Work Breakdown Structure forOne Naval Personnel System

Prepared by: Villanueva, Roxan Micah D. Date: February 6, 2015

1.0 Project Planning and Initiation JAN30,20151.1 Analysis of Proposed System JAN30-FEB11.2 Requirements and Data Gathering FEB01-07,2015

1.2.1 Conducting a Face-to-Face Interview with the ClientFEB08-10,20151.3 Establishing the Requirements FEB11-16,20151.4 Describing the Project Scope FEB17-20,2015

2.0 System Analysis and Design FEB21-MAR072.1 Initial Drafting of the Website FEB21-MAR212.2 Submission of Initial Drafts MAR22

2.2.1 Acceptance of Recommendations and Suggestions MAR23-242.3 Submission of Final Drafts MAR25

2.3.1 Final Checking of Draft MAR26-272.3.2 Approval of the Draft MAR28

3.0 Implementation and Testing MAR29-AUG313.1 Creating the database model MAR29-APR293.2 Project development APR30

3.2.1 Developing the Website APR30-MAY303.2.2 Creating the Database MAY31-JUNE303.2.3 Integrating the Database on the Website JULY1-AUG31

3.3 Testing and Error-Handling SEPT13.3.1 Functionality Testing SEPT1-SEPT223.3.2 Performance Testing SEPT23-OCT73.3.3 User Acceptance Testing OCT8-OCT293.3.4 Compatibility Testing OCT29-NOV53.3.5 Handling Errors NOV6-DEC6

4.0 Evaluation4.1 Finishing the Project Documentation DEC6-DEC284.2 Final Report DEC29

5.0 Deployment DEC30