14 June 2007 VELO Eddy Jans 1
Recent VELO-installation++ activities
June 14, 2007
• Potmeter calibration• Bake-out• Cabling & Commissioning
14 June 2007 VELO Eddy Jans 2
Potmeter calibration
Fred Schimmel has written PVSS-code to do the job:• buitengebied: simultaneously XA: 28 2 mm
XC: -28 -2 mmstep , default =2 mm
• binnengebied: XC=-10; XA= 10 -4.5 mm, step , default =1 mmXA=10; XC= -10 4.5 mm, step , default =1 mm
• y-calibration XA=2, XC=-2, Y= -4.5 4.5 -4.5 mmstep , default =0.5 mm
(See next talk by HdV)Limits, steps, etc. OK ??
14 June 2007 VELO Eddy Jans 3
Bakeout of VELO-tank & LHCb-beampipeEverything (=beam pipe, neon injection line, flanges of VELO-tank, 2 ion getter pumps) equipped with heaters, isolation and thermocouples by AT-VAC.
14 June 2007 VELO Eddy Jans 4
14 June 2007 VELO Eddy Jans 5
14 June 2007 VELO Eddy Jans 6
Neon injection system on balcony
Bake out campaign: from 14h00 on Wednesday June 6 till 17h00 on Tuesday June 12
14 June 2007 VELO Eddy Jans 7
Temperature profile
VELO @ 120oC
VELO @ 150oC
Test bakeoutRF-boxes
BakeoutRF-boxes
VELO @ 100oC
VELOcooldown
14 June 2007 VELO Eddy Jans 8
Pressure profile
VELO to 120oC
VELO to 150oCBakeoutRF-boxes
unvoluntary air injection
(see plots HdV)
startup of ion getter pumps
VELO to 100oC
beam
det.
VELO cooldown
10-10
10-8
10-6
10-4
14 June 2007 VELO Eddy Jans 9
System is presently being vented with ultra-pure Neon.
Bypass valve may NOT be opened, i.e. NO movements allowed.
System will be kept “locked”, i.e. no neon supply and no balancing of pressures in beam and detector volumes.
End pressures:beam@VELO: 5x10-10 , beam@MUON: 2x10-11 VELO-detector: 3x10-8 mbar
14 June 2007 VELO Eddy Jans 10
Cabling & Commissioning• All HAPTAS temperature cables are connectorized by PdG + JS.• Connectorizing of analog cables by INEO in D3 is ongoing, till end July.• HV is almost finished• LV has not started yet
• First crate with TELL1’s installed in D3 and configured.• First crate with control boards installed on P1.• Control + readout of one VELO-slice this week.• Then readout of a dummy module with full DAQ-chain.
14 June 2007 VELO Eddy Jans 11
What’s next, apart from everything else ??
• finish one detector half completely• perform turn-over test with 2 cranes• organize transport from Meyrin IP8 + through shaft• prepare area (extra platform, store cables, clean, etc.) • open VELO-tank• install fitting frame• measure• remove fitting frame• install detector half• flush with dry air (how ?) and measure IV-curves or• evacuate, measure IV-curves, vent with Neon
• finish PLC-coding motion system• ELOG has moved to the following CERN Web-site http://lbweb01.cern.ch:8080