Virtual Design and Construction in Horizontal Construction-05!03!12

Embed Size (px)

Citation preview

  • 7/29/2019 Virtual Design and Construction in Horizontal Construction-05!03!12

    1/11

    1

    Virtual Design and Construction in Horizontal Infrastructure Projects

    By Eric Cylwik and Kevin Dwyer

    May 3, 2012

    In the past year, the Heavy/Civil Division of Sundt Construction, Inc.,based in Tempe, Ariz., has

    used virtual design and construction (VDC) to transform its approach to the construction of

    horizontal infrastructure projects like highways and bridges. VDC allows Sundt to design the

    best construction solutions for project owners by facilitating communications, reducing change

    orders and requests for information, eliminating rework, increasing productivity and quality,

    shortening schedules, creating computerized as-built drawings and specifications, and most

    importantly reducing costs.

    Sundt led the industry in applying Building Information Modeling (BIM) to vertical construction

    projects like office buildings, and is now transferring the lessons learned in that arena to

    horizontal projects. Although the principles, methods, software, hardware, and equipment

    involved in VDC and BIM are similar, participants in horizontal projects are wary of the BIM

    acronym because they believe that it applies exclusively to buildings. Therefore, Sundt uses the

    more neutral designation of VDC when referring to the creation and use of intelligent,

    parametric, interactive computer models in the realm of horizontal projects.

    Process

    VDC is not simply an improved tool it is an improvedprocessaimed at facilitating

    communication between participants at all levels. VDC improves the process and experience for

    owners, architects, engineers, general contractors, subcontractors, suppliers, and the public in thedesign and construction of complex, expensive, and time-consuming horizontal construction

    projects, regardless of the delivery method whether its design-bid-build, design-build, or

    construction manager at risk. When different portions of the improved process are executed

    under the right conditions at the right time, the process enhancements are seen and felt by

    everyone on the project team.

    Sundt began applying VDC to horizontal construction projects by asking questions about current

    construction methods and looking for technologies that improve capability, efficiency, and

    quality. Since the initial use of BIM, Sundt began searching for technologies to enhance specific

    horizontal construction processes. After a year of research, development, and testing, Sundt,along with other stakeholders, are reaping the benefits.

    Sundt first recognized the link between BIM and VDC as applied to horizontal projects while

    working on light rail projects. Similar to clash detection on HVAC and other systems in

    vertical building projects, VDC allowed Sundt to model and detect clashes between

    underground utilities like sewers and water lines. However, clash detection on horizontal projects

  • 7/29/2019 Virtual Design and Construction in Horizontal Construction-05!03!12

    2/11

    2

    is arguably more critical because of the inherent differences between most vertical and horizontal

    construction projects. Unlike vertical projects, which are usually unoccupied until completed,

    builders of many horizontal projects must accommodate traffic during construction and VDC

    helps with the process.

    Sundt plans to create construction-ready VDC models during preconstruction of most horizontalprojects and believes that the models have the potential to transform all phases of the

    construction process from surveying to paving to recording as-built information and everything

    in between including excavation and forming. Since VDC is in its infancy, Sundt continues to

    evaluate enhancements.

    Differences between Vertical and Horizontal Construction

    Construction processes in the world of vertical buildings are often repeated and repeatable. For

    instance, builders may use the exact same formwork when placing concrete decks on two

    separate buildings. The same trusses and supports used to support one deck can be used on thefloor above as well as on a deck at a project across town. Horizontal projects are different. The

    design and construction of highways, bridges, roads, and associated utilities are more complex

    due to changing surface conditions and the need to tie into existing infrastructure elements. VDC

    allows Sundt to cope with complexity while improving efficiency and meeting contractual

    requirements.

    When building roads, bridges or utility projects, builders must deal with the variable contours of

    the land, site conditions, and the need to coordinate traffic during construction. In view of these

    factors, the software and methods used in VDC often have to be more flexible than those used in

    BIM. In contrast to the deck example cited earlier, the inherent complexity of horizontal projectsprevents the creation and use of single static elements of a model over the entire scope of a

    project. A single section of a road can easily have more than ten different conditions that can

    change in a short span.

    VDC on Horizontal Projects

    The VDC process may begin by

    obtaining a 3D laser scan of the project

    site that is accurate to within a

    millimeter. A 3D laser scan measures

    any visible objects by timing how long

    it takes light to bounce back. This

    method creates millions of very precise

    measurements that together create a

    point cloud. Figure 1 shows the millions of

    points as white dots that represent real structures and objects. This model can be navigated in 3D

    and the user can take measurements directly in the program. This allows estimators to

    Fi ure1

  • 7/29/2019 Virtual Design and Construction in Horizontal Construction-05!03!12

    3/11

    3

    incorporate the laser scan into a preliminary VDC model based on the design that allows them to

    explore existing conditions and evaluate proposed construction methods such as project phasing,

    traffic control, excavation sequencing, and material selection. Figure 2 demonstrates how an

    estimating team reconstructed an existing

    bridge.

    Estimates created within the context of

    VDC can require more time and effort at the

    beginning, but the resulting models are

    accurate and flexible enough to handle

    many project variables and alternative

    scenarios. Because the models are created

    within a 3D virtual environment, estimators

    can evaluate different construction methods

    without incurring the costs of mockups or prototypes.For instance, at the click of the mouse, an estimator can

    change a Type A Shored Trench, to a Type B Single

    Bench Trench, or even a Type C Multiple Bench

    Trench in an effort to explore quantity, productivity, and

    cost impacts. Figure 3 shows sample options that an

    estimator can select. Beyond selecting general shapes such

    as vertical or stepped sides, they can also specify

    parameters like slopes and distances. Instead of spending

    time calculating quantities by hand, estimators may focus

    their efforts on adding value by delivering the best solutions

    to project owners. As the VDC model evolves, project

    teams can identify and resolve coordination issues before

    construction begins and costs are incurred. For instance,

    Sundt is able to model existing and new utilities and to rectify clashes before encountering the

    conditions in the field. Figures 4, 5, and 6 are taken from a three-mile-long light rail project

    through the heart of Phoenix, Ariz. Being able to see underground was critical to ensuring all

    costs were captured and accounted for in the estimate. Not only can this process uncover

    Figure2

    Figure4 Figure5 Figure6

    Figure3

  • 7/29/2019 Virtual Design and Construction in Horizontal Construction-05!03!12

    4/11

    4

    coordination issues, it can also reveal construction issues because methods such as trenching are

    incorporated in the model. In VDC software, common trench styles, such as those in Figure 3,

    are simplified down to basic and specific instructions regarding distances and angles, such as

    the trench bottom is six inches below the invert elevation, or the trench width is five feet.

    VDC software approaches instructions like these with packets of commands called

    subassemblies.

    Subassemblies

    Subassemblies are small, intelligent sets of instructions that electronically depict road surfaces,

    retaining walls, typical road details, bridges, grading standards, rail tracks, utilities, trenching

    methods and more. Subassemblies are stored in libraries within the VDC software and inserted

    where appropriate. Figure 7 represents a small sample of instructions that are used in a

    subassembly. It shows starting from a specific point and moving a certain distance horizontally

    and vertically based on input from the user. Subassemblies are parametric in that they allow the

    components to stretch inappropriate ways to

    accommodate the specific

    application. Imagine a

    stretchy piece of paper: if

    it were parametric, it could

    stretch to 11 x 17, 24 x 36, or even 5 x 3, all while still being

    the same piece of paper. Similar stretching is accomplished through

    parametric subassemblies. For instance, a road subassembly can

    stretch to accommodate various road widths, thicknesses of aggregate

    base course or asphaltic concrete, or changes to the slope of the

    shoulder.

    Owners, including departments of transportation, often define these

    types of instructions in their standard specifications. For example, a

    Type I retaining wall subassembly may contain consistent

    dimensions for the footings, specific requirements for the footing toe,

    and adjustable dimensions for the height of the footing wall. To

    model these features, subassemblies contain variables such as footing

    width, wall thickness, and wall height along with rules or algorithms

    to define slopes and other features. Based on specific input, subassemblies calculate physically

    accurate shapes. These shapes contain information about quantities, survey points, and guide

    machines in conjunction with total stations or the global positioning system.

    VDC models are often able to implement subassemblies by reading the types of spreadsheets that

    estimators have traditionally created. For instance, when estimators take off a retaining wall, they

    Figure7

    Figure8

  • 7/29/2019 Virtual Design and Construction in Horizontal Construction-05!03!12

    5/11

    5

    typically generate a spreadsheet with cells that represent the top of wall profile, top of footing

    profile, and the structural type of the wall.

    Figure 8 is a typical department of transportation retaining wall. It defines the shape of a

    retaining wall similar to a subassembly. The standard defines the thickness of the footing from

    the top of footing point down a distance of B as the first instruction. The second instruction ofa subassembly might be to go W units over, creating the width of the footing. Now the

    subassembly knows the shape and size of the footing. Figure 9 is a sample showing the values

    for all of the variables associated with the retaining wall. Figure 10 shows the final result: a

    subassembly based on the logic from Figure 8 and the dimensions from Figure 9. The diagonal

    lines on the left represent a decision made by the subassembly. The spreadsheet, along with a 3D

    topographical file or laser scan, can provide the

    input needed for a subassembly to create

    retaining walls based on real world information,

    not guesses or assumptions.

    In contrast to relying solely on spreadsheets,

    models also incorporate real world coordinates to

    calculate existing and finished grades and

    provide more accurate takeoffs of cut and fill

    quantities. An excellent example is a 45-foot

    trench on a site improvement project that Sundt

    was recently awarded. Traditionally, an estimator

    would have reviewed the plans to figure out the

    average existing surface elevation and the average trench

    depth. He or she would plug those numbers into a spreadsheet to calculate the excavation

    quantities. The same is also true for calculating volumes of shapes that curve, for example, a

    retaining wall that bends as it approaches an intersection. VDC software can calculate volumes

    on a curve just as easily as volumes on a straight

    section of road.

    By using a VDC model, estimators can calculate

    every foot of the trench from exact existing

    elevations and exact trench depths and apply a slope

    formula to figure out the exact amount of excavation

    required. The set of commands in the subassembly

    can incorporate intelligent commands like, start at

    the invert elevation of the pipe at the current

    station, and the next command can be if the

    existing grade is more than twenty feet, build trench

    A. If it is less than twenty feet, build trench B.

    Figure9

    Figure10

  • 7/29/2019 Virtual Design and Construction in Horizontal Construction-05!03!12

    6/11

    6

    Laser scanning improves the process further since it provides up-to-date information on the

    existing terrain instead of relying on outdated data. Other examples are bridges that typically

    follow standard tub, stem, or beam designs promulgated by departments of transportation with

    the profile and slope information applied. Using estimators spreadsheets, VDC models can

    generate quantities of materials needed along with the capability to plan the work. An estimator

    can utilize this same file to generate survey quality data on specific points or surfaces of the

    bridge.

    Fourth and Fifth Dimensions

    Modeling projects properly during the estimating process allows construction teams to link the

    schedule the fourth dimension (4D) and budget the fifth dimension (5D) to the three

    dimensional model and to begin

    construction immediately after receipt of

    the notice to proceed. A detailed phasing

    plan for complex steel arches is shown inFigure 11. Not only does this model

    include the physical pieces to install, it

    shows the order and the phasing of the

    scaffolding.Sending VDC models tosubcontractors facilitates the development

    of shop drawings and allows the

    incorporation of subsidiary models

    prepared by subcontractors for their scopes

    of work. VDC can be used as a platform

    for communication of the huge volumes of information contained in a project, as opposed to a

    CAD file that only contains line work. VDC also facilitates the creation of animations that

    dramatically demonstrate the construction process over time and allows Sundt to identify the

    most efficient means of construction.Recently, Sundt self-performed deep

    excavations with shoring subcontractors by

    creating a VDC model that showed the

    volumes to be excavated for an

    underground structure. Sundt was able to

    calculate the surface area that required

    shoring at the end of each shift. This

    process allowed Sundt and its

    subcontractors to communicate better as

    well as reduce costs and possible time

    impacts of miscalculated quantities. Having specific quantities for each shift ensured that

    proper crews and equipment were onsite based on each days need. Figure 12 is an excavation pit

    Figure11

    Figure12

  • 7/29/2019 Virtual Design and Construction in Horizontal Construction-05!03!12

    7/11

    7

    for a basement thirty feet underground. The model was not only able to calculate specific dirt

    volume quantities, but also the area exposed when the volumes were removed.

    Ancillary Benefits of VDC

    Other benefits flow from VDC models. For instance, project managers and superintendents mayuse quantity information generated by VDC models to create work plans as shown in Figure 12,

    generate daily reports, and provide feedback on the status of construction. In addition, the public

    may view models in order to visualize and monitor construction activities and coordinate travel

    and work plans.

    In Portland, Ore., Multnomah County instituted a public relations program on the Sellwood

    Bridge project that allowed Sundt to publish construction models suitable to the needs of the

    public. A series of videos atwww.sellwoodbridge.orgshows construction phasing for this

    complex bridge project that

    involves moving an existingbridge almost sixty feet to

    carry traffic while a new

    bridge is built. Figure 13

    shows the bridge after the

    move to its temporary

    location. The object in red is

    the original bridge pier.

    Traffic flow is represented

    with green arrows.Another example illustrates the advantages of VDC. Traditionally, surveyors have calculated the

    points needed to define the location of roads by plugging numbers into as many as six different

    formulas. Since the complexity of roads varies considerably, it is difficult to define the typical

    amount of time and expense of using traditional

    methods. Nevertheless, to demonstrate the

    advantages of VDC, Figure 14 illustrates a

    typical 20-step process for calculating bridge

    points. A surveyor following traditional

    processes might spend 20 hours calculating the

    1,400 points needed to define a complex sectionof road, if we assume that each point takes an

    average of one minute to calculate (a

    conservative assumption).

    Figure13

    Figure14

  • 7/29/2019 Virtual Design and Construction in Horizontal Construction-05!03!12

    8/11

    8

    In contrast, by using VDC and creating models of typical road sections, surveyors can

    visualize the project, understand the requirements, and avoid spending large blocks of time

    solving math problems that computers can solve instantaneously. Based on Sundts experience,

    using this method can easily reduce calculation time by up to thirty percent. If discrepancies

    arise, the survey crew can use the construction documents to verify features and components in

    the model.

    VDC and Equipment

    After the participants on a horizontal construction project verify the VDC model and set the

    controls on the jobsite, operators can upload files containing the alignment and 3D surface of the

    road to computers in heavy equipment like graders or excavators. The surface model provides

    operators with information needed to grade roads or dig trenches. A computer screen in the

    grader or excavator displays exactly where to cut or fill based on the location of the blade or

    bucket. When work has progressed to the point of the final pass, operators can turn on automated

    machine guidance and allow computers to make the millions of micro adjustments needed toachieve a perfect grade.

    For example, when lowering the profile of an existing 5,000-foot stretch of Interstate-17 in

    Arizona, Sundt used this process to ensure proper survey calculations and loaded the model

    directly into computerized monitors on heavy civil equipment. Not only did it save time by

    eliminating the need for a two-man survey crew to spend two weeks blue topping the road

    (placing wooden stakes to define the top of the grade), the productivity rate of Sundts equipment

    and crews increased significantly since there was constant and direct communication via

    automated machine guidance. Sundt was able to deliver a quality product to the owner without

    need for rework.

    Other efficiencies that flow from VDC include less wear and tear on equipment, reduced fuel

    consumption, and fewer injuries. In addition, VDC models can adjust to changes in elevation,

    baseline, superelevated roadways, and drainage conditions as well as blending finished grades

    into other construction elements. For instance, one segment of roadway might daylight at a 4:1

    grade while ten feet way it might daylight at 3:1. Figure 15 shows an intelligent model with five

    different road scenarios on

    the left, and a standard option

    on the right. The model is

    able to read conditions anddecide which scenario to use.

    VDC also allows surveyors to

    establish elevations for specific points on concrete bridges in a one-step process, instead of the

    traditional two-step process. By using a 3D model of the proposed deck surface, computerized

    equipment is able to calculate real time cut and fill dimensions for any spot on the bridge. They

    Figure15

  • 7/29/2019 Virtual Design and Construction in Horizontal Construction-05!03!12

    9/11

    9

    no longer have to collect 3D points in the field and then return to the office to calculate the

    corresponding proposed elevations by hand. The model computes the required coordinates by

    comparing real world data uploaded into the model against the design coordinates in real time

    out in the field. The surveyors equipment uses the same process as the grader to display real

    time information showing existing conditions compared to proposed conditions. As a result,

    surveyors can give instant feedback about any given point on a bridge and no office calculation

    time is required.

    One of the greatest benefits of VDC is that it facilitates the discovery of clashes and coordination

    issues within the virtual environment of the computer not in the field and consequently

    reduces requests for information and change orders along with the associated health and safety

    risks. On a recent project involving a complex trenching method, Sundt utilized VDCs accurate

    dimensional modeling capabilities to comply with OSHA regulations that stipulate that if the

    bottom of a trench is more than twenty feet deep, it needs to have a bench in the sidewall to

    prevent the walls from caving in and potentially injuring workers. VDC leads to solutions by

    enhancing communications between participants by allowing them to visualize challenges in an

    intuitive environment that may be manipulated to illustrate problems and create solutions.VDC also improves quantity calculations and reduces raw material costs. For example, models

    allow builders to know instantly whether they have placed the proper quantities of materials like

    aggregate base course because the model is linked directly to computers in the cabs of heavy

    equipment. Traditionally, builders erred on the side of placing too much material rather than too

    little in order to meet or exceed specifications. In short, teams using VDC experience fewer

    communication problems due to the wealth of information communicated via virtual design and

    construction software. When a designer specifies a road width or structural thickness, it is

    communicated to every stakeholder through VDC software on demand and the designers intent

    is not hidden in hundreds of pages of project plans and specifications.

    Case Study

    Recently, Sundt submitted a

    bid on a medical hospital

    project for the U.S. Army that

    included placing a sewer pipe

    forty-five feet below grade.

    Traditionally, on this type ofproject estimators would have

    used an Excel spreadsheet

    similar to the one showed in

    Figure 16 that includes

    information about depth and the existing grade with the concomitant potential for errors. In

    contrast, a VDC model allowed the estimator to evaluate the process quickly and efficiently.

    Figure16

  • 7/29/2019 Virtual Design and Construction in Horizontal Construction-05!03!12

    10/11

    10

    By analyzing different scenarios with a VDC model, the estimator analyzed daylight slopes on

    the side of the trench, which allowed Sundt to make an informed decision regarding the best

    method of construction. The VDC model allowed the estimator to evaluate three scenarios:

    digging the entire trench in one pass and moving all of the dirt elsewhere on the site; a two-pass

    method that involved moving excavated dirt two times; and a two-pass method that involved

    moving the dirt once. Each scenario implied different quantities and costs. The model allowed

    Sundt to visualize the sections of the trench based on the alignment and profile of the pipe.

    Using VDC, the estimator explored a two-step process to install the sewer pipe at a lower cost

    than using traditional methods. The first step analyzed using a scraper to plough out a flat area

    twenty-five feet below the existing grade. The area excavated followed the slopes of the existing

    parcel as well as the alignment and profile

    of the proposed sewer pipe while

    automatically displaying offset and

    elevation information.

    To reduce construction costs, the scraper

    will dig the trench wide enough to hold

    the dirt excavated from the twenty-foot

    trench required for installation of the pipe

    at forty-five feet below grade. This

    innovative method avoids the costs and

    delays associated with placing the dirt in

    trucks, hauling it to another location

    during construction, and then hauling itback to fill the trench. Figure 17 is a

    section through the proposed trench. The

    orange area illustrates the first scraper

    pass, the light green the excavator pass,

    and the dark green where the extra dirt

    was placed. Figure 18 is the 3D model

    showing a section every twenty-five feet.

    In addition, the VDC model of the trench

    was loaded directly onto scrapers andexcavators with automated machine guidance. This provided instant feedback to the operators

    and ensured that the trench precisely followed the model used to estimate the project. As a

    bonus, during construction Sundt generated as-built information at no additional cost using the

    GPS features on the excavator.

    Figure17

    Figure18

  • 7/29/2019 Virtual Design and Construction in Horizontal Construction-05!03!12

    11/11

    11

    Contrary to the concerns of current industry professionals, participants do not necessarily need to

    become experts on using VDC software because subassemblies or templates can read

    spreadsheets that provide the information needed by models. After the information is loaded and

    checked, intelligent templates or subassemblies can precisely calculate angles, elevations, grade

    breaks, and volumes. Estimators may then use the resulting model to take off quantities and to

    plan the project since the model is a byproduct of the estimate.

    Conclusion

    Lagging productivity and adversarial relationships plague the construction industry. As part of its

    commitment to deliver quality horizontal projects to owners on time and within budget, Sundt

    has demonstrated that VDC improves the constructionprocessand frees skilled professionals to

    concentrate on creating solutions instead of calculating quantities or fixing problems in the field.

    VDC enables all participants in a horizontal construction project owners, architects, engineers,

    general contractors, subcontractors, suppliers, and the public to visualize the entireprocess in a

    seamless, holistic way and to create innovative techniques to meet increasingly constrainedbudgets and deadlines. Sundt invites all participants to join us as we explore the possibilities.