Upload
others
View
2
Download
0
Embed Size (px)
Citation preview
Byron Williams – Senior Project Manager Pact PM Suite 2.04/41 McLaren Street North Sydney NSW 2060 16 October 2019 Dear Byron, OPAL AGED CARE MARSDEN PARK DA COST ESTIMATE QUANTITY SURVEYOR’S REPORT As requested WT Partnership has prepared a DA cost estimate for the works at the above and advise that the estimated development cost at rates current at October 2019 is $33,961,457 exclusive of GST and $37,357,602 inclusive of GST.
We refer you to the attached report which provides an Executive Summary, Summary of Costs together with Schedule of Information Used, and Exclusions.
We trust the enclosure is in accordance with your requirements, however please do not hesitate to contact us should you require any further information or wish to discuss any aspect of the report.
Yours faithfully, WT Partnership KEVIN DAVIS
National Director ([email protected])
OPAL AGED CARE MARSDEN PARK DA COST ESTIMATE QUANTITY SURVEYOR’S REPORT
16 October 2019
CONTENTS
CONTENTS 1 EXECUTIVE SUMMARY 1
2 SUMMARY OF COSTS 1
3 SCHEDULE OF INFORMATION USED 2
4 EXCLUSIONS 2
APPENDIX A REGISTERED QUANTITY SURVEYOR’S REPORT
APPENDIX B DETAILED COST ESTIMATE
197648 DA COST REPORT 1
1 EXECUTIVE SUMMARY As requested, WT Partnership (WT) has prepared this DA cost report in accordance with the definition in Clause 25J and Clause 255 of the Environmental Planning Assessment Regulation 2000.
Based upon the above definition, we estimate the development cost for the project to be $37,357,602 including GST, as summarised below.
2 SUMMARY OF COSTS
COST ESTIMATE
1 SITE PREPARATION AND DEMOLITION 416,099
2 SUBSTRUCTURE 1,533,005
3 COLUMNS 374,299
4 UPPER FLOORS 1,367,693
5 STAIRCASES 63,000
6 ROOF 2,242,174
7 EXTERNAL WALLS AND FAÇADE 2,987,362
8 INTERNAL WALLS 1,723,435
9 INTERNAL DOORS 523,040
10 INTERNAL SCREENS 182,650
11 WALL FINISHES 1,066,205
12 FLOOR FINISHES 1,010,473
13 CEILING FINISHES 978,398
14 FIXTURES AND FITTINGS 2,249,500
15 SPECIAL EQUIPMENT 15,000
16 HYDRAULICS SERVICES 2,168,717
17 ELECTRICAL SERVICES 2,928,848
18 MECHANICAL SERVICES 2,457,879
19 AUDIO VISUAL SERVICES Excluded
20 FIRE SERVICES 659,272
21 LIFT SERVICES 257,500
197648 DA COST REPORT 2
22 EXTERNAL WORKS 1,522,478
23 EXTERNAL SERVICES AND INFRASTRUCTURE 770,000
SUBTOTAL – TRADE COST (EXCL GST) 27,497,027
24 PRELIMINARIES AND MARGIN 4,949,000
SUBTOTAL – CONSTRUCTION COST (EXCL GST) 32,446,027
25 DESIGN FEES 1,515,430
SUBTOTAL – DEVELOPMENT COST (EXCL GST) 33,961,457
26 GST 3,396,145
TOTAL – DEVELOPMENT COST (INCL GST) 37,357,602
3 SCHEDULE OF INFORMATION USED The following information was used and or considered in the preparation of the estimate:
Architecture drawings dated 20/09/2019 provided by Custance Architect
o DA1.20 Revision D Ground Floor Plan
o DA1.21 Revision D Level 1 Plan
o DA1.22 Revision D Roof Plan
o DA3.00 Revision E External Elevations 1
o DA3.01 Revision E External Elevations 2
o DA3.10 Revision D Building Sections
o DA3.11 Revision D Building Sections
Landscape Architecture drawings dated 20/09/2019 provided by Taylor Brammer
Landscape Architect
o LA200 Revision A Landscape Masterplan
o LA201 Revision A Community Courtyard
o LA202 Revision A Memory Support & Public Courtyard
o LA203 Revision A Evening Courtyard – Level 1
o LA400 Revision A Planting Plan & Schedules
o LA501 Revision A Typical Details
4 EXCLUSIONS The estimate of development cost is subject to the following exclusions in accordance with Clause 25J of the Environmental Planning Assessment Regulation 2000.
197648 DA COST REPORT 3
Taxes, levies or charges (other than GST)
Legal fees
Marketing costs
Finance and related fees and charges
Land purchasing and holding costs
Authority fees
Project Management fees
Building insurance costs
Contingency
Escalation (beyond October 2019)
197648 DA COST REPORT 4
APPENDIX A REGISTERED QUANTITY SURVEYOR’S REPORT
Registered Quantity Surveyors Report
Complete this Registered Quantity Surveyor’s Report if your Development costs are $500,000 or
more
DA Number: Date:
Applicant’s name: Development address:
Applicant’s address:
DEVELOPMENT DETAILS
GFA – Commercial (m2): GFA – Parking (m2):
GFA – Residential (m2): GFA – Other (m2):
GFA – Retail (m2): Total GFA (m2):
Total development cost: Total site area (m2):
Total construction cost: Total car parking spaces:
Total GST:
ESTIMATE DETAILS
Professional fees ($): Construction (Commercial):
% of construction cost: Total construction cost:
% of demolition cost: $/m² of site area:
Demolition and site preparation: Construction (Residential):
Total construction cost: Total construction cost:
$/m² of site area: $/m² of site area:
Excavation: Construction (Retail):
Total construction cost: Total construction cost:
$/m² of site area: $/m² of site area:
Fitout (Residential): Fitout (Commercial):
Total construction cost: Total construction cost:
$/m² of site area: $/m² of site area:
Fitout (Retail): Parking:
Total construction cost: Total construction cost:
$/m² of site area: $/m² of site area:
$/space
I certify that I have:
• Inspected the plans the subject of the application for development consent;• Prepared and attach an elemental estimate generally prepared in accordance with the Australian
Cost Management Manuals from the Australian Institute of Quantity Surveyors;
• Calculated the development costs in accordance with the definition of development costs inclause 25J of the Environmental Planning and Assessment Regulation 2000 at current prices;
• Included GST in the calculation of development cost; and• Measured Gross Floor Areas in accordance with the Method of Measurement of Building Areas in
the AIQS Cost Management Manual Volume 1, Appendix A2.
16/10/2019Lot 2890 in DP1230906, Northbourne Drive, Marsden Park NSW 2765
9,358 m29,358 m2
10,060 m2
$1,666,9735%
$130,578$13/m2
$409,519$41/m2
$34,890,058$3,468/m2
$260,474$26/m2
Signed:
Name: Gary Mayor
Position and qualifications
Date: 16/10/2019
Associate Director - AAIQS
Included
$35,690,629$37,357,602
$3,396,14551 no.
197648 DA COST REPORT 5
APPENDIX B DETAILED COST ESTIMATE
Opal Marsden ParkOpal Marsden Park16 October 2019
Opal Marsden ParkPROJECT:
REPORT:
Quantity Unit Rate (AUD) Total
Opal Marsden Park
Opal Marsden Park DA Cost Report Summary:
Opal Marsden Park DA Cost Report
OPAL MARSDEN PARK RCF - Budget Estimate
Based on 20/09/2019 DA documentation
In accordance with the definition of development costs inclause 25J of the Environmental Planning andAssessment Regulation 2000
3 October 2019
Site Preparation and Earthworks m29,358 44 416,099
Substructure m29,358 164 1,533,005
Columns m29,358 40 374,299
Upper Floors m29,358 146 1,367,693
Staircases m29,358 7 63,000
Roof m29,358 240 2,242,174
External Walls and Façade m29,358 319 2,987,362
Internal Walls m29,358 184 1,723,435
Internal Doors m29,358 56 523,040
Internal Screens m29,358 20 182,650
Wall Finishes m29,358 114 1,066,205
Floor Finishes m29,358 108 1,010,473
Ceiling Finishes m29,358 105 978,398
Fixtures & Fittings m29,358 240 2,249,500
Special Equipment m29,358 2 15,000
Hydraulic Services m29,358 232 2,168,717
Electrical Services m29,358 313 2,928,848
Mechanical Services m29,358 263 2,457,879
Audio Visual Services m29,358 0 Excluded
Fire Services m29,358 70 659,272
Lift Services m29,358 28 257,500
External Works m29,358 163 1,522,478
External Services and Infrastructure m29,358 82 770,000
Subtotal - Trade Costs m29,358 2,938.34 27,497,027
HEAD CONTRACTORS PRELIMINARIES & MARGIN(18%)
m29,358 529 4,949,000
Subtotal - Construction Cost [ExcludingContingency]
m29,358 3,467.20 32,446,027
DESIGN CONTINGENCY Excluded
WT Partnership / 197648 Page i
Opal Marsden ParkPROJECT:
REPORT:
Quantity Unit Rate (AUD) Total
Opal Marsden Park
Opal Marsden Park DA Cost Report Summary:
Opal Marsden Park DA Cost Report
CONSTRUCTION CONTINGENCY Excluded
ESCALATION Excluded
CLIENT FFE Excluded
CLIENT IT Excluded
CONSTRUCTION COST ESTIMATE [Excluding GST] m29,358 3,467.20 32,446,027
DESIGN FEES 1,515,430
LOCAL AUTHORITY FEES AND CHARGES Excluded
LONG SERVICE LEVY Excluded
DEVELOPMENT COST ESTIMATE [Excluding GST] 33,961,457
GST 3,396,146
DEVELOPMENT COST ESTIMATE [Including GST] 37,357,602
FECA : m28,325
UCA : m21,033
GFA : m29,358
No of Units: No148
No of Beds: No148
Construction Cost Per m2 (excluding GST) /m23,467
Construction Cost Per Bed (excluding GST) /bed219,230
Development Cost Per m2 (excluding GST) /m23,629
Development Cost Per Bed (excluding GST) /bed229,469
WT Partnership / 197648 Page i
Code Description Quantity Unit Rate (AUD) Total
Opal Marsden ParkOpal Marsden Park DA Cost Report
PROJECT:
REPORT:
Opal Marsden Park
Site Preparation and EarthworksDemolition
Allow for demolition N/A
Site Preparation
Allow for site preparation 10,060 m2 10.00 100,5991/A
Bulk Excavation
Cut 3,530 m3 30.00 105,9001/B
Extra over for rock excavation (assume 10%) 353 m3 50.00 17,6501/C
Filling
Fill with excavated material 2,010 m3 35.00 70,3501/D
Disposal
Disposal offsite (assumed VENM, 2t/m3) 1,520 m3 80.00 121,6001/E
Total Site Preparation and Earthworks 416,099$
WT Partnership / 197648 Page 1
Code Description Quantity Unit Rate (AUD) Total
Opal Marsden ParkOpal Marsden Park DA Cost Report
PROJECT:
REPORT:
Opal Marsden Park
SubstructureSubstructure
Allow for bored piers 4,838.60 m2 95.00 459,6882/A
Allow for lift pit 17.53 m2 1,583.00 27,7502/B
Allow for slab on ground, assume 200mm thick 5,700.24 m2 155.00 883,5372/C
Allow for strip footing, assume 400mm wide x 800mmdeep
501.64 m 323.00 162,0302/D
Total Substructure 1,533,005$
WT Partnership / 197648 Page 2
Code Description Quantity Unit Rate (AUD) Total
Opal Marsden ParkOpal Marsden Park DA Cost Report
PROJECT:
REPORT:
Opal Marsden Park
ColumnsColumns
Allow elemental rate for columns 9,357.47 m2 40.00 374,2993/A
Total Columns 374,299$
WT Partnership / 197648 Page 3
Code Description Quantity Unit Rate (AUD) Total
Opal Marsden ParkOpal Marsden Park DA Cost Report
PROJECT:
REPORT:
Opal Marsden Park
Upper FloorsUpper Floors
Allow for reinforced concrete suspended slab, 250 thick 4,054.44 m2 325.00 1,317,6934/A
Extra over to form setdown 1 Item 50,000.00 50,0004/B
Total Upper Floors 1,367,693$
WT Partnership / 197648 Page 4
Code Description Quantity Unit Rate (AUD) Total
Opal Marsden ParkOpal Marsden Park DA Cost Report
PROJECT:
REPORT:
Opal Marsden Park
StaircasesFire / Circulation stair - Internal 17 mrise 3,000.00 51,0005/A
Fire / Circulation stair - External 4 mrise 3,000.00 12,0005/B
Total Staircases 63,000$
WT Partnership / 197648 Page 5
Code Description Quantity Unit Rate (AUD) Total
Opal Marsden ParkOpal Marsden Park DA Cost Report
PROJECT:
REPORT:
Opal Marsden Park
RoofRoof
Allow for reinforced concrete roof slab, includingwaterproofing
982 m2 415.00 407,5136/A
Allow for light weight steel framed metal roof 4,786 m2 250.00 1,196,5036/B
Allow for fibre cement eave soffit 1,006 m2 195.00 196,0806/C
Allow for roof plant platform 1 Item 85,000.00 85,0006/D
Allow for roof access hatch 1 Item 25,000.00 25,0006/E
Allow for roof plumbing 1 Item 65,000.00 65,0006/F
Allow for skylight 1 Item 5,000.00 5,0006/G
Allow for roof anchor points 1 Item 25,000.00 25,0006/H
Pergola over Balconies to Sitting Nook 98 m2 750.00 73,5986/J
Vergola over Outdoor Dining 73 m2 1,500.00 109,8606/K
Revised Porte Cochere 54 m2 1,000.00 53,6206/L
Total Roof 2,242,174$
WT Partnership / 197648 Page 6
Code Description Quantity Unit Rate (AUD) Total
Opal Marsden ParkOpal Marsden Park DA Cost Report
PROJECT:
REPORT:
Opal Marsden Park
External Walls and FaçadeExternal Walls and Facade
External Wall
Allow for Vitrapanel cladding with 92mm steel stud,insulation and 13mm plasterboard lining internally
1,774.89 m2 390.00 692,2077/A
Wall type 1a, assume comprising Vitrapanel claddingboth sides, 92mm steel stud
68.30 m2 620.00 42,3467/B
Single layer face brick wall 423.93 m2 215.00 91,1457/C
Extra over for feature brick with pattern to wall next toentrance, assumed extent 4.4m wide x 4.1m high
18 m2 150.00 2,7067/D
Wall type 3, assume comprising face brick, cavity,92mm steel stud with insulation and 13mm plasterboardlining internally
678.71 m2 315.00 213,7947/E
Extra over for replacing inner layer with 140 block wall toBOH area
148.16 m2 75.00 11,1127/F
Wall type 3a, face brick parapet wall to roof garden,details to be confirmed
40.59 m 575.00 23,3397/G
Face brick finish wall to north elevation, details to beconfirmed
71.00 m2 250.00 17,7507/H
Sunshading and Screens
Type 1
Aluminium sunshade, 0.9m/1.2m deep x 4.8m girth 168.48 m2 500.00 84,2407/J
Type 2
Aluminium sunshade (horizontal) to MSU bedrooms 22.50 m2 500.00 11,2507/K
Type 3
Vertical sunshades to Level 1 bedrooms, east and westsides
78.12 m2 500.00 39,0607/L
Type 4
Privacy screen, 1.5m high 74 m2 425.00 31,4507/M
Vertical Battens
To resident balconies facing the courtyards 372.00 m 100.00 37,2007/N
Aluminium battens to fire stairs 53.69 m2 500.00 26,8457/P
Aluminium timber look vertical battens to Sitting areanext to open stair
47.60 m 85.00 4,0467/Q
Allow for timber look aluminium battens, vertical, tooutdoor area to Allied
34 m 100.00 3,4007/R
Horizontal Battens
Timber look aluminium batten screen to east and westside bedrooms
1,875.20 m 85.00 159,3927/S
Aluminium timber look horizontal battens to Sitting andAudio area glazing
152.10 m2 650.00 98,8657/T
Balustrades
WT Partnership / 197648 Page 7
Code Description Quantity Unit Rate (AUD) Total
Opal Marsden ParkOpal Marsden Park DA Cost Report
PROJECT:
REPORT:
Opal Marsden Park
Glazed balustrade, 1.5m high, to Level 1 bedroomsfacing courtyard
59 m 650.00 38,3508/A
Allow for 1.5m high glazed balustrade, to commonbalconies
80.97 m 650.00 52,6318/B
Glazed balustrade over parapet wall, assume 500mmhigh
28.46 m 350.00 9,9618/C
Allow for glazed balustrade to GF North and Eastterraces and outside Sitting area, approx 1m high
120.54 m 550.00 66,2978/D
Allow for aluminium balustrade to North Westernresident rooms
47.70 m 300.00 14,3108/E
Glazing
Glazed wall 774.63 m2 650.00 503,5108/F
Double height glazed wall, to entrance and courtyard 68.94 m2 750.00 51,7058/G
Air lock glazing 28.99 m2 750.00 21,7438/H
Extra over for automatic door to entrance and alliedhealth
3 No 15,000.00 45,0008/J
Extra over for single swing door 19 No 1,000.00 19,0008/K
Extra over for double swing door 5 No 1,500.00 7,5008/L
Extra over for double auto-sliding door 6 No 5,000.00 30,0008/M
Extra over for bi-folding door to Gym 1 No 3,500.00 3,5008/N
Sliding doors to terrace and balcony 487 m2 650.00 316,5508/P
Allow for aluminum framed windows, including lintelsand sills
328 m2 550.00 180,5608/Q
Louvre
Glass louvres to Winter Garden / Outdoor Dining 14 m2 800.00 11,2008/R
Door
Allow for single solid core fire door to fire stairs 5 No 1,450.00 7,2508/S
Allow for double solid core fire door to services on southelevation
2 No 2,250.00 4,5008/T
Single solid core hinged door to Men's shed and loading 2 No 1,450.00 2,9008/U
Roller door to Loading, assume approx 3m wide x 3.2mhigh
1 No 7,500.00 7,5008/V
Roller shutter to men's shed, 2700 wide x 2500 high 1 No 3,250.00 3,2508/W
Total External Walls and Façade 2,987,362$
WT Partnership / 197648 Page 8
Code Description Quantity Unit Rate (AUD) Total
Opal Marsden ParkOpal Marsden Park DA Cost Report
PROJECT:
REPORT:
Opal Marsden Park
Internal Walls Internal Walls
Reinforced concrete walls to lift and stair cores 444 m2 445.00 197,5809/A
Allow for block walls to BOH area, assuming 13mmplasterboard on furring channel to both sides
671 m2 265.00 177,8159/B
Partitions to common area, and between unit andcorridor, assume comprising 92mm steel stud and13mm plasterboard on both sides
3,422 m2 145.00 496,1909/C
Party wall between units, assume double stud wall withplasterboard lining on both sides
2,250 m2 200.00 450,0009/D
Allow for riser wall, assume comprising 92mm steel studand 13mm plasterboard on one side
1,374 m2 80.00 109,9209/E
DEDUCT
Allow for riser wall, assume comprising 92mm steel studand 13mm plasterboard on one side
1,374 m2 80.00 -109,9209/F
ADD
Wall between bedroom and corridor, assumecomprising 92mm steel stud, 13mm plasterboard onboth sides and insulation
687 m2 120.00 82,4409/G
Partitions between bedroom and ensuites 1,386 m2 125.00 173,2509/H
Extra over for moisture resistant plasterboard to wetarea
3,094 m2 10.00 30,9409/J
Allow for wall reinforcement (marine ply) to wet areawalls for fixtures, 2.5m high
1,950 m2 35.00 68,2509/K
deduction for p-trap WC pans to reduce peno's 1 Item -15,900.00 -15,9009/L
Internal Walls to Allied Health
Allow for block walls as party wall between Allied Healthand other areas, assuming 13mm plasterboard onfurring channel to both sides
113 m2 265.00 29,9199/M
Partitions, assume comprising 92mm steel stud and13mm plasterboard on both sides
227 m2 145.00 32,9519/N
Total Internal Walls 1,723,435$
WT Partnership / 197648 Page 9
Code Description Quantity Unit Rate (AUD) Total
Opal Marsden ParkOpal Marsden Park DA Cost Report
PROJECT:
REPORT:
Opal Marsden Park
Internal DoorsInternal Doors
All doors includes paint finishes & statutory signage Note
Single sliding doors to Ensuites 148 no 980.00 145,04010/A
Single solid swing doors; frame and hardware 212 no 1,100.00 233,20010/B
Double solid swing doors; frame and hardware 19 no 2,000.00 38,00010/C
Single fire door; frame and hardware 9 no 1,450.00 13,05010/D
Double smoke door; frame and hardware 17 no 4,000.00 68,00010/E
Roller door to Loading, assume 2.7m wide x 2.7m high 1 no 3,650.00 3,65010/F
Allowance for doors not shown on plan 1 Item 10,000.00 10,00010/G
Internal Doors to Allied Health
Single solid swing doors; frame and hardware 11 no 1,100.00 12,10010/H
Total Internal Doors 523,040$
WT Partnership / 197648 Page 10
Code Description Quantity Unit Rate (AUD) Total
Opal Marsden ParkOpal Marsden Park DA Cost Report
PROJECT:
REPORT:
Opal Marsden Park
Internal ScreensToilet cubicle to WC 4 each 1,500.00 6,00011/A
Allow for full height glazed partition 177 m2 550.00 97,35011/B
Extra over for single hinged door 10 No 750.00 7,50011/C
Extra over for automatic sliding door 3 No 5,000.00 15,00011/D
Allow for glazed balustrade to void, assume 1500mmhigh
16 m 800.00 12,80011/E
Feature screen to dining/lounge, assume 2.7m high 44 m2 1,000.00 44,00011/F
Total Internal Screens 182,650$
WT Partnership / 197648 Page 11
Code Description Quantity Unit Rate (AUD) Total
Opal Marsden ParkOpal Marsden Park DA Cost Report
PROJECT:
REPORT:
Opal Marsden Park
Wall FinishesWall Finishes
Lining
Plasterboard lining to lift and stair walls (the side facingcorridor / rooms)
352 m2 45.00 15,84012/A
Painting
Painting to plasterboard lining 11,962 m2 15.00 179,43012/B
Painting to Internal Doors [Included in Doors Budget] Note Incl.
Tiling
Allow for tiling to Ensuites (PC sum $30/m2), 2400mmhigh, including waterproofing
2,761.24 m2 145.00 400,38012/C
Extra over for feature tiles to Ensuite (PC sum$200/m2), 300mm wide x 2400mm high
106.56 m2 190.00 20,24612/D
Allow for tiling to WC & Hair Salon (PC sum $30/m2),assume 2700mm high
351.60 m2 145.00 50,98212/E
Vinyl
Allow for vinyl to Kitchen, Serveries, Laundry and DirtyUtility, assume 2700mm high
780.82 m2 85.00 66,37012/F
Allow for vinyl to Cleaner's room, assume 2700mm high 102.85 m2 85.00 8,74212/G
Skirting
Painted timber skirting 4,429.68 m 20.00 88,59412/H
Coved vinyl skirting to Ensuites, WC, Hair Salon,Kitchen, Serveries, Laundry, Dirty Utility, Cleaner's room
1,588.22 m 35.00 55,58812/J
General
Allowance for bump rails and corner protection tocommon areas
1 item 110,000 110,00012/K
Allowance for Internal Feature Wall Finishes 1 item 50,000 50,00012/L
Allied Health
GYM 47 m2 15.00 70912/M
Treatment Rooms 186 m2 15.00 2,79112/N
Wait/Reception 64 m2 15.00 96712/P
Admin/Office 128 m2 15.00 1,92512/Q
Store 48 m2 15.00 71512/R
Corridor 35 m2 15.00 52712/S
Allow for Feature Finishes to Reception / Waiting 1 item 7,200.00 7,20012/T
Battens to Colonnade 52.00 m 100.00 5,20012/U
Total Wall Finishes 1,066,205$
WT Partnership / 197648 Page 12
Code Description Quantity Unit Rate (AUD) Total
Opal Marsden ParkOpal Marsden Park DA Cost Report
PROJECT:
REPORT:
Opal Marsden Park
Floor FinishesFloor Finishes
Concrete Sealer
Allow sealer to Stairs, Loading zone, Garbage andServices area
407 m2 15.00 6,10513/A
Tiling
Allow tiling to Entry, Cafe and Lift Lobby 155 m2 110.00 17,05013/B
Allow tiling to Hair Salon 21 m2 145.00 3,04513/C
Vinyl
Allow vinyl to Ensuites 713 m2 165.00 117,70413/D
Allow vinyl to common area WCs 88 m2 165.00 14,52013/E
Allow vinyl to Cleaner's room 29 m2 165.00 4,78513/F
Allow vinyl to Laundry and Dirty Utility 192 m2 200.00 38,40013/G
Allow vinyl to Kitchen and Servery 218 m2 200.00 43,60013/H
Allow vinyl to Nurse Stations and Medical Rooms 149 m2 85.00 12,66513/J
Allow vinyl to other Back of House area 208 m2 65.00 13,52013/K
Allow vinyl to Dining 384 m2 85.00 32,64013/L
Carpet
Allow carpet to Bedrooms 2,906 m2 55.00 159,83013/M
Allow carpet to Corridor 1,419 m2 85.00 120,61513/N
Allow carpet to Offices and Admins 281 m2 85.00 23,88513/P
Allow carpet to Sitting, Lounge, Activity and AudioRooms
882 m2 95.00 83,79013/Q
Entry Mat
Allow entry mat 8 m2 650.00 5,20013/R
External Tiling / Paving
Allow tiling to Winter Garden 61 m2 200.00 12,17013/S
Allow unit pavers to Balconies / Terraces 1,029 m2 250.00 257,21013/T
Allied Health
Allow rubber finish to Gym 55 m2 180.00 9,90013/U
Allow carpet to Wait and Reception 34 m2 95.00 3,23013/V
Allow carpet to Office 37 m2 85.00 3,14513/W
Allow vinyl to Treatment Rooms 58 m2 85.00 4,93013/X
Allow vinyl to Store 17 m2 65.00 1,10513/Y
Allow carpet to Corridor 17 m2 85.00 1,42813/Z
General
Allow for Feature Floor Finishes 1 Item 20,000.00 20,00013/AA
WT Partnership / 197648 Page 13
Code Description Quantity Unit Rate (AUD) Total
Opal Marsden ParkOpal Marsden Park DA Cost Report
PROJECT:
REPORT:
Opal Marsden Park
8,329 m214/A
Total Floor Finishes 1,010,473$
WT Partnership / 197648 Page 14
Code Description Quantity Unit Rate (AUD) Total
Opal Marsden ParkOpal Marsden Park DA Cost Report
PROJECT:
REPORT:
Opal Marsden Park
Ceiling FinishesCeiling Finishes
Painting
Allow painting to to Stairs, Loading zone, Garbage andServices area
407 m2 15.00 6,10515/A
Plasterboard
Painted plasterboard generally 6,403 m2 80.00 512,24015/B
Painted Moisture Resistant plasterboard to wet area 1,296 m2 85.00 110,16015/C
Fibre cement
Painted FC soffit 163 m2 120.00 19,56015/D
Bulkhead
Plasterboard bulkhead, provisional quantities 692 m 100.00 69,20015/E
Cornice
Allow for cornice 6,005 m 15.00 90,07415/F
Allow for curtain recesses 628 m 80.00 50,27415/G
Allied Health
Painted plasterboard generally 218 m2 80.00 17,44015/H
Allow for cornice 223 m 15.00 3,34515/J
General
Allow for Feature Ceiling Finishes 1 Item 100,000.00 100,00015/K
Total Ceiling Finishes 978,398$
WT Partnership / 197648 Page 15
Code Description Quantity Unit Rate (AUD) Total
Opal Marsden ParkOpal Marsden Park DA Cost Report
PROJECT:
REPORT:
Opal Marsden Park
Fixtures & FittingsFurniture; Fixtures & Fitments
FF&E to Resident Rooms - By Client. Note
Joinery to Resident Single Rooms 135 each 3,200 432,00016/A
Joinery to Resident Large Single Rooms 13 each 3,600 46,80016/B
WC fitment to ensuite 148 each 3,000 444,00016/C
Allow for glass memory box outside door (assumed 1no. per resident room)
148 each 650 96,20016/D
Allowance for Joinery to General Areas
Reception/Waiting 1 item 15,000 15,00016/E
Facility manager 1 item 2,000 2,00016/F
Administration Officer 1 item 7,500 7,50016/G
Nurse Stations 5 item 5,000 25,00016/H
Lounge 2 level 20,000 40,00016/J
Dining Areas 2 level 20,000 40,00016/K
Sitting Areas 2 level 15,000 30,00016/L
Activities 2 item 5,000 10,00016/M
Consultation 1 item 2,000 2,00016/N
Storerooms 2 level 8,000 16,00016/P
Audio Rooms 2 level 10,000 20,00016/Q
Dirty Utility 2 level 8,000 16,00016/R
Hairdresser 1 item 15,000 15,00016/S
Serveries 2 level 16,000 32,00016/T
WC and Wash Station fitment 1 item 40,000 40,00016/U
Medical Rooms 5 item 3,000 15,00016/V
Cleaners Rooms 2 level 1,000 2,00016/W
Resident Facilities Fitout 1 PROV 40,000 40,00016/X
Administration Fitout 1 PROV 80,000 80,00016/Y
Allowance for statutory signage 1 PROV 20,000 20,00016/Z
Fireplace 2 Level 15,000.00 30,00016/AA
Equipment
Laundry Fitout 1 PROV 196,570 196,57016/AB
Kitchen Fitout 1 PROV 305,105 305,10516/AC
Cafe Fitout 1 PROV 53,325 53,32516/AD
Serveries Fitout 1 PROV 125,000 125,00016/AE
Allied Health
Reception 1 item 8,000 8,00016/AF
WT Partnership / 197648 Page 16
Code Description Quantity Unit Rate (AUD) Total
Opal Marsden ParkOpal Marsden Park DA Cost Report
PROJECT:
REPORT:
Opal Marsden Park
Admin / Office 2 item 3,500 7,00017/A
Treatment room 6 item 2,500 15,00017/B
Storages 2 item 1,500 3,00017/C
Gym Fitout 1 item 20,000 20,00017/D
Total Fixtures & Fittings 2,249,500$
WT Partnership / 197648 Page 17
Code Description Quantity Unit Rate (AUD) Total
Opal Marsden ParkOpal Marsden Park DA Cost Report
PROJECT:
REPORT:
Opal Marsden Park
Special EquipmentLaundry Chute. 1 item 15,000 15,00018/A
Garbage Compactor - Excluded. Note Excluded
Nurse call. Note Included
Medical Gases. Note Excluded
Total Special Equipment 15,000$
WT Partnership / 197648 Page 18
Code Description Quantity Unit Rate (AUD) Total
Opal Marsden ParkOpal Marsden Park DA Cost Report
PROJECT:
REPORT:
Opal Marsden Park
Hydraulic ServicesAllowance for Hydraulic Services 9,358 m2 225.00 2,105,55019/A
BWIC 1 item 63,167 63,16719/B
Budget advice provided by Wood & Grieve Engineers 1 Item 911,550.00 019/C
Total Hydraulic Services 2,168,717$
WT Partnership / 197648 Page 19
Code Description Quantity Unit Rate (AUD) Total
Opal Marsden ParkOpal Marsden Park DA Cost Report
PROJECT:
REPORT:
Opal Marsden Park
Electrical ServicesAllowance for Electrical Services 9,358 m2 280.00 2,620,24020/A
BWIC 1 item 78,607 78,60720/B
Extra over for feature lighting 1 Prov 50,000.00 50,00020/C
Extra over for PV panels 1 Prov 180,000.00 180,00020/D
Generator excluded Note
Budget advice provided by Wood & Grieve Engineers 1 item 3,464,096.00
020/E
Total Electrical Services 2,928,848$
WT Partnership / 197648 Page 20
Code Description Quantity Unit Rate (AUD) Total
Opal Marsden ParkOpal Marsden Park DA Cost Report
PROJECT:
REPORT:
Opal Marsden Park
Mechanical ServicesAllowance for Mechanical Services 9,358 m2 255.00 2,386,29021/A
BWIC 1 item 71,589 71,58921/B
Budget advice provided by Acor 1 item 2,286,600.00
021/C
Total Mechanical Services 2,457,879$
WT Partnership / 197648 Page 21
Code Description Quantity Unit Rate (AUD) Total
Opal Marsden ParkOpal Marsden Park DA Cost Report
PROJECT:
REPORT:
Opal Marsden Park
Fire ServicesAllowance for Dry Fire 9,358 m2 15.00 140,37022/A
Allowance for Wet Fire 9,358 m2 55.00 514,69022/B
BWIC 1 item 4,211 4,21122/C
Budget advice provided by Wood & Grieve Engineers 1 item 719,970.00 022/D
Total Fire Services 659,272$
WT Partnership / 197648 Page 22
Code Description Quantity Unit Rate (AUD) Total
Opal Marsden ParkOpal Marsden Park DA Cost Report
PROJECT:
REPORT:
Opal Marsden Park
Lift ServicesMain core passenger lifts from Ground to Level 1 2 each 125,000 250,00023/A
BWIC 1 item 7,500 7,50023/B
Total Lift Services 257,500$
WT Partnership / 197648 Page 23
Code Description Quantity Unit Rate (AUD) Total
Opal Marsden ParkOpal Marsden Park DA Cost Report
PROJECT:
REPORT:
Opal Marsden Park
External WorksExternal Works
Low retaining wall, maximum 300mm high 61.62 m 303.00 18,67124/A
Retaining wall, average 500mm high 80.84 m 417.50 33,75124/B
Retaining wall, average 600mm high 22.23 m 456.00 10,13724/C
Retaining wall, average 750mm high 64.03 m 536.25 34,33624/D
Retaining wall, average 1.5m high 50.54 m 870.00 43,97024/E
Retaining wall, approx. 2.25m high 9.64 m 1,203.75 11,60424/F
Soft landscaping
Artificial turf 131 m2 125.00 16,36924/G
Multi-purpose artificial turf (lawn bowl) 132 m2 125.00 16,46424/H
Turf 439 m2 25.00 10,98224/J
Mass planting 1,413 m2 80.00 113,04224/K
Extra over for raised planters 101 m2 60.00 6,08524/L
Trees 130 No 750.00 97,50024/M
Hard landscaping
Carpark pavement - asphalt 1,214 m2 100.00 121,42324/N
Driveway (entrance) pavement - concrete, including busbay
395 m2 150.00 59,25024/P
Forming crossovers 2 Item 10,000.00 20,00024/Q
Kerb 193.24 m Incl24/R
Perimeter footpath (assume concrete) including fireegress path
175 m2 125.00 21,81824/S
Unit paving on pedestals to private terraces included inFloor Finishes
Note
Coloured concrete footpath to courtyards 190 m2 180.00 34,25424/T
Feature paving to front entry including colonnade 267 m2 250.00 66,85024/U
Timber deck 400 m2 300.00 119,95824/V
Teahouse pergola complete, including bridge, decking,seating, kitchenette and water proof cover
1 Item 37,500.00 37,50024/W
Gardening nook, including waterproof pergola, outdoorkitchen, potting bench and timber cabinetry (2 no.)
55 m2 1,350.00 74,77724/X
Timber and steel pergola, including vines andwaterproof canopy
115 m2 500.00 57,68024/Y
Built in seat attached to planter wall 11 m 250.00 2,84824/Z
Built in table under pergola on roof garden 6 m 500.00 2,98024/AA
Dry creek bed with sculptural planting 47 m2 250.00 11,63524/AB
Sitting nook with memory wall 13 m 1,500.00 18,81024/AC
Timber bench 14.61 m 750.00 10,95824/AD
WT Partnership / 197648 Page 24
Code Description Quantity Unit Rate (AUD) Total
Opal Marsden ParkOpal Marsden Park DA Cost Report
PROJECT:
REPORT:
Opal Marsden Park
Putt putt court (9 holes) including artificial turf, island ofsensory planting
290 m2 150.00 43,50625/A
Water features 4 No 7,500.00 30,00025/B
Vegetable gardens with integrated seating 3 No 4,500.00 13,50025/C
Planter walls, assume 1m high 188.02 m2 400.00 75,20825/D
Allow for concrete edges 111.30 m 75.00 8,34825/E
Activity wall 12 m 750.00 8,67025/F
Bench, approx 2m long 2 No 1,500.00 3,00025/G
Feature pots 5 No 500.00 2,50025/H
Stainless steel mesh creeper frame 64 m2 150.00 9,62625/J
Discovery playground 22 m2 2,500.00 54,12525/K
Loose furniture 0
Allow for Canopy to Colonnade 70 m2 1,000.00 69,90025/L
Allow for Entry Statement & Signage 1 Item 25,000.00 25,00025/MAllow for BBQ to outdoor dining 1 Item 25,000.00 25,00025/N
1.8m high pallisade style fence 178.81 m 200.00 35,76225/P
1.8m high metal fence 191.80 m 200.00 38,36025/Q
2.1m high metal fence 19.66 m 220.00 4,32525/R
Allow for bollards 2 No 1,000.00 2,00025/S
Total External Works 1,522,478$
WT Partnership / 197648 Page 25
Code Description Quantity Unit Rate (AUD) Total
Opal Marsden ParkOpal Marsden Park DA Cost Report
PROJECT:
REPORT:
Opal Marsden Park
External Services and InfrastructureAllow for services connections 1 Item 125,000.00 125,00026/A
Allow for stormwater 1 Item 245,000.00 245,00026/B
Allow for external lighting and security 1 Item 50,000.00 50,00026/C
Allow for substation 1 Item 250,000.00 250,00026/D
Allow for underground rainwater tank, 25kL 2 No 50,000.00 100,00026/E
Total External Services and Infrastructure 770,000$
WT Partnership / 197648 Page 26
Code Description Quantity Unit Rate (AUD) Total
Opal Marsden ParkOpal Marsden Park DA Cost Report
PROJECT:
REPORT:
Opal Marsden Park
DESIGN FEESAs per PactPM advice (design fees only) 1 1,515,430.0
01,515,43027/A
Total DESIGN FEES 1,515,430$
WT Partnership / 197648 Page 27
197648 DA COST REPORT 6
SERVICES WT Partnership is an international consultancy providing independent project management, cost management and other specialist advisory services for the property and construction industries.
We work in partnership with our clients and their advisers at all phases of the project development process, giving professional, timely and reliable advice on all aspects of cost, value and risk.
Our goal is the achievement of our client’s ultimate commercial objectives through optimised cost solutions.
◼ QUANTITY SURVEYING AND CONSTRUCTION COST MANAGEMENT
◼ INFRASTRUCTURE COST ENGINEERING
◼ BUILDING AND ENGINEERING SERVICES COST MANAGEMENT
◼ FACILITIES MANAGEMENT CONSULTANCY AND COST CONTROL
◼ TECHNICAL ADVISORY SERVICES
◼ SUSTAINABILITY
wtpartnership.com.au Oceania | Asia | Europe | North America