Upload
others
View
1
Download
0
Embed Size (px)
Citation preview
04 MW HYDEL POWER PLANT
THAK NULLAH, CHILAS
INITIAL ENVIRONMENTAL EXAMINATION
REVISED
June, 2012
IEE Report for 04MW Thak Nullah Hydropower Plant
- 1 -
EXECUTIVE SUMMARY
Introduction:
Initial Environmental Examination Report of 4 MW Thak Nullah Hydropower Project presents the
environmental assessment of the construction and the operation phases of the project. It is to ensure
that the potential adverse environmental impacts are appropriately addressed in line with ADB's SPS
2009 as well as meeting the requirements of Pakistan Environmental Protection Act 1997. The Project
is covered by Schedule B of Energy Sector as per “Policy and Procedures for Filing, Review and
Approval of Environmental Assessment” issued by Pak - EPA in August 2000 and Category “B” Under
ADB's SPS 2009 which requires preparation of an IEE Report for submission to EPA Gilgit Baltistan
for their approval.
Project Description:
The project site is located about 15 Km east of Chilas town. The project area is accessible from Chilas
Babusar pass highway running along Thak nullah off-taking from Chilas-Gilgit road (Karakoram
Highway). It is located on Thak Nullah which is a left bank tributary of Indus river having a length of 23
km. Its confluence with the Indus river is at about 5km east of Chilas. The weir intake is proposed on
right side of Thak Nullah in Khun village where as the powerhouse is proposed about 4.5 Km
downstream of the weir intake
Environmental Baseline:
The project area falls in the Diamer district which lies in the southwest of Gilgit-Baltistan. The field
surveys conducted in February 2012 to collect primary and secondary data in respect of physical,
biological and socio-economic environment and to verify the inventory of affected assets. Meetings
were also held with officials of departments of revenue, agriculture, health, education, meteorology.
Public consultations were held with locals including project affectees. The population of the 7 villages
within the influence of the project is at present 3,510. All households have access to electricity with
irregular supply. The water supply and sanitation conditions need improvement.
Environmental Impacts and Mitigation:
The project impacts have been discussed with reference to design, construction and operation related
impacts and positive impacts. The design related impacts relate to loss of land and assets due to
construction of project structures. Construction related impacts, in particular, relate to loss of land and
built-up structures due to laying out of penstock pipe and approach road along the penstock pipe. The
construction related impacts will be manageable if the mitigation measures are implemented
thoroughly.
Out of total 7.469 acres of land acquisition, the project will also affect 1.523 acres cultivated land
comprising wheat and vegetables crops. A total of 32 fruit and shade/wood trees, and various
structures including 4 houses made up of mud stone with thatched roofing measuring 299.749m2,
IEE Report for 04MW Thak Nullah Hydropower Plant
- 2 -
boundary walls 2,820.201m3 (including 74.513m
3 private boundary walls, 2560m3 NHA road
boundary walls and 185.688m3 community based boundary walls), cattle shed measuring 27.890m
2
and a garage measuring 28.014m2 will also be affected due to construction of penstock pipe.
In addition, community based structures such as Madrasa measuring 71.596m2, civil supply
Chowkidar room measuring 20.821m2, and two number of water channels of 275m length will partially
be affected due to construction of penstock pipe.
Based on these land and non-land impacts, the project will impact a total of 44 families with a total of
470 family members. All the affectees will be compensated according to the rate as fixed by the
Revenue Department.
Institutional Requirements:
Environmental impacts associated with construction and operation of the project need to be mitigated
for which institutional arrangements have been proposed by establishing a project management unit
(PMU) headed by a full time project director to ensure compliance with ADB policies and procedures.
For addressing complaints and grievances of project affectees, a grievance redress committee (GRC)
has been proposed.
Environmental Management Plan:
The environmental management plan (EMP) has been drawn up to address environmental concerns,
recommend mitigation measures and assign responsibility to implement and monitor them. The
environmental management plan should be used as a basis for environmental compliance programme
and be included in the contract document.
IEE Report for 04MW Thak Nullah Hydropower Plant
I. INTRODUCTION
1. For the updation of IEE report already prepared in the year 2008 for 04 MW Hydel Power
Plant Project, arrangements were made to provide consultancy services by Pakistan Engineering
Services (Pvt.) Ltd. in the year 2012 by Water and Power Department Gilgit Baltistan. In order to
consider project financing, an Asian Development Bank Mission visited the project area during
August 2011. Before detailed design is undertaken by EPC Contractor Environmental Assessment
(IEE Report) and Land Acquisition and Resettlement Plan (LARP) Report is to be completed. It is
mandatory that no objection certificate of the IEE Report is obtained from EPA GB before proceeding
with the construction of the project.
2. This Initial Environmental Examination (IEE) presents the environmental assessments
regarding the design, construction and operation of the proposed hydel power plant. This IEE has
been carried out to ensure that the potential adverse environmental impacts are appropriately
addressed in line with ADB's Safeguard Policy Statement (SPS) 2009. This IEE has also been
updated to meet the requirements of the GoP for environmental assessment.
3. This IEE will be submitted to ADB by the Government of Gilgit Baltistan on behalf of Gilgit
Baltistan Water and Power Department (GB-WPD). This report is to be submitted for review and
approval by the Gilgit Baltistan Environmental Protection Agency (GB-EPA) as required by the
Pakistan Environmental Protection Act, 1997.
A. ENVIRONMENTAL REGULATORY COMPLIANCE
4. Section 12(1) of the Pakistan Environmental Protection Act 1997 requires that “No
proponent of a project1 shall commence construction or operation unless he has filed with the
Federal Agency2 an initial environmental examination or, where the project is likely to cause an
adverse environmental effect, an environmental impact assessment, and has obtained from the
Federal Agency approval in respect thereof."
5. The National Environmental Quality Standards is (NEQS) applicable to any process
emission or effluent from the subproject. However, no such emission or effluent is envisaged from
this project.
1 Defined as "any activity, plan, scheme, proposal or undertaking involving any change in the environment and includes-(a)
construction or use of buildings or other works; (b) construction or use of roads or other transport systems; (c) construction or operation of factories or other installations; (d) mineral prospecting, mining, quarrying, stone-crushing, drilling and the like; (e) change of land use or water use; and (f) alteration, expansion, repair, decommissioning or abandonment of existing buildings or other work roads or other transport systems, factories or other installations. 2 The Ministry of Environment, Government of Pakistan has delegated the power of the Federal Agency for EIA and IEE reviews for projects falling in different provinces to the environmental protection agencies of the respective provinces. Federal Agency in this case is the NA Environmental Protection Agency.
IEE Report for 04MW Thak Nullah Hydropower Plant
6. Pak - EPA in August 2000 issued “Policy and Procedures for Filing, Review and Approval
of Environmental Assessment”, which includes Schedules A, B and C defining development projects
in terms of requirements for EIA and IEE. Schedule A defines projects which require an EIA. It deals
with list of major projects which have the potential to affect a large number of people. The impact of
such projects may be irreversible and could lead to significant changes in land use and in the social,
physical and biological environment. The Section of Schedule A relating to Energy Sector states that
hydropower generation above 50 MW will require environmental impact assessment report.
Schedule B defines projects which require an IEE. It deals with projects where the range of
environmental issues is comparatively narrow and issues can be understood and managed through
less extensive analysis. The Section of Schedule B states that hydropower electric generation below
50 MW will require IEE Report. Schedule C combines everything not in Schedule A and B. Thus
Thak Nullah Hydel Power Plant Project is covered by Schedule B which requires preparation of an
IEE Report for submission to EPA GB for their approval.
B. ENVIRONMENTAL CATEGORY OF THAK NULLAH HPP
7. ADB uses a classification system to reflect the significance of a project‟s potential
environmental impacts. A project‟s category is determined by the category of its most
environmentally sensitive component including direct, indirect, cumulative, and induced impacts in
the project‟s area of influence. Each proposed project is scrutinised as to its type, location, scale, and
sensitivity and the magnitude of its potential environmental impacts. Projects are assigned one of the
four categories (A, B, C, or FI) for environmental assessment. The category is assigned based on the
project's potential for environmental impact as follows:
Category A: A proposed project is classified as category A if it is likely to have significant adverse
environmental impacts that are reversible, diverse, or unprecedented. These impacts may affect an
area larger than the sites or facilities subject to physical works. An environmental impact assessment
is required.
Category B: A proposed project is classified as category B if its potential adverse environmental
impacts are less adverse than those of category of A projects. These impacts are site specific, few if
any of them are reversible, and in most cases mitigation measures can designed more readily than
for category A projects. An initial environmental examination is required.
Category C: A proposed Project is classified as category C if it is likely to have minimal or no
adverse environmental impacts. No environmental assessment is required although environmental
implications need to be reviewed.
Category FI: A proposed project is classified as category of FI if it involves investment of ADB funds
to or through a F1.
IEE Report for 04MW Thak Nullah Hydropower Plant
8. Under ADB's SPS 2009, the proposed project is a Category “B” project. Therefore an IEE
has been prepared „‟with its narrower scope, has been conducted for the project with its limited
impacts that are few in number, generally site-specific, largely reversible, and readily addressed
through mitigation measures.‟‟
C. OBJECTIVES AND SCOPE OF IEE
9. The objectives of the IEE are to:
i) Assess the existing environmental conditions to the areas where the project is
located including the identification and information of environmentally sensitive
areas;
ii) Assess the proposed activities, identify and evaluate the potential impacts and
determine their significance;
iii) Proposed appropriate mitigation measures that can be incorporated into the
proposed activities to minimize any adverse impacts, ensure that residual
impacts are acceptable and to propose appropriate monitoring requirements.
10. This lEE is based on field reconnaissance surveys, secondary sources of information and
public consultation undertaken specifically for this project.
D. REPORT STRUCTURE
11. Following (i) introduction, this report contains eight more sections including (ii) project
description; (iii) environmental baseline; (iv) environmental impacts and mitigation; (v) stakeholders
consultation; (vi) institutional requirements and environmental management plan; (vii) environmental
related costs; (viii) findings and recommendations; and (ix) conclusions.
12. Assessment of environmental flow is given in Appendix – I, list of participants of local
consultations and line departments in Appendix II, environmental management plan in Appendix - III
and photographic documentation of the project area is provided at the end of the report.
IEE Report for 04MW Thak Nullah Hydropower Plant
II. PROJECT DESCRIPTION
A. BACKGROUND AND JUSTIFICATION
13. According to data provided by GBWPD, there are 3,600 electricity consumers in Chilas
and surrounding areas. Of these 3,200 (89%) are domestic, 300 (8%) are commercial, whereas 100
(3%) are industrial. The total power demand is 2.4 MW however; the total installed capacity of hydel
and thermal power plants is 1.7 MW. Thus there is a shortfall of 0.7 MW. Unless new sources of
power are added, the situation is likely to aggravate with time as the demand is projected to increase
to 4.2 MW by 2015. The proposed 04 MW plant will be an important project to bridging the widening
gap between demand and supply.
B. LOCATION
14. The proposed Hydel Power Project is located on Thak Nullah which is a left bank tributary
of Indus river having a length of 23 km. Its confluence with the Indus river is at about 5km east of
Chilas. The project site is located about 15 Km east of Chilas town. The project area is accessible
from Chilas Babusar pass highway running along Thak nullah off-taking from Chilas-Gilgit road
(Karakoram Highway).The weir intake is proposed on right side of Thak Nullah in Khun village where
as the powerhouse is proposed about 4.5 Km downstream of the weir intake. The location of the
project on map of Pakistan is sown in Figure 1 where as its location on regional map of Chilas is
given in Figure 2.
Figure 1: Project Location in the Map of Pakistan
Thak Nullah HPP
IEE Report for 04MW Thak Nullah Hydropower Plant
Figure 2: Location of the Project on Regional Map of Chilas
D. PROJECT COMPONENTS
15. The layout of the project showing various project components is given in Figure 3.
Figure 3: Layout Plan of Thak Nullah HPP
16. The layout of the project comprises of a diversion weir, intake channel, settling tank, by
pass channel, fore bay, powerhouse, tail race channel, spill channel, penstock pipe and surge tank.
Salient features of the layout are listed below.
IEE Report for 04MW Thak Nullah Hydropower Plant
Table 1: Project Components
Sr. # Item Units Quantity
i. Design Discharge m3/s 1
ii. Gross Head meter 325
iii. Net Head meter 300
iv. Installed Capacity MW 4
v. Mean Annual Energy GWh 27.33
vi. Plant Factor % 78
vii. Penstock Diameter meters 1
viii. Penstock Length meters 4,620
ix Turbines Nos. 2
x Type of Turbines - 750ppm,twin jet Pelton wheel
xi Capacity of Each Turbine MW 2
xii Forebay capacity m3 3,900
xiii Powerhouse Type Surface -
xiv Powerhouse Size m 15m x 6m x7m
xv Grid station m 15m x15m
xvi Generator output MW 2
xvii Transformer capacity MVA 5
xviii. Length of 11kV Transmission Line Km 10
17. Diversion Weir: The typical weir made of gabions is proposed for diversion of water at the
take of point. The crest of the weir is proposed to be 4m above the nullah bed to provide sufficient
head. Two guide walls have been provided to divert water into the intake channel.
18. Intake and By Pass channels: A trapezoidal open channel is proposed for conveyance of
water from the weir to the intake structures.
19. Settling Tank: a settling tank has been proposed for the removal of sand and silt
particles. At the entrance of the settling tank a trash rack is proposed to be provided for the removal
of floating objects and bigger particles which may find their way through the intake channel. The tank
is also provided with a sluice valve fro periodic flushing.
20. Forebay: A circular tank of 35m dia is proposed for the storage of water for the lean
period. The tank can hold 3850m3 of water to meet the requirements in lean period.
21. Surge Tank: A surge tank of the same size as for the forebay is proposed on the hill slope
near the power house at the height of 315m from the entry point of the penstock at the power house.
22. Penstock: A penstock pipe of about 4.5km long having 1m dia is proposed to bury
underground.
IEE Report for 04MW Thak Nullah Hydropower Plant
23. Grid Station and Transmission Line: The 33kv grid station has been proposed in Jaldas
in Chilas town thereby developing a stable and flexible distribution network in the area.
24. The 33 kV power transmission line is proposed to transfer the electrical power of Thak
Nullah hydel power plant over a distance of 10 km along the existing transmission line to the
proposed 33kV grid station at Jaldas in Chilas Town.
25. Access Road to Weir Site: The project site is accessible through Babusar Pass Highway
off taking from Karakoram Highway near Chilas town. The powerhouse and the weir site are located
on this highway at 10km and 14km form Karakoram Highway respectively. No access road
construction or rehabilitation would require for project implementation.
26. Manpower: About 200 people will be employed for the implementation of the project
where as 20 persons will get permanent employment for its operation and maintenance.
27. Construction Schedule: The implementation period of the project is 4 years
starting from 2012.
28. Environmental Flow: The weir on Thak Nullah is designed to divert 1.0 m3/s of water for
the power generation of 4MW. Between October and April the average flow in Thak Nullah is
1.7m3/s. Thus in these months, more than half of the water will be diverted for power production and
there would be minimal flow in the stream between the weir site and the proposed powerhouse site,
a distance of about 4 km. The minimal flow i.e. 0.7m3/s is much higher than the 10% of average
minimum flow 0.17m3/s which is considered as environmental flow for bare survival of biota in the
vulnerable reach. During the months of February and March the average monthly flow reduces to
1.17m3/s. These months have been declared as lean months and the powerhouse will not be
operated at full capacity. Only one turbine will operate using 0.5m3/s of flow thus allowing the
remaining water as environmental releases.
IEE Report for 04MW Thak Nullah Hydropower Plant
III. ENVIRONMENTAL BASELINE
A. FIELD SURVEY
29. The field work for determining socio-economic setting and environmental baseline of the
project area was undertaken from 07-2-2012 to 11-02-2012. The survey team consisted of PES and
PMU professional staff including Project Manager, Senior Environmentalist, sociologist, ecologist,
and Engineers. The work consisted of project area socio-environmental survey through participatory
rural appraisal/focused group discussions with locals and owners of land, primary/ secondary data
collection, visits/ discussion with line department officials. The baseline data collected regarding
existing socio-economic and environment condition of the project area is discussed in the following
sections whereas the photographic documentation of the field survey is given in at the end of the
report.
B. PHYSICAL ENVIRONMENT
30. The project area falls in the Diamer district of the GB. Diamer District lies in the southwest
of the GB. The Karakoram Highway enters the GB in this district The Indus River runs in the east to
west direction through the middle of the district. The elevation near the Indus is less than 1,500 m. At
north and south of the Indus valley the elevation increases to more than 4,000 m. Nanga Parbat, the
9th highest peak in the world at 8,126 m, lies in Diamer district at its border with Astore district.
31. The climate of the Diamer District has considerable variation with elevation. The areas
below 3,000 m are warm and have very little precipitation. The summer season in low lying valleys is
hot but at high altitude is very pleasant. Similarly, winter season at high altitude is extremely cold as
compared to the valleys. During winter the northern winds blow constantly bringing the temperature
down considerably.
32. At Chilas, the mean maximum temperature is 39.6°C in July, the hottest month and 12.3°C
in January, the coldest month. The mean minimum temperatures are 27.3°C in July and 0.9°C in
January, respectively. The annual precipitation is less than 200 mm. Half of the rain falls in three
months March to May.
33. Climatic data in the form of mean of daily maximum mean of daily minimum, Maximum
recorded, minimum recorded, and average monthly precipitation at Chilas is given in Table 2.
34. Rivers and Streams: The glaciers and the snow bound peaks bring out streams and
rivers in the beautiful valleys finally merge in the mighty Indus. Plenty of springs and streams flow
throughout the district providing clean water for drinking and irrigation. GB is drained by the mighty
Indus which rises in Tibet. Other two river Shingo on Shyok passing through Kargil area join the
Indus in GB.
IEE Report for 04MW Thak Nullah Hydropower Plant
Table 2: Climatic Data of Chilas
Month
Temperature °C Average
Monthly Rainfall
(mm)
Mean of
Daily
Maximum
Mean of
Daily
Minimum
Maximum
Recorded
Minimum
Recorded
January 12.3 0.9 19 -4.4 8.4
February 14.5 3.4 22.8 -2.8 12.7
March 20.1 8.4 31 0 30
April 26.1 13.8 37.2 3.9 31.9
May 31.1 18.4 42.2 7.2 27.7
June 37.6 24.3 46.4 13 7.6
July 33.6 27.3 47 15.6 11.6
August 38.6 26.7 48.1 15.6 12.4
September 35.1 22.5 43.6 11.1 3
October 28.4 14.6 37.8 6 12,8
November 20.9 7.1 29 -0.6 4
December 13.7 2.1 20.4 -3.1 11.1
35. Thak Nullah has a total catchment of about 190 km2 at the proposed weir site;
the annual rainfall in the catchment is estimated to be about 300 mm. The rainfall is almost evenly
distributed throughout the year. The contribution of the rain to the discharge of the Thak Nullah is
insignificant. The major contribution to the nullah is the melting snow at higher altitudes.
36. The mean annual flow in the stream at the site is 5.64 m3/s. The minimum flow of1.17 m
3/s
is recorded in February and March. With the onset of summer the flow in the stream increases and a
peak flow of 18.0 m3/s is recorded in July as indicated in Table 3. The gross head available for
generation is 325 meters and the net useful head after allowing for the frictional and intake structure
losses is 300 m.
Table 3: Record of Flow in Thak Nullah (1963-1993)
Sr. # Month Average Flow (m3/s)
1 January 1.28
2 February 1.18
3 March 1.17
4 April 2.08
5 May 6.45
6 June 10.0
7 July 18.0
8 August 14.2
9 September 7.22
10 October 2.64
11 November 1.91
12 December 1.49
Annual Average 5.64
IEE Report for 04MW Thak Nullah Hydropower Plant
37. Geology: The geology of the region is very diverse. Bed rock consists of a wide variety of
igneous and metamorphic rocks, which had undergone extensive deformation. Superficial materials
occur mainly as glacial deposit terraces along the river valleys, as alluvial fans at the confluence of
Indus and its tributaries and as recently deposited alluvial material in and along the nullahs and the
river-beds.The region has been affected by the collusion of Indian and Asiatic mass with a
sedimentary basin in between. Rugged mountains, deep U-shaped valleys, flat terraces and narrow
flood plains, characterize the area. The rocks exposed are mostly Norites. These rocks range from
Precambrain to Moicene in age
38. Siesmicity: Northern Areas is located in moderate to major damage seismic zone for
which the seismic factor is between g/10 to g/5. During detail design phase EPC contractor will carry
out investigation for PGA (g) and other geological parameters.
39. Soils: The alluvial soils are mainly clayey and silty shallow to moderately deep over
gravels. They are rich in organic matter and are fertile. There is almost no soil cover on the high
rocky mountains. The terraces are generally infested with gravels and boulders and interbeded and
intermixed with some fine material mainly sand and clay. Some moraine deposits and some sandy
patches are also seen.
C. AIR ENVIRONMENT
40. The air quality of the Project area is generally fresh and free of any pollutants. This is so
because there is no major source of air pollution like industrial activity, or vehicular traffic. This may
result in a rise in suspended particulate matter (SPM) during high winds or major traffic movement
which is of temporary nature.
41. During transportation of construction material and heavy equipment, dust levels are
expected to rise in the project area. The large particles of the dust will deposit in the adjoining areas
and smaller particles will remain suspended in the air causing air pollution in the surrounding areas.
Although the problem will be temporary and localised still special measures should be taken to
reduce this impact.
D. BIOLOGICAL ENVIRONMENT
42. Flora: Diamer has the best forest resources in the GB. The forests cover is about 217,000
hectares which constitutes more than 75% of the total forest in the NA. All of the forests are
classified as private and none has any legal protection. The forests in Diamer are mainly classified
as montane dry temperate coniferous forests. This forest type contains blue pine (Pinus waltichiana),
edible pine (Pinus gerardiana), cedar (Cedrus deodara) and juniper, in pure and mixed stands. There
are no protected forests in the project area. On lower elevation a variety of trees including shrubs
and medicinal plants are found which are listed below.
IEE Report for 04MW Thak Nullah Hydropower Plant
Sr. No. Botanical Name
Trees
1. Dalbergia sisso
2. Melia azdarach
3. Olea cuspidala
4. Populous spp.
5. Salix spp.
Shrubs
7. Ross muschata
8. Dodonea viscosa
Medicinal Plants
10. Rumex
11. Aconitum
12. Prunus
13. Carum
14. Curui
Fruit Trees
15. Chalghoza
17. Wallnut
18. Almond
19. Mulberry
20. Grapes
21. apricort
43. A high growth rate of human population has put increasing pressure on the regional
natural resource base. As a result, processes such as deforestation, firewood collection, overgrazing
and over-hunting have become major threats to the remaining biodiversity in GB. The continuing loss
of forest habitat, with its associated fauna and flora, will have serious implications for the GB's other
natural ecosystems.
44. Fauna: A number of globally significant species of mammals are found in the area
including some of the threatened species reported from the Diamer District are Woolly flying squirrel
(Hylopetes cinereus}, the flare-horned markhor or Astore markhor (Capra falconeri) on the hill tops,
the snow leopard (Uncia uncia} in the valley during winters, and Himalayan black bear (Ursus
thlbetanus). List of existing fauna in the project area is given below;
List of Existing Fauna in the Project Area
Sr.No. Species Name IUCN Red List/Govt. of Pakistan
1. Black bear Endangered Species IUCN Red List
2. Brown bear Endangered Species IUCN Red List
3. Chukor Common Government of Pakistan
4. Eagle Common Government of Pakistan
5. Falcon Endangered Species Government of Pakistan
6. Golden eagle Endangered Species Government of Pakistan
7. Himalayan snowcock Endangered Species Government of Pakistan
8. H.Ibex Endangered Species Government of Pakistan
9. Marco Polo sheep Endangered Species IUCN Red List
IEE Report for 04MW Thak Nullah Hydropower Plant
11. Markhor Endangered Species IUCN Red List
12. Musk Dear Endangered Species Government of Pakistan
13. Pigeon Common Government of Pakistan
14. Red fox Rare Government of Pakistan
15. Urial Rare Government of Pakistan
16.. Wolf Endangered Species IUCN Red List
45. About 230 species of birds, 20 species of freshwater fish, 54 mammals, 23 reptiles and 6
amphibians are reported from GB. In comparison, the corresponding figures for the whole of
Pakistan are 668, 198, 174, 177, and 22, respectively. The anthropogenic activities that have
contributed to this includes the settlements, land clearing, and more recently the Babusar pass
highway.
46. Protected Areas: No protected areas such as game reserve, game sanctuaries, national
park etc are found in the nearby vicinity of the project area.
47. Fishery: Earlier studies suggest that 17 species of native fish and three species of exotic
fish occur in the region. Four of the native species are believed to be endemic to GB, while several
others have restricted ranges and are confined to one or two localities. The three exotic species of
fish are the brown trout, North American rainbow trout and the Chinese carp. The brown trout that
was introduced to the GB in the early 20th
century is now well established and is found in most of the
rivers and lakes of Gilgit and Ghizar Districts. The North American rainbow trout and Chinese carp,
have been introduced for aquaculture, and are found only in water bodies in which they are stocked.
Their natural breeding is reportedly very restricted.
48. During present fish studies mainly specimen of snow carp was reported to be found in the
reach of Thak nullah as reported by Assistant Director Fishery, Chilas. The fishing catch effort –
capture ratio assessment methods shows that snow carp mainly inhabits powerhouse site to its
confluence at Indus.
49. No commercial or major recreational fishing has been reported from the Thak Nullah reach
of the project area.
E. SOCIAL AND CULTURAL ENVIRONMENT
50. Northern areas of Pakistan lying in the extreme north of the country are officially
designated as Gilgit Baltistan (GB) province. This province borders Khyber Pakhtunkhwa to the west,
Afghanistan to the North, China to the northeast, the state of Azad Jammu and Kashmir (AJK) and
Indian occupy state of Jammu and Kashmir to the south and southeast. Administratively, GB is
divided into 7 districts namely Astore, Diamer, Ghizer, Gilgit, Hunza-Nagar, Ghanche and Skardu.
Gilgit town is the political and administrative headquarter of GB. Other important urban centres
include Skardu and Chillas. The Thak Nullah project area lies in Diamer district near Chilas town.
IEE Report for 04MW Thak Nullah Hydropower Plant
51. Diamer District was created in 1972 and covers 6500 sq km of mostly arid mountainous
area. The district is administratively divided in two sub divisions, Chilas, Darel/Tangir, with three
tehsils (Chilas, Babusar and Darel). With its headquarter in Chilas Town, the district has 23 main and
secondary valleys where most of the population is concentrated. Diamer is a gateway to the Northern
Areas from South western side, as the Karakoram highway and via Babusar pass. Both pass through
the district and connect NAs to rest of the country. The area is home to 7th highest peak of the world
“Nanga Parbat” often narrated as Killer Mountain. Climatic conditions are at extreme in various
localities. Chilas subdivision has a sub tropical climate with hot summers and extremely severe
winters.
52. Diamer has historically been a strongly patriarchal society with strong tribal mores and a
heavy influence of orthodox clergy. The area is predominantly Sunni with history of fractious relations
with Shia and Ismaeli communities in neighbouring districts. All the ethics and life style of a typical
tribal society prevail. Class stratification runs quite deep with Shin and Yashkoon wielding the
political, social and economic clout.
53. Population: According to 1998 census, 274 villages in Diamer district have population of
1,35,000 human beings residing in 31,300 households. The project area falls in the Thak Nayat
village limits of the diamer sub-division. The village limits include all the villages in the Thak valley.
Total population of Thak valley in 1998 was 4,300 and the present population is estimated at the rate
of 2.74 % pa to be 6,110.
54. Project Area Population: A map showing of location of various villages with respect to
different project components is placed as Figure 4.
Figure 4: Villages / Communities Falling in the Vicinity of the Project Area
IEE Report for 04MW Thak Nullah Hydropower Plant
55. The population of these villages has been obtained during the field survey and shown in
Table 4. Their population according to field survey conducted in 2012 is 3,510 living in 309
households. The average no. of persons per household is 12.6.
Table 4: Socio-Economic Indicators of Villages Falling around Project Area
S. # Villages Population
2012
Total No. of
Households
Household
Size
1. Khun 350 25 14.0
2. Shingle 340 24 14.1
3. Kot 375 29 12.9
4. Dewaray 1400 135 10.4
5. Sar 180 14 12.8
6. Ghanch 170 12 14.2
7. Jal 700 70 10.0
Total 3510 309 12.6
56. The population is living mostly in a joint and extended family system with all family
members, even the married son, living under one roof but managing family affairs under the authority
of father, as head of the family.
57. All the ethics and life style of a typical tribal society prevail. The majority of population
belong to Suni school of thought. Balties form the over-whelming majority of ethnic groups with a
small component of Shins, Yashkuns, Kashmiries Pathans and Punjabies wielding the political,
social and economic clout. People are staunch followers of religion and the clergy plays an important
role and influence over the population.
58. Education Facilities: The education facilities in the project area are poor. The number of
educational institutions in the surveyed villages of the project area is almost nill. Only one middle
school and a Madrasa exist in the Khun village. To obtain higher secondary education the students
of the project area have to travel to Gilgit, Mansehra and Abbottabad.
59. The literacy rate of the area is very low as compared to rest of the region and country with
men‟s literacy rate at 9 % where as women‟s <1 %. In a population of 135,000 there is only one high
and five primary schools for girls in relation to hundreds of schools for boys. The 91% illiteracy rate
show a dismal picture of the literacy rate of the area, particularly, since the literacy among women is
almost nonexistent as there is no girl‟s schools in the surveyed villages of the project area.
60. Majority of the population is small farmers who have a nomadic pattern of life. These
IEE Report for 04MW Thak Nullah Hydropower Plant
nomadic families with their livestock move to summer pasture for six months where women are
responsible for most of the animal rearing. The elder of a house is responsible to look after all the
social matters and other activities of the house including income and expenditure.
61. Agriculture: Cultivated land is irrigated with irrigation channels built along mountain
slopes. Maize and wheat are the major crops along with forage. Cropping pattern was conventional
and terrace and contour farming was mainly practiced. Horticulture is restricted to few trees for self
use and for culinary purposes. Chalghoza and walnut are the main fruit trees grown in the area.
Cash crops like peas and sweet pepper are also grown at a very small scale. Vegetables are grown
for domestic use.
62. Livestock: Majority of the people led semi nomad life going to the high altitude pastures
during summers and coming to the lower elevations during winters. Livestock has historically been
the mainstay of economy and a strong reason for this nomadic. Livestock is an important component
of rural economy.
63. Cow, bullock, goat, sheep, poultry and mule are found in the project area. Physical
condition and general health of the animals is not satisfactory especially in winter due to the shortage
of fodder. Animal diseases cause considerable losses to the livestock. Productivity of cattle is
generally low because of severe winter and lack of proper feed. Sufficient grass and grazing areas
are available. There is need for introducing improved variety to encourage people to keep more
animals.
64. Sources of Income: Table - 5 shows main source of income of economically active
population in the surveyed villages. Agriculture is the dominant sector as it is reflected at 85% in the
villages around the project site. However, most of these 85% go for par time labour as and when
available.
Table 5: Sources of Income in Surveyed Villages
Sr.# Occupations No. of
Persons %
1. Agriculture/ Forestry/Livestock/Fishery 1836 85
2. Business 21 1
3. Service 21 1
4 Labour 282 13
Total: 2160 100
Source: Primary data collected in Januaryr 2012
65. Overwhelming majority of the households is involved in agriculture as the primary source
IEE Report for 04MW Thak Nullah Hydropower Plant
of income. The second occupation is mostly wage labour in off farm activities. The average annual
income of the households found to Rs.84,000. They grow their own wheat, rear their own animals,
and use their milk, butter and meat as well as poultry for eggs and meat. Grow peas and pepper to
earn cash.
66. Table – 6 below gives the average annual income of the households ranges
between 80,000 and 300,000.
Table 6: Average Annual Income per Household in Surveyed Villages
%age of Population Annual Income (Rs)
55 < 84,000
25 84,000 – 180,000
15 180,000 – 250,000
5 > 250,000
Source: Primary data collected in February 2012
67. Their income is more in kind than in cash. They grow their own wheat, eat and sell
Chalghoza, walnut and almond, rear their own animals, use their milk, butter and meat as well as
poultry for eggs and meat, grow potatoes to earn cash. About half of the population (Table 6) have
annual income less than Rs. 84,000 (i.e minimum monthly wages of labour Rs.7000 as fixed by the
GOP).
68. Poverty was endemic due to narrow production base, small landholdings, traditional
agriculture practices, short production seasons and poor communication network.
69. Social Infrastructure: Availability of social services, such as schools, health care
services, water supply facilities are mostly unavailable or very basic. Majority of the people have their
own houses, although some 80% of the total houses are stone and mud houses with thatched roof
and floor. The remaining 20% are made with cement and concrete blocks or bricks.
70. Electricity: All APs of sampled population had an electricity connection but were
complaining regarding regular power failures
71. Sanitation: Sanitation services in terms of sewerage system, wastewater treatment,
drainage and solid waste management are non-existent in the surveyed villages. Therefore the
project area is characterised by inadequate sanitation conditions. However, in surveyed villages of
the project area 90% of the households use open space for excretion.
72. Health Services: The availability of health services in terms of hospitals, health clinics,
dispensaries and medicines are nonexistent in the surveyed villages. There is one non-functional
dispensary in Dewaray village. Diseases like diarrhoea, cholera, chest-infections, pneumonia,
IEE Report for 04MW Thak Nullah Hydropower Plant
meningitides, abdominal problems and seasonal infections (cold, cough etc.) are common among the
villagers. Skin disease like scabies and leishmaniasis also occurs due to overcrowding mainly in
winter and the later due to sand fly. TB is the most common amongst the diseases found. The people
have difficulty in obtaining the necessary medicines. For serious illnesses people have to go to
Chilas town for treatment and most of them cannot afford this.
73. Archaeological and Cultural Sites: Historical and cultural sites in the form of mosques,
shrines, graveyards or of archaeological significance will not be affected as none of such sites exist
in the project area.
74. Chance Find: In case of chance find it will be the responsibility of the project engineer to
stop the activities and report to the Archaeological Department for further necessary action.
75. Role, Position and Status of Women in the Project Area: Life in the villages is entirely
male dominated and women face many problems due to restricted mobility, lack of decision-making,
poor access to social services, limited productive employment opportunities, early marriages, no
family planning practices and no awareness about health and hygiene. The women often suffer from
health problems after childbirth and there are no regular immunizations of the children.
76. Women take all responsibilities including taking care of household activities, bringing up of
children, agriculture (sowing, watering, weeding), livestock, poultry and collection of wood for cooking
etc. Now women are taking interest in all the fields specially education and health.
D. INDIGENOUS PEOPLE
77. The project areas consist of many diverse linguistic, ethnic and religious groups living in
many isolated valleys intercepted with some of the world's highest mountains. The major groups are
divided into various ethnic groups including syed, Shin, Yashkun, Kamin and Dom. The communities
living together share common cultural, linguistic and historical heritage gone through the
transformation process on various economic, political, and education fronts. The transformation
process through expansion of state system education, trade, tourism and out migration working with
major cities of Pakistan in formal and informal sectors and abroad had integrated the local
inhabitants to the ideas, traditions, cultures and languages of Pakistan and become fully
mainstreamed with Pakistani dominant society. None of the households are tribal or minority
members and all affected land is held in private ownership. It would thus be difficult to apply to any
one of these groups the notion of IP as defined by the ADB policy which is based on the idea of
discrete groups.
78. Therefore, standard provisions of the Land Acquisition and Resettlement Framework are
sufficient to ensure an effective compensation process and the requirements of ADB Policy on
IEE Report for 04MW Thak Nullah Hydropower Plant
Indigenous People as specified in the Indigenous Peoples Development Framework (IPDF) prepared
for this project is not triggered.
H. GENDER IMPACTS
79. Life in the villages is entirely male dominated and women face many problems due to
restricted mobility, lack of decision-making, poor access to social services, limited productive
employment opportunities, early marriages, no family planning practices and no awareness about
health and hygiene. According to the women, health is one of the biggest problems in their villages.
The women often suffer from health problems after childbirth and there are no regular immunizations
of the children. Since the women lack awareness about health and hygiene, the children suffer from
various health problems due to poor hygienic conditions.
80. Access to electricity will have positive impacts on women‟s lives that bear the responsibility
and hardship of main household chorus. With the availability of sufficient electricity and the use of
electric appliances relieve women from physically demanding work and reduce their workload. As a
result women have more choices to manage their daily work. Besides lighting, electricity provides the
basic tools for small business like entertainment, access to communication media, and other
commercial and productive activities.
IEE Report for 04MW Thak Nullah Hydropower Plant
IV. ENVIRONMENTAL IMPACTS AND MITIGATION
81. This section of the IEE discusses the potential environmental impacts of the proposed
project and identifies mitigation measures to minimize the impacts in the design, construction and
operational phases. The process of impact prediction is the core of the environmental assessment
process and it is critical that the recommendations and mitigation measures are carried out during
the construction and operation of the project in accordance with the ADB's SPS 2009.
A. DESIGN RELATED IMPACTS
82. The following design principles will be presented to the design engineers by GBWPD at
the commencement of their design commission:
i) EPC contractor during design stage will ensure that any disruption to utility
services is avoided and in case of any damage, restoration is carried out.
ii) The total land requirement will be kept to a minimum.
iii) Wherever possible the design concept will aim permit the maximum use of
prefabricated materials in order to minimize construction impacts and speed up
the construction process.
83. The design will be reviewed by the GBWPD prior to the finalization to ensure that all
environmental requirements are being met and that the design will facilitate mitigation of
environmental impacts to an acceptable level.
84. Loss of Land: The total land area required for construction of project components is 7.469
acres which includes 5.957 acres of permanent land and 1.152 acres of temporary land acquisition.
Out of this 5.957 acres of permanent land acquisition, ROW of Babusar Chilas Road owned by
National Highway Authority Pakistan (NHA) will also be affected due to burying of penstock pipeline.
This will involve overtaking of 3.032 acres of land including retaining wall measuring 2560m³ along
the road. The affected /damaged section of the NHA road will be rehabilitated by the EPC contractor
for which complete safeguards will be kept in tender documents of EPC contractor. The remaining
permanent land acquisition includes 1.523 acres private cultivated land, 0.199 acres uncultivated
private land, 0.538 acres barren private land and 0.665 acres government barren land. The
permanent land acquisition will affect 44 households with 470 APs. The affectees will be
compensated based on the rates fixed by the land revenue department. All the land related issues
have been addressed in LARP of the project.
85. Loss of Economic Assets: Implementation of the project will also involve loss of economic
assets which are discussed below, however, the details have been provided in LARP.
Affected Crops: As a result of construction of project structures, 1.523 acres of cultivated
IEE Report for 04MW Thak Nullah Hydropower Plant
land will be affected which will result in crops damages such as wheat, vegetables and
fodder. Total crop damage is estimated to 2,440 kg. The affectees will be compensated
according to the prevailing market rates.
Boundary Walls: Stone made two no. of privately boundary walls measuring 74.513 m3
to protect agriculture land and houses will be affected. The two affectees will be
compensated at the agreed rate finalized by PMU and land revenue department. All AFs
are entitled to take the salvage material from these affected structures for their personal
use.
Houses: Four numbers of houses measuring 299.749 m2
and one garage measuring
28.014m2 will be affected by laying out of penstock pipe and construction of approach
road along the penstock pipe.These structures are built up of stone and mud. The owners
of these houses will be compensated at the agreed rate finalized by GBPWD and land
revenue department.
Cattle Shed: One cattle shed built-up of stone and mud measuring 92.888 m2 will be
affected by laying out of penstock. The owner will be compensated at the agreed rate
finalized by PMU and land revenue department.
Affected Trees: It is estimated that 32 private trees owned by 11AFs will be affected due
to the construction of project. Of these, 22 trees are fruit trees while remaining 10 trees
are fuel wood trees. Out of 22, there are only 2 nos. tall and fruit bearing trees, rest all
the trees are non fruit bearing and have been categorized as small and medium. The AFs
receiving compensation for trees will be allowed to take timber of their acquired trees for
their domestic use.
It will be the responsibility of the contractor to avoid maximum tree cutting during widening
of access road. Trees, the removal of which is unavoidable for construction shall have
compensatory planting and replacement. Only indigenous tree species will be selected for
replacement and no alien invasive species will be used. At least seven 7 new trees shall
replace each cut tree and maintained alive for three years as part of the contractual
agreement and milestone payments.
B. CONSTRUCTION RELATED IMPACTS
86. Construction related activities would result in negative but short lived impacts in terms of
noise, dust and exhaust pollution on the nearby settlements and specifically to the sensitive
receptors like school, madrasa and dispensary (presently non-functional). The distances of these
settlements/receptors from the weir and power house sites are given in Table 7 where as the
locations are given in Figure 4.
IEE Report for 04MW Thak Nullah Hydropower Plant
Table 7: Distances of Settlements/Sensitive Receptors from the Weir
and Power House Sites
Sr. No. Nearby Settlements/
Sensitive Receptors
Distances from
Weir Site
Distances from
Powerhouse Site
1. Khun Village 1km 5km
2. Dewaray Village 4.5km 1.5km
3. Middle School 4.5km 1.5km
4. Madrasa 4.5km 1.5km
5. Dispensary (non-functional) 4.5km 1.5km
87. Dust Impacts: Most of the construction work will take place close to the villages and
agricultural fields. This is likely to generate dust. Among the variety of options to control dust
(particulate matter) emissions from construction sites the most effective is wet suppression. Spraying
water on exposed surfaces and soil with adequate frequency to keep soil moist at all times can
reduce the total dust emission from the project by as much as 75%. The following mitigation
measures will be implemented during construction to control emission of dust;
i) Water will be sprayed daily on all exposed surfaces sufficient to suppress
emissions of dust. The frequency of spraying will be increased as necessary
but controlled such that the surface remains just moist at all times, particularly
when wind is blowing towards any nearby sensitive receivers.
ii) Dust emission from soil and aggregate storage stockpiles used for road
construction will be reduced by appropriate measures. These will include: (a)
covering the pile with tarpaulin or thick plastic sheets when not in use and at the
end of the working day; (b) erecting windshields / walls on three sides of the piles
such. that the walls project 0.5 m above the top of the pile and (c) keeping the
material moist by spraying of water at appropriate intervals to prevent emissions.
ii) The construction vehicles will maintain a speed limit of 20 Km/h or less on all
unpaved areas within the construction route. Speed limit signposts will be erected
in highly visible positions along the access road and within the route and
maintained for the duration of the construction. Speed bumps will be constructed
near all sensitive receptors such as schools, where there is a risk that vehicles
may exceed the speed limit.
iii) Construction materials will be transported to the route and around the route in
trucks securely covered with tarpaulins or equivalent to prevent dust emission
during transportation.
IEE Report for 04MW Thak Nullah Hydropower Plant
88. Noise and Exhaust Pollution during Construction: Gaseous emission and dusty
atmosphere will result from movement of heavy vehicles for transportation of equipment and
construction materials. Similar effects would be caused by drilling, pressure shaft and caverns. The
EPC contractor would be required to control noise and exhaust pollution by construction
management techniques as per NEQS.
89. Another noise concern is the construction activities near the Khun and Dewaray villages.
Operation of construction vehicles can be a nuisance for the community. Noise can be minimized
by a) preventing construction work during night time 21:00 hrs to 06:00 hrs within 500 m of the
nearest human settlement; b) prevention of blowing of horns by the project vehicles except in
emergencies; c) use of powered mechanical equipment that is acoustically insulated to reduce
noise impacts; d) tuning and proper maintenance of construction equipment and vehicles; and e)
restricting the blasting work to day time only.
90. Impact on Water Quality: The construction works are likely to affect the water quality
temporarily by increasing the silt content in it. However, the river water is not used for drinking
purposes. Therefore, any significant impact on the water quality is not anticipated during the
construction period.
91. Disposal of Excavated Material: Project implementation will involve excavation of
material as very significant activity. The excavation material will consist of rocks, overburden, broken
stones, stone dust, sand and top soil. In case of tunnelling some material will also result from over
break.
92. The overall volume of excavated material, in part, will be used for backfill as well as it will
be re-used for construction of project components in terms of mass concrete, reinforced cement
concrete, concrete lining, approach road, burying of connecting channel, pitching of side slopes and
rip-rap. Some excavated material can also find its way for use by locals for land levelling, nullah
management and other purposes.
93. The excavated material due to laying of penstock pipe would be 3185m3 consisting mainly
of overburden. The estimate for backfill is 2,051.56 m3. The remaining excavated material
1,133.44 m3 will require about 0.1acre of land for disposal for which environmental protection would
be ensured instead throwing it into the stream of the project area. Surplus material site to be
approved by GB-WPD. It is important that overburden consisting of top soil whenever met during
construction activity should be saved for use in spoil disposal areas before such areas can be
beneficially put to agriculture use, forestry or development in parts.
94. Mitigation measures to deal with surplus material may consist of the following steps:
processing; installation of a gravel and rock crushing, sorter and recycling plant at the site of the
IEE Report for 04MW Thak Nullah Hydropower Plant
asphalt plant; reuse; fit the material for road foundation; use for the production of mass concrete and
other building material; use for backfilling, use for the reconstruction of agricultural terraces;
installation of alternate dumping sites of surplus material at places without affecting settlements,
agricultural activities, communication lines, river beds or valuable natural habits.
95. Soil Erosion: Soil erosion will be caused due to the construction of different project
components such as weir, laying of penstock pipe and construction of approach road along the
penstock pipe. Because of low slopes and gravelly nature of the area it is visualized that the soil
erosion will not be a significant problem. However, to minimize soil erosion slope should be kept as
flat as is reasonably possible. Methods such as slope rounding, terracing and/or construction of
diversion channel should be applied.
96. Vegetation and forestation are the most effective long term and economical measures.
These methods are recommended as the preferred options for erosion control. The affected areas
should be planted with grass cover, tiny bushes and trees.
97. Loss of Trees: The project in no way affects the reserve forest areas as they occur in the
far upper reaches. Trees would be cut which at present exist on the land designated for the laying of
penstock pipe and approach road along the penstock pipe. As a mitigation measure, it is
recommended that only the smallest possible number of trees should be cut to clear the land.
However, it will be the responsibility of the contractor to avoid maximum tree cutting. Trees, the
removal of which is unavoidable for construction shall have compensatory planting and replacement.
Only indigenous tree species will be selected for replacement and no alien invasive species will be
used. At least seven new trees shall replace each cut tree and maintained alive for three years as
part of the contractual agreement and milestone payments.
98. Water Supply, Sanitation and Solid Waste Management: To meet the demand of the
drinking water supply and sanitation during the construction period, it is recommended that proper
water supply system should be provided at the site using water from springs. For proper sanitation
facilities, pour flush type latrines with septic tanks are recommended. Also proper arrangements of
solid waste management should be made in construction camps. All such facilities are to be provided
by the contractors.
99. Public Health and Safety of Workers: The contractor shall provide on-site safety
induction training for his personnel upon starting of construction work.
The contractor shall provide personal protective equipment, including hard hats gloves,
safety shoes, and such other equipment as required, and shall take all measures or
actions for the protection and safety of contractor personnel.
Non-metallic hard hats shall be worn at all times by all personnel at work site with the
exception of those areas where the engineer has indicated it not necessary to do so.
Safety glasses if required shall meet international standards and be available for use
IEE Report for 04MW Thak Nullah Hydropower Plant
and worn in specified worksites areas. As a minimum, safety glasses shall be worn for
the following types of work, hammering, chipping, welding, grinding, use of electricity
powered or pneumatic equipment, insulation handling, spray painting, working with
solvents, and other jobs where the potential of an eye injury exists.
Personnel shall not be permitted to work whilst wearing personal clothing or footwear
likely to be hazardous to themselves or others.
Hearing protection, including muffs, plugs or a combination thereof, shall be provided
for all personnel operating in areas where the noise level exceeds 90 decibels.
The contractor shall encourage employees to wear substantial work gloves whenever it
is practical and is safe to do so.
100. Community Health, Safety and Security: Public health and safety measures will also be
undertaken such as barriers and warning signs at required places. All safety, health, environmental
and other safety notices and signs shall be clearly displayed and written in both Urdu and English.
101. Traffic Disruption and Community Safety: The construction related traffic on the road
can disrupt existing traffic and can also create safety hazards for the villagers, particularly children. A
traffic management plan will be developed and submitted by the contractor at least one month before
commencement of construction work. The main objectives of the plan shall be to maximize the safety
of the workforce and the travelling public. The secondary objective will be to keep traffic flowing as
freely as possible.
102. Site Specific Environmental management Plans (SSEMP): The Contractor will prepare
all relevant management plans as part of SSEMP before start of construction. The contractor will
submit all plans to ADB prior to start of construction activities for approval. These plans are listed
below;
Temporary traffic management plan
Drainage and utilities re-provisioning plan
Materials management plan
Waste management plan
Excavated material disposal plan
Tree compensatory planting plan
Noise and dust control plan.
Blasting management plan
Oil spill management plan
103. Workers Camp and Storage Areas: Construction activity camp will require a camp site
for the construction labour and storage. Some 200 persons may reside in the camp at a given time.
One camp site is proposed to be spread over an area of 1.152 acres, near powerhouse site.
IEE Report for 04MW Thak Nullah Hydropower Plant
D. OPERATION RELATED IMPACTS
104. Loss of Water to the River System: The local communities in GB depend on the rivers
and streams for various need such as irrigation, drinking, livestock, watermills and small hydropower
plants. There are several places on the Thak Nullah where water is drawn for agricultural purposes.
One small hydel power plant of 2 MW capacity operated by GB-WPD is located just downstream of
the proposed Thak Nullah power plant. The water released from the Thak Nullah power plant will be
allowed to fall in the intake channel of the existing 2 MW hydel power plant.
105. The weir on Thak Nullah is designed to divert 1.0 m3/s of water for the power generation of
4MW. Between October and April the average flow in Thak Nullah is 1.7m3/s as shown in Table 8.
Thus in these months, more than half of the water will be diverted for power production and there
would be minimal flow in the stream between the weir site and the proposed powerhouse site, a
distance of about 4 km. The minimal flow i.e. 0.7m3/s is much higher than the 10% of average
minimum flow 0.17m3/s which is considered as environmental flow for bare survival of biota in the
vulnerable reach. During the months of February and March the average monthly flow reduces to
1.17m3/s. These months have been declared as lean months and the powerhouse will not be
operated at full capacity. Only one turbine will operate using 0.5m3/s of flow thus allowing the
remaining water as environmental releases.
106. There are few cultivated lands just downstream of the proposed weir. The community uses
the stream water for irrigation through water channels coming from the springs. Irrigation water for
crops is required in the summer months when natural flow in the Nullah is relatively high. Adequate
water will be available for irrigation in summer months (May – September) even when the project is
working at full capacity. During these months, on average 9% of the water in Thak Nullah would be
diverted for power production, whereas about 91% would flow in the Nullah normally as shown in
Table 8. The community's drinking water sources are the various springs in the hills. Therefore no
specific mitigation measures are required, however, GBWPD has to ensure through monitoring that
the existing community water channels coming from spring Nullahs and the flow in them are not
affected.
Table 8: Flow in Thak Nullah (1963-1993)
Sr. # Month Average Flow (m3/s)
Summer Months
1 May 6.45
2 June 10.0
3 July 18.03
4 August 14.22
5 September 7.22
Total Summer Months Flow 55.92
Average Flow of Summer Months 11.18
IEE Report for 04MW Thak Nullah Hydropower Plant
Sr. # Month Average Flow (m3/s)
Winter Months
6 October 2.64
7 November 1.91
8 December 1.49
9 January 1.28
10 February 1.18
11 March 1.17
12 April 2.08
Total Winter Months Flow 11.75
Average Flow of Winter Months 1.67
Annual Average 5.64
107. Environmental Flow (EF): Ecological considerations for the Thak nullah, downstream of
water abstraction require reserved or minimum flow. All definitions of reserved or minimum flow place
emphasis on the protection of natural life in the nullah. From the point of view of environmental
considerations there are numerous methods and formulas for calculation of reserved flow or
minimum flow which are briefly discussed in paras below.
108. EF Methods Based on Hydrologic or Statistic Values: Within these methods, a first
subgroup refers to the average flow rate (MQ) of the river at a given cross section. These methods
give values between 5 and 60 % of MQ; the latter one in case of high economic importance of
fishery. A second subgroup of methods refers to the minimum mean flow (MNQ) in the river. The
values calculated can vary from 33 to 100 % of MNQ. A third subgroup of methods refers to the
prefixed values on the Flow Duration Curve (FDC). In this group there are a wide variety of methods:
from a reserved flow equal to 20% of Q300 (flow rate exceeding 300 days of duration) to incredibly
complex interpolating formulas.
109. EF Methods Based on Physiographic Principles: These methods basically refer to a
prefixed specific flow rate expressed as l/s.km2 of catchment area. Values can vary from 1.6 to 9 or
more l/s.km2 (in cases of abundance of fish). These methods are easily applicable presuming there
is good basic data. However no hydraulic parameters are considered and neither the effect of
tributaries nor the length of the diversion reach is taken into account.
110. EF Formulas Based on Velocity and Depth of Water: Also in this group of methods
there is a wide range of variation: one says water velocity in case of reserved flow may not fall below
a prefixed threshold value of 0.3 - 0.5 m/s and the minimum depth of water must be greater than a
prefixed value of 10 cm. Another suggests 1.2 – 2.4 m/s and 12 - 24 cm water depth and so on. The
great advantage of these formulas is that the shape of the profile is included in the calculation and
there is no need for hydrological data. Nevertheless diversion length and tributaries are not
considered.
IEE Report for 04MW Thak Nullah Hydropower Plant
111. EF Methods Based on Multi-Objective Planning Taking into Consideration Ecological Parameters: These
methods are generally very complex in their application and require considerable expertise in doing
so. They require site-specific flow observations and take into account hydrological, hydraulic,
ecological, and meteorological data, embracing both ecological and economic parameters. Methods
are expensive in data collection and mathematical computing and are suitable only for particular
types of rivers. Their transferability is doubtful.
112. CEMAGREF FORMULA: The formula developed for environmental flow by CEMAGREF
Agricultural and Environmental Research Institute, Antony, France is Q = [(0.0651 Qmm+2) /100]
Qam where Qmm is monthly mean and Qam is annual mean discharge of the Thak nullah weir.
According to this formula the environmental flow required is 0.134m3/s using values given in Table 9.
As can be seen by comparison with Table 9 the flow downstream of the weir is in excess of designed
flow of 1.0 m3/s throughout the year.
Table 9: Environmental Flow Requirements (m3/s) Based on CEMAGREF Formula
Sr.
# Months
Monthly
Mean
Flow Qmm
(1963-1993)
Environmental
Flow Q
Water
Required
for Power
Generation
Release of Water
Downstream of
Weir
1 January 1.28 0.134 1.00 0.28 overspill
2 February 1.18 0.134 1.00 0.18 overspill
3 March 1.17 0.134 1.00 0.17 overspill
4 April 2.08 0.134 1.00 0.95 overspill
5 May 6.45 0.134 1.00 5.32 overspill
6 June 10.00 0.134 1.00 8.87 overspill
7 July 18.03 0.134 1.00 16.90 overspill
8 August 14.22 0.134 1.00 13.09 overspill
9 September 7.22 0.134 1.00 6.09 overspill
10 October 2.64 0.134 1.00 1.51 overspill
11 November 1.91 0.134 1.00 0.78 overspill
12 December 1.49 0.134 1.00 0.36 overspill
Annual Mean 5.64
113. EF Montana Method: The period February to March is a period of lean flow as given in
table below. According to this method 10% of lean month average flow which is 0.117 m3/sec has
been considered as environmental flow for bare survival of biota in vulnerable reach and also taking
stock of riparian users‟ minimum requirements during this period. Flows of water available for power
generation at full capacity throughout the year is more than the designed flow of 1.0m3/s. The
minimum flow requirement to keep the power plant in operation is 0.5m3/s when only one turbine will
be generating 2MW power during the lean months of February and March after the release of
environmental flow whereas for the remaining months two turbines will generate 4MW using 1.0m3/s
flow. The following Table -10 is prepared to explain the situation.
IEE Report for 04MW Thak Nullah Hydropower Plant
Table -10: Environmental Flow Requirements (m3/s) in Thak Nullah Based on Montana Method
Lean Months
Mean Lean
Months Flow
(1966-97)
No. Of Turbine in Operation
Flow Requirement for Turbine Operation
(m3/s)
Environmental Flow
(m3/s) %
1 2 3 4 (1-3) 5
January 1.28 2 2 x 0.5 = 1.00 0.28 22
February 1.18 1 1 x 0.5 = 0.5 0.68 58
March 1.17 1 1 x 0.5 = 0.5 0.67 57
April 2.08 2 2 x 0.5 = 1.00 1.08 52
May 6.45 2 2 x 0.5 = 1.00 5.45 84
June 10.00 2 2 x 0.5 = 1.00 9.00 90
July 18.03 2 2 x 0.5 = 1.00 17.03 94
August 14.22 2 2 x 0.5 = 1.00 13.22 93
September 7.22 2 2 x 0.5 = 1.00 6.22 86
October 2.64 2 2 x 0.5 = 1.00 1.64 62
November 1.91 2 2 x 0.5 = 1.00 0.91 47
December 1.49 2 2 x 0.5 = 1.00 0.49 33
Lean Months Total Flow 67.67 - - 56.67 83.7
Average Flow for Lean Months 5.64 - - 4.72 83.7
114. The table shows that the release of environmental flow downstream of weir site will not
in any way compromise on water availability for downstream ecological requirements which is from
22 to 94% of the total flow. These figures are much above the 10% as suggested in the formula.
According to Montana method the environmental releases during lean months are above 10% of
natural flow, varying between 57 to 58%. The detail of assessment of environmental flow is given in
Appendix – I.
E. POSITIVE IMPACTS
115. The proposed 04 MW plant will be an important project for bridging the widening gap
between demand and supply. At present, there are 3,600 electricity consumers in Chilas and
surrounding areas. Of these 3,200 (89%) are domestic, 300 (8%) are commercial, whereas 100 (3%)
are industrial. The total power demand is 2.4 MW however; the total installed capacity of hydel and
thermal power plants is 1.7 MW. Thus there is a shortfall of 0.7 MW. Unless new sources of power
are added, the situation is likely to aggravate with time as the demand is projected to increase to 4.2
MW by 2015.
116. No drinking water supply is available in the project area. The whole of the population
depends on springs for drinking water. It has, therefore, been decided to provide drinking water
supply scheme at Dewaray and Jal villages on the demand of villagers. The provision of water supply
scheme planned under the project will be a significant development. It is planned that the EPC
contractor will establish water supply scheme in these villages.
117. Availability of power would reduce consumption of fuel wood and other fossil fuels by
villagers for heating and cooking purposes.
IEE Report for 04MW Thak Nullah Hydropower Plant
118. The project will provide unskilled jobs during the construction phase and a limited number
of jobs during project operation to locals.
119. Hydropower is a clean and renewable source of energy and its use instead of thermal
power reduces the emission of pollutants such as carbon dioxide (CO2), particulate matter (PM),
sulphur dioxide (SO2), carbon monoxide (CO) and oxides of nitrogen (NOx), and hydrocarbons. The
annual reduction in the production of CO2, the main greenhouse gas, as compared to a power of
similar capacity operating on oil, gas, or coal is shown in Table below. It is estimated that more than
28,732 tons of carbon dioxide emission will be saved annually by using hydropower rather than fossil
fuels.
Reduction in Annual Greenhouse Gas Emission
Fuel Source Oil Gas Coal
Total Saving (tons CO2) 24,528 14,716 28,732
IEE Report for 04MW Thak Nullah Hydropower Plant
V. STAKEHOLDERS CONSULTATION
120. The objectives of the stakeholder consultation process were to disseminate information on
the project and its expected long-term and short-term impacts among stakeholders, and to gather
information on relevant issues so that the feedback received could be used to address these issues
at early stages of project design. Another important objective was to determine the extent of the
concerns amongst the community and recommend means to address these in the project
implementation and suggest appropriate mitigation measures.
A. IDENTIFICATION OF STAKEHOLDERS
121. Stakeholders are people, groups, or institutions that may be affected by or can significantly
influence, or are important to the achievement of the stated purpose of the proposed project. For this
project, primary stakeholders are the communities living in Khun, Sharat, Kot, Dawary, Saroh,
Ghunch and Jal villages, in particular those who would be affected by land acquisition. Other
stakeholders are the non-governmental organizations working in these villages, and the government
departments, particularly the GB-WPD.
B. CONSULTATION PROCESS
122. Consultations were carried out through focus group discussions, public meetings,
community discussions with key stakeholders, and formal meetings with government officials, to
ascertain their views and identify their needs and preferences for compensation and rehabilitation
measures. During the consultation, the stakeholders were informed about the project and their
concerns were recorded. Views on compensation and related issues were also discussed with the
persons likely to be affected by land acquisition. Photographs of the scoping sessions / consultations
are placed at the end of the report.
123. The survey team undertook public consultations during the month of February 2012. The
list of participants is given in Appendix II. The main concerns of the participants are summarized
below.
C. SUMMARY OF CONSULTATION
124. During the consultation, the concerns and comments by the stakeholder included the
following:
i) In general, everyone welcomed the project. No one expressed any concerns by
the project itself.
ii) During the road construction by NHA, compensation was not paid to poor APs.
GBWPD should not repeat the same mistake.
iii) Timely and fair compensation should be provided against the affected assets.
Compensation should be at market rate, transparent, fairly executed. Some
respondents had concerns on the basis of previous experiences.
IEE Report for 04MW Thak Nullah Hydropower Plant
iv) Employment during construction and operation was a major subject of discussion.
The community expects that new job opportunities will be created by the project
directly.
v) Since land holdings are very small, to the extent possible project should avoid
land acquisition.
D. MEETINGS WITH OFFICERS OF LINE DEPARTMENTS
125. The team of consultants‟ also visited line department in Chilas to obtain information on
various aspects of Fisheries, Wildlife, Agriculture, Health and Land acquisition. The list of Line
Departments visited is given in Appendix III.
E. FUTURE CONSULTATION
126. Public consultations were earlier conducted in the project area during April, May 2008. The
same were updated in February 2012. Such an exercise will be continued during and after detail
design of the specific intervention and components. The objective of the future consultation will
mainly focus on timing of work, overall schedule, minimizing disturbance to business, and public
safety and gender issues. Further consultation will be carried out during project implementation
phase. These will be carried out during and after the detailed designs of the specific interventions
and components.
F. PROCEDURE FOR PUBLIC DISCLOSURE
127. Information Disclosure: In promoting transparency and accountability, PMU will continue
to provide relevant information to the stakeholders in a timely manner in a form and language (urdu)
that are understandable and accessible to them. Illiterate people will be informed verbally during
regular consultation process by the PMU.
128. PMU will disclose the IEE report and related documents to Environmental Protection
Agency of Gilgit Baltistan. IEE report will be disclosed at the ADB‟s website. The local community will
be provided with the Summary of IEE report and project information at different stages of the
consultation.
129. The information will be made available in locations that are easily accessible to
stakeholders. Depending upon the capacity of a stakeholder and nature of the information to be
disseminated, such locations can be local villages, project site office, PMU office, government
department or local government setup.
130. Overall, the consultation activities and disclosure will be designed so as to maximize
community awareness of the project and to create reasonable opportunities for community input and
involvement.
IEE Report for 04MW Thak Nullah Hydropower Plant
VI. INSTITUTIONAL REQUIREMENTS AND ENVIRONMENTAL
MANAGEMENT PLAN
A. INSTITUTIONAL ARRANGEMENT
131. The project will be executed through GB-WPD with support from all relevant department
and line agencies. GB-WPD will exercise its functions through establishing a Project Management
Unit (PMU), at project site headed by a full time Project Director who will be responsible for general
project execution. In this regard, a well defined institutional structure will be placed in the PMU and
staff will be assigned to specific roles. The PMU will ensure compliance with the ADB policies and
procedures.
132. Within the project coordination office established in GBWPD, an Environment and Social
Development Cell (ESDC) will be established, reporting directly to the Project Coordinator, which will
be accountable and responsible for implementation of EMP and the LARP. The ESDC will initially
consist of two permanent members: an environment specialist and a resettlement specialist, who will
be directly hired by GB-WPD to provide technical assistance in implementation of the environment
and resettlement plans. The number may be increased depending on the number of projects. The
ESDC will be set up within the initial three months of PMU establishment and will be supported
intermittently by international experts in resettlement and environment. The ESDC will work in close
cooperation with the PMU on the day-to-day activities - EMP and the LARP implementation. The
ESDC will also be responsible for internal monitoring.
133. The ESDC would ensure that IEE and LARP are prepared and approved prior to awards of
contracts for the project. Any subsequent changes to these documents will also be responsibility of
the ESDC. The project Coordination Office will ensure budgets are delivered in time to the competent
authority for timely implementation of LARP and EMP.
134. The main contractor of the project will have a full-time health, safety and environment
(HSE) officer to manage the tasks assigned under this IEE.
B. COMPLAINTS AND GRIEVANCES REDRESS
135. For the purpose of addressing grievances by the community about the implementation of
IEE and EMP, a Grievance Redress Committee (GRC) will be established for the project as soon as
project implementation commences. However, with careful observance of the provisions of the EMP
by all stakeholders involved, grievances can be avoided.
136. The Committee will be established at the project level with the primary objective of
IEE Report for 04MW Thak Nullah Hydropower Plant
providing a mechanism to mediate conflict. The committee will constitute the Project Director, one
elected representative, one representative of district revenue officer and three representatives of the
affected community.
137. If necessary, the aggrieved person will first address the complaint to Grievance Redress
Committee who will strive for settlement within 10 days of lodging of the complaint. If the complaint
cannot be settled, the grievance will be referred to ESDC. Within 30 days the Grievance Redress
Committee will discuss the matter and refer the grievance to PMU, and obtain a resolution. If the
grievance redress mechanism fails to satisfy the aggrieved person, s/he can approach the Gilgit
Baltistan Environmental Protection Agency or court of law.
C. ENVIRONMENTAL REVIEW AND APPROVAL
138. Environmental regulations of the Govt of Pakistan (GoP) require proponents of projects
that have reasonably foreseeable qualitative and quantitative impacts to submit environmental
assessment report of the project for review and approval. Thak Nullah Hydropower Project with a
generation capacity of less than 50 MW falls within Schedule B of the GoP Regulations, which
require preparation of an Initial Environmental Examination (IEE) Report.
139. The Project Director will have the responsibility to ensure that IEE Report is submitted to
Environmental Protection Agency Gilgit Baltistan (EPA-GB) to obtain approval prior to
commencement of construction work.
D. ENVIRONMENTAL MANAGEMENT PLAN
140. This IEE concludes that the construction impacts will be manageable if the mitigation
measures are implemented thoroughly. An Environmental Management Plan (EMP) has been
prepared (Appendix IV) by close reference to the best practices and in line with ADB's SPS 2009.
EMP is based on the type, extent and duration of the identified environmental impacts, mitigation
measures, their timing, location, and implementation/ monitoring responsibility.
141. PMU should check that contractors have all the necessary valid licenses and permits such
as those for use of powered mechanical equipment. The need to confirm that contractors and their
suppliers have complied with statutory requirements for licenses will also be checked by PMU.
142. The effective implementation of the EMP should be audited as part of the loan conditions
and the executing agency must be prepared for this. In this regard, the Implementing Agency must
IEE Report for 04MW Thak Nullah Hydropower Plant
be prepared to guide the design engineers and contractors on the environmental aspects.
143. Prior to implementation, the EMP shall be amended and reviewed by the ESDC after
detailed designs are complete and contracting arrangements are known. Such a review shall be
based on reconfirmation and any additional information on the assumptions made at the feasibility
stage on location, scale and expected operating conditions of the project. For example, if there is
additional land required, the designs may be amended and the environmental significance must be
reviewed. Although no major additional impacts would be anticipated based on the information
provided to date, the performance and evaluation schedules to be implemented during project
construction and operation can be reviewed, updated, and costs estimates can be revised if
necessary.
144. The EMP must be reviewed by the ESDC and approved before any construction activity is
initiated, to take account of any subsequent changes and fine tuning. It is recommended that this
takes place before contracts are worked out in detail and before pre-qualification, so that the
environmental status of the project area is monitored to set a baseline to benefit monitoring using
some of the key EMP mitigation measures as the performance indicators.
145. This IEE including the EMP should be used as a basis for an environmental compliance
programme and an updated EMP should be included in the revised contract documentation for all
components. The updated EMP, any conditions of the environmental clearance from the GB EPA,
and any subsequent licenses and approvals from GB EPA should also be included in the
environmental requirements for the contractors in the compliance program. Therefore, continued
monitoring of the implementation of mitigation measures, and monitoring of the environmental
impacts related to the construction of all future works should be properly carried out and reported
periodically in monthly progress reports. Compliance with all of the EMP requirements shall also be
reported in other periodic project performance reports.
146. The contractor is to prepare a Site Specific Environmental Management Plan (SSEMP)
after contract award. The SSEMP is to be approved by ADB before the start of civil works on the
project site.
147. The impacts from construction and operation of the projects will be manageable and no
insurmountable impacts are predicted providing that the updated EMP is included in the contract
documents and implemented to its full extent. The details of the current summary
IEE Report for 04MW Thak Nullah Hydropower Plant
EMP (Appendix - IV) are in the form of the matrix and may require revision as the project reaches
detailed design. The matrix details the mitigation measures recommended for each of the identified
impacts, approximate location of the mitigation sites, time span of the implementation of mitigation
measures, an analysis of the associated costs and the responsibility of the institution. The
institutional responsibility has been specified for the purpose of the implementation and the
supervision. The matrix is supplemented with a monitoring plan for the performance indicators. The
EMP has been prepared following best practice and the ADB‟s SPS 2009.
E. MONITORING AND EVALUATION
148. The environmental performance of the project will be monitored internally by the
PMU/ESDC, assisted by the Design 'and Supervision Consultant. Internal monitoring will be routinely
carried out by ESDC, and the results will be communicated to ADB through the quarterly project
implementation reports. Indicators for the internal' monitoring will be those related to process and
immediate outputs and results. This information will be collected directly in the field by ESDC on
monthly basis to assess the environmental performance of the project and to adjust the work
program, if necessary. The monthly reports will be consolidated quarterly in the standard supervision
reports to ADB. Specific monitoring benchmarks will be:
i) Information campaign and consultation with stakeholders;
ii) Contractor(s) compliance with EMP;
iii) Complaints received and addressed by the Grievance Redress Committee;
iv) Environmental effects.
149. An environmental monitoring plan showing implementation responsibilities and schedule
has been drawn up and places as Table 11.
150. Monitoring activities during implementation will focus on compliance with license
conditions, recording implementation of mitigation measures, recording environmental parameters,
reviewing contractor environmental performance and proposing remedial actions to address
unexpected impacts during construction. Some of these tasks can be assigned to the contractors
and managed by the ESDC.
151. During the pre-construction period, the monitoring activities will focus on (i) checking the
contractor's bidding documents, particularly to ensure that all necessary environmental requirements
have been included; and (ii) checking that the contract documents' references to environmental
IEE Report for 04MW Thak Nullah Hydropower Plant
mitigation measures requirements have been incorporated as part of contractor's assignment. Where
detailed design is required (e.g. for further elaboration of the recycling facilities at the treatment
plants and pipelines) the checking of updated designs must be carried out. During the construction
period, the monitoring activities will focus on ensuring that environmental mitigation measures are
implemented, and some performance indicators will need to be monitored to record the project's
environmental achievements and to guide any remedial action to address unexpected impacts.
152. To facilitate EMP implementation, during preparation for construction the contractors must
be prepared to cooperate with local population in the mitigation of impacts. However, experience
suggests that contractors may have little impetus or interest in dealing with environmental problems
in the absence of performance-linked criteria. Therefore, the required environmental mitigation must
be clearly described in a memorandum of understanding and other contract documents at the
bidding stage; the completion of mitigation should be linked to payment milestones.
Table 11: Environmental Monitoring Plan
No. Environmental Monitoring Tasks 8
Implementation
Responsibility
Implementation
Schedule
1 Design Phase
1.1 Audit project bidding documents to ensure IEE
and EMP is included. PMU through .ESDC
Prior to issue of bidding
documents.
1.2 Disclosure of the project to NEPRA PMU through ESDC Prior to issue of bidding
documents.
1.3 Monitor final site selection (alignment) and its
environmental compliance with EMP PMU through ESDC
Prior to PMU approval of
detailed designs.
2 Construction Phase
2.1
Regular (monthly) monitoring and reporting
(quarterly) of Contractor's compliance with
statutory environmental requirements
PMU through ESDC Continuous throughout
construction period.
2.2
Regular (monthly) monitoring and reporting
(quarterly) of contractor's compliance with
contractual environmental mitigation measures
PMU through ESDC Continuous throughout
construction period.
2.3
Regular (monthly) monitoring and reporting
(quarterly) of complaints and responses of
environmental mitigation measures
PMU through ESDC
Continuous throughout
construction period.
2.4
Monitor adjustments to the EMP and the
thorough implementation of detailed EMP
PMU through ESDC
During all phases of the
project
2.5
.Commissioning phase monitoring of as built
equipment and facilities versus environmental
contractual performance criteria
PMU through ESDC
At commissioning.
IEE Report for 04MW Thak Nullah Hydropower Plant
No. Environmental Monitoring Tasks 8
Implementation
Responsibility
Implementation
Schedule
3 Operation and Maintenance Phase
3.1
Observations during routine maintenance
inspections of facilities. Inspections will include
monitoring implementation of operational
mitigation measures versus environmental
criteria specified in EMP for operational
impacts.
Chief Engineer GBWPD As per EMP
8. Monitoring of issues related to compensation of landowners for land acquisition and loss of economic assets etc. are
addressed in the Land Acquisition and Resettlement Plan.
IEE Report for 04MW Thak Nullah Hydropower Plant
VII. ENVIRONMENTAL RELATED COSTS
153. EMP implementation includes staffing and monitoring activities to be undertaken by PMU.
For this purpose PMU will established Environmental and Social Development Cell (ESDC) which
together with Supervision Consultant will implement the EMP. The environmental related cost for
EMP implementation and monitoring totals to Rs. 6.050 million as detailed in the Table below which
have also been included in Contract Agreement.
Table 12: Summary of Estimated Environmental Cost
Item Sub Item
Estimated Total
Costs
(Rs.)
Monitoring 2 persons for 1 year (intermittent) 1,200,000
Mitigation measures As prescribed under EMP as IEE 4,000,000
Transport 1 vehicle for 1 year 300,000
Contingency 10% contingency 550,000
Total 6,050,000
154. The land acquisition and resettlement (LARP) cost consisting of land acquisition,
economic assets, vulnerability allowances and contingencies add up to Rs. 14.649 million as given
in LARP report.
IEE Report for 04MW Thak Nullah Hydropower Plant
VIII. FINDINGS AND RECOMMENDATIONS
155. In carrying out this IEE study, secondary data were used to assess the environmental
impacts in a comprehensive manner along with public consultations. On - site environmental surveys
were carried out in order to complete the environmental assessment and recommendation of suitable
mitigation measures
156. Several actions are required during the detailed design stage to minimize impacts to
acceptable levels and described in the EMP. The negative environmental impacts from the project
will mostly take place during the construction stage but there are also some potential negative
impacts for the operational stage as well as many significant beneficial impacts. The construction
impacts are very predictable and manageable and with appropriate mitigation few, residual impacts
are likely.
157. Some key actions are required after the detailed designs are developed. PMU should
include the IEE and EMP, updated if necessary, as contractual requirements, accepted by all
contractors prior to 'signing the contract(s). The contractor will be required to prepare an SSEMP
including temporary traffic management, materials management master plan, waste management
plan, blasting management plan and oil spill management plan. The SSEMP should be deliverable
by the contractors and approved by ADB before construction commences.
158. At the detailed design stage, a review should be conducted of the monitoring activities
proposed in this IEE to establish the parameters to be checked during the construction and
operation.
159. The IEE, including the EMP, should be used as a basis for an environmental compliance
program and be included in the contract documentation. The EMP shall be reviewed at the detailed
design stage. In addition, any conditions that are part of the environmental clearance from the GB-
EPA should also be as a basis for the environmental compliance program. Therefore, continued
monitoring of the implementation of mitigation measures, the implementation of the environmental
conditions for work and environmental clearance, and monitoring of the environmental impact related
to the operation of the treatment plants and pipelines subprojects should be properly carried out and
reported monthly to track and determine the net environmental benefits that have accrued. These
should be summarized by GB-WPD in regular quarterly progress reports to ADB. Bi-annual
environmental monitoring reports will also be prepared on ADB prescribed template and for
submission to ADB. The negative environmental impacts will mostly take place during the
IEE Report for 04MW Thak Nullah Hydropower Plant
construction. There are no operational impacts to be addressed in the detailed designs. If the
projects are managed in line with internationally accepted environmental auditing procedures very
significant environmental benefits can be expected to be demonstrated in the operational stage.
160. The implementation of the environmental mitigation measures during the construction
period will be assigned to the contractors. However, experience suggests that contractors may have
little impetus or interest to deal with environmental problems in the absence of performance linked
criteria. Therefore, the required environmental mitigation must be clearly described in the contract
documents at the bidding stage and, the completion of mitigation.
IEE Report for 04MW Thak Nullah Hydropower Plant
IX. CONCLUSIONS
161. Environmental impacts associated with the construction and operation of the Thak Nullah
HPP need to be mitigated and institutional arrangements are to be made available. Additional human
and financial resources will be required by GB-WPD to complete the detailed designs and
incorporate the environmental recommendations effectively and efficiently in the contract documents,
linked to payment milestones. The proposed mitigation and management plans are practicable but
require additional resources.
162. Monitoring activities will need to focus on compliance with license conditions, recording
implementation of mitigation measures, adherence to agreed waste disposal practices, reviewing
contractor environmental performance and proposing remedial actions to address unexpected
impacts.
163. The implementation of the Thak Nullah HPP is a feasible and sustainable environmental
option but thorough implementation of the EMP is required throughout the design, construction and
operation of the project in order to minimize impacts and retain public support for the project.
APPENDIX - I
ASSESSMENT OF
ENVIRONMENTAL FLOW
IEE Report for 04 MW Thak Nullah Hydropower Plant Appendix - I
- 1 -
ENVIRONMENTAL FLOW ASSESSMENT
1. INTRODUCTION
Thak Nullah Hydropower project aims at generating 04MW of electricity under a
design flow of 1.0m3/s using two Pelton Wheel Turbines. The protection of aquatic
environment is an important consideration in developing schemes for utilization of
water resources. Where schemes involve altering the natural flow regime of a surface
water system (river or stream etc), it is important to allow a certain share of water,
generally referred to as environmental flows, through the existing course of the water
so that biological life in the affected stretch can be maintained. While in principle the
concept of environmental flows is accepted uniformly, the methodologies for
establishing the levels of environmental flows vary considerably amongst experts,
environmental agencies or countries. In Pakistan, there does not exist any specific
legislation or ruling or instruction from relevant governments or statutory bodies or
regulatory agencies which establish a specific framework or methodology for
determining environmental flow. Consequently, in water resource development
schemes, where the level of environmental flows has to be established, consultants
rely on existing precedents or use their own experience and understanding to
propose such flow requirements. In this note, the environmental flow adopted for
Thak Nullah Hydropower Project is discussed for further clarity and understanding.
2. ENVIRONMENTAL FLOW ASSESSMENT METHODOLOGIES
There are many formulas for the calculation of environmental flow. At present the
number of formulas worldwide is 207 [1]. This number is tending to increase day by
day. This demonstrates that no good universally valid solution for environmental flow
determination exists at the moment and probably will never exist.
The various groups of formulas available for Environmental Flow Assessment (EFA)
are based on the following aspects [2].
i) Methods based on hydrologic or statistic values;
ii) Methods based on physiographic principles;
iii) Formulas based on velocity and depth of water; and
iv) Methods based on multi-objective planning taking into consideration
ecological parameters.
2.1 Methods Based on Hydrologic or Statistical Values
Within these methods, a first subgroup refers to the average flow rate (MQ) of the
river at a given cross section. These methods give values between 5 and 60 % of
MQ; the latter one in case of high economic importance of fishery.
IEE Report for 04 MW Thak Nullah Hydropower Plant Appendix - I
- 2 -
A second subgroup of methods refers to the minimum mean flow (MNQ) in the river.
The values calculated can vary from 33 to 100 % of MNQ.
A third subgroup of methods refers to the prefixed values on the Flow Duration Curve
(FDC). In this group there are a wide variety of methods: from a reserved flow equal
to 20% of Q300 (flow rate exceeding 300 days of duration) to complex interpolating
formulas.
2.2 Methods Based on Physiographic Principles
These methods basically refer to a prefixed specific flow rate expressed as l/s.km2 of
catchment area. Values can vary from 1.6 to 9 or more l/s.km2 (in cases of
abundance of fish).
These methods are easily applicable presuming there is good basic data. However
no hydraulic parameters are considered and neither the effect of tributaries nor the
length of the diversion reach is taken into account.
2.3 Formulas Based on Velocity and Depth of Water
Also in this group of methods there is a wide range of variation: one says water
velocity in case of reserved flow may not fall below a prefixed threshold value of 0.3-
0.5 m/s and the minimum depth of water must be greater than a prefixed value of 10
cm. Another suggests 1.2 – 2.4 m/s and 12 - 24 cm water depth and so on.
The great advantage of these formulas is that the shape of the profile is included in
the calculation and there is no need for hydrological data. Nevertheless diversion
length and tributaries are not considered.
2.4 Methods Based on Multi-Objective Planning Taking Into Consideration
Ecological Parameters
These methods are generally very complex in their application and require
considerable expertise in doing so. They require site-specific flow observations and
take into account hydrological, hydraulic, ecological, and meteorological data,
embracing both ecological and economic parameters. Methods are expensive in data
collection and mathematical computing, and are suitable only for particular types of
rivers. Their transferability is doubtful.
3. COMPARATIVE STUDY OF EFA FORMULAS FOR THAK NULLAH HPP
2.5 CEMAGREF FORMULA
According to this formula Q = [(0.0651 Qmm+2) /100] Qam (Ref. CEMAGREF:
Agricultural and Environmental Research Institute, Antony, France; Formula
developed for Minimum Flow for Ecological Requirements, 2006) where Qmm is
mean minimum monthly flow and Qam is annual mean discharge of the Thak Nullah
at the weir site. Using 1.17 m3/s for Qmm and 5.64 m3/s for Qam, the required
ecological flow Q is equal to 0.134 m3/s as environmental flow.
IEE Report for 04 MW Thak Nullah Hydropower Plant Appendix - I
- 3 -
The same formula was earlier used by Fitchner Consultants of Germany for 106 MW
Golen Gol HPP, Chitral Pakistan. Golen Gol HPP is being developed by WAPDA, the
state-owned organization for the development of water resources and hydropower.
The EIA for Golen Gol HPP has already been approved by EPA showing no
reservations on the environmental flow calculation method.
This formula was later on used by Star Hydropower Ltd. for ADB finance 147MW
Patrind Hydropower Project, AJ&K which is under construction stage at present.
The following Table-1 compares the Formula value of 0.134 m3/sec as
environmental flow with the estimated monthly flows of Thak Nullah in the reach from
weir site to powerhouse site.
Table-1: Environmental Flow Requirements (m3/s) in Thak Nullah Based on
CEMAGREF FORMULA
Sr. # Months
Monthly
Mean
Flow Qmm
(1963-1993)
Environmental
Flow Q
Water
Required
for Power
Generation
Release of
Water
Downstream of
Weir
1 January 1.28 0.134 1.00 0.28 overspill
2 February 1.18 0.134 1.00 0.18 overspill
3 March 1.17 0.134 1.00 0.17 overspill
4 April 2.08 0.134 1.00 0.95 overspill
5 May 6.45 0.134 1.00 5.32 overspill
6 June 10.00 0.134 1.00 8.87 overspill
7 July 18.03 0.134 1.00 16.90 overspill
8 August 14.22 0.134 1.00 13.09 overspill
9 September 7.22 0.134 1.00 6.09 overspill
10 October 2.64 0.134 1.00 1.51 overspill
11 November 1.91 0.134 1.00 0.78 overspill
12 December 1.49 0.134 1.00 0.36 overspill
Annual Mean 5.64
The Table shows that the quantity of water available for power generation throughout
the year would be more than the design flow of 1.0 m3/s. The effect on aquatic life
during lean months February to March is not considered significant when viewed
from the fact that substantial fish culture does not exist in the reach under
consideration. Therefore, diversion of the stream for power generation in the section
immediately downstream of the weir will not affect fish population indicating
insignificant impact on the fishing.
IEE Report for 04 MW Thak Nullah Hydropower Plant Appendix - I
- 4 -
2.6 EF Montana Method
The period February to March is a period of lean flow as given in the Table below.
According to this method 10% of lean months average flow which is 0.117 m3/sec
has been considered as environmental flow for bare survival of biota in vulnerable
reach and also taking stock of riparian users‟ minimum requirements during this
period. Flow of water available for power generation at full capacity throughout the
year is more than the designed flow of 1.0m3/s. The minimum flow requirement to
keep the power plant in operation is 0.5m3/s when only one turbine will be generating
2MW power during the lean months of February and March after release of
environmental flow whereas for the remaining months two turbines will generate
4MW using 1.0m3/s flow. The following Table -2 is prepared to explain the situation.
Table-2: Environmental Flow Requirements (m3/s) in Thak Nullah Based on
Montana Method
Lean Months
Mean Months
Flow (1966-97)
No. Of
Turbine in
Operation
Flow
Requirement for
Turbine
Operation (m3/s)
Environmental
Flow
(m3/s) %
1 2 3 4 (1-3) 5
January 1.28 2 2 x 0.5 = 1.00 0.28 22
February 1.18 1 1 x 0.5 = 0.5 0.68 58
March 1.17 1 1 x 0.5 = 0.5 0.67 57
April 2.08 2 2 x 0.5 = 1.00 1.08 52
May 6.45 2 2 x 0.5 = 1.00 5.45 84
June 10.00 2 2 x 0.5 = 1.00 9.00 90
July 18.03 2 2 x 0.5 = 1.00 17.03 94
August 14.22 2 2 x 0.5 = 1.00 13.22 93
September 7.22 2 2 x 0.5 = 1.00 6.22 86
October 2.64 2 2 x 0.5 = 1.00 1.64 62
November 1.91 2 2 x 0.5 = 1.00 0.91 47
December 1.49 2 2 x 0.5 = 1.00 0.49 33
Total Flow 67.67 - - 56.67 83.7
Average Flow 5.64 - - 4.72 83.7
The table shows that the release of environmental flow downstream of weir site will
not in any way compromise on water availability for power generation thus having
least impact on power generation while ensuring the downstream ecological
requirements from 22 to 94% as compared to 10%.
IEE Report for 04 MW Thak Nullah Hydropower Plant Appendix - I
- 5 -
4. CONCLUSION
Two methods, namely, CEMAGREF Formula and Montana Method have been
used to assess the environmental releases downstream of the weir.
According to CEMAGREF Formula environmental flow varies from 8 to 15% of
natural flow during lean months from November to April every year.
According to Montana method the environmental releases during lean months
are above 10% of natural flow, varying between 57 to 58%.
The average of environmental flow throughout the year (4.72m3/s) is 83.7% of
average annual flow (5.64m3/s) which, therefore, has been adopted for the
project.
IEE Report for 04 MW Thak Nullah Hydropower Plant Appendix - I
- 6 -
REFERENCES
1. Tharme R.F. Global Prospective on Environmental Flow Assessment
Freshwater Institute, University of Cape Town, Rhodes Gift, 7701, South Africa,
Proceedings of a Symposium held in Wellington, New Zealand, August 2003.
2. Environmental Integration of Small Hydropower Plants. ESHA – European Small
Hydropower Association. Rue d‟ Arlon, 63-65, 1040 Brussels, Belgium.
3. CEMAGREF: Agricultural and Environmental Research Institute, Anthony, France.
APPENDIX - II
CONSULTATION WITH STAKEHOLDERS
IEE Report for 04 MW Thak Nullah Hydropower Plant Appendix - II
1
SUMMARY OF CONSULTATION WITH STAKEHOLDERS
Date: February 8, 2012 Venue: Khun Village
Sr. # Main Participants Occupations of Participants
1 Riaz S/o Satmar Farmer
2 Like Zaib S/o Roop Farmer
3 Zaka ullah S/o Ambia Student
4 Muhammad Aslam S/o Mazhar Farmer
5 Mashroob S/o Spat Farmer
Date: February 8, 2012 Venue: Sharat Village
Sr. # Main Participants Occupations of Participants
1 Soboat S/o Saidwal Job
2 Sharif S/o Saidwal Farmer
3 Rafique S/o Rash Khan Farmer
4 Muhammad Nawaz S/o Faiz Khan Farmer
5 Akbar Rehman S/o Gul Khan Farmer
6 Fazal Rehman S/o Gul Khan Farmer
7 Rehman S/o Gul Khan Farmer
Date: February 8, 2012 Venue: Kot Village
Sr. # Main Participants Occupations of Participants
1 Saif-ul-Rehman S/o Samandar Farmer
2 Mujawar S/o Ahmed Farmer
3 Zaboor S/o Ahmed Farmer
4 Allah Din S/o Lajwar Farmer
5 Shuhab Din S/o Lajwa Farmer
6 Saif-ul-Din S/o Jumma Sideeque Farmer
Date: February 8, 2012 Venue: Dawar Village
Sr. # Main Participants Occupations of Participants
1 Baksheer S/o Qadeem Farmer
2 Bazir S/o Sadeem Farmer
3 Zia-ul-Rehman S/o Ibrahim Farmer
4 Hanan S/o Gageer Farmer
5 Rahamdil S/o Ibrahim Farmer
6 Abdul Baqi S/o Ahmed Farmer
IEE Report for 04 MW Thak Nullah Hydropower Plant Appendix - II
2
Date: February 8, 2012 Venue: Sar Village
Sr. # Main Participants Occupations of Participants
1 Zaib Alam S/o Kinkho Farmer
2 Zia-ul-Haq S/o Jalo Farmer
3 Sakeel S/o Roup Farmer
Date: February 8, 2012 Venue: Ghunch Village
Sr. # Main Participants Occupations of Participants
1 Like S/o Ahmed Rauf Farmer
2 Abdul Rehim S/o Abdul Rauf Farmer
3 Nakleem S/o Soan Khan Farmer
4 Adil Zaib S/o Otail Farmer
5 Alam Zaib S/o Otail Farmer
6 Noor Muhammad S/o Otail Farmer
Date: February 8, 2012 Venue: Dar Village
Sr. # Main Participants Occupations of Participants
1 Mustafa S/o Rehmat Farmer
2 Haji Jahangir S/o Hadees Farmer
3 Taj S/o Jumma Khan Farmer
4 Ibrahim S/o Faqeer Farmer
APPENDIX - III
LIST OF LINE DEPARTMENTS VISITED
IEE Report for 04 MW Thak Nullah Hydropower Plant Appendix - III
1
LIST OF LINE DEPARTMENTS VISITED
Date
(2011) Place
Organization / Person
consulted
Position
Reason for visit
Topics discussed
February 9 Chilas Fishery Department
Fida Alam
Assistant Director
- Fisheries development in Thak Nullah
- Catching of fish in the project area
minimal ecological flow, ecological projects
in the area
February 9
Chilas Forest Department
Staff Available and
discussed them
Forest types / trees
Location of forests / pastures
Sustainable use of forests by community
February 9 Chilas Agriculture Department
Shabir ullah
Agriculture Officer
Crop calendar, Crop yield
Irrigation water, Cropping Pattern
February 9 Chilas Health Department
Dr. Jan Alam
Acting M.S. District
Headquarter Hospital
Chilas
Public health situation including water
supply and sanitation conditions in the
project area.
Prevalent diseases
Health Department role in disease
prevention and control
February 9 Chilas Education Department
Hadayatullah
District Inspector of
School
Existing schools in the project area
Education facilities
February 9 Chilas Office of the DC
Shah Zaib Saeed
Deputy Commissioner
LAA - 1894
Role of District Revenue Officer in land
acquisition and payment of compensation
Redress procedures
February 9 Chilas NGO, DCDP Office
Ashfaq Ahmed
Programm Manager
Women status and poverty level in the
area
APPENDIX - IV
1
ENVIRONMENTAL MANAGEMENT PLAN
IEE Report for 04 MW Thak Nullah Hydropower Plant Appendix - IV
- 1 -
ENVIRONMENTAL MANAGEMENT PLAN
Environmental
Concern Objectives
Mitigation Measures (MM)
Recommended
Timing to
Implement MM
Locations to
Implement MM
Responsibility to
Implement MM
Responsibility to
Monitor MM
DESIGN STAGE
1. Project
disclosure
Statutory compliance with
Pak-EPA 1997
IEE report submission to GB-EPA. Detailed design
commencement
Entire project Project Director Secretary GB-
WPD
2. Project
boundaries
change
Compliance with statutory
requirements
P-EPA 1997
Environmental assessment in line with P-EPA
and ADB Guidelines
Update IEE and confirm findings and
recommendations.
Submit revised IEE and EMP to ADB.
Completion of detailed
design
Entire project Contractor, SC Project Director,
Contractor, SC
3. Land
acquisition
Compensation to
affectees
LARP Implementation. Implementation
schedule
Entire project Project Director,
DRO
Secretary GB-
WPD, Project
Director PMU,
ADB
CONSTRUCTION STAGE
1. Loss of
productive
agriculture
Minimize need to acquire
agricultural land for
temporary facilities
Consultation with land owners.
.
Detailed design stage.
Entire project ESDC, DDC Project Director,
SC
2. Waste disposal Sound environmental
management
Design consultants to explore and identify
reuse options.
Design consultant to identify disposal
locations for excavated materials and
requirements in contracts.
Disposal at identified sites
Detail design output.
Within one month of
award of contract or
earlier
Entire project DDC ESDC, SC
3. Plans to control
environmental
and associated
impacts
Avoid impacts from
unplanned activities
Construction contractor to prepare following plans
as part of SSEMP:
Temporary traffic management plan
Drainage and utilities re-provisioning plan
Materials management plan
Submission to ADB
prior to construction
activity
Entire project Contractor ESDC/SC
IEE Report for 04 MW Thak Nullah Hydropower Plant Appendix - IV
- 2 -
Environmental
Concern Objectives
Mitigation Measures (MM)
Recommended
Timing to
Implement MM
Locations to
Implement MM
Responsibility to
Implement MM
Responsibility to
Monitor MM
Waste management plan
Excavated material disposal plan
Tree compensatory planting plan
Noise and dust control plan.
Blasting management plan
Oil spill management plan
4. Loss of trees To avoid adverse
impacts due to removal of
trees.
Payments linked to tree re-establishment and
not to tree removal:
Minimize tree cutting.
Seven new trees will be planted to replace
each cut tree
Select only indigenous tree species for
replacement; no alien invasive species to be
used
One month prior to
and during
construction of
relevant activities
Entire project Contractor ESDC, CSC
5. Soil erosion To minimize excessive
erosion of embankments
and slopes.
Maintain proper slope
Compaction of soil material
Tree plantation on the slope
Construction activities All embankments
and slopes with
protection
measures.
Contractor ESDC,SC
6. Environmental
orientation of
contractor and
workers
Develop capacity to
implement environmental
requirements and
mitigation measures
Contractor tender documents to include
resources and funds for mitigation measures
as detail in No. 3 of Construction Stage.
The contractor shall be responsible for
implementation of an affective environmental
monitoring and reporting system using
checklists of all contractual environmental
requirements and EMP
Before
commencement of
construction work.
Refreshers at early
stages of construction
Construction Sites Contractor, ESDC Project Director
IEE Report for 04 MW Thak Nullah Hydropower Plant Appendix - IV
- 3 -
Environmental
Concern Objectives
Mitigation Measures (MM)
Recommended
Timing to
Implement MM
Locations to
Implement MM
Responsibility to
Implement MM
Responsibility to
Monitor MM
7. Exploitation
handling,
transportation and
storage of
construction
materials
Minimization and
avoidance of adverse
environmental impacts
due to construction
material exploitation,
handling,
transportation and
storage
Contract documents to specify:
Fuel and bulk storage covered with tarpaulin
against wind and away from the residential
area.
Proper maintenance of transport vehicles
Work areas to be re-vegetated and
landscaped, wherever appropriate, to minimize
erosion and to avoid creating hazards for
people and livestock
Construction activities A list of routes of
transport of
construction
material is to be
prepared for the
contract and
agreed one month
prior to construction
activities.
Contractor ESDC, SC
8. Explosive
Material for
Blasting
To minimize the damage
around specific site.
To control the noise level
To ensure the workers‟
safety.
Use required quantity of explosive material for
blasting.
Blasting should be at day time and in bounded
area.
Handle the explosive material under
manufacturer\s specifications and Explosive
Act 1884, of the government.
During excavation
activities such as
tunnel excavation etc
At tunnel sites Contractor ESDC, SC
9. Air quality To minimize particulate
matter released to the
atmosphere.
Stockpiled soil and sand to be sprinkled with
water
Stockpiled soil and sand shall be slightly
wetted before loading, particularly in windy
conditions.
Fuel-efficient and well-maintained haulage
trucks shall be employed to minimize exhaust
emissions.
The road near communities shall be sprayed at
Construction activities. All construction
sites
Contractor to
comply with
NEQS
ESDC, SC
IEE Report for 04 MW Thak Nullah Hydropower Plant Appendix - IV
- 4 -
Environmental
Concern Objectives
Mitigation Measures (MM)
Recommended
Timing to
Implement MM
Locations to
Implement MM
Responsibility to
Implement MM
Responsibility to
Monitor MM
least twice per day with water to suppress
dust.
Concrete batching plants, asphalt plant and
rock crusher activities to be controlled (e.g.
asphalt hot mix plants should not be located
within 500m of any sensitive receiver, river-
bank or irrigation channel but located at
convenient sites nearby but downwind of and
at least 500nm from sensitive receptors such
as schools and hospitals.
10. Construction
Waste Disposal
Minimize the impacts
from construction waste
disposal.
Preparation of waste management plan
including estimates of amounts and types of
construction waste to be generated by the
project.
Identify opportunities for waste to be reused in
the project or by other interested parties.
Identifying potentially safe disposal sites close
to the project or those designated sites in the
contract.
Waste shall not be burned as open burning Is
contrary to good environmental practice.
One month prior to
construction activities
quarterly.
All construction
sites
Contractor
GB WPD
ESDC, SC
11. Water quality Minimization of adverse
impacts on water quality
Storage of lubricants, fuels and other
hydrocarbons more than 50m away from water
bodies.
Proper disposal of solid waste from
construction activities and labor camps.
Covering the construction material and spoil
stockpiles with a suitable material to reduce
material loss and sedimentation.
Avoiding stockpiling to water bodies.
Construction activities Entire project Contractor ESDC,SC
IEE Report for 04 MW Thak Nullah Hydropower Plant Appendix - IV
- 5 -
Environmental
Concern Objectives
Mitigation Measures (MM)
Recommended
Timing to
Implement MM
Locations to
Implement MM
Responsibility to
Implement MM
Responsibility to
Monitor MM
Excavated material shall not be stored where
natural drainage will be disrupted.
Borrow sites should not be close to sources of
drinking water.
12. Worker camp To ensure that the worker
facilities does not
adversely affect the
surrounding environment
and residents in the area.
Felled trees and other cleared or pruned
vegetation should not be burned.
LPG to be provided for cooking at worker
camps.
Drinking water and sanitary facilities shall be
provided for employees.
Solid waste and sewage shall be managed
according to the waste management plan.
The Contractor shall document that all liquid
and solid hazardous and non-hazardous waste
are separated, collected and disposed of
according to the given requirements and
regulations.
Entire project
construction activities
Construction
camps
Contractor EDSC,SC
13. Workers‟
Safety
To ensure safety of
workers and equipment.
Placing adequate warning signs.
Providing workers with PPE .
Establish all relevant safety measures as
required by law and good engineering
practices.
First aid facilities should be available at
construction sites with at least one qualified
first-aider
During construction Workers camp
Construction sites
Contractor ESDC,SC
14. Traffic
Condition
Minimize disturbance of
vehicular traffic &
pedestrians during
haulage of materials,
spoil, equipment and
Implement traffic management plan.
Formulation and implementation of a
construction related traffic management plan.
Assign traffic control personnel.
Vicinity of residential areas, schools to be
Day Time during
construction activities
Existing access
road
Construction sites
Contractor ESDC,SC
IEE Report for 04 MW Thak Nullah Hydropower Plant Appendix - IV
- 6 -
Environmental
Concern Objectives
Mitigation Measures (MM)
Recommended
Timing to
Implement MM
Locations to
Implement MM
Responsibility to
Implement MM
Responsibility to
Monitor MM
machinery.
considered for installation of traffic warning
signs and speed bumps.
No blocking access to the road
15. Restoration of
Temporary
land
All vacated sites should
be restored to pre-project
conditions
All construction sites, all debris and waste shall
be removed.
All temporary structures, including office
buildings, shelters, waste receptacles and
toilets shall be removed.
All vacated sites should be restored to pre-
project conditions
At conclusion of the
project
All temporary
acquired sites
Contractor, Project director
OPERATIONAL STAGE
1. Water quality Maintain the quality and
quantity of water to be
supplied to community.
The drinking water quality used by the
community in the project area shall be
monitored.
Starting from the
construction period
and continuing for the
first three years of the
project operation.
Thak Nullah Chief engineer
GB WPD
Chief engineer
GB WPD
2. Fishery To document the fishing
activities in the Kachura
Lungma
Monitor fishery resources. Starting from the
construction period
and continuing for the
first three years of the
project operation.
Thak Nullah Director, fishery
department,
Chief engineer
GB WPD
PHOTOGRAPHIC DOCUMENTATION
IEE Report for 04MW Thak Nullah Hydropower Plant
- 1 -
A- Photographs Showing Meetings with Officers of Line Departments
Meeting with DC Diamer in his Office Meeting with Assistant Director District Diamer in
his Office at Chilas
Discussion with the Agriculture Research Officer
A view of Meeting with Inspector Education
A view of meeting with Acting M.S. District
Headquarter Hospital Chilas
Meeting with Mr. Ashfaq
Representative of NGO in Chilas
IEE Report for 04MW Thak Nullah Hydropower Plant
- 2 -
B- Photographs Showing Scoping Sessions / Consultations with Locals of the Project Area
Discussion with PMU Staff at Power House Site Discussion with PMU Staff at Weir Site
Consultation with Locals at Dewary Village
Consultation with Locals in Khun Village
Consultation with Locals in Khun Village Local consultation at Weir Site
IEE Report for 04MW Thak Nullah Hydropower Plant
- 3 -
C- Photographs Showing Sites of Various Project Components
Power House Site Intake Weir Site
IEE Report for 04MW Thak Nullah Hydropower Plant
TOC - I
INITIAL ENVIRONMENTAL EXAMINATION
04MW THAK NULLAH HYDROPOWER PROJECT
Table of Contents
ACRONYMS
EXECUTIVE SUMMARY ........................................................................................................................ 1
I. INTRODUCTION .................................................................................................................... 1
A. Environmental Regulatory Compliance 1
B. Environmental Category of Thak nullah HPP 2
C. Objectives and Scope of IEE 3
D. Report Structure 3
II. PROJECT DESCRIPTION ..................................................................................................... 4
A. Background and Justification 4
B. Location 4
D. Project Components 5
III. ENVIRONMENTAL BASELINE ............................................................................................. 8
A. Field Survey 8
B. Physical Environment 8
C. Air Environment 10
D. Biological Environment 10
E. Social and Cultural Environment 12
D. Indigenous People 17
H. Gender Impacts 18
IV. ENVIRONMENTAL IMPACTS AND MITIGATION .............................................................. 19
A. Design Related Impacts 19
B. Construction Related Impacts 20
D. Operation Related Impacts 25
E. Positive Impacts 28
V. STAKEHOLDERS CONSULTATION .................................................................................. 30
A. Identification of Stakeholders 30
IEE Report for 04MW Thak Nullah Hydropower Plant
TOC - II
B. Consultation Process 30
C. Summary of Consultation 30
D. Meetings with Officers of Line Departments 31
E. Future Consultation 31
F. Procedure for Public Disclosure 31
VI. INSTITUTIONAL REQUIREMENTS AND ENVIRONMENTAL MANAGEMENT PLAN.... 32
A. Institutional Arrangement 32
B. Complaints and Grievances Redress 32
C. Environmental Review and Approval 33
D. Environmental Management Plan 33
E. Monitoring and Evaluation 35
VII. ENVIRONMENTAL RELATED COSTS ............................................................................... 38
VIII. FINDINGS AND RECOMMENDATIONS ............................................................................. 39
IX. CONCLUSIONS ................................................................................................................... 41
TABLES
Table 1: Project Components
Table 2: Climatic Data of Chilas
Table 3: Record of Flow in Thak Nullah (1963-1993)
Table 4: Socio-Economic Indicators of Villages Falling around Project Area
Table 5: Sources of Income in Surveyed Villages
Table 6: Average Annual Income per Household in Surveyed Villages
Table 7: Distances of Settlements/Sensitive Receptors from the Weir and Power House Sites
Table 8: Flow in Thak Nullah (1963-1993)
Table 9: Environmental Flow Requirements (m3/s) Based on CEMAGREF Formula
Table 10: Environmental Flow Requirements (m3/s) in Thak Nullah Based on Montana Method
Table 11: Environmental Monitoring Plan
Table 12: Environmental Related Cost
FIGURES:
Figure 1: Project Location in the Map of Pakistan
Figure 2: Project Location in the Map of Chilas
Figure 3: Layout Plan
Figure 4: Villages/ Communities in the Vicinity of the Project Area
IEE Report for 04MW Thak Nullah Hydropower Plant
TOC - III
APPENDICES:
Appendix – I Assessment of Environmental Flow
Appendix – II List of Participants of Local Consultation
Appendix - III List of Officials of Line Departments Visited
Appendix – IV Environmental Management Plan
PHOTOGRAPHIC DOCUMENTATION
IEE Report for 04MW Thak Nullah Hydropower Project
i
LIST OF ACRONYMS
ADB : Asian Development bank
amsl : above mean sea level
DP : Affected Person
BHU : Basic Health Unit
CAS : Compulsory Acquisition Surcharge
CSC : Construction Supervision Contractor
DCO : District Coordination Officer
DDC : Detailed Design Contractor
DFO : Divisional Forest Officer
EIA : Environmental Impact Assessment
EMP : Environment Management Plan
EO : Environment Officer
EPA : Environmental Protection Agency
ESDC : Environment and Social Development Cell
Ft. : Feet
GB : Gilgit Baltistan
GRC : Grievance Redress Committee
GWh : Giga Watt Hour
Ha/ha : Hectare
HH : Household
HPP : Hydropower Project
IEE : Initial Environmental Examination
Km : Kilometer
KPK : Khyber Pakhtunkhwa
kV : Kilo Volt
kW : Kilowatt
LAA : Land Acquisition Act (1894)
LAC : Land Acquisition Collector
LARP : Land Acquisition and Resettlement Plan
GB-WPD : Gilgit Baltistan Water and Power Department
IEE Report for 04MW Thak Nullah Hydropower Project
ii
LIST OF ACRONYMS
NEPRA : National Electrical Power Regulatory Authority
NGO : Non-Government Organization
P&D : Planning and Development Department
PD : Project Director
PES : Pakistan Engineering Services (Private) Ltd.
PMU : Project Management Unit
PRs : Pakistani Rupees
RP : Resettlement Plan
TOR‟s : Terms of Reference
UC : Union Council
WAPDA : Water and Power Development Authority
WHO : World Health Organisation