Upload
fingrid-oyj
View
125
Download
3
Embed Size (px)
Citation preview
New electricity highway on the west coast
Antero Reilander, Grid Planning, Fingrid [email protected]
New Ulvila 400 kV switchyard
2
Fingrid in brief
The main grid in numbers- Power lines- Submarine cable- Substations- Reserve power plants
14400 km300 km
11310, >935 MW
Number of customers- Power producers - Power-intensive industries- DistributorsBalance service customersCross-border transmission customers
11229316242
1
Revenue- Grid revenue- Sale of imbalance power
567 million €326 million €151 million €
Balance sheet 2150 million €
Grid capital expenditureOther capital expenditure
118 million €11 million €
Equity ratio 31 %
Personnel at the end of year 313
2009
2010
2011
2012
2013
2014
2015
2016
2017
2018
2019
2020
2021
2022
2023
2024
Fenno-Skan 2 DC connection to Sweden
Forssa reserve power plant
Yllikkälä - Huutokoski B 400 kV
Hyvinkää - Hikiä 400 kV
Estlink 2 DC connection to Estonia
Ulvila - Kristinestad 400 kV
Hikiä - Forssa 400+110 kV -yhteys
Hirvisuo - Pyhänselkä 400 kV
Lieto - Forssa 400+110 kV
Hikiä - Orimattila 400 kV
Reinforcement of Helsinki region network
Reinforcement of north-south connections
Keminmaa - Pyhänselkä 400 kV
3rd AC interconnection to Sweden
Grid connection of nuclear and wind power
Yllikkälä
Ulvila
Forssa
Hirvisuo
Lieto
Keminmaa
Hikiä
HuutokoskiKristinestad
Tuovila
Pyhänselkä
Koria
Petäjävesi
Main grid development plan
EIA / Preliminary design
Detailed planning and permits
Implementation90 % of new power lines will be constructed along or next to an existing right of way
400 kV main grid
400 kV under construction
main grid base line scenarios
Background of the main grid development plan in OstrobothniaVision:
Consumers, producers and electricity market have a safe, reliable and adequate transmission network at disposal.
Strategy:
Old and insufficient 220 kV transmission system is replaced by 400 and 110 kV network solutions.
Grounds:• New production• New consumption• Condition on old 220 kV network• Reliability• Keeping Finland as one price area• Use of 220 kV lines in 110 kV voltage level
makes connecting easier for wind power and distribution network.
Seinäjoki
AlajärviTuovila
Ulvila
Kristinestad
Pyhänselkä
Uusnivala
5
Main grid development plan in Ostrobothnia220 kV network in Ostrobothnia will be replaced totally by the end of 2016.
Development is done in phases
1. New Uusnivala 400/110 kV transformer stationNew Seinäjoki – Tuovila 400+110 kV power line and new Tuovila 400/110 kV transformer station.(ready 2011)
2. New Ulvila – Kristinestad 400 kV power line and Kristinestad 400/110 kV transformer station.Renewal of Ulvila 400 and 110 kV station.
3. New Hirvisuo – Pyhänselkä 400 kV power line and new Hirvisuo 400/110 kV transformer station.Kristinestad – Tuovila – Hirvisuo power line change to 400 kV voltage level.Many 220 kV lines are changed to 110 kV voltage level.
New Jylkkä 400/110 kV transformer station and new Siikajoki 110 kV substation for connecting wind power.
400 kV line is in 220 kV use
Seinäjoki
Alajärvi
Petäjävesi
Tuovila
Ulvila
Kristinestad
Hirvisuo
Pyhänselkä
Uusnivala
Tuloksena:• 400 kV grid from Pori to Oulu• 5 new 400/110 kV transformer
stations• 350 km 400 kV power lines• 150 km 110 kV power lines• 220 kV voltage level demolished in 9
stations.TOTAL COSTS ~280 M€
Jylkkä
Siikajoki
6
Need a grid connection? Start here:http://www.fingrid.fi/en/customers/connection
Wellcome to Fingrid's stand B 1-2. We are here for You.