Upload
others
View
0
Download
0
Embed Size (px)
Citation preview
Gary Lee Moore, P.E., City Engineer Vince Jones, P.E., Deputy City Engineer
WHITE POINT LANDSLIDE GEOTECHNICAL INVESTIGATION
January 2012 Status Report
White Point Landslide Geotechnical Investigation January 2012 Status Report Page 2 January 17, 2012
City of Los Angeles, Bureau of Engineering
TABLE OF CONTENTS
1.0 Background 2.0 Site Observations and Activities for the Period December 21,
2011 to January 12, 2012
3.0 Landslide Monitoring for the Period December 21, 2011 to January 12, 2012
4.0 Geotechnical Investigation
5.0 Survey Monitoring
Attachment 1– Status Report Prepared by Shannon & Wilson, Inc. for 12/17/11 through 1/12/12 White Point Landslide Investigation
Attachment 2– Summary of Survey Monitoring Points at Weymouth Avenue and Paseo Del Mar, prepared by the Bureau of Engineering January 12, 2012
Attachment 3– DRAFT Preliminary Geotechnical Report by Shannon & Wilson January 6, 2012
White Point Landslide Geotechnical Investigation January 2012 Status Report Page 3 January 17, 2012
City of Los Angeles, Bureau of Engineering
1.0 Background This January 2012 Status Report provides a progress summary of the Geotechnical Investigation and monitoring of the White Point Landslide for the period if December 21, 2011 to January 12, 2012. The Bureau of Engineering (BOE) continues to oversee and support the geotechnical investigation of the landslide being conducted by Shannon and Wilson, Inc., a private consulting firm. Attached to this report are the January 2012 Status Report by Shannon & Wilson, Inc. (Attachment 1), the Summary of Survey Monitoring Points by the Bureau of Engineering (Attachment 2), and the DRAFT Preliminary Geotechnical, January 6, 2012 by Shannon & Wilson (Attachment 3). 2.0 Site Observations and Activities for the Period December 21, 2011 to
January 12, 2012 During this last month Shannon & Wilson completed exploratory drilling of the landslide. This effort included the drilling of nine (9) borings around the margin and headward area of the landslide, collection of soils samples, construction of groundwater monitoring wells and installation of earth movement monitoring instruments. The Bureau authorized Shannon & Wilson to engage the services of a private survey firm to prepare a detailed topographic survey map of the landslide and surrounding area. The Bureau directed that the survey be very detailed so as to document ground surface variations of as little as six inches. This map was completed on January 6, 2012, and is used as the base for Figure 1 of Attachment 1 and will be used by Shannon & Wilson in the future phases of the landslide investigation. Geologists from both BOE and Shannon &Wilson continue to conduct site observation of the landslide and surrounding area. Observation of existing ground cracks around the immediate edge of the landslide suggests that the ground within a few feet of the head of the landslide is tilting and crumbling and may fall toward the landslide. Future activities will include opening of the abandoned "The Launcher Area at White Point, Los Angeles Defense Missile Site LA-43." facility within the nature park for the purpose of observing its condition.
3.0 Landslide Monitoring for the Period December 21, 2011 to January 12, 2012 As described in Attachment 1, Shannon & Wilson continues with the measurement of earth monitoring instruments (inclinometers) that were placed in some borings to detect ground movement (see Table 1). A Draft Preliminary Geotechnical Report by Shannon &Wilson (Attachment 3) indicates that ground measuring instruments show no significant movement. Shannon & Wilson indicate that this suggests that over the time of instrument readings, properties adjacent to the landslide and the newly constructed storm drain improvements have not been subject to movement related to the current landslide limits.
White Point Landslide Geotechnical Investigation January 2012 Status Report Page 4 January 17, 2012
City of Los Angeles, Bureau of Engineering
BOE is currently working to install a series of ground surface monitoring stations to help detect potential ground movement. These survey stations will be installed on the sides and landward perimeter of the landslide and will be periodically monitored for evidence of ground movement. 4.0 Geotechnical Investigation A status report prepared by Shannon and Wilson and dated January 13, 2011 is presented in Attachment 1. This report summarizes the progress of the Geotechnical investigation through January 12, 2012. As indicated in the report, drilling at the site was completed on December 21, 2011. Completion of the field exploration by Shannon & Wilson is a significant milestone in the investigation of the White Point Landslide. At BOE direction Shannon & Wilson has prepared a 300 page Draft Preliminary Report (Attachment 3) which provides a description of their site observations and initial findings. This report was submitted to BOE and is currently under review. Based on their studies completed to date, Shannon & Wilson preliminarily conclude that the risk of landslide movement beyond the chain link fence placed along the White Point Nature Preserve trail is low. This early phase reporting allows the Bureau to confirm that the perimeter fencing erected around the landslide is appropriate and continues to provide a safe setback of the public from the landslide area. 5.0 Survey Monitoring The BOE continues survey monitoring of points set on the street, curb and ground around the landslide to check for evidence of ground movement which might indicate landslide movement or enlargement. A summary of the survey monitoring is provided in Attachment 2. Survey measurements continued during this period on the three monitoring points reported in the previous status report. Two additional survey monitor points were measured during this period and the data has been included on Figures 1 and 2, Attachment 2. Figure 1 in Attachment 2 shows the location of the monitoring points. As indicated previously, the first three monitor points were established on November 3, 2011. Points #4 and #5, shown on Figure 1, were established on November 21, 2011, subsequent to the landslide event on November 20, 2011. Survey measurements are reported in hundredths of a foot. Therefore, a reading of 0.02 represents approximately ¼ of an inch. Figure 2 indicates the horizontal and vertical movement of each of the points. The expected limits of precision for the monitoring measurements is + 0.02’. The survey monitoring data therefore indicates that no movement has occurred at these points. Survey data shows no indication of ground movement at this time which might signal landslide enlargement.
Attachment 1
Status Report Prepared By Shannon & Wilson, Inc.
ALASKA CALIFORNIA
COLORADO FLORIDA
MISSOURI OREGON
WASHINGTON
664 WEST BROADWAY GLENDALE, CALIFORNIA 91204-1008 www.shannonwilson.com 51-1-10052-012
January 13, 2012 Bureau of Engineering 1149 South Broadway Street, Suite 120 Los Angeles, California 90015 Attn: Mr. Mark Oborne
RE: STATUS REPORT FOR 12/17/11 THROUGH 1/12/12 WHITE POINT LANDSLIDE INVESTIGATION CITY OF LOS ANGELES W.O. E1907483, TOS 11-087 SHANNON & WILSON PROJECT NO. 51-1-10052-012
We are providing this letter outlining the subtask status for the period ending January 12, 2012. Shannon & Wilson is performing a subsurface investigation of the White Point Landslide following significant movement of the landslide on November 20, 2011. During the course of our services, we have not observed new surface cracks outside of the fenced perimeter of the landslide. We recorded groundwater depths in the inclinometer borings and wells that were installed (Table 1) along the landslide perimeter at depths ranging from approximately 50 to 98 feet below ground surface. Groundwater levels measured within the recently completed borings appear to be relatively stable with only minor fluctuations (Table 2). We believe the projected landslide failure plane is about 100 feet deep in the area of the active landslide.
As previously reported, ground cracks immediately adjacent to the landslide widened a few inches after the initial landslide movement. Visual observation of the existing cracks adjacent to the main head scarp suggests that the material immediately adjacent to the scarp is moving or rotating into the graben area. We expect to see periodic calving of this material throughout the upcoming winter months. It is also likely that the main landslide mass will continue to move ocean-ward and likely accelerate during periods of heavy precipitation. No new significant ground cracks have been observed in the area between the fence and main landslide mass. These conclusions are preliminary and are subject to change as our studies develop.
Mr. Mark Oborne City of Los Angeles January 13, 2012 Page 2 of 3
51-1-10052-012-L02rev3.docx/wp/DGF 51-1-10052-012
SUBTASK STATUS
The status of each subtask is listed below:
Subtask Status 1. Health and Safety Plan Complete 2. Geologic Mapping Ongoing - 95% Complete 3. Preliminary Report Submitted for Review 4. Subsurface Exploration Complete 5. Waste Handling and Management Ongoing - 30% Complete 6. Geophysical Downhole Logging Complete 7. Laboratory Testing of Samples Ongoing - 5% Complete 8. Geologic Cross Sections Ongoing - 20% Complete 9. Stability Analysis Pending 10. Meetings Ongoing – 33% Complete 11. Geotechnical Report Ongoing - 5% Complete
TASKS COMPLETED FOR THIS PERIOD
For this work period, tasks completed include:
Completion of the subsurface exploration program on December 21, 2011.
The Draft Preliminary Report was submitted to the City on January 6, 2012. The report included a preliminary geologic map, preliminary boring logs, inclinometer baseline readings, and preliminary observations regarding the landslide and immediate areas adjacent to the landslide. The base map includes the Navigate LA 2006 topographic contours.
Completion of the aerial survey flown on December 13, 2011 and submittal of the updated topographic base map to the City on January 6, 2012
Instrumentation installation and reading dates shown in Tables 1 and 2. Instrumentation will be read on weekly basis for the first month following installation to monitor the landslide area for groundwater elevations and possible subsurface movement.
Site observations for landslide movement during the weeks of 12/12/11, 12/19/11, 12/26/11, 1/2/12 and 1/9/12. Based on visual observations, no ground fractures have appeared at the fenced perimeter of the landslide area.
White Point LandslideCity of Los Angeles
TABLE 1Summary of Explorationsand Instrumentation
Shannon & Wilson, Inc.
Boring
Nam
e
Drill Type
Status
Dep
th (feet)
Completion
Type
(2)
Well/VW
P Install D
ate
Date
Installed
Baseline
Reading
12/28/11
Reading
1/4/12
Reading
1/11
/12
B‐1 Rotary Core (1) Complete 130 11/29/11 VWP/ Incl. 11/29/11 11/29/11 (4) 0.0 <0.1 in. <0.1 in.B‐2 Bucket Auger Complete 120 12/2/11 None ‐B‐3 Bucket Auger Complete 120 12/6/11 Well (3) 12/22/11B‐4 Bucket Auger Complete 100 12/8/11 None ‐B‐5 Bucket Auger (1) Complete 121 12/15/11 VWP/ Incl. 12/16/11 12/16/11 0.0 <0.1 in. <0.1 in.B‐6 Sonic Core Complete 110 12/16/11 Well 12/16/11B‐7 Rotary Core (1) Complete 118 12/14/11 VWP/ Incl. 12/16/11 12/16/11 0.0 <0.1 in. <0.1 in.B‐8 Sonic Core Complete 110 12/18/11 Well 12/18/11B‐9 Rotary Core (1) Complete 120 12/20/11 VWP/ Incl. 12/21/11 12/21/11 0.0 <0.1 in. <0.1 in.
Notes:(1) Inclinometer installed in boring (Total of 4)(2) VWP = Vibrating Wire Piezometer(3) 8‐inch diameter well installed(4) Baseline re‐established 12/28/11
InstrumentationExploration Information Inclinometer Cumulative Displacement
1/20/2012, Copy of Exploration Summary Status No. 2a Rev2.xlsx, RTD Page 1 of 1 51‐1‐10052‐012
White Point LandslideCity of Los Angeles
Table 2Groundwater Data
Shannon & Wilson, Inc.
Reading Date
Water Elevation
(ft.)
Water Elevation
(ft.)
Water Elevation
(ft.)
Water Elevation
(ft.)
Water Elevation
(ft.)
Water
Depth2
(ft.)
Water Elevation
(ft.)
Water
Depth1
(ft.)
Water Elevation
(ft.)
Water
Depth2
(ft.)
Water Elevation
(ft.)
Water Elevation
(ft.)
11/29/2011 60 * 63
12/2/2011 88 * 36.5
12/8/2011 98 * 26.5 55 * 75
12/16/2011 68 * 56
12/30/2011 25.4 50.2 86.5 75.5 52.0
1/4/2012 59.4 60.2 95.4 27.1 86.5 (4) 42.5
1/11/2012 59.2 25.6 60.0 50.0 86.7 95.5 27.0 75.6 51.9 36.6
Notes:
1. Measured using vibrating wire piezometer.
2. Measured using electronic well sounder from the top of the casing.
Top of casing below ground surface:
B-3 ~ 6 inches
B-6 ~ 4 inches
B-8 ~ 5.5 inches
3. (*) Measured during drilling.
4. Suspected Insturment Error
63.8 98.4 64.0 92.4
98.6
63.6 63.8
Elev. ~122.5 ft. Elev. ~128 ft. Elev. ~129 ft.
Water
Depth1 (ft.)
Water
Depth3 (ft.)
Water
Depth2 (ft.)
Water
Depth3 (ft.)
Water
Depth1 (ft.)
Water
Depth1 (ft.)
B-6 B-7 B-8 B-9
Elev. ~123 ft. Elev. ~ ft. Elev. ~124.5 ft. Elev. ~ ft. Elev. ~124 ft. Elev. ~137 ft.Well/ VWP
B-1 B-2 B-3 B-4 B-5
1/20/2012, 51‐1‐10052‐003‐T01.xlsx, JXM Page 1 of 1 51‐1‐10052‐011
148.675 AT4
122.400 AT5
123.5
40.3
41.0
CONC
GNV
ASPH
ASPH
CONC
GNV
GNV
GNV
GNV
PIPE
PIPE
PIPE
PIPE
PIPE
DIRT
DIRT
DIRT
ASPH
ASPH
ASPH
ASPH
ASPH
PACIFIC OCEAN
PASEO DEL MAR
CONC
CONC
CONC
ROCKS
ROCKS
PIPE
DI
DI
ASPH
ASPH
144.6
137.1 136.4 136.5
137.1 136.6
139.1
137.5
132.8132.3
132.1 131.6
131.9 131.1
131.1
143.1
130.6
128.6
129.3128.9
128.3
127.9
129.8130.3
127.2
126.7126.4 125.7
125.2124.7
126.2
128.3
124.4
123.7123.2
122.7122.4
122.5
124.9125.2
123.4
131.9
132.3
133.5 134.6
132.5131.8
131.9
128.3
129.3
144.8
142.5138.5
138.1138.1
138.9
137.9
138.3138.1138.1
138.3138.4
138.5
138.4
138.5
138.5
138.3
138.3
138.1
137.1
132.8
133.1133.8
137.8
135.4
135.3
137.1
138.8139.6
135.9
134.8
BRUSH
BRUSH
BRUSH
CONC CONC
CONC
CONC
TREES
CONC
CONC
TREES
CONC
CONC
CONC
CONC
CONC
CONC
BRUSH
BRUSH
BRUSH
BRUSH
BRUSH
BRUSH
BRUSH
CONC
CONC
DIRT
DIRT BRUSH
BRUSH BRUSH
BRUSH
TREES
BRUSH
BRUSH
BRUSH BRUSH
CONCASPH
ASPH ASPH
CONC
81.6
82.7
87.2
88.5
74.5
64.7
67.4 76.2 98.9
112.1
107.8
116.0
GNV
GNV
VC
VC
VC VC
UB
VC VCVC
VC
VC
VC
ROCKS
R
R
R
ROCKS
ROCKS
PIPE
S
PIPES
PIPES
PIPES PIPES
PIPE
DI
PACIFIC OCEAN
PACIFIC OCEAN
PASEO DEL MAR
ASPH
ASPH
ASPH
ASPH
ASPH
DIRT
DIRT
DIRT
DIRT
138.1137.4
136.5
136.6
137.1
138.1
138.3
137.9
136.9
137.4
127.9
128.1128.8128.5
128.5
137.8
131.1
131.9130.9
138.4
127.2
127.2
126.9
126.7
124.2
122.5
123.9 123.9
125.2
126.2
122.2121.9
122.7 122.7
123.0 122.7
121.5
123.5
127.2
126.2
126.2125.7
126.2
122.7
122.0
122.2 122.7
122.7
122.2
123.2
123.7123.4
125.2
148.4
240.9
239.3
132.5
91.2
101.0
124.2123.7
124.4
120.2
137.8
133.9
132.3132.6
133.1
132.3
136.4
135.6
138.1
140.9
138.6139.8
141.8
140.5
142.5
WEY
MOUT
H AV
E.
37TH ST.
HAMI
LTON
AVE.
prepared by
Advanced Digital Maps, Inc
626-33 7-997 1
Map Scale: 1" - 40'
ADM 2371
Photo Date: 12-14-11
Con tour In terval= .5 Ft.
PASEO DEL MAR LANDSLIDE
0'120'80'40'
SCALE 1"=40'
CONCCONC
CONC
CONC
GNV
E 6,467,200
N 1,718,400
N 1,718,800
145
130
127.5
125
122.5
130
132.5
122.5
120115
110105100
9590
8580
22.5
52.5
7.5
3545
5565
75
125
2.557.5
12.515
20253035404550
110
105
70
107.5
67.570
72.5
95
122.5
85 82.590
82.580
2.55
7.5
3040
50
60
7080
90
100
122.5
122.5
120
120
122.5
125
145
142.5
140
137.5
135
132.5
130
147.5
150
152.5
155
257.5
265
260
137.5
135
130
132.5
127.5
140
142.5
137.5
142.5
132.5
142.5
140.6
137.8137.1
128.6
137.8
147.1
150.5
142.9
137.6
141.9
ROCKS
ROCKS
61.2
68.5
7.2
22.8
20.6
6.7
8.8
85.774.9
80.0
92.2
70.7
94.2
75.7 119.2
70.9 71.060.8
6.7 5.56.2 6.4
8.4
125.7
126.9
126.7
122.7
127.9128.1
136.3
128.8
124.2
138.3
138.3
137.9
138.4
138.5
133.3
139.5
!>!(
!.
!(
!> !.
!.
!>
!>Paseo Del Mar
Qsf
?
?
B-7
B-1
B-3
B-8B-9
B-4
B-6
B-2 B-5
Filen
ame:
I:\PR
OJEC
TS\10
052 S
an P
edro
Land
slide
\Grap
hics\P
ROPO
SED
BORI
NG LO
CATIO
NS.M
XD
White Point LandslideSan Pedro District
Los Angeles, California
SITE AND EXPLORATION PLAN
FIG. 1January 2012 51-1-10052-012
³
1 inch = 100 feet0 100 20050 Feet
LEGEND!( Boring!. Groundwater Well!> Inclinometer
Head ScarpApproximate Access Routes
City of Los Angeles, Bureau of Engineering
Attachment 2
Summary of Survey Monitoring Points
FIGURE 2
PT #1 N= 1718635.94 E= 6467068.78 EL= 121.92
DATE HORIZ CHANGE VERT CHANGE11/3/2011 0.00 0.0011/7/2011 0.01 0.00
11/14/2011 0.01 0.0111/21/2011 0.00 0.0011/25/2011 0.04 0.0111/26/2011 0.04 0.0012/21/2011 0.02 0.0012/28/2011 0.01 0.00
1/5/2012 0.02 0.001/12/2012 0.01 0.01
Standard Deviation 0.015 0.004
PT #2 N= 1718655.69 E= 6467008.02 EL= 121.53
DATE HORIZ CHANGE VERT CHANGE11/3/2011 0.00 0.0011/7/2011 0.01 0.00
11/14/2011 0.01 0.0111/21/2011 0.00 0.0011/25/2011 0.01 0.0111/26/2011 0.01 0.0112/21/2011 0.00 0.0012/28/2011 0.01 0.01
1/5/2012 0.02 0.021/12/2012 0.00 0.02
Standard Deviation 0.006 0.007
PT #3 N= 1718667.49 E= 6466973.29 EL= 121.50
DATE HORIZ CHANGE VERT CHANGE11/3/2011 0.00 0.0011/7/2011 0.03 0.01
11/14/2011 0.02 0.0011/21/2011 0.00 0.0011/25/2011 0.01 0.0111/26/2011 0.01 0.0112/21/2011 0.01 0.0112/28/2011 0.00 0.01
1/5/2012 0.03 0.021/12/2012 0.02 0.02
Standard Deviation 0.011 0.007
White Point Landslide
Page 1
FIGURE 2White Point Landslide
PT #4 N= 1718768.94 E= 6466747.41 EL= 121.97
DATE HORIZ CHANGE VERT CHANGE11/21/2011 0.00 0.0011/25/2011 0.03 0.0011/26/2011 0.01 0.00
1/5/2012 0.01 0.011/12/2012 0.01 0.00
Standard Deviation 0.014 0.004
PT #5 N= 1718777.57 E= 6466719.69 EL= 121.74
DATE HORIZ CHANGE VERT CHANGE11/21/2011 0.00 0.0011/25/2011 0.01 -0.0211/26/2011 0.03 0.00
1/5/2012 0.03 0.001/12/2012 0.03 0.01
Standard Deviation 0.016 0.008
The standard deviation for the measurements listed above are within the expected errors generated by the instrumentation and techniques employed to obtain the
values.
These results indicate that there is no observable ground movement.
Page 2