Woodbridge High School
Woodbridge SchoolDistrict
Schematic Design forWoodbridge High School
17 January 2012
Woodbridge High School
Schematic Design
Building
Woodbridge High School
Building Plans
• First Floor Plan
Woodbridge High School
Building Plans
• Second Floor Plan
Woodbridge High School
Perspectives
• Rear
• Front
Woodbridge High School
Woodbridge School DistrictTotal Project Cost Summary
Building Construction Costs $ 46,470,770
Design & Consulting Fees $ 2,498,500
State, County, Local & Agency Fees $ 1,365,641
FF&E & Technology Equipment $ 1,970,000
Subtotal $ 52,304,911
Total Project Costs $ 52,304,911
Woodbridge School District Budget $ 52,539,700
Total Amount Under / (Over) Budget $ 234,789
Proposed Add Alternates $ 2,850,000
January 17, 2012
Woodbridge High School
Woodbridge School DistrictProject Schedule
Space programming 09/22/11 – 11/16/11
Schematic Designs (30%) 11/11/11 – 01/17/12
Design Development (60%) 12/19/11 – 04/23/12
Construction Documents 03/22/12 – 08/23/12
Bid Pack A (Site Concrete & Steel) 8/20/12
Bid Pack B (building & Systems) 10/02/12
Funding available $10.5 m 10/2011 (FY-12)
Funding available $21.0 m 10/2012 (FY-13)
Funding available $21.0 m 10/2012 (FY-13)
Woodbridge High School
Woodbridge SD AdministrationFearn - Clendaniel Architects
EDiS Company
Thank you!
Questions and Answers