Upload
nilesh-dhotre
View
1.704
Download
4
Embed Size (px)
Citation preview
CASE STUDY ON CHUNNEL TUNNEL PROJECT
Team 5
Overview:• Designed to create spur in Economic Development• Improve the trade relations with alternate high speed transportation• One of the largest privately funded construction Project between two countries• 51.5 Km long double rail tunnel.• Project was initially estimated at 5.5 Billion dollars on completion the cost increased
to 14.9 Billion dollars
Chunnel Tunnel Group/French Manche (BOT basis)
Transmanche Link (TML) (Construction)
French and British Govts.,
Scope Management
Inception
• Lack of defined scope
• Scope defined in Lump sum basis
• Difficulty in Resource planning
• Formation of IGC
Development
• Enormous scope• Measures to
prevent the scope creep was not put in place
• Project Planning, cost estimation, Funding was affected due to scope change
Implementation
• IGC had major control over scope
• Frequent change in scope
• Door and A/c System contributed to major scope changes
Closeout
• Even when the tunnel was deemed to complete, there were discrepancies over scope of some works.
Rating : 2
2
2 22
Time Management
Inception
• Hasty Bidding and concept development
• Not enough time provided to complete detailed design studies
Development
• Change in requirement by IGC caused delay
• Approval of drawings mandated from both governments
• Very good tracking with hefty status report
Implementation
• Faster Tunneling• Rail and car
systems were delivered late
• Alteration of passenger door sizes caused delay for 9 months.
Closeout
• Cascading effects of previous phases
• 19 month delay• Project
management team could not be held responsible
Rating : 3
3
3 2
2
Cost Management
Inception
• Estimated cost of USD 5.5 bn.
• Initial Cost Estimates were not detailed out.
• Financing arranged via equity and capital market
Development
• USD 2.25 Bn claim against Eutotunnel by contractor was not anticipated
• Use of sophesticted equipment not anticipated
Implementation
• Unnecessary use of costly technologies in some cases like grouting.
• Wrong selection of TBM.
Closeout
• Efforts were driven towards settlemnt of claims rather than analysing on sources of cost overrun.
Rating : 2
1
2
1
2
Quality Management
Inception
• Difference in standards -> Higher standard
• Latest laser and computer technology proposed to bore the tunnel.
Development
• Good PAC was framed.
• No margin for errors
• Formation of IGC
Implementation
• Stringent requirements from IGC
• Very high accuracy maintained.
Closeout
• Quality parameters achieved were above industry average.
Rating : 5
4
55
5
Human Resources Management
Inception
• Team work envisaged
• Good structure with proper responsibilities formed.
Development
• Every British team member had French counter part
Implementation
• Managed 15,000 workers in good manner
• Workers from different cultures were engaged with high level of efficiency
Closeout
• Most of the persons were demotivated due to non settlement of claims.
• Win-win situation was lost
Rating : 3
3
3 2
3
Communications Management
Inception
• Difference in languages of two countries
Development
• Limited communication between two teams since both of them were trying to meet in middle.
• This lead to difference of opinion at later stages
Implementation
• Delay in communication regarding specification change.
Closeout
• Negotiations not proper at Closeout since bankers did not settle for claims.
Rating : 2
3
3 1
2
Risk Management
Inception
• Technical risk only considered
• Process and approval risk were not envisaged
• Both governments denied to provide financial guarantee.
• Social cost benefit analysis not done.
Development
• Over management of risk – advanced techniques considered
• Contingencies and margins were barest mimimum.
• Contractors forced to consider best situation.
• Risk assessment plan was not made.
Implementation
• Fast tracking of design and construction processes done without risk analysis.
• New unproven technology increased risk
• Banks were involved for minimising the risk, however IGC was controlling.
Closeout
• Courts ruled in favour of contractor.
Rating : 2
2
2
22
Procurement Management
Inception
• Rigorous time constraints caused hasty procurement plan/contracts.
• Procurement of rolling stock and associated major equipment finalised on cost plus percentage fee basis
Development
• Procurement delayed since scope/ specification was changing.
Implementation
• Fixed price contracts with several contractors
• Differences in goals since many contractors were having equity.
Closeout
• Cascading effect of implementation created 17 months delay.
• Non settlement of extra claims
Rating : 2
2
22
3
Integration Management
Inception
• Various international agencies took part for conceptualisation.
• Mistrust among agencies since both govts didn’t provide guarantee but placed requirements.
Development
• 46 contractors were deployed for design
• 7 Lakh shareholders, 220 Lending banks were involved for financing.
Implementation
• Huge resources, huge scope of work were managed in best of industry standards.
• Logistical and communication challenges.
Close out
• Teams not integrated due to poor communication.
• Each party tried to focus on their own interests.
• International chamber of commerce engaged for dispute resolution
Rating : 3
2
3 2
3
Project Management Area
Inception Phase
Development Phase
Implementation Phase
Closeout Phase
Average
Scope Mgt 2 2 2 2 2Time Mgt 3 3 2 2 3Cost Mgt 1 2 2 1 2Quality Mgt 4 5 5 5 5HRM 3 3 3 2 3Communications Mgt 3 3 2 1 2
Risk Mgt 2 2 2 2 2Procurement Mgt 2 2 3 2 2
Integration Mgt 2 3 3 2 3
Rating Scale - Summary
Rating Scale : 5-Excellent, 4- Very Good, 3- Good, 2- Poor, 1- Very Poor
Key Dates
Year Key Developments1802 Albert Mathieu put forward a cross channel proposal1875 Channel Tunnel Company Ltd began preliminary trials
1882 Experimental work on both sides of the Channel started but soon idea was abandoned citing national defense security.
1975 A UK–France government backed scheme that started in 1974 was cancelled
1984 British & French govt. agreed to common safety, environmental & security concern, prior opening up the project to bidder
1985 British & French govt. asked for proposals.
1986 Project awarded to Eurotunnel on BOOT basis with 55 year concession period with initial cost of US$ 5.5 billion.
June 1988 In France, first tunneling was startedDecember
1988 Tunneling operation was started in UK
May 1994 Tunnel was formally inaugurated & started functioning. Project was completed with cost & time over run.
Major Area of Strength Managing this Project
QUALITY MANAGEMENT
• Quality management was implemented successfully. • Technical expertise .
TEAM WORK
• Excellent team work between two groups.• Construction of tunnel completed 3 months ahead of schedule.• Project office support was excellent.
SAFETY MANAGEMENT
• Accidents below industry average.• 15000 workmen, numerous engineers, handled precisely.
Major Opportunities for improvement from Management P.O.V
SCOPE MANAGEMENT
• Detailed Functional requirement & Technical specification • Consideration of Scope contingency
CONTRACT MANAGEMENT
• Applicability of Single Contract to both group.• Coverage of risk exposures
COMMUNICATIONMANAGEMENT
• Communication protocol preparation• Protocol for escalating unresolved / pending issue• Tracking & monitoring
Major Opportunities for improvement from Management P.O.V (cont.)
RISK MANAGEMENT
• Project process & approval risk was overlooked.• Not prepared to handle the degree of IGC supervision & change
management controls.• Contingencies for known & unknown risk & a strategy for handling
change management missing.
COST MANAGEMENT
• Use a standardized change-control management to eliminate cost considerations issues imposed by out-of-control-change management control processes.
• Specification and validation of functional and technical requirements at front.
• Replacement of material, equipment with alternate option of same specification.
STAKEHOLDER MANAGEMENT
• Project Stakeholder management plan was not prepared in detailed and also not followed throughout project life cycle. By implementing this, variance in cost, schedule and extra claims could have been minimized.
Major Project Management Lessons learned
Review past engineering studies & take them in consideration
Technical as well functional aspects of project management should be given
equal importance
Detailed risk analysis required in inception stage & needs to be tracked,
monitored during PLC of project
Major Project Management Lessons learned
Maintaining communication throughout the life of project yields better operational
project results.
In large international construction projects of the involving countries, Govt. support &
communication channels should be roped in.
Whole hearted effort to be made right from the inception of project in order to avoid
adverse situation at the end
Conclusion:
• Time Over run – 19 months delay
• Cost Over run – USD 9.4 Bn
• Trail of unhappy investors and stakeholders
• Key learnings
• Modern Engineering Marvel
• Undoubted Public benefit
Thank You