Upload
lokesh-konganapalle
View
225
Download
1
Embed Size (px)
Citation preview
8/19/2019 WBS-
1/1
LIS - 02
PACKAGE LIS-02
IMPLEMENTATION
0
LIS - 02.1
GENERAL
0
LIS - 02.1.1
CONTRACTUAL
MILESTONES
0
LIS - 02.1.2
SITE PREPRATIONS
& UTILITY
0
LIS - 02.1.3
INTERFACE ISSUES
0
LIS - 02.1.4
PERMITTING &
APPROVALS
0
LIS - 02.1.5
OFFICES &
TEMPORARY
0
LIS - 02.1.6
INSURANCES
0
LIS - 02.1.7
BONDS AND
GUARANTEES
0
LIS - 02.1.8
PROJECT
ASSURANCES
0
LIS - 02.1.9
METHOD
STATEMENTS
0
LIS - 02.1.10
OVERALL TESTING
AND
0
LIS - 02.1.11
OTHER
CONTRACTUAL
0
LIS - 02.2
PROCUREMENT-GEN
0
LIS - 02.2.1
MATERIALS
0
LIS - 02.2.2
PLANT & EQUIPMENT
0
LIS - 02.2.3
SUB CONTRACTORS
0
LIS - 02.2.3.1
GEOTECHNICAL
INVESTIGATION
0
LIS - 02.2.3.2
PRE & POST SURVEY
WORKS
0
LIS - 02.2.3.3
MATERIAL T ESTING
LABORATORY
0
LIS - 02.2.3.4
UTILITY DIVERSION
WORKS
0
LIS - 02.2.3.5
TEMPORARY
WORKS
0
LIS - 02.2.4
PRECAST
SEGMENTS
0
LIS - 02.3
EXECUTION
0
LIS - 02.3.1
EXECUTION-GENERA
0
LIS - 02.3.1.1
COORDINATION AND
DATA CO LLECTION
0
LIS - 02.3.1.2
SURVEY WORKS
AND
0
LIS - 02.3.1.3
DESIGN CRITERIA &
OTHER GENERAL
0
LIS - 02.3.2
DRIVE 01-ALL LINES
UPSTREAM OF SH 32
0
LIS - 02.3.2.1
TEMPORARY WORK
SHAFTS0
LIS - 02.3.2.2
PIPE JACKING
0
LIS - 02.3.2.3
MANHOLE
0
LIS - 02.3.3
DRIVE 02-FROM SH
32 TO SH 21
0
LIS - 02.3.3.1
TEMPORARY WORK
SHAFTS
0
LIS - 02.3.3.2
PIPE JACKING
0
LIS - 02.3.3.3
MANHOLE
0
LIS - 02.3.4
DRIVE 03-FROM SH
21 TO SH 11
0
LIS - 02.3.4.1
TEMPORARY WORK
SHAFTS
0
LIS - 02.3.4.2
PIPE JACKING
0
LIS - 02.3.4.3
MANHOLE
0
LIS - 02.3.5
DRIVE 04-FROM SH
11 TO WS 07 & SH
0
LIS - 02.3.5.1
TEMPORARY WORK
SHAFTS
0
LIS - 02.3.5.2
PIPE JACKING
0
LIS - 02.3.5.3
MANHOLE
0
LIS - 02.4
SUBSTANTIAL
COMPLETION
0
LIS - 02.4.1
MISCELLANEOUS
WORKS
0
LIS - 02.4.2
DESIGN
-PERMANENT
0
LIS - 02.4.3
PERMANENT ROUTE
MARKER
0
LIS - 02.4.4
FLOW METER
INSTALLATION
0
LIS - 02.4.5
SNAGLIST
CLEARENCE
0
LIS - 02.4.6
AS BUILT DRAWING
0
LIS - 02.5
MAINTENANCE
PERIOD
0
LIS - 02.5.1
FINAL HAND OVER
0
WBS CodeWBS Name
At Completion Labor