) shall be made available to government personnel who have the

authority to conduct inspections and test for regulatory compliance. The work area(s) will also be

inspected by the ENVIRONMENTAL REPRESENTATIVE.

B. The CONTRACTOR shall use only qualified, licensed trades people for installation of temporary

services and facilities.

C. Eating, drinking, smoking, or chewing tobacco or gum by CONTRACTOR’S personnel or others

shall not be allowed within the asbestos regulated areas.

1.5 AUTHORITY TO STOP WORK

A. A Stop Work Order may be issued by the ENVIRONMENTAL REPRESENTATIVE if work is

not being conducted in accordance with federal, state and local asbestos regulations and/or these

written specifications.

B. The CONTRACTOR shall immediately implement corrective actions after receipt of a Stop Work

Order. Abatement work may not resume until corrective action(s) have been performed to the

satisfaction of the ENVIRONMENTAL REPRESENTATIVE, and the ENVIRONMENTAL

REPRESENTATIVE provides written authorization to proceed. Standby time and corrective

actions are at the CONTRACTOR’S expense.

1.6 REFERENCES

A. All American National Standards Institute (ANSI), American Society for Testing Materials

(ASTM), Compress Gas Association, Inc. (CGA), National Fire Protection Association (NFPA),

National Institute for Occupational Safety and Health (NIOSH), Ohio Department of Health

(ODH), Occupational Safety and Health Administration (OSHA), Ohio Environmental Protection

Agency (OEPA), United States Environmental Protection Agency (USEPA), United States

Department of Transportation (USDOT) regulations and publications are hereby incorporated into

this specification. Except to the extent that more explicit or more stringent requirements are

written directly into the Contract Documents, all applicable standards have the same force and

effect (and are made a part of the Contract Documents by reference) as if copied directly into the

Contract Documents, or as if published copies are bound herewith. Where two or more of the

Page 9: University of Akron Addendum No. 3€¦ · to specification 262923 “Variable Frequency Motor Controllers”. Item D7: Sheet E2.1; ... Item Q1: There is no mention of temperature

THE UNIVERSITY OF AKRON

LABORATORY RENOVATION PROJECT

ASBESTOS ABATEMENT 020702-5

referenced standards establish different or conflicting requirements for minimum quantities or

quality levels, the most stringent requirement will be enforced.

B. Other Regulations: All other federal, state, county, municipal, and local statutes, ordinances,

regulations, or rules pertaining to asbestos, including its abatement, storage, transportation and

disposal; construction safety and health and hazard communication (Worker Right-To-Know), and

CONTRACTOR or other licensure, certification and regulation, which are now in effect or which

may come into effect prior to project completion.

PART 2 - PRODUCTS

2.1 PERSONAL PROTECTIVE EQUIPMENT

A. Respirators: Select respirators approved by the National Institute for Occupational Safety and

Health (NIOSH), and OSHA, for use in atmospheres containing asbestos fibers.

1. Single-use, disposable or quarter-face respirators are not permitted for asbestos work.

2. Provide respiratory protection appropriate for the fiber level based on the initial exposure

assessment and/or air sampling performed during the Project. The level of respiratory

protection which supplies an airborne fiber level inside the respirator, at the breathing zone

of the wearer, at or below 0.01 f/cc is the minimum level of protection allowed.

3. Respiratory protection shall be worn at all times when there is any possibility of disturbance

of ACM. Regardless of airborne fiber levels, during any work involving the disturbance of

ACM, the minimum level of respiratory protection used shall be half-face air-purifying

respirators (APRs) with HEPA filters.

4. All APRs shall be equipped with HEPA filters. In addition, appropriate chemical cartridges

shall be added to APRs if solvents or other chemicals will be used or encountered.

5. The CONTRACTOR shall supply a sufficient quantity of respirator filters, so that workers

can change filters after each decontamination session.

6. Full-face respirators shall be equipped with a nose cup or other anti-fogging device as

necessary.

B. Special Clothing: Furnish personnel working in asbestos regulated areas with disposable

protective whole body clothing, head coverings, gloves, and foot coverings as required for the

particular work process. Furnish disposable plastic or rubber gloves to protect hands. Cloth

gloves may be worn inside the plastic or rubber gloves for comfort, but shall not be used alone.

Use tape to secure sleeves at the wrists and to secure foot coverings at the ankles.

C. Boots: Steel toed shoes/boots are required on the job site at all times. Boots may not be

removed from asbestos regulated areas for any reason after being contaminated with asbestos.

Page 10: University of Akron Addendum No. 3€¦ · to specification 262923 “Variable Frequency Motor Controllers”. Item D7: Sheet E2.1; ... Item Q1: There is no mention of temperature

THE UNIVERSITY OF AKRON

LABORATORY RENOVATION PROJECT

ASBESTOS ABATEMENT 020702-6

D. Hard hats: Furnish a hard hat as required by OSHA. Thoroughly decontaminate hard hats before

removing them from asbestos regulated areas.

E. Eye Protection: Safety glasses are required on the job site at all times. Provide goggles for

personnel engaged in asbestos operations when the use of a full face respirator is not required,

such as disposal container loadout.

F. Hearing Protection: Furnish hearing protection as required by OSHA to personnel involved with

asbestos abatement if noise levels in the work areas exceed 84 dBA.

G. Protective Clothing for the ENVIRONMENTAL REPRESENTATIVE: The CONTRACTOR

shall furnish the ENVIRONMENTAL REPRESENTATIVE with appropriate disposable

protective clothing (hooded coveralls with booties, and gloves) for use when inspecting work

area(s).

2.2 WARNING SIGNS AND LABELS

A. Warning Signs: Provide warning signs at approaches to regulated areas containing airborne

asbestos fibers. Locate signs at such a distance that personnel may read the sign and take the

necessary protective steps required before entering the area. Warning signs shall be of sufficient

size (minimum 14" x 20") to be clearly legible and display the following information:

DANGER

ASBESTOS

CANCER AND LUNG DISEASE HAZARD

AUTHORIZED PERSONNEL ONLY

RESPIRATORS AND PROTECTIVE CLOTHING ARE REQUIRED

IN THIS AREA

B. Warning Labels: Provide warning labels and affix to asbestos materials, scrap, waste, debris, and

other products contaminated with asbestos. Warning labels shall be of sufficient size (minimum

3" x 5") to be clearly legible, printed in large, bold letters on a contrasting background, and display

the following legend:

DANGER

CONTAINS ASBESTOS FIBERS

AVOID CREATING DUST

CANCER AND LUNG DISEASE HAZARD

2.3 TOOLS AND EQUIPMENT

A. Airless Sprayer: An airless sprayer, suitable for application of encapsulating material, shall be

used.

B. Scaffolding, ladders, and/or staging, etc., as necessary to accomplish the work of this contract.

Scaffolding may be of suspension type or standing type such as metal tube and coupler, tubular

Page 11: University of Akron Addendum No. 3€¦ · to specification 262923 “Variable Frequency Motor Controllers”. Item D7: Sheet E2.1; ... Item Q1: There is no mention of temperature

THE UNIVERSITY OF AKRON

LABORATORY RENOVATION PROJECT

ASBESTOS ABATEMENT 020702-7

welded frame, pole or outrigger type or cantilever type, and must be implemented by a

professional scaffolding company. The type, erection and use of all scaffolding shall comply with

all applicable safety regulations. The maximum height-to-base ratio for free-standing scaffolding

is 4:1. The CONTRACTOR shall be responsible for any damage which occurs as a result from

improper scaffolding use.

C. Transportation Equipment: Transportation equipment as required shall be suitable for loading,

temporary storage, transporting, and unloading of asbestos waste without exposure to persons or

property.

D. Vacuum Equipment: All vacuum equipment utilized in the work area shall utilize HEPA filtration

systems.

E. Water Sprayer: The water sprayer shall be an airless or other low pressure sprayer for amended

water application.

F. HEPA filtration units: Provide the required number of HEPA filtration units in accordance with

regulatory standards and the contract documents.

G. Fire extinguishers:

1. Provide Type “A” fire extinguishers for temporary offices and similar spaces where there is

minimal danger of electrical or grease/oil/flammable liquid fires.

2. In other locations, provide 20-pound, Type “ABC” dry chemical extinguishers, or a

combination of several extinguishers of NFPA-recommended types for the exposures in

each case. Provide at least one fire extinguisher per work area.

H. Other Tools and Equipment: The CONTRACTOR shall provide all other suitable tools for the

stripping, removal, encapsulation, and disposal activities including but not limited to: axes, spud

bars, knives, brushes, sponges, shovels, carts, etc.

2.4 TEMPORARY ELECTRICITY

A. Electric is available at the Facility. All requirements for connection to an electrical distribution

source shall be accomplished by the CONTRACTOR, including all connecting, wiring, and

connection apparatus. The CONTRACTOR shall be responsible for disconnection and de-

energization of the system when not in use. A licensed electrician shall perform all electrical work.

2.5 TEMPORARY WATER

A. Water is available at the Facility. All requirements for connection to a water supply shall be

accomplished by the CONTRACTOR as necessary to accomplish the work. Valves shall be

temperature- and pressure-rated for operations at the temperatures and pressures encountered.

2.6 MATERIALS

Page 12: University of Akron Addendum No. 3€¦ · to specification 262923 “Variable Frequency Motor Controllers”. Item D7: Sheet E2.1; ... Item Q1: There is no mention of temperature

THE UNIVERSITY OF AKRON

LABORATORY RENOVATION PROJECT

ASBESTOS ABATEMENT 020702-8

A. Removal Encapsulant: Provide a penetrating type encapsulant designed specifically for removal

of ACM. Use a material which results in the wetting of ACM and retardation of fiber release

during disturbance of the material.

B. Surfactant: As a minimum the surfactant shall be 50% polyoxyethylene ether and 50% polyglycol

ester. Mix according to manufacturer's written instructions.

C. Construction Materials: Lumber, nails, hardware, shower stalls, hoses, plumbing, drain pans,

sump pumps, storage drums, etc.

D. Polyethylene Sheeting: Sufficient quantities of 6 mil, flame retardant polyethylene sheeting to

perform all required sealing, regulated area construction, and wrapping of asbestos-containing

waste. Sheeting should be provided in the large sizes possible to minimize seams. Black or

opaque sheeting shall be used for the decontamination area.

E. Glue, Duct Tape, Furring Strips: Sufficient quantities of glue, duct tape, spray adhesives, furring

strips, or other materials to hold together polyethylene sheeting for regulated area construction and

wrapping of asbestos-containing waste.

F. Disposal Bags: Provide 6-mil thick, leak-tight, polyethylene disposal bags for the disposal of

asbestos-containing waste materials.

G. Fiberboard Drums: Provide heavy-duty, leak-tight, fiberboard drums with tight sealing, locking

metal tops.

H. First-aid supplies to comply with governing regulations and recognized recommendations within

the construction industry.

PART 3 - EXECUTION

3.1 WORK AREA SET-UP

A. Use of the Site: The CONTRACTOR shall confine operations at the site to the areas permitted

under the contract. Portions of the site beyond areas on which work is indicated are not to be

disturbed. Placement of storage trailers/containers and employee parking shall be coordinated

with the UNIVERSITY OF AKRON.

B. Safe temporary power and lighting shall be provided by the CONTRACTOR.

C. Warning signs, as required by OSHA, shall be posted by the CONTRACTOR.

D. Removal of Miscellaneous Equipment Prior to Establishment of Regulated Area.

1. If during removal of miscellaneous equipment a major release episode occurs, the

CONTRACTOR shall immediately notify the ENVIRONMENTAL REPRESENTATIVE

and implement response actions in accordance with current regulations and the personnel

Page 13: University of Akron Addendum No. 3€¦ · to specification 262923 “Variable Frequency Motor Controllers”. Item D7: Sheet E2.1; ... Item Q1: There is no mention of temperature

THE UNIVERSITY OF AKRON

LABORATORY RENOVATION PROJECT

ASBESTOS ABATEMENT 020702-9

protective provisions of this specification.

2. Upon complete removal of the equipment, the CONTRACTOR may proceed with the

establishment of a regulated area for asbestos abatement.

E. Where the CONTRACTOR has not produced a negative exposure assessment pursuant to

paragraph (f)(2)(iii) of OSHA’s Asbestos Standard for the Construction Industry, or where during

the job, changed conditions indicate there may be exposure above the PEL or where the

CONTRACTOR does not remove the ACM in a substantially intact state, the CONTRACTOR

shall use one of the following methods to ensure that airborne asbestos does not migrate from the

regulated area;

• Critical barriers shall be placed over all openings to the regulated area; or,

• The employer shall use another barrier or isolation method which prevents the migration of

airborne asbestos from the regulated area, as verified by perimeter area monitoring or

clearance monitoring which meets the criteria set out in paragraph 29

CFR1926.1101(g)(4)(ii)(B).

• Impermeable dropcloths shall be placed on surfaces beneath all removal activity;

F. Negative Air Filtration

The CONTRACTOR shall provide negative air with the Work Area to assist in maintaining fiber

concentration within acceptable levels. Locate HEPA filtration units so that makeup air enters the

work area primarily through the decontamination area and traverses the work area as much as

possible. The HEPA-filtered negative air units shall be ducted to the outside of the Work Area(s).

When the building is occupied, the ducts shall exhaust into the outside air; otherwise, they may

exhaust into an area of the building outside of the work area. The air filtration devices shall

provide a minimum of four air changes per hour.

G. Construction of a Personal Decontamination Unit

An equipment room shall be located outside of and adjacent to the Work Area for worker

decontamination and waste loadout. The area must be of sufficient size as to accommodate

cleaning of equipment and removing personal protective equipment without spreading

contamination beyond the area (as determined by visible accumulations). Work clothing must be

cleaned with a HEPA vacuum before it is removed. All equipment and surfaces of containers

filled with ACM must be cleaned prior to removing them from the equipment room. This

equipment room shall be HEPA vacuumed and wet wiped at least once per shift.

3.2 ENGINEERING AND WORK PRACTICE CONTROLS

A. The following Engineering controls shall be implemented by the Contractor regardless of the

classification (Class I, Class II, Class III, Class IV) of work [1926.1101(g)(1)(i-iii)]:

1. A HEPA vacuum will be provided to collect dust and debris.

Page 14: University of Akron Addendum No. 3€¦ · to specification 262923 “Variable Frequency Motor Controllers”. Item D7: Sheet E2.1; ... Item Q1: There is no mention of temperature

THE UNIVERSITY OF AKRON

LABORATORY RENOVATION PROJECT

ASBESTOS ABATEMENT 020702-10

2. Wet methods will be used to control employee exposure.

3. All asbestos waste will be immediately cleaned-up and disposed of.

B. The following Work Practice controls are prohibited from being used by the Contractor at the

Facility [1926.1101(g)(3)(i-iii)]:

1. Any cutting or grinding apparatus will be equipped with point of work HEPA ventilation.

2. Compressed air will not be used.

3. No dry sweeping, shoveling or other dry clean-up of dust and debris containing asbestos

will be performed.

3.3. CEMENTITIOUS MATERIAL REMOVAL

A. The cementitious countertops and Cementitious panels – Associated with Hood Vent outlined in

Section 1.2 shall be removed in accordance with the following work methodology:

1. All asbestos-containing cementitious materials located in Rooms 313, 322 and 323 will

be abated in accordance with OSHA Class 2 Requirements [29 CFR 1926.1101 (g)(7)]

and specifically Section 29 CFR 1926.1101 (g)(8)(iii).

2. Cutting, abrading or breaking of the cementitious material shall be prohibited unless the

CONTRACTOR can demonstrate that methods less likely to result in asbestos fiber

release cannot be used.

3. The cementitious material shall be sprayed with amended water prior to removal.

4. Screws shall be removed or nails shall be cut with flat, sharp instruments.

5. The cementitious materials shall be immediately placed in an impervious waste bag or

wrapped in plastic sheeting and removed from Work Area.

3.4 FIRE DOORS

A. Fire doors outlined in Section 1.2, if fire doors are to be removed, remove fire doors intact and

dispose of as ACM.

3.5 VISUAL INSPECTION

A. The CONTRACTOR’S Superintendent shall conduct a detailed visual inspection of the asbestos

regulated area after cleaning has been completed. All surfaces within the regulated area shall be

inspected for debris from any sources, residue, dust or other matter. If any such debris is found,

the CONTRACTOR shall repeat cleaning and continue decontamination procedures.

Page 15: University of Akron Addendum No. 3€¦ · to specification 262923 “Variable Frequency Motor Controllers”. Item D7: Sheet E2.1; ... Item Q1: There is no mention of temperature

THE UNIVERSITY OF AKRON

LABORATORY RENOVATION PROJECT

ASBESTOS ABATEMENT 020702-11

B. The ENVIRONMENTAL REPRESENTATIVE shall then inspect the asbestos regulated area

after the area has been cleaned to the satisfaction of the CONTRACTOR’S Superintendent. If any

debris is found, the CONTRACTOR shall repeat cleaning and continue decontamination

procedures until the regulated area has been cleaned to the satisfaction of both the

ENVIRONMENTAL REPRESENTATIVE and CONTRACTOR’S Superintendent. Cleaning is

not considered complete until the ENVIRONMENTAL REPRESENTATIVE and

CONTRACTOR’S Superintendent have signed the Certificate of Visual Inspection form

(02071A) located at the end of this section.

3.6 CLEARANCE AIR SAMPLING

A. Clearance Air Samples will be collected by the ENVIRONMENTAL REPRESENTATIVE after

the Work Area has passed final visual inspection. Clearance air samples will be sent via courier to

a laboratory so that verbal reports on samples can be obtained within 24 hours of receipt by the

laboratory or will be read on site by a NIOSH 7400 trained individual.

B. If analysis by PCM indicates that the concentration of fibers in any of these samples exceeds the

Release Criteria of 0.01 f/cc, the CONTRACTOR shall continue to clean the work area until air

monitoring has indicated that fiber concentrations have fallen below this limit.

3.7 RE-ESTABLISHMENT OF THE WORK AREA

A. Re-establishment of the work area shall only occur after clearance air monitoring has been

performed and documented to the satisfaction of the ENVIRONMENTAL REPRESENTATIVE.

B. Following satisfactory clearance of the Work Area, the negative air units may be turned off.

Before moving the negative air machines out of the work area, remove and properly dispose of

pre-filters and seal intake to machine(s) with 6-mil polyethylene sheeting.

C. Remove the critical barriers separating the Work Area from the rest of the facility, and dispose of

materials as asbestos-contaminated waste.

D. Remove the equipment room. Remove any small quantities of residual material found with wet

wiping and HEPA-filtered vacuum cleaners.

E. Remove all equipment, materials and waste from the work site.

F. Dispose of all waste materials as specified in this Section 3.8.

3.8 WASTE DISPOSAL

A. Once double bagged or placed in drums or otherwise containerized (wrapped), containers should

be decontaminated by wet cleaning and loaded into an enclosed truck for transportation to the

designated disposal site. Asbestos waste shall not be placed into trucks with non-asbestos waste.

Page 16: University of Akron Addendum No. 3€¦ · to specification 262923 “Variable Frequency Motor Controllers”. Item D7: Sheet E2.1; ... Item Q1: There is no mention of temperature

THE UNIVERSITY OF AKRON

LABORATORY RENOVATION PROJECT

ASBESTOS ABATEMENT 020702-12

B. Dispose of waste asbestos material at an EPA or a state permitted disposal site off the property as

approved by the ENVIRONMENTAL REPRESENTATIVE.

C. Procedures for hauling and disposal shall comply with all applicable federal, state and local

standards.

D. Personnel off-loading containers at the disposal site shall wear protective equipment consisting of

disposable head, body, and foot protection and, at a minimum, half-facepiece, dual cartridge

respirators equipped with HEPA filters. Following the removal of all containerized waste, the

truck cargo area shall be decontaminated to meet the no visible residue criteria. Polyethylene

sheeting shall be removed and discarded along with contaminated cleaning materials and

protective clothing, in bags or drums at the disposal site. The CONTRACTOR shall submit all

chain-of-custody forms signed by the disposal site operator accepting the waste ACM, to the

ENVIRONMENTAL REPRESENTATIVE for review for compliance to regulations.

3.9 CERTIFICATE OF COMPLETION

Following this Section is a "Certificate of Completion" (Form 02071B). This certification is to be

completed by the CONTRACTOR and certified by the ENVIRONMENTAL REPRESENTATIVE.

Page 17: University of Akron Addendum No. 3€¦ · to specification 262923 “Variable Frequency Motor Controllers”. Item D7: Sheet E2.1; ... Item Q1: There is no mention of temperature

THE UNIVERSITY OF AKRON

LABORATORY RENOVATION PROJECT

ASBESTOS ABATEMENT 020702-13

FORM 02071A

CERTIFICATE OF VISUAL INSPECTION

Project Name:

Building Name/Number:

Work Area Description:

The CONTRACTOR hereby certifies that he has visually inspected the work area (all surfaces, including pipes,

beams, ledges, walls, ceiling and floor, decontamination unit, sheet plastic, etc.) and has found no dust, debris or

residue.

By: Date:

(Signature)

(Print Name) (Print Title)

(Print Company Name)

ENVIRONMENTAL REPRESENTATIVE CERTIFICATION

The ENVIRONMENTAL REPRESENTATIVE hereby certifies that he/she has accompanied the

CONTRACTOR on the CONTRACTOR’S visual inspection and verifies that this inspection has been thorough,

and to the best of the ENVIRONMENTAL REPRESENTATIVE’S knowledge and belief, the CONTRACTOR’S

Certification above is a true and honest one.

By: Date:

(Signature)

(Print Name) (Print Title)

(Print Company Name)

FORM 02071B

Page 18: University of Akron Addendum No. 3€¦ · to specification 262923 “Variable Frequency Motor Controllers”. Item D7: Sheet E2.1; ... Item Q1: There is no mention of temperature

THE UNIVERSITY OF AKRON

LABORATORY RENOVATION PROJECT

ASBESTOS ABATEMENT 020702-14

CERTIFICATE OF COMPLETION

CLIENT/ PROJECT:

LOCATION:

TYPES OF ACM:

INSPECTION CHECKLIST

Yes / No The Asbestos Abatement Contractor was present during the visual inspection.

Yes / No A written detailed scope of work or written specification was provided prior to the inspection

to verify all required asbestos-containing materials were removed.

Yes / No All materials and equipment were properly removed from the work area according to the scope

of work or written specification.

Yes / No Plastic sheeting present in the work area was wet wiped to remove visible debris.

Yes / No All surfaces, materials, and equipment not covered with plastic sheeting in the work area were

wet wiped to remove visible debris.

Yes / No Decontamination units were wet wiped to remove visible debris and waste was properly

filtered or bagged.

Signature of Inspector:________________________________ Date:_______________

Printed Name:________________________________ Time:______________

Certification State and No:_____________________________

ENCAPSULATION AND CLEARANCE AIR MONITORING CHECKLIST

Yes / No Lock down encapsulant was applied to all specified surfaces.

Yes / No Clearance air sampling was specified or required for this work.

PCM / TEM Type of clearance air samples collected.

• If PCM, minimum of 3 samples required per work area; area clear if all samples

results less than or equal to 0.01 fibers per cubic centimeter (f/cc).

• If TEM, 5 inside work area samples required; area clear if average is less than or

equal to 70 structures per square millimeter (s/mm2).

Other criteria? Explain

Sample No.: _______ _________ _________ _________ _________ ________

PCM Result: 1)_____ 2)________ 3)_______ 4)_______ 5)_______ 6)______

TEM Result: 1)_____ 2)________ 3)_______ 4)_______ 5)_______ 6)______

Comments: ______________________________________________________________

Signature of Inspector: ________________________________ Date:___________

Printed Name:________________________________ Time:______________

Certification State and No: _____________________________

Page 19: University of Akron Addendum No. 3€¦ · to specification 262923 “Variable Frequency Motor Controllers”. Item D7: Sheet E2.1; ... Item Q1: There is no mention of temperature

THE UNIVERSITY OF AKRON

LABORATORY RENOVATION PROJECT

ASBESTOS ABATEMENT 020702-15

FORM 02071B

CERTIFICATE OF COMPLETION

Project Name:

Building Name/Number:

Work Area Description:

I, the undersigned, certify that the asbestos removal portion of the work which occurred on

_____________________________ (Date(s)) has been performed according to federal, state and local

regulations, “state-of-the-art” technologies, and in accordance with specifications and drawings for this project.

By: Date:

(Signature)

(Print Name) (Print Title)

(Print Company Name)

ENVIRONMENTAL REPRESENTATIVE CERTIFICATION

The ENVIRONMENTAL REPRESENTATIVE hereby certifies that he/she has inspected the CONTRACTOR’S

work and verifies that the work has been performed in accordance with the above-referenced documents, and to

the best of the ENVIRONMENTAL REPRESENTATIVE’S knowledge and belief, the CONTRACTOR’S

Certification above is a true and honest one.

By: Date:

(Signature)

(Print Name) (Print Title)

(Print Company Name)

Page 20: University of Akron Addendum No. 3€¦ · to specification 262923 “Variable Frequency Motor Controllers”. Item D7: Sheet E2.1; ... Item Q1: There is no mention of temperature
Page 21: University of Akron Addendum No. 3€¦ · to specification 262923 “Variable Frequency Motor Controllers”. Item D7: Sheet E2.1; ... Item Q1: There is no mention of temperature

THE UNIVERSITY OF AKRON

LABORATORY RENOVATION PROJECT

SURGE PROTECTION FOR LOW-VOLTAGE ELECTRICAL POWER CIRCUITS

264313 - 1

SECTION 264313 - SURGE PROTECTION FOR LOW-VOLTAGE ELECTRICAL POWER CIRCUITS

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections, apply to this Section.

1.2 SUMMARY

A. Section includes field-mounted SPDs for low-voltage (120 to 600 V) power distribution and control equipment.

B. Related Requirements:

1. Section 262416 "Panelboards" for factory-installed SPDs.

1.3 DEFINITIONS

A. Inominal: Nominal discharge current.

B. MCOV: Maximum continuous operating voltage.

C. Mode(s), also Modes of Protection: The pair of electrical connections where the VPR applies.

D. MOV: Metal-oxide varistor; an electronic component with a significant non-ohmic current-

voltage characteristic.

E. OCPD: Overcurrent protective device.

F. SCCR: Short-circuit current rating.

G. SPD: Surge protective device.

H. VPR: Voltage protection rating.

1.4 ACTION SUBMITTALS

A. Product Data: For each type of product.

1. Include rated capacities, operating characteristics, electrical characteristics, and furnished

specialties and accessories.

Page 22: University of Akron Addendum No. 3€¦ · to specification 262923 “Variable Frequency Motor Controllers”. Item D7: Sheet E2.1; ... Item Q1: There is no mention of temperature

THE UNIVERSITY OF AKRON

LABORATORY RENOVATION PROJECT

SURGE PROTECTION FOR LOW-VOLTAGE ELECTRICAL POWER CIRCUITS

264313 - 2

2. Copy of UL Category Code VZCA certification, as a minimum, listing the tested values for VPRs, Inominal ratings, MCOVs, type designations, OCPD requirements, model

numbers, system voltages, and modes of protection.

1.5 INFORMATIONAL SUBMITTALS

A. Field quality-control reports.

B. Sample Warranty: For manufacturer's special warranty.

1.6 CLOSEOUT SUBMITTALS

A. Maintenance Data: For SPDs to include in maintenance manuals.

1.7 WARRANTY

A. Manufacturer's Warranty: Manufacturer agrees to replace or replace SPDs that fail in materials

or workmanship within specified warranty period.

1. Warranty Period: Five years from date of Substantial Completion.

PART 2 - PRODUCTS

2.1 GENERAL SPD REQUIREMENTS

A. SPD with Accessories: Listed and labeled as defined in NFPA 70, by a qualified testing agency, and marked for intended location and application.

B. Comply with NFPA 70.

C. Comply with UL 1449.

D. MCOV of the SPD shall be the nominal system voltage.

2.2 PANEL SUPPRESSORS

A. Manufacturers: Subject to compliance with requirements, available manufacturers offering

products that may be incorporated into the Work include, but are not limited to, the following:

1. ABB France.

2. Advanced Protection Technologies Inc. (APT).

3. Eaton Corporation. 4. Emerson Electric Co.

5. GE Zenith Controls.

Page 23: University of Akron Addendum No. 3€¦ · to specification 262923 “Variable Frequency Motor Controllers”. Item D7: Sheet E2.1; ... Item Q1: There is no mention of temperature

THE UNIVERSITY OF AKRON

LABORATORY RENOVATION PROJECT

SURGE PROTECTION FOR LOW-VOLTAGE ELECTRICAL POWER CIRCUITS

264313 - 3

6. LEA International; Protection Technology Group. 7. Leviton Manufacturing Co., Inc.

8. PowerLogics, Inc.

9. Schneider Electric Industries SAS.

10. Siemens Industry, Inc.

B. SPDs: Comply with UL 1449, Type 1.

1. Include LED indicator lights for power and protection status.

2. Internal thermal protection that disconnects the SPD before damaging internal suppressor components.

3. Include Form-C contacts rated at 5 A and 250-V ac, one normally open and one normally

closed, for remote monitoring of protection status. Contacts shall reverse on failure of

any surge diversion module or on opening of any current-limiting device. Coordinate with building power monitoring and control system.

C. Peak Surge Current Rating: The minimum single-pulse surge current withstand rating per phase

shall not be less than 100 kA. The peak surge current rating shall be the arithmetic sum of the ratings of the individual MOVs in a given mode.

D. Comply with UL 1283.

E. Protection modes and UL 1449 VPR for grounded wye circuits with 208Y/120 V, three-phase, four-wire circuits shall not exceed the following:

1. Line to Neutral: 700 V for 208Y/120 V.

2. Line to Ground: 700 V for 208Y/120 V.

3. Neutral to Ground: 700 V for 208Y/120 V. 4. Line to Line: 1200 V for 208Y/120 V

F. Protection modes and UL 1449 VPR for 240/120-V, single-phase, three-wire circuits shall not

exceed the following:

1. Line to Neutral: 700 V.

2. Line to Ground: 700 V.

3. Neutral to Ground: 700 V. 4. Line to Line: 1200 V.

G. SCCR: Equal or exceed 100 kA.

H. Inominal Rating: 10 kA.

2.3 ENCLOSURES

A. Indoor Enclosures: NEMA 250, Type 1.

B. Outdoor Enclosures: NEMA 250, Type 4.

Page 24: University of Akron Addendum No. 3€¦ · to specification 262923 “Variable Frequency Motor Controllers”. Item D7: Sheet E2.1; ... Item Q1: There is no mention of temperature

THE UNIVERSITY OF AKRON

LABORATORY RENOVATION PROJECT

SURGE PROTECTION FOR LOW-VOLTAGE ELECTRICAL POWER CIRCUITS

264313 - 4

2.4 CONDUCTORS AND CABLES

A. Power Wiring: Same size as SPD leads, complying with Section 260519 "Low-Voltage

Electrical Power Conductors and Cables."

PART 3 - EXECUTION

3.1 INSTALLATION

A. Comply with NECA 1.

B. Install an OCPD or disconnect as required to comply with the UL listing of the SPD.

C. Install SPDs with conductors between suppressor and points of attachment as short and straight as possible, and adjust circuit-breaker positions to achieve shortest and straightest leads. Do not

splice and extend SPD leads unless specifically permitted by manufacturer. Do not exceed

manufacturer's recommended lead length. Do not bond neutral and ground.

D. Use crimped connectors and splices only. Wire nuts are unacceptable.

E. Wiring:

1. Power Wiring: Comply with wiring methods in Section 260519 "Low-Voltage Electrical

Power Conductors and Cables." 2. Controls: Comply with wiring methods in Section 260519 "Low-Voltage Electrical

Power Conductors and Cables."

3.2 FIELD QUALITY CONTROL

A. Perform the following tests and inspections with the assistance of a factory-authorized service

representative.

1. Compare equipment nameplate data for compliance with Drawings and Specifications.

2. Inspect anchorage, alignment, grounding, and clearances. 3. Verify that electrical wiring installation complies with manufacturer's written installation

requirements.

B. An SPD will be considered defective if it does not pass tests and inspections.

C. Prepare test and inspection reports.

3.3 STARTUP SERVICE

A. Complete startup checks according to manufacturer's written instructions.

Page 25: University of Akron Addendum No. 3€¦ · to specification 262923 “Variable Frequency Motor Controllers”. Item D7: Sheet E2.1; ... Item Q1: There is no mention of temperature

THE UNIVERSITY OF AKRON

LABORATORY RENOVATION PROJECT

SURGE PROTECTION FOR LOW-VOLTAGE ELECTRICAL POWER CIRCUITS

264313 - 5

B. Do not perform insulation-resistance tests of the distribution wiring equipment with SPDs installed. Disconnect SPDs before conducting insulation-resistance tests, and reconnect them

immediately after the testing is over.

C. Energize SPDs after power system has been energized, stabilized, and tested.

3.4 DEMONSTRATION

A. Train Owner's maintenance personnel to operate and maintain SPDs.

END OF SECTION 264313

Page 26: University of Akron Addendum No. 3€¦ · to specification 262923 “Variable Frequency Motor Controllers”. Item D7: Sheet E2.1; ... Item Q1: There is no mention of temperature