View
304
Download
1
Embed Size (px)
DESCRIPTION
Citation preview
BROOKLAND COMMUNITY MEETING – MARCH 23, 2013
Stanton Elementary School
Community Meeting
June 11, 2014
BROOKLAND COMMUNITY MEETING – MARCH 23, 2013
AGENDA / GOALS
• Team Introductions
• Project Overview
• Project Schedule – Next Steps
• What to Watch For
• Questions
BROOKLAND COMMUNITY MEETING – MARCH 23, 2013
PROJECT TEAM
• Department of General Services
• Gregory Benson – Project Manager
• Adnan Mamoon – Program Manager
• LITTLE Diversified Architects / Millennium Design Architects
• Tompkins Builders
BROOKLAND COMMUNITY MEETING – MARCH 23, 2013
PROJECT OVERVIEW
• Phase 1
• Interior Renovation, New Windows, New HVAC system
• Phase 2
• New Addition
BROOKLAND COMMUNITY MEETING – MARCH 23, 2013
PROJECT SCHEDULE
- Construction Start: June 20th 2014
- Substantial Completion (Phase 1): August 15th, 2014
- First Day of School: August 25th, 2014
- Construction Start (Addition): Summer 2014
- Substantial Completion (Addition): August 15th, 2015
BROOKLAND COMMUNITY MEETING – MARCH 23, 2013
WHAT TO WATCH FOR
BROOKLAND COMMUNITY MEETING – MARCH 23, 2013
SUMMER LOCATION
• Garfield Elementary School
• 2435 Alabama Ave SE, Washington, DC 20020
BROOKLAND COMMUNITY MEETING – MARCH 23, 2013