Upload
shirley-rivera
View
193
Download
0
Embed Size (px)
Citation preview
IntegratedIntegrated Permit Permit Planning Planning
Update and Primer on Permitting
CADER Conference - Distributed Energy Resources
Sustaining the Momentum: Delivering BenefitsJanuary 28, 2004 | San Diego California
Presented by:Shirley F. Rivera | Resource Catalysts
Discussion OverviewDiscussion Overview WHO . . . is involved?
WHAT . . . is involved?– Project and Development Objectives– Approvals / Plans Acquisition
WHEN . . . does it matter?– Project Phases
WHY . . . does it matter?– Potential Project Pitfalls
Presentation ElementsPresentation Elements
…will address– project examples
lessons learned– “human resource”
element multiple agencies
and organizations– cross-cutting issues
approval acquisition
… will not address– specific approval
requirements– project economics
capital and O&M costs financial benchmarks
– equipment, technologies and project configurations
Getting Projects On-LineGetting Projects On-Line
project alternatives
project feasibility
approval acquisition
construction/start-up
operations
Define Project = Eval Phases = Approvals
“Who’s Who”Project TeamDG “Hit List”
Agency ProcessFees/ScheduleCross-Cutting
““WHO’s WHO” Lists …WHO’s WHO” Lists ……all projects have …
– developer– land use/property owner– financing arm– owner(s) (of project)– operator/maintenance (of
equipment)– “end-user(s)”
(recipient(s) of power)– distribution company– natural gas supplier
……the “Project Team”the “Project Team” design procurement engineering system integration construction installation operation facility
management
… includes, but not limited to,– Project managers– Sales– Procurement– Contracts– Engineers– Financial analysts– Facility operators– Government affairs– Consultants
Environmental “Environmental “Hit ListHit List” for DG siting” for DG siting Environmental
– air quality– land use– noise impacts– visual impacts– water quality, supply,
and discharge– hazardous material/waste– safety– other “site specific”, e.g.,
biological resources wetlands, coastal
Energy/Engineering– interconnection– gas pipeline connection– building department– other organizations, e.g.,
OSHPD, school/architect
Social– environmental justice– risk communication– emission reduction
credits and trading; mitigation
““Issue” & Potential PitfallsIssue” & Potential PitfallsDefine ProjectDefine Project
Project Team communications Roles and responsibilities definition(s)
Source/Location – Owner/Operator criteria Air quality permit issue, esp. at existing site Contractual obligations, liabilities, etc.
Project parameters that are acceptable Fuel use, capacity, hours of operation, rates, etc.
““Issue” & Potential PitfallsIssue” & Potential PitfallsEvaulation of PhasesEvaulation of Phases
Location, Location, Location AB 3205 (CA) - K-12 within 1,000 feet of site; 30-day public Environmental impacts, e.g., noise, wetlands Engineering issues, e.g., pipeline, wires Site constraints, e.g., building, noise, construction, etc.
Emissions – Data-specific needs Uncontrolled emissions vs. controlled % VOC/toxic controls; design for BACT/LAER Testing in project cost & schedule; agency witness
““Issue” & Potential PitfallsIssue” & Potential PitfallsApprovalsApprovals
Agency availability/process Knowledge-base; timing of agency approvals Include agency people into project milestones Cross-cutting issues - CEQA, air quality, building permit
Public involvement – timing issue Project approval delays; project reconfiguration
Operations – Hardware needs Monitoring equipment of some level
Project Examples / Lessons Project Examples / Lessons LearnedLearned
Approval process/Agency interdependence Level/complexity of CEQA review
Dependence of CEQA review/acceptance and AQ permit Building department relies on AQ permit (A/C) issued
CEQA for other project activities Distribution - Natural gas pipeline; wires Existing site/building modifications
Project Examples (cont’d)Project Examples (cont’d) Emissions test requirements
80% load (maximum rated capacity) Conform with specifications - access, test
platform/sampling Other pollutant testing - toxics Operating parameters over various loads
Environmental plans/programs for operations Air quality - emissions test plan, monitoring plan, O&M Hazardous materials - business plan, quantities, location Water quality - storm water, other discharge
Project Examples (cont’d)Project Examples (cont’d) Equipment/services procurement
AQ - monitoring devices, emission test firms Alternative CEMS vs. formal CEMS (San Joaquin Valley) Portable analyzer options
Hazardous materials/water Engineering - proper storage; proper containment
Building/land use - noise abatement; visual/aesthetics
Project Examples (cont’d)Project Examples (cont’d) Engineering/Technical Specifications
uncontrolled vs. controlled emissions abatement equipment exhaust parameters
on-site / indoor air quality impacts
Zoning Land use compatibility
Wrap-Up PresentationWrap-Up Presentation Human Resource Responsibilities Costs and Savings Procedures Approvals and
Plans Milestones “Public Factor”
For questions or more information:For questions or more information:
R|CATRESOURCE CATALYSTS| REGULATORY STRATEGY/ADVOCACY |
| PROJECT FEASBILITY ANALYSES | | PERMITTING & COMPLIANCE |
for| AIR QUALITY |
| ENERGY PROJECTS | | ENVIRONMENTAL COMMUNICATIONS |
Shirley F. Rivera | [email protected]: 619-497-0120 | Fax: 619-497-0793