27/05/2019C238hume
SCHEDULE 1 TO CLAUSE 45.06 DEVELOPMENT CONTRIBUTIONS PLANOVERLAYLAYShown on the planning scheme map as DCPO1.
CRAIGIEBURN R2 PRECINCT STRUCTURE PLAN DEVELOPMENT CONTRIBUTIONS PLAN
1.027/05/2019C238hume
Area covered by this development contributions planAll land within the Craigieburn R2 Precinct Structure Plan area as shown in the DCPO1.
Map 1 to the Schedule to Clause 45.06
HUME PLANNING SCHEME
Page 1 of 3
2.018/11/2010C120
Summary of costs in 2010 dollars
Proportion ofcostattributable todevelopment%
Actual costcontributionattributable todevelopment $
Time ofprovision
Total cost $Facility
100%$5,170,000Refer to DCP$5,170,000Roads & intersections(including land for roads)
100%$14,652,100Refer to DCP$14,652,100Land acquisition (activeopen space & communityfacilities)
82%$9,883,000Refer to DCP$12,000,000Active open space(construction)
24%$15,041,920Refer to DCP$62,709,000Community facilities(construction)
$44,747,020$94,531,100TOTAL
3.009/11/2017GC75
Summary of contributions
LEVIES PAYABLE BY THE DEVELOPMENTFACILITY
Allinfrastructure*
Communityinfrastructure(2017 dollars)
DevelopmentInfrastructure
Residentialdevelopment
ResidentialNon-governmentschool
Residentialdevelopment
$14,313.40$0$3,578.35$14,313.40Roads & intersections(including land forroads)
$40,565.06$0$0$40,565.06Land acquisition(active open space &community facilities)
$20,514.95$785.01$0$20,514.95Active open space(construction)
$38,737.32$0$38,737.32Community facilities(construction)
$114,130.73 perNDha (+ $785.01[2017 dollars] per
$785.01 perdwelling
$3,578.35 perHectare
$114,130.73 perNet DevelopableHectare (NDHa)
TOTAL
dwelling forCommunityInfrastructure)
*No community infrastructure levy is payable by non-government school development.
The Community Infrastructure Levy (CIL) payable under this Development ContributionsPlan (DCP)
Section 46L of the Planning and Environment Act 1987 sets the maximum CIL amount that canbe collected under an approved DCP
If the maximum amount of the CIL which may be collected under an approved DCP is variedunder section 46L of the Planning and Environment Act 1987, the collecting agency may adjustthe amount of the CIL payable under this DCP in accordance with section 46L of the Planningand Environment Act 1987.
HUME PLANNING SCHEME
Page 2 of 3
If the collecting agency adjusts the amount of the CIL payment under this DCP, the collectingagency will publish the adjusted amount of the CIL payable under this DCP on its website.
4.018/11/2010C120
IndexationThe capital cost for each infrastructure item will be adjusted by applying the Building Price Index,as published in the latest edition of Rawlisons Australian Construction Handbook on 1st Januaryand 1st July each year;
The land values for each infrastructure item, where applicable, will be adjusted on 1 July eachyear following site specific land valuations undertaken by a registered valuer.
5.018/11/2010C120
Land or development excluded from development contributions planLand required for the following (as set out in the Craigieburn R2 Precinct Structure Plan):
Railway reservations, government schools.
Melbourne Water drainage reserves and retarding basins.
Heritage and conservation areas.
Open Space (passive).
This schedule sets out a summary of the costs and contributions prescribed in the development contributionsplan. Refer to the incorporated development contributions plan for full details
Note:
HUME PLANNING SCHEME
Page 3 of 3