New electricity highway on the west coast

Antero Reilander, Grid Planning, Fingrid [email protected]

New Ulvila 400 kV switchyard

2

Fingrid in brief

The main grid in numbers- Power lines- Submarine cable- Substations- Reserve power plants

14400 km300 km

11310, >935 MW

Number of customers- Power producers - Power-intensive industries- DistributorsBalance service customersCross-border transmission customers

11229316242

1

Revenue- Grid revenue- Sale of imbalance power

567 million €326 million €151 million €

Balance sheet 2150 million €

Grid capital expenditureOther capital expenditure

118 million €11 million €

Equity ratio 31 %

Personnel at the end of year 313

2009

2010

2011

2012

2013

2014

2015

2016

2017

2018

2019

2020

2021

2022

2023

2024

Fenno-Skan 2 DC connection to Sweden

Forssa reserve power plant

Yllikkälä - Huutokoski B 400 kV

Hyvinkää - Hikiä 400 kV

Estlink 2 DC connection to Estonia

Ulvila - Kristinestad 400 kV

Hikiä - Forssa 400+110 kV -yhteys

Hirvisuo - Pyhänselkä 400 kV

Lieto - Forssa 400+110 kV

Hikiä - Orimattila 400 kV

Reinforcement of Helsinki region network

Reinforcement of north-south connections

Keminmaa - Pyhänselkä 400 kV

3rd AC interconnection to Sweden

Grid connection of nuclear and wind power

Yllikkälä

Ulvila

Forssa

Hirvisuo

Lieto

Keminmaa

Hikiä

HuutokoskiKristinestad

Tuovila

Pyhänselkä

Koria

Petäjävesi

Main grid development plan

EIA / Preliminary design

Detailed planning and permits

Implementation90 % of new power lines will be constructed along or next to an existing right of way

400 kV main grid

400 kV under construction

main grid base line scenarios

Background of the main grid development plan in OstrobothniaVision:

Consumers, producers and electricity market have a safe, reliable and adequate transmission network at disposal.

Strategy:

Old and insufficient 220 kV transmission system is replaced by 400 and 110 kV network solutions.

Grounds:• New production• New consumption• Condition on old 220 kV network• Reliability• Keeping Finland as one price area• Use of 220 kV lines in 110 kV voltage level

makes connecting easier for wind power and distribution network.

Seinäjoki

AlajärviTuovila

Ulvila

Kristinestad

Pyhänselkä

Uusnivala

5

Main grid development plan in Ostrobothnia220 kV network in Ostrobothnia will be replaced totally by the end of 2016.

Development is done in phases

1. New Uusnivala 400/110 kV transformer stationNew Seinäjoki – Tuovila 400+110 kV power line and new Tuovila 400/110 kV transformer station.(ready 2011)

2. New Ulvila – Kristinestad 400 kV power line and Kristinestad 400/110 kV transformer station.Renewal of Ulvila 400 and 110 kV station.

3. New Hirvisuo – Pyhänselkä 400 kV power line and new Hirvisuo 400/110 kV transformer station.Kristinestad – Tuovila – Hirvisuo power line change to 400 kV voltage level.Many 220 kV lines are changed to 110 kV voltage level.

New Jylkkä 400/110 kV transformer station and new Siikajoki 110 kV substation for connecting wind power.

400 kV line is in 220 kV use

Seinäjoki

Alajärvi

Petäjävesi

Tuovila

Ulvila

Kristinestad

Hirvisuo

Pyhänselkä

Uusnivala

Tuloksena:• 400 kV grid from Pori to Oulu• 5 new 400/110 kV transformer

stations• 350 km 400 kV power lines• 150 km 110 kV power lines• 220 kV voltage level demolished in 9

stations.TOTAL COSTS ~280 M€

Jylkkä

Siikajoki

6

Need a grid connection? Start here:http://www.fingrid.fi/en/customers/connection

Wellcome to Fingrid's stand B 1-2. We are here for You.

Powering Finland.