Scaling Up Production - University of Nottingham...–Fermentation attemperation –FV crash cooling...

Preview:

Citation preview

  • 24/10/2017

    1

    Scaling Up Production

    Dick Murton

    www.murtonbrewing.com

    dickmurton@aol.com

    Why upsize?

    • Successful business – Insufficient brewhouse capacity

    • Mash tun too small

    • Insufficient or no chilled liquor

    • Insufficient HLT capacity

    – Insufficient tank capacity • FVs, CTs, BBTs

    – Insufficient packaging capacity

    – Paying for excessive hours for additional revenue

    – No personal time outside work

    http://www.murtonbrewing.com/http://www.murtonbrewing.com/

  • 24/10/2017

    2

    Other example drivers • Need to replace equipment anyway

    – Unsafe – Poor quality or damaged equipment – Not suitable for beer / yeast types used – Cannot produce consistent quality beer

    • Lack of insulation • Cannot control liquor or beer temperatures accurately • Infection prone • Cannot pressurise tanks for carbonation

    • Poor extracts • Need to move anyway

    – lease expiring – limited space for existing capacity – limited access – permit problems

    Possible alternatives

    • Contract brew

    • Cuckoo brew

    • Double brew and rent larger FVs / CTs

    • e.g. ninkasi tank rentals

    • Use contract packager for bottles / cans

    – separate company

    – mobile packager

  • 24/10/2017

    3

    Deciding what you need

    For a given brewery size and style, the brewing recipes should be used to determine brewery design, e.g.

    • Turnaround time

    • Numbers and capacities of vessels

    • Vessel dimensions and design features

    • CIP facilities

    • Extract performance

    • Cask, keg, bottle, can storage

    – empties, secondary packaging materials

    – full packages

    Level of spec

    • Detail the required performance criteria • Will the kit you are considering achieve these? • Make sure you can safely and effectively clean &

    sanitise it

    • Automation, welded cladding will cost extra capital, but probably save revenue costs, physical effort, time

    • Will probably improve consistency & quality and possibly extract performance

  • 24/10/2017

    4

    Grist preparation

    Pre-ground malt • Convenient, but some consider it inconsistent

    Own mill • Optimised grist fractions can

    – Improve extract efficiency – reduced malt costs – Increase runoff rates / reduce set beds – Reduce debris in wort

    Grist case • Large enough for maximum grist weight • Pre-ground malt, or • Mill night before • Can also mash in directly from mill – no GC req’d

    – But max 20 minutes to mash in

  • 24/10/2017

    5

    Mash system

    • To cope with largest grist weight, e.g. – Maximum volume & normal gravity, e.g. 5% – Reduced volume at higher gravity, e.g. 10%

    • Mashing in – Manual mixing OK up to 10 brl / 400 kg – Mash mixer essential above this for most people – Mashing time – 20 mins max

    • Mashing profile – Isothermal with simple MT – Rising temperature infusion with MT – not controllable – Decoction & rising temp mashes – additional kit

    • How are you going to remove spent grains?

  • 24/10/2017

    6

  • 24/10/2017

    7

    Liquor tanks

    • Incoming water supply flow and quality

    • Break tank?

    • Chlorine removal

    • Acid treatment?

    • CLT working capacity = > 1.3 x maximum wort volume

    • HLT working capacity > 1.3 x maximum wort volume

    • Temperature and time control of HLT

    • Handling different mash and sparge temps

    Wort copper / kettle

    • Flexible heating to allow full / reduced volumes

    • Ability to vigorously boil entire contents

    • Ability to handle hop formats being used in copper – WP – pellets only

    – Hopback – whole hops only

    • Heating – Direct flame to bottom of kettle – rare

    – Electric heating elements

    – Direct gas fired – internal heating coil

    – Steam heated jackets / calandria

  • 24/10/2017

    8

  • 24/10/2017

    9

    FVs / CTs

    • Bottom / top cropping yeast ?

    • “Flat” bottom should still be sloped

    • CCVs - 60 deg internal angle

    – require extra vertical height for cone

    • Top access for top cropping

    • Lower side access for bottom cropping

    • Cooling / temperature probes for full and part brews

    • Temperature control system

  • 24/10/2017

    10

    Cooling

    • Common glycol cooling system better if =>10 brl

    • Sizing – supplier will need volumes, times, rates of

    – Fermentation attemperation

    – FV crash cooling

    – CLT cooling

    – CT / BBT cooling

    – Cold store conditions – size, temperature

    Pipework

    • Generally 10 brl (1635 litre) kit can / should use 25 mm pipe

    – Ideal flow = 2,900 –> 3,800 litres / hr

    – Mashing in 350 kg @ 3:1 = 3,150 l / hr (20 min mash)

    • Many suppliers use 1.5 inch (36 mm), but not cleanable with the pumps often supplied

  • 24/10/2017

    11

    Cleaning

    • Manual cleaning not practical for enclosed vessels – access, safety, confined working space

    • Simple CIP system particularly beneficial at 10 brl +

    • Typically single use

    • Vessels must not be continuously ponded

    • Pipe flows must be turbulent

    Packaging

    Cask / keg washing • For 10 brl kit, at least 2 head

    – More heads reduces attention required

    Bottling, canning, kegging ? • Filtered? Unfiltered? Package conditioned? • How much of each to determine size, and level of

    manual input

    Outsource • But need sensible minimum quantities - costs • Agree quality expectations

  • 24/10/2017

    12

    Other considerations

    • Filtration?

    – KG, sheet, lenticular?

    – How are you going to clean and sterilise?

    • Carbonation

    – “Natural” – krausening, primings – time required

    – “Forced” - in tank sinter

    – “Forced” - in-line

    Brewery space requirements

    • Individual pieces of kit

    • Working space for each item

    • Storage space for materials and packaged beer

    • Admin

    • Lab

    • Mess room & toilets

    • Bar / food ?

    • Off sales area

  • 24/10/2017

    13

  • 24/10/2017

    14

    The building

    • Do NOT compromise on structural safety

    – Floor and wall strengths / loadings

    • Access to get tanks in

    • Sufficient height for tank installation

    • Insulated

    • Outside space for access, parking waste storage

    10 brl FV – large brewery ratio

    3.65 metres 3.3 metres

    3.0 metres

    10 brl FV – smaller brewery ratio

    3.1 metres

  • 24/10/2017

    15

    Hygiene – non negotiable

    • You are producing food products

    • Non porous walls / ceilings – tiles / plastic / polypropylene boarding

    – impermeable paint

    • Non porous surfaces (floors and vessels) essential

    • Good falls / gullys not essential

    • Ventilation – for moisture & CO2

    • Pest control

    • Toilet / washing / personal kitchen facilities

  • 24/10/2017

    16