ECAL planning, 10 Jul 2003 AB CMS schedule draft v33.1:surface

Preview:

Citation preview

ECAL planning, 10 Jul 2003 AB

CMS schedule draft v33.1:surface

ECAL planning, 10 Jul 2003 AB

CMS schedule draft v33.1 : underground

ECAL planning, 10 Jul 2003 AB

Reduced underground magnet test

trackerES mechbeampipecool mag & closetest magnetopen CMS

trackerES mechbeampipetest mag coolingpixel moni

start EE/ES installation

start EE/ES installation

v33.1

v33

ECAL planning, 10 Jul 2003 AB

YE1 +/- schedule: draft May 03(assumed 3 month shift wrt v33)

pivotal point is stillEE/ES cable installation

delay will impactHE- RBX connection

ECAL planning, 10 Jul 2003 AB

Proposed routings passing critical areas are worked out indetailed designs and are checked on the integration model

YE1 cabling

ECAL planning, 10 Jul 2003 AB

Cabling from nose runs under ME/RE1

ECAL planning, 10 Jul 2003 AB

HE-coil gap

ECAL planning, 10 Jul 2003 AB

20032002 2004 2005

ME1/1+

HE+HE-1004

2

ME1/1-MF-1010

2

MF-1015ME1/1+ 2

HE-1002HE- 2

HE-HE-005

1 HE+ 1

HE-006

MF-1014 ME1/1- 2

HE Delivery to CERN

HE Assembly

HE Cabling&Test HE-012

1

ME1/1 Ready for Installation

ME1/1 Assembly

ME1/1 Cabling&Test MF-071

1

MF-1017

1

Installation Schedule of HE and ME 1/1

ECAL planning, 10 Jul 2003 AB

YE1: some possible schedule hang-ups

cooled cableway design & occupancy vs time ( need cartoons of cable-way filling vs time) procurement/manufacture of remaining cableways layout of YE 1 patch panel & cable service loops

RE1/1 link board boxes and cables EE/ES cooling & cable definition for pre-installation latest mid 04.

electronics definition. LV & HV system definitionsLV regulators (rad tolerance, operating margin, noise rejection)LV cable noise immunity/rejectionPatch panel “dummies” & cable storage

Can we converge on a relatively conservative scheme which meets the constraints and gets all EE/ES cables installed on YE1+ by mid-04? What part of the EE/ES services can be installed earlier than this? extra expenditure may be justified to maintain a simple SX5 sequence!

ECAL planning, 10 Jul 2003 AB

Cable chains: freeze occupancy in Sept 03

Patch panel on cable chain: fix definition by Sept clear to discusscooling, gas, inertion, sniffers, grounding, other low count HV & LVcollectively oversheathed cables requiring breakout optical fibres start by confirming cable count in YE1 chain (through cabling link-person)

ECAL planning, 10 Jul 2003 AB

Precabling of endcap detectors

Hadron Endcap Muon Endcap 1/1

(dummy) Preshower

(dummy) EM endcap

who is responsiblefor PP definitionand dummy fabrication?

ECAL planning, 10 Jul 2003 AB

Preshower design

2 completely cabled 1/2 disk (radiator + Si detectors)

front & rear windows + inner drum (moderator)full disk pre-mounted before beampipe installation.

detectors can be installed/removed without removing beampipe or moderator

Rob Loos

logical time to install ES detectors is (just) after EE.

ECAL planning, 10 Jul 2003 AB

EE/ES cable duct occupancy

Studies & CTF reports by W.Funk.EMC, forces due to B-field, integration of HE & RE cables in duct?