FY 2011 Industrial Wastewater Utilization and Treatment Facility Refurbishment and Upgrade (Groundwater Reuse Project) Ken Kono, Project Manager NASA Ames Research Center March 11, 2010

FY 2011 Industrial Wastewater Utilization and Treatment Facility Refurbishment and Upgrade

Embed Size (px)

Citation preview

Page 1: FY 2011 Industrial Wastewater Utilization and Treatment Facility Refurbishment and Upgrade

FY 2011 Industrial Wastewater Utilization and Treatment Facility Refurbishment and Upgrade

(Groundwater Reuse Project)

Ken Kono, Project ManagerNASA Ames Research CenterMarch 11, 2010

Presenter
Presentation Notes
CEV ISHM In-Space Propulsion TPS TRIPS
Page 2: FY 2011 Industrial Wastewater Utilization and Treatment Facility Refurbishment and Upgrade

UTILIZE AVAILABLE GROUNDWATER DISCHARGES TO MEET ALL INDUSTRIAL WATER NEEDS OF

NASA AMES ARC JET COMPLEX AND UNITARY PLAN WIND TUNNELS

PROJECT GOAL

Page 3: FY 2011 Industrial Wastewater Utilization and Treatment Facility Refurbishment and Upgrade

ARC JET COMPLEX

UTILIZES 110,000 GALLONS PER DAY* OF POTABLE WATER TO OPERATE THE STEAM VACUUM SYSTEM

*OPERATING DAY, APPROX. 170 OPERATING DAYS/YEAR

Page 4: FY 2011 Industrial Wastewater Utilization and Treatment Facility Refurbishment and Upgrade

UNITARY PLAN WIND TUNNELS

UTILIZES 60,000 GALLONS PER DAY* OF POTABLE WATER TO MEET FACILITY COOLING REQUIREMENTS

*OPERATING DAY, APPROX. 170 OPERATING DAYS/YEAR

Page 5: FY 2011 Industrial Wastewater Utilization and Treatment Facility Refurbishment and Upgrade

ACTIVE PUMP AND TREAT FACILITIES AT AMES

WATS Nov. 1998

MEW N.101Oct. 1998

NASA RGRP Sept. 2001

Page 6: FY 2011 Industrial Wastewater Utilization and Treatment Facility Refurbishment and Upgrade

PRELIMINARY ENGINEERING PHASE

• ASSESS WATER QUALITY AND QUANTITY

• ASSESS EXISTING SOURCE INFRASTRUCTURE

• DEFINE NPDES REQUIREMENTS

Page 7: FY 2011 Industrial Wastewater Utilization and Treatment Facility Refurbishment and Upgrade

IN SITU SDI (SILT DENSITY INDEX) TESTING AT TREATMENT FACILITIES

Page 8: FY 2011 Industrial Wastewater Utilization and Treatment Facility Refurbishment and Upgrade

CURRENT DISCHARGE RATEFACILITY AVERAGE FLOW

(gallons per day)DESTINATION REMARKS

N 101 (MEW) 179,000 STEVENS CREEK VIA 6” DIA. PIPE, PARTIAL RE-USE AT N271

NASA RGRP 22,000 STEVENS CREEK JOINS N 101 PIPE

WATS 95,000 STORM WATER RETENTION BASIN

VIA STORM WATER CONVEYANCE SYSTEM

TOTAL FLOW = 296,000 GALLONS PER DAY OR OVER 108 MILLION GALLONS PER YEAR IS AVAILABLE FOR RE-USE

CURRENTLY, LESS THAN 10% IS RE-USED

Page 9: FY 2011 Industrial Wastewater Utilization and Treatment Facility Refurbishment and Upgrade

DAILY PEAK DEMANDWATER FLOW DIAGRAM

CONSOLIDATEDGROUNDWATER

243,000 GAL

296,000 GAL 53,000 GAL

UNUSED GROUNDWATER 126,000 GAL

73,000 GALCONCENTRATE170,000 GAL

PERMEATE

110,000 GAL 60,000 GAL

R.O.FACILITY

0.85 MGPERMEATESTORAGE

ARC JET COMPLEX

UNITARY PLANWIND TUNNELS

COMBINED DISCHARGE TOSTEVENS CREEK

Page 10: FY 2011 Industrial Wastewater Utilization and Treatment Facility Refurbishment and Upgrade

ANNUAL WATER FLOW DIAGRAM

CONSOLIDATEDGROUNDWATER

42 MG

108 MG 66 MG

UNUSED GROUNDWATER 79 MG

13 MGCONCENTRATE 29 MG

PERMEATE

19 MG 10 MG

R.O.FACILITY

0.85 MGPERMEATESTORAGE

ARC JET COMPLEX

UNITARY PLANWIND TUNNELS

COMBINED DISCHARGE TOSTEVENS CREEK

(MG = MILLION GALLONS)

Page 11: FY 2011 Industrial Wastewater Utilization and Treatment Facility Refurbishment and Upgrade

EXISTING DISCHARGE AND DISTRIBUTION FLOW DIRECTION

Page 12: FY 2011 Industrial Wastewater Utilization and Treatment Facility Refurbishment and Upgrade

ASSESS EXISTING TREATMENT FACILITY2002 - 2006

CONSERVED APPROXIMATELY 7 MGAL/YEAR OF POTABLE WATER

EXISTING REVERSE OSMOSIS VESSELS

Page 13: FY 2011 Industrial Wastewater Utilization and Treatment Facility Refurbishment and Upgrade

MODEL EXISTING AND PROPOSED PIPING SYSTEM

Page 14: FY 2011 Industrial Wastewater Utilization and Treatment Facility Refurbishment and Upgrade

WORK WITH THE STATE WATERBOARD

• NOTIFY THE BOARD OF NASA’S INTENT

• SUBMIT APPLICATION FOR NPDES PERMIT

Page 15: FY 2011 Industrial Wastewater Utilization and Treatment Facility Refurbishment and Upgrade

PROJECT SCHEDULE

•PRELIMINARY ENGINEERING SEPT 2009 – MAR 2010

•FINAL DESIGN APRIL 2010 – OCT 2010

•CONSTRUCTION FEB 2011 – OCT 2011

Page 16: FY 2011 Industrial Wastewater Utilization and Treatment Facility Refurbishment and Upgrade

QUESTIONS?