32
SEEPAGE ANALYSIS UNDERNEATH DIYALA WEIR FOUNDATION TERM PAPER PRESENTATION CEL-754 Geotechnical Processes in Rock Engineering Presented by: Saravanan Winfred George

Seepage analysis final

Embed Size (px)

DESCRIPTION

Design of Cutoff for barrages

Citation preview

  • 1. Presented by:SaravananWinfred George

2. Introduction The construction of Diyala weir commenced in 1966 and wascompleted in 1969. The structure includes a road bridge and new canal head works. This structure is located 7km downstream from the Hamrendam, approximately 130 Km northeast of Baghdad, near the townof Sidor. The main purpose of this Weir is to divert outflow of the Hamrendam to the Khalis and Sadr Al-Mushtarak canals for irrigation. 3. Section of Diyala Weir 4. The Problem Seepage of water is one of the major problems, which has an effectupon hydraulic structures. Diyala weir structure is suffering from such engineering problems.It was taken as a case study and it had been checked against pipingand uplift pressure by using numerical model. The effect of removing one of the three sheet piles rows wasstudied and evaluated to investigate the quantity of seepage, upliftpressure and expected exit hydraulic gradient for these cases. 5. Input Data for Seepage Analysis Total length of a weir foundation equals 24.5 m. Depth of 1st row of sheet piles (upstream sheet pile) equals 4.5 m. Depth of 2nd row of sheet piles (middle sheet pile) equals 2.5 m. Depth of 3rd row of sheet piles (downstream sheet pile) equals 3.5 m. Unit weight of the soil underneath Diyala weir equals 18 kN/m2. Permeability for clay soil underneath Diyala weir equals 1e-5 m/s. Depth of impervious layer below Diyala weir foundation equals 11mfrom the bed level (B.L). Soil foundation underneath the weir is saturated, isotropic andhomogenous. 6. Seepage Analysis by FEA 7. Seepage Analysis by FEA (Contd.) 8. FEM Model Properties The Eight noded quadrilateral elements were used to idealize thevertical cross section of permeable soil underneath Diyala weirwith the following Mesh Properties,Mesh type: gradedAnalysis Type: Plane StrainNumber of elements: 1278 Solver Type: Gaussian Elimination Maximum Number of Iterations: 500Number of nodes: 3989 Tolerance: 1e-006 9. Diyala Weir Model in Phase2 with all Cutoff 10. Seepage Results from Phase2 with all cutoff 11. 6.005.004.003.00 15.00 16.00 17.00 18.00 19.00 20.00 21.00 22.00 23.00 24.00 12. Uplift Pressure (Contd.) The thickness of weir impervious floor at any point should notbe less than 2/3 of uplift pressure. The required floor thickness for points below downstream floorand the provided floor thickness are tabulated below, 13. Uplift Pressure along Base Slab 0.00 4.00 8.00 12.00 16.00 20.00 24.0062.0063.0064.0065.0066.0067.0068.00 14. Floor ThicknessDistanceFloor Elevation Total Pressure at Required Floor Provided FloorUplift Pressure (m) Calculated by Diffalong D/s (m) (m) Base (m)Thickness (m)Thickness (m) Authors0.00 61.50 68.00 6.504.33 - 6.001.671.00 60.50 66.05 5.553.70 - 5.922.222.00 60.50 66.03 5.533.69 - 5.581.903.00 60.50 66.01 5.513.67 - 5.241.574.00 61.50 65.51 4.012.67 - 3.911.245.00 61.50 65.50 4.002.66 - 3.580.916.00 61.33 65.47 4.142.76 - 3.410.657.00 61.00 65.43 4.432.95 - 3.410.458.00 60.67 65.36 4.693.13 - 3.400.289.00 60.33 65.27 4.943.29 - 3.400.11 10.00 60.00 65.17 5.173.45 - 3.40-0.05 11.00 59.67 65.05 5.393.59 - 3.40-0.19 12.00 59.33 64.92 5.593.73 - 3.40-0.33 13.00 59.00 64.76 5.763.84 - 3.40-0.45 14.00 59.00 64.61 5.613.74 - 3.06-0.68 15.00 59.00 64.46 5.463.64 2.492.73-0.92 16.00 59.00 64.33 5.333.55 2.412.50-1.05 17.00 59.00 64.19 5.193.46 2.342.50-0.96 18.00 59.00 64.06 5.063.37 2.262.50-0.87 19.00 59.00 63.91 4.913.27 2.222.50-0.77 20.00 59.50 63.81 4.312.87 1.932.00-0.87 21.00 59.50 63.73 4.232.82 1.892.00-0.82 22.00 59.50 63.66 4.162.77 1.852.00-0.77 23.00 59.50 63.61 4.112.74 1.832.00-0.74 24.00 59.50 62.05 2.551.70 1.002.000.30 15. Exit Gradient (Contd.) The critical hydraulic gradient (icr ) was calculated from, The unit weight of saturated soil underneath the weir structure is18 kN/m2 and unit weight of water 9.807 kN/m2. The calculatedvalue of the critical hydraulic gradient is 0.835. This lead to factor of Safety against piping equals; The exit gradient from the Analysis is 0.17, lead to Fs = 4.9. A factorof safety (Fs) of 4.9 is considered adequate for the safe performanceof the Diyala weir structure against piping 16. Exit Gradient Plot from Phase2 with all cutoffThe Exit Gradient Value from SEEP / W is 0.17The Exit Gradient from Phase 2 is 0.18 17. Pressure Plot with No U/S cutoff 18. Exit Gradient Plot with No U/S cutoff The Exit Gradient Value from SEEP / W is 0.19 The Exit Gradient from Phase 2 is 0.24 19. Pressure Plot with No U/S cutoff 20. Pressure Plot with No Middle cutoff 21. Exit Gradient Plot with No Middle cutoff The Exit Gradient Value from SEEP / W is 0.17 The Exit Gradient from Phase 2 is 0.20 22. Pressure Plot with No End cutoff 23. Exit Gradient Plot with No End cutoff The Exit Gradient Value from SEEP / W is 0.21 The Exit Gradient from Phase 2 is 0.25 24. Seepage and Exit Gradient The below results of quantity of seepage and exit gradient for eachcase as one sheet pile assumed to be removed.Without Ist Sheet PileWithout IInd Sheet PileWithout IIIrd Sheet PileDescriptionAuthors Ours AuthorsOurs Authors OursQuantity of Seepage1.10E-05 1.33E-05 9.62E-061.19E-05 1.05E-05 1.31E-05 (m3/s) Exit Gradient0.190.240.17 0.2 0.21 0.25Factor of Safety4.4 3.5 4.94.2 3.93.34 It is noted from the results of removing the first sheet pile is moreeffective on increasing of seepage while removing the third sheetpile is more effective on increasing of exit gradient values but thefactor of safety against piping (Fs) for all values represent safesituation. 25. Summary of ResultsThe following results are obtained by using 2-D finite elementmodel of Diyala Weir, Foundation of Diyala weir is safe against piping and any excessiveuplift pressures. The defect in one or more of the three sheet piles has causeddisplacement of the downstream floor (apron slab), cracking inweir foundation and scour of soil underneath the weir, due toincreasing the quantity of seepage, uplift pressure and exitgradient. 26. Summary of Results (Contd.) Investigation of failure leads to suspect that the sheet piles inupstream is exposing, and could be corroded and defected. The defects in the first row of sheet piles are more effective onincreasing uplift pressure and quantity of seepage than the othertwo rows of sheet piles while defects in the last rows of sheet pilesare the most effective on increasing the exit hydraulic gradient. 27. Conclusion This research suggests solutions for preventing expected weirfoundation failure problems by: Improving the seal between elements of the sheet piles andrepairing any defects. Sealing any cracks in the weir foundation by injection of chemicalmaterials or cement grout. The Same Problem also validated with another FEM software(Phase2) successfully. 28. Diyala Weir Model in SEEP/W 29. Seepage Results from SEEP/W