11 - HMC 5Dec Norwegian Society of Lifting Technology[1]

Embed Size (px)

Citation preview

  • 7/30/2019 11 - HMC 5Dec Norwegian Society of Lifting Technology[1]

    1/50

    Norwegian Society of Lifting Technology

    How can we assist in you r sub sea development

    Presented by: Danny Mus

    Date: 5 December 2012

  • 7/30/2019 11 - HMC 5Dec Norwegian Society of Lifting Technology[1]

    2/50

    Introduction, How can we assist in your subsea development

    Introduction

    Presentation contents How can we assist in your subsea development:

    - Selection of subsea project from the past

    - Typical project phases- Engineering phase

    - Transport from yard to offshore site

    - Field preparations: Survey and Positioning

    - Lower structures through splashzone and set down on seabed

    - Offshore Decision making

    2

  • 7/30/2019 11 - HMC 5Dec Norwegian Society of Lifting Technology[1]

    3/50

    Subsea Lifting Experience (selection)

    3

    2005 | Norsk Hydro Ormen Lange

    (Heaviest Subsea Template @ 850 msw)

    2008 | DSME Tombua Landana

    2009 | Hydro O&G Troll & Vega

    2010 | BP Block 31

    (Worlds Deepest Foundation Piles @ 2,030 msw)

    2012 | Total Laggan & Tormore

  • 7/30/2019 11 - HMC 5Dec Norwegian Society of Lifting Technology[1]

    4/50

    Ormen LangeNorway

    4

    Record Lift

    Heaviest Subsea Template @ 850 waterdepth

  • 7/30/2019 11 - HMC 5Dec Norwegian Society of Lifting Technology[1]

    5/50

    Client

    DSME

    Scope

    Tower Base Section

    Tower Base Template

    Leveling Pile Template

    Max. Weight

    29,500 mT

    Water Depth

    370 m

    Period

    Q1 2008

    Location

    Block 14, Cabinda, Angola

    Tombua LandanaAngola

    5

  • 7/30/2019 11 - HMC 5Dec Norwegian Society of Lifting Technology[1]

    6/50

    LEVELLING PILES TEMPLATE

    (LPT, 520mT)

    -370 m.

    waterline

    GROUTED

    CONNECTION

    TOWER BOTTOM SECTION,

    TBS, 29,500mT)

    GROUTED

    CONNECTION

    TOWER BASE TEMPLATE

    (TBT, 3010mT)

    4 No. LEVELLING PILES (315mT each)12 No. FOUNDATION PILES (850mT each)

    TOPSIDES ( Total

    weight: 30,000T)

    TOWER TOP SECTION,

    TTS, 7000mT)

    Tombua LandanaAngola

  • 7/30/2019 11 - HMC 5Dec Norwegian Society of Lifting Technology[1]

    7/50

    Troll & VegaNorway

    7

  • 7/30/2019 11 - HMC 5Dec Norwegian Society of Lifting Technology[1]

    8/50

    Laggan TormoreUnited Kingdom

  • 7/30/2019 11 - HMC 5Dec Norwegian Society of Lifting Technology[1]

    9/50

    Block 31Angola

    9

  • 7/30/2019 11 - HMC 5Dec Norwegian Society of Lifting Technology[1]

    10/50

    BP Block 31 PSVMExtend of Subsea Scope: Free Standing Riser installation

    10

    9 x Single Line Hybrid Riser (SLHR)

  • 7/30/2019 11 - HMC 5Dec Norwegian Society of Lifting Technology[1]

    11/50

    Riser Base FoundationBallast Module & Driven Pile

    11

    12m

    12m

    ~330mT @ 2,030m

  • 7/30/2019 11 - HMC 5Dec Norwegian Society of Lifting Technology[1]

    12/50

    12

    Lower Riser Assembly

    Weight = 23-36mT

    Length = 41m

  • 7/30/2019 11 - HMC 5Dec Norwegian Society of Lifting Technology[1]

    13/50

    13

    Upper Riser Assembly

    Weight = 60-75mT

    Length = 40m

  • 7/30/2019 11 - HMC 5Dec Norwegian Society of Lifting Technology[1]

    14/50

    14

    Buoyancy Tank

    Weight = 180-240mT

    Length = 35-47m

    Weight = 180-240 mT

    Length = 35-47 m

  • 7/30/2019 11 - HMC 5Dec Norwegian Society of Lifting Technology[1]

    15/50

    15

    Buoyancy Tank Stabbing into Upper Riser Assy

  • 7/30/2019 11 - HMC 5Dec Norwegian Society of Lifting Technology[1]

    16/50

    16

    Install riser string into Riser base Foundation

    Steel wire rigging

    Riser string weight 500-600 mTRiser length ~1900 m

    Polyprop stretcher in rigging

  • 7/30/2019 11 - HMC 5Dec Norwegian Society of Lifting Technology[1]

    17/50

    Rotolatch functionality (1)

    17Ready to insert rotolatch(lowering)

    rotate rotolatch(lowering)

    lock rotolatch(lifting)

    A Rotolatch is a locking

    / unlocking device

    Load transfer from

    steel rigging to

    polyprop stretcher

    Installation vessel heave is +/- 1m

    Riser pre-tension by stretcher.

    Stretcher is the absorber to

    compensate heave of vessel.

  • 7/30/2019 11 - HMC 5Dec Norwegian Society of Lifting Technology[1]

    18/50

    Rotolatch functionality (2)

    18

    3 pairs of cams

    Cam1

    Cam2

    Toolreleased

    Toolengaged

    2nd horizontal

    left rotation

    1st horizontal

    left rotation

  • 7/30/2019 11 - HMC 5Dec Norwegian Society of Lifting Technology[1]

    19/50

    Lower complete riser string to locking position in base foundation

    19

    Freestanding Riser Systems: Stabbing Riser

    Transferring weight from polyprop stretcher to buoyancy tank

    Riser string weight is transferred from steel wire arrangement to

    polyprop stretcher arrangement (damping motions)

    Heave of vessel is absorbed by polyprop stretcher

    Free stabbing Rotolatch connector at seabed

    Inserting and locking of Rotolatch in foundation

  • 7/30/2019 11 - HMC 5Dec Norwegian Society of Lifting Technology[1]

    20/50

    Free Stabbing of Riser

    20

    Position and lowerLower and Rotate

    Lift and engage

    Final position

  • 7/30/2019 11 - HMC 5Dec Norwegian Society of Lifting Technology[1]

    21/50

    Typical Project Phases

    21

  • 7/30/2019 11 - HMC 5Dec Norwegian Society of Lifting Technology[1]

    22/50

    Project Phases and Issues encountered

    22

    Engineering preparation stage

    Transport from fabrication yard to offshore location

    Field preparations for survey and positioning

    Lift structure from barge or SSCV deck

    Lower structure through the waterline (splashzone)

    Lower structure through the watercolumn

    Position and land the structure on the mudline/seabed/template or

    foundation already installed

    Level structure if necessary

    Completion work

  • 7/30/2019 11 - HMC 5Dec Norwegian Society of Lifting Technology[1]

    23/50

    Engineering Preparation Phase

    23

    Typical Subsea Transport and Installation Project, engineering topics:

    Barge transport engineering (motion response analysis, grillage and seafastening

    design, bollard pull requirement)

    Transfer transport unit to SSCV option

    Single vs dual crane installation

    Anti twist system, anti rotation system

    Rigging release systems

    Installation engineering (rigging design, dynamic analysis, suction foundation analysis

    etc)

    ROV detailed scope of work

    Survey and positioning detailed scope of work

    Handling equipment specification

    Installation manual

  • 7/30/2019 11 - HMC 5Dec Norwegian Society of Lifting Technology[1]

    24/50

    Transport from yard to Offshore Site

    24

    Typical Subsea Transport and Installation Project:

    Transport from fabrication yard to offshore location

    On barge

    On SSCV deck

    Combination of both (inshore transfer)

    Laggan Tormore structures on 400 barge

    Vega structures on barge

  • 7/30/2019 11 - HMC 5Dec Norwegian Society of Lifting Technology[1]

    25/50

    Transport from yard to Offshore Site

    25

    Laggan Tormore structures on Thialf

    Deck

    Tombua Landana TBT on barge H627

  • 7/30/2019 11 - HMC 5Dec Norwegian Society of Lifting Technology[1]

    26/50

    Transport from yard to Offshore Site

    26

    Barge vs Thialf deck transport:

    Size and weight structure

    Space on deck SSCV

    Liftable from deck

    Quay location

    Access barge vs access SSCV

    Workability (lift off from barge vs lift off from Thialf deck)

    Offshore lift from barge weather sensitive

    Offshore lift from SSCV deck less weather sensitive

    Transfer lift to SSCV deck in sheltered waters

  • 7/30/2019 11 - HMC 5Dec Norwegian Society of Lifting Technology[1]

    27/50

    Lift Structure from Barge or SSCV deck

    27

    Lifting the structures from SSCV deck or barge

    Pros lift from SSCV deck Pros lift from barge deck

    Lift off no critical weather operation Heavier and larger structures can be installed

    Preparations to structures direct from SSCV

    deck

    No height restriction of structure

    No barge mooring operations offshore

    No people transfer to offshore barge

    Rigging attachment less weather restrictive

  • 7/30/2019 11 - HMC 5Dec Norwegian Society of Lifting Technology[1]

    28/50

    Field Preparations, Survey and Positioning

    28

    Installation tolerances drive the field preparations. In order to position the

    structure within tolerances (position and heading) a few methods/options can be

    distinguished:

    1. Positioning via DP and subsea transponder array

    2. Positioning via gravity (pre-installed) anchors

    3. Subsea infrastructure already present, dock structure over other structure

    Each of above mentioned methods have their own accuracy. As back up method

    the installation of subsea marker buoys are often used.

  • 7/30/2019 11 - HMC 5Dec Norwegian Society of Lifting Technology[1]

    29/50

    Positioning by Transponders

    29

    1. Positioning via DP and subsea transponder array

    Transponder array to be pre installed and surveyed

    Transponders on subsea structure for communication with array

    ROV interface

    Example: Laggan Tormore

    Installation Tolerances for positioning SWPS:

    Final as built data, position from target:

    Structure Position Heading

    SWPS +/- 0.50m +/- 2.00

    Structure Position Heading

    SWPS 0.14m 0.30

  • 7/30/2019 11 - HMC 5Dec Norwegian Society of Lifting Technology[1]

    30/50

    30

    Laggan Tormore Example

    Transponder array

    Template Target

    Typical Survey plot:

  • 7/30/2019 11 - HMC 5Dec Norwegian Society of Lifting Technology[1]

    31/50

    Positioning by Gravity Anchor

    31

    2. Positioning via gravity (pre-installed) anchors

    Gravity anchors to be pre installed and surveyed

    Sling length determined and custom made

    Subsea attachment by ROV

    Example: Ormen Lange

  • 7/30/2019 11 - HMC 5Dec Norwegian Society of Lifting Technology[1]

    32/50

    Positioning on Structure

    33

    3. Subsea Structure already present; dock structure over other structure

    Docking guides and receptors required for positioning and guiding

    Docking loads during installation (steel on steel, docking study)

    Subsea connection between foundation and structure

    Example: Tombua Landana Compliant Tower, TBT Installation

  • 7/30/2019 11 - HMC 5Dec Norwegian Society of Lifting Technology[1]

    33/50

    Positioning on Structure (2)

    34

    TBT; L*B*H ~ 34*34*22,

    W ~ 3010mT

    Foundation Piles; L ~ 190m, diam 108

    W ~ 850mT each

    Barge H-627; L*B*H ~ 177*49*11m

  • 7/30/2019 11 - HMC 5Dec Norwegian Society of Lifting Technology[1]

    34/50

    Installation sequence, TBT landen on LPT

    (Levelling Pile Template)

    Primary, secondary and tertiary docking pin

    engaged

    36

    Tombua Landana Example

    Mudline -370 m.

  • 7/30/2019 11 - HMC 5Dec Norwegian Society of Lifting Technology[1]

    35/50

    Lower Structures Through the Waterline

    (Splashzone)

    37

    Lifting structures Through the Splash Zone

    Dynamic Loads! (DNV-RP-H103) vs design forces

    Multiple installation stadia

    Structure mass and drag area vs water particle acceleration and velocity,

    Hoist wire dynamics, hatch loads, equipment loads etc

    Wave force on structure, transferred to rigging and hoists

    2 Stages (multiple stages can be defined): Roof just above water and roof just

    below waterline:

  • 7/30/2019 11 - HMC 5Dec Norwegian Society of Lifting Technology[1]

    36/50

    Orbital wave motion

    Source picture: http://fcit.usf.edu/florida/teacher/science/mod2/beach.profiles.html

    38

    Lower Structures Through the Waterline

    (Splashzone)

  • 7/30/2019 11 - HMC 5Dec Norwegian Society of Lifting Technology[1]

    37/50

    Wave particle motion for deep water described as circles, decreasing with waterdepth:

    39

    Wave orbital motion

    Wave period

    Waterdepth

    Short waves highest effect on slamming

    loads but depth effect is large

    Lower Structures Through the Waterline

    (Splashzone)

  • 7/30/2019 11 - HMC 5Dec Norwegian Society of Lifting Technology[1]

    38/50

    40

    Wave particle motion for deep water described as circles, decreasing with water depth:

    Lower Structures Through the Waterline

    (Splashzone)

  • 7/30/2019 11 - HMC 5Dec Norwegian Society of Lifting Technology[1]

    39/50

    Influence crane tip motions (velocity and acceleration) is very minimal wrt water

    particle velocity and acceleration. For a wave period of 6 s, the heave velocity

    and acceleration is ~ 2% of the water particle velocity and acceleration!

    In other words, the installation vessel hardly moves and slamming loads are

    only wave induced, not vessel (motion) induced

    41

    Lower Structures Through the Waterline

    (Splashzone)

  • 7/30/2019 11 - HMC 5Dec Norwegian Society of Lifting Technology[1]

    40/50

    Resulting maximum wave

    height based on maximum

    allowable dynamics (rigging

    design driven, template

    design more critical):

    42

    Lower Structures Through the Waterline

    (Splashzone)

  • 7/30/2019 11 - HMC 5Dec Norwegian Society of Lifting Technology[1]

    41/50

    Result is completely

    opposite of normal

    installation limits.

    Normal limits driven by

    vessel induced motions

    Characterized by:

    Hs

    43Tp

    Lower Structures Through the Waterline

    (Splashzone)

  • 7/30/2019 11 - HMC 5Dec Norwegian Society of Lifting Technology[1]

    42/50

    Effect: short crested waves defined the installation limit

    for wave periods around 6 seconds

    Low(er) workability!

    SSCV is a very large vessel, what is the influence of

    the SSCV on the local wave field?

    SSCV Shielding study

    Shielding effect of SSCV: SSCV, installing a template

    on the lee side of the vessel, sheltered from (short

    crested) waves.

    44

    Wave

    propagation

    SSCV

    Template

    Lower Structures Through the Waterline

    (Splashzone)

  • 7/30/2019 11 - HMC 5Dec Norwegian Society of Lifting Technology[1]

    43/50

    Wave Reflection effects

    SSCV Radiation effects

    Wave Diffraction effects +

    Installation Vessel Shielding Study

    Input characteristics

    JOHNSWAP Wave Spectrum

    6s < Tp < 20s

    0 degr < wave heading < 355 degr

    Results

    Tp = 6s

    Wave heading 225 degr (bow quartering)

    50% reduction on wave height

    45

    Lower Structures Through the Waterline

    (Splashzone)

    Installation Vessel

    Wave

    propagation

  • 7/30/2019 11 - HMC 5Dec Norwegian Society of Lifting Technology[1]

    44/50

    Set-down structures on seabed

    Dynamic Loads vs design forces

    Maximum set down velocity on seabed (~ 0.5m/s)

    Hoist wire dynamics (max DAF)

    Vessel induced motions characterize dynamics,

    transferred to rigging and hoists

    Mass Spring System, natural behavior defined by:

    * mass and added mass template

    * waterdepth / reeving length

    * Environmental Conditions / crane tip motions(wave induced vessel motions)

    * hoist wire stiffness (spring term)

    * template drag (damping term)

    46

    Lower Structures

    (Set-down on seabed)

    Mudline

    Crane tip

    Motions

    Hoist wires

    Vessel

    Motions

    Template

    Motions

    Waves

  • 7/30/2019 11 - HMC 5Dec Norwegian Society of Lifting Technology[1]

    45/50

    Create model (frequency domain) Thialf, hoist wires, template:

    Per wave heading, obtain template heave velocity RAO and

    Hoist wire dynamic force RAO.

    47

    Lower Structures

    (Set-down on seabed)

  • 7/30/2019 11 - HMC 5Dec Norwegian Society of Lifting Technology[1]

    46/50

    Create model (frequency domain) Thialf, hoist wires, template:

    Per wave heading, obtain template heave velocity RAO and

    Hoist wire dynamic force RAO.

    For maximum allowable template velocity 0.5m/s and hoist wire dynamics,

    define allowable wave height per peak period and wave heading:

    48

    Lower Structures

    (Set-down on seabed)

    Hsallowable

    Hsallowable

    V < 0.5m/s DAF < allowable

  • 7/30/2019 11 - HMC 5Dec Norwegian Society of Lifting Technology[1]

    47/50

    At start of project, wave rider buoy is deployed and directional full spectral

    wave and weather predictions obtained.

    Decision making tool: compare measurements with predictions, with

    RAOs decide on installation window where DAF and set down velocity

    will be within limits.

    49

    Lower Structures

    (Offshore Decision making)

  • 7/30/2019 11 - HMC 5Dec Norwegian Society of Lifting Technology[1]

    48/50

    50

    Lower Structures

    (Offshore Decision making)

    Check predicted vs measured

    waves (Hs)

    Check near bottom vertical heave

    velocity template within limits

    Check DAF within limits

    Date, time

    Limiting criterion dynamic force

    Limiting criterion heave velocity

    Hs

    Vheave

    Fdyn

  • 7/30/2019 11 - HMC 5Dec Norwegian Society of Lifting Technology[1]

    49/50

    51

    Position template on seabed

    When a suitable window is there:

    Attach rigging

    Cut seafastening

    Lift from deck, lower through the

    water column and set down on

    seabed

    Release rigging

    Perform hatch operations

    Apply suction (if needed)

    Completions

  • 7/30/2019 11 - HMC 5Dec Norwegian Society of Lifting Technology[1]

    50/50

    Questions?

    Email: [email protected]

    mailto:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]