Seminar Agenda• 11:40 – 11:50 – Quick Introductions• 11:50 – 12:20 – OMNINET & OMNITRACKER background• 12:20 – 12:45 – Lunch• 12:45 – 1:30pm – OMNITRACKER Project & Requirements• 1:30 – 1:45pm – Q&A and General Wrap up
Copyright 2003 Kifinti Solutions Inc.
Who are we?
Kifinti – means “how are you?” in Maltese”
20+ strong (Toronto, Ottawa, and Montreal)
Go to partner for several top technology vendors
Leading technology, Best Practices & expertise, and Local Support, Service & Training
Copyright 2003 Kifinti Solutions Inc.
What we do?• Service Management – “PROCESS LAYER”
• Project Management, ITIL, IT Support , Customer Service and process that needs to be automated• ITAM, Asset Management
• Infrastructure Management – “MANAGEMENT LAYER”• Inventory Discovery (HW & SW), Software License Compliance• Software Distribution & OS Imaging• Patch & End Point Management & Security Policy Enforcement
• Identity & Access Management – “SECURITY LAYER”• User Request approval and provisioning, Single Sign On• Security Information & Event Management
•Network Management – “MONITORING LAYER”• Integration of Monitoring technologies with ITSM strategy
Copyright 2003 Kifinti Solutions Inc.
Our Value add?• Free Training
• No charge training on ITSM, IPCM, HEAT, & OTHER PRODUCTS
• Experts blended with Ongoing Support & Service• Ongoing Assistance Program• Local User Groups• Ongoing Webinars
• Client Collaboration• Encourage collaboration & sharing amongst clients• Leveraging Investments
• Experienced, Involved & Local Account Management• Heavily involved in verticals like Pension Plans• Senior account teams
Copyright 2003 Kifinti Solutions Inc.
[email protected] 2003 Kifinti Solutions Inc.
More Customers…
[email protected] 2003 Kifinti Solutions Inc.
And Still More Customers…
[email protected] 2003 Kifinti Solutions Inc.
Ok enough with the customers!
Seminar Summary• Learn “Kifinti” means “How are you in Maltese”• OMNITRACKER Project & Requirements Management technology• OMNITRACKER is more then a good PM or RM APP…this is a
WORKFLOW platform• This platform is something that you can expand upon
– ITSM– TASK MANAGEMENT– RISK MANAGEMENT– CONTRACT MANAGEMENT– CUSTOMER SERVICE– AND MORE
Copyright 2003 Kifinti Solutions Inc.
18.04.2023 - 13 - © OMNINET
Introduction to OMNITRACKER Project Management Center &
Requirement Management Center
18.04.2023 - 14 - © OMNINET
Introduction to OMNINET
OMNITRACKER: Concept, Architecture, USPs
Project Management Center
Requirement Management Center
Demo
18.04.2023 - 15 - © OMNINET
Brief history of OMNINET
Foundation 1995
1997 -1998 Development of OMNITRACKER as QM-System / Defect-Tracking for software development projects
1999 OMNITRACKER was released as market-ready software solution, first customer implementations
2000 OMNITRACKER provides ITIL compliant
service management processes. Setting up the sales of OMNITRACKER
now 12 application templates for different
business processes > 35.000 concurrent clients > 450 customer installations 100+ employees (80+ in Eckental)
OMNINET Headquarter
18.04.2023 - 16 - © OMNINET
Partner Strategy
Partner coverage today • Germany• Austria• Switzerland• Benelux• Canada• Russia• Denmark• Czech Republic• Slowenia• France• Hungary
• UK • Ireland• Romania• Bulgaria• Greece• UAE• Saudi-Arabia• Australia• New Zeeland• Kuwait• Iran
18.04.2023 - 18 - © OMNINET
Introduction to OMNINET
OMNITRACKER: Concept, Architecture, USPs
Project Management Center
Requirement Management Center
Demo
18.04.2023 - 19 - © OMNINET
OMNITRACKER, a flexible IT workflow platform
ITSM
SOM
PMC
SEC
SMC
CMCRMC
OMNITRACKER
…
ERP-Software
3rd partySoftware
OMNITRACKER provides an organization with the platform to drive their business processes integrated to other success-critical applications.
In combination with ERP-Systems
and other 3rd-party-Software,
OMNITRACKER allows the
customers to use their resources
in an optimal way.
18.04.2023 - 20 - © OMNINET
Core System
Core Components
Templates
Applications
OMNITRACKER: Platform Architecture
Business Platform
Clients
Windows, web and mobile clients
Data Im- / Export
Web-Service
Automation Interface
Very powerful integration capabilities
Release compatibility guaranteed by contract
18.04.2023 - 21 - © OMNINETCore System
technical overview
Architecture
Core Components
Templates
Clients
IT Service Management
Center
Requirements Management
Center
Sales Management
Center
Document Management
Stock & Order Management
Systems Engineering
Center
Customer Care Center
Contract Management
Center
Project Management
Center
Risk Management
Task Management
Dispatch Center
individual Template
TemplateIm-/Export
18.04.2023 - 22 - © OMNINETCore System
technical overview
Architecture
Core Components
Templates
Clients
eMail-Gateway
Web-Gateway Scanning-Gateway
CTI-Gateway
Interface Bus GIS-Gateway
Dashboard
18.04.2023 - 23 - © OMNINET
OMNITRACKER: Platform Architecture
In OMNITRACKER both objects and business rules are stored in ‘Folders’. Adding additional Application Templates means: adding new Folders.
18.04.2023 - 24 - © OMNINET
Introduction to OMNINET
OMNITRACKER: Concept, Architecture, USPs
Project Management Center
Requirement Management Center
Demo
18.04.2023 - 25 - © OMNINET
OMNITRACKER Project Management Center
Administrative basics
All OMNITRACKER templates use the same ‘Master Data’.
18.04.2023 - 26 - © OMNINET
OMNITRACKER Project Management Center
For hour registration a ‘Personnel Record’ needs to created first, linked to a user account.
Every month, a new ‘Time Account’ is created automatically, to group time entries per month.
Time Entries are linked to a ‘Service’, a Time Account and an Activity
Administrative basics
As a result: OMNITRACKER can provide automated analyses and views based on registered time entries, per person, per month, per project and per service.
18.04.2023 - 27 - © OMNINET
– Supports the full project lifecycle– Calculation and monitoring of crucial parameters (deliverable, deadline, budget, quality)– Based on concepts developed by the Project Management Institute (PMI) and methods of
PRINCE2 (Projects IN Controlled Environments)
OMNITRACKER Project Management Center
Main processes supported: Project initiation Project planning Project execution Project monitoring Project closure
Other supported processes: Employee time recording and billing
of travel expenses Reporting Project documentation
OMNITRACKER Project Management basics
Existing links to other OT applications: IT Service Management Requirement Management System Engineering Sales Management Risk Management
18.04.2023 - 28 - © OMNINET
OMNITRACKER Project Management Center
Project
Project Phase
Activity
Time Entry
Travel Expense
Time Account
Employee Master Data
Contract
Budget Control
Planning
Time Registration
Project Management Center
Contract / Project layerfor scope definition and approval process
Project-Phase layerfor phase- and budget planning and control
Activity layerto structure the work in easier manageable parts, for resource planning and time scheduling
Time Entry and Travel Expense layer for recording time efforts and travel expenses
PMC database model: layered approach
18.04.2023 - 29 - © OMNINET
OMNITRACKER Project Management Center
New projects can be created manually or using the project wizard, to create a project out of a pre-defined project template.
Project structure and planning
Activities can be planned as successors/predecessors and parents/children.
Resources can be scheduled taking utilization into account
18.04.2023 - 30 - © OMNINET
OMNITRACKER Project Management Center
Set workflow state to „Approved“ to allow execution of a project component
Project execution Each object (project, phase, activity) has its own workflow.
Each object (project, phase, activity) can have another responsible person.
Hour registration can only be done, when the related Activity is set to ‘approved’ and by assigned employees.
18.04.2023 - 31 - © OMNINET
OMNITRACKER Project Management Center
Hour Registration
Via the ‘calendar view’
Or fast entry, via the ‘grid view’
Only on assigned and approved Activities!
18.04.2023 - 32 - © OMNINET
OMNITRACKER Project Management Center
Two thresholds per project-phase to escalate
The Responsible gets a notification e-mail if thresholds are exceeded
Color scheme used for visualization
OMNITRACKER Budget Monitoring, at Project Phase
18.04.2023 - 33 - © OMNINET
On Activity Level: based on completion% and registered hours, the expected total required hours are visualized. Red: > expected, green: < expected
OMNITRACKER Project Management Center
Actual Project Phase parameters calculated based on: Estimated effort versus registered effort Completion% Planned end date versus expected end date Internal hourly rate
OMNITRACKER Budget Monitoring: Earned Value Analysis (EVA)
18.04.2023 - 35 - © OMNINET
OMNITRACKER Project Management Center
Personnel Capacity Utilisation grouped by projects
Time recording totalTime recording invoicable
18.04.2023 - 36 - © OMNINET
Introduction to OMNINET
OMNITRACKER: Concept, Architecture, USPs
Project Management Center
Requirement Management Center
Demo
18.04.2023 - 37 - © OMNINET
Covers the entire process, from elicitation of requirements up to release of their implemented functions
Workflow based process control Generic information model, easy adaptable
and extensible Common platform for customer (ordering
party) and the contractor: Client Portal Clear, logged communication between the
involved party HOOD INSIDE certified
OMNITRACKER Requirement Management Center
OMNITRACKER Requirement Management Center, basics
Problem area
Solution area
Customer Requirements
System Requirements
Design Requirements
Sub-System
System Requirements
Design Requirements
Generic Information Model(according to HOOD)
18.04.2023 - 38 - © OMNINET
OMNITRACKER Requirement Management Center
Relation with other OT applications
Out-of-the-box integration with: OT Project Management Center OT System Engineering (defect management) Risk Management
18.04.2023 - 39 - © OMNINET
OMNITRACKER Requirement Management Center
Customer Requirements: Describe from a customer´s point of view what
functionality the system has to support Define specific objectives, which have to be fulfilled
by implementation
System Requirements: Describe what has to be delivered to satisfy the
Customer Requirements
Design Requirements: Define in detail how to realize the
System Requirements
Modeling of Requirements
Customer Requirement
n
mn
m
System Requirement
n
mn
m
Design Requirement
n
m
Several layers of abstraction
Activity
18.04.2023 - 40 - © OMNINET
OMNITRACKER Requirement Management Center
Requirement Specification Elicitation Specification Analysis Review
Realization Implementation Test Release
.
Workflow: Requirement
Requirement workflow
18.04.2023 - 42 - © OMNINET
OMNITRACKER Requirement Management Center
Administration and versioning of specifications
Supporting different specification types, e.g. Customer Requirements Specification
(CRS) System Requirements Specification (SRS) Design Requirements
Specification (SDS)
Grouping and structuring of requirements, information and graphics
Automatic creation of documents in different file formats (e.g. MS Word, PDF, RTF, MS Excel, XML)
Tree view: Specifications
Specifications (Requirement Documents )
18.04.2023 - 43 - © OMNINET
OMNITRACKER Requirements Management Center
01. Specifications Creation of a new system specification Definition of the structure of the specification
(optionally using a template) Creation of part specifications and chapters Printing of the specification
02. Content Management of individual requirement
specifications– Customer, System and Design
Requirements (CREQs, SREQs, DREQs) Management of optional content
– for example Information objects, Use Cases
03. Stakeholders Creation and management of Stakeholder
details
04. Roles Predefined roles within Requirements
Management Center (RMC)
Table of Contents View
Content
Persons
Folder structure
18.04.2023 - 44 - © OMNINET
OMNITRACKER Requirement Management Center
Webportal
Used to allow external users access, so they can create new requirements edit existing requirements add documents as attachments retrieve the state of the process perform state transitions
All interaction and communication is transparent and logged
Enables the client to take part in creating, approving and testing of requirements
The web portal offers extensive search and filter features for efficient usage
Client (web) portal
18.04.2023 - 45 - © OMNINET
OMNITRACKER Requirement Management Center
Requirement collection options
Top down: creating a Specification, based on an existing template
Bottom up. By fast entry of requirements, using the ‘grid view’ and later collecting, grouping and reorganizing them in a Specification
With help of the customer via the web portal: let the client define the scope and later start adding details based on that.
A combination of these methods.
18.04.2023 - 46 - © OMNINET
Integration PMC, RMC, SEC and RM
1. Activities contain links to Requirements
2. Requirements contain links to test cases and bugs
3. Projects contain links to Risks
Estimated effort Requirements versus estimated effort Activities
Registered hours versus estimated effort, on Activity level and Requirement Level
State of activities => state of related Requirements
Which requirements are linked to Activities and which not (scope check)?
All people involved work in the same tool: Business Analysts, Project Managers, Developers, Testers, Clients, Contractors ....
18.04.2023 - 47 - © OMNINET
Customer benefits
OMNITRACKER is…
… fast- ready to use business-templates- standardized project-model - step-by-step implementation- quick return on investment
… flexible– scalable– easily extendable
(licenses / processes)– highly integrable / open interfaces– configurable and adaptable
(without programming)
… fair- many license-models (buy, rent,
pay as you use, SaaS)- clear cost-model- contractual warranted release-
compatibility- customer-influence on product
development via RFC- know-how-transfer to customer
18.04.2023 - 48 - © OMNINET
Introduction to OMNINET
OMNITRACKER: Concept, Architecture, USPs
Project Management Center
Requirement Management Center
Demo
18.04.2023 - 50 - © OMNINET
OMNINET GmbHD-90542 Eckental
[email protected] – http://www.omninet.de
OMNINET Austria GmbHA-1030 Wien
[email protected] – http://www.omninet.at
OMNINET Technologies NV/SAB-3018 Leuven
[email protected] – http://www.omninet.be
OMNINET NederlandNL-2517 Den Haag
[email protected] – http://www.omninet.nl
OMNINET RussiaRUS-Moscow 121099
[email protected] – http://www.omninet.ru
OMNINET GmbH (Schweiz)CH-3072 Ostermundigen
[email protected] – http://www.omninet.ch
OMNINET Software Solutions
18.04.2023 - 51 - © OMNINET
Introduction
Company data
• Founded in 1995, private company, no debt
• 100+ employees (80+ in Eckental)
• Business areas • Uniquely flexible suite of OMNITRACKER
ITSM and Business Process applications
• Including specific application developments using the same OMNITRACKER core suite
• Consistent growth, 450+ active customers supporting in-excess of 35.000 concurrent users
• All core development in one place
OMNINET Headquarters in Eckental
18.04.2023 - 52 - © OMNINET
General
– Requirements Management and System Engineering process tool, allowing for easy and quick implementation, enabling fast ROI
– Generic information model, easily adaptable to customer processes
– Supports several levels of abstraction (e.g. Customer-, System- and Design-Requirements)
– Provides a common understanding between customer and contractor about the system to be developed and its functionality and technical features
– Grouping and structuring of requirements as specifications (documents)
– Efficient OMNITRACKER data structures support linking of requirements and their visualization across several levels of abstraction
OMNITRACKER Requirements Management Center Summary of technical features 1/3
18.04.2023 - 53 - © OMNINET
– Control the completeness of a derivation (traceability of requirements) using extensible filter and search mechanism
– Automatic creation of documentation with report/print-out functionality for specifications, requirements and use cases
– Entire documentation and logging of interactions between customer and contractor
Process control
– Role-based authorization concept
– Workflow-based process control for specifications, requirements and use cases
– Workflow-based escalations
Miscellaneous
– Web login for external access
– Integration of additional OMNITRACKER solutions
OMNITRACKER Requirements Management Center Summary of technical features 2/3
18.04.2023 - 54 - © OMNINET
Definition of requirements
– Define system scope
– Management of stakeholders, their roles and issues
– Elicitation, specification and analysis of requirements
– Allows for a fast input of requirements and derived requirements in grid view (without exchanging the form)
– Management and support of review and release process
– Management and versioning of requirements
– Recording and administration of use cases
Realization of implementation
– Management of the implementation of requirements
– Providing requirements for approval by the customer
– Recording and providing test results
– Approval of the implementation by the customer's project manager
OMNITRACKER Requirements Management Center Summary of technical features 3/3