Upload
charibackup
View
213
Download
0
Embed Size (px)
Citation preview
7/29/2019 Virtual Design and Construction in Horizontal Construction-05!03!12
1/11
1
Virtual Design and Construction in Horizontal Infrastructure Projects
By Eric Cylwik and Kevin Dwyer
May 3, 2012
In the past year, the Heavy/Civil Division of Sundt Construction, Inc.,based in Tempe, Ariz., has
used virtual design and construction (VDC) to transform its approach to the construction of
horizontal infrastructure projects like highways and bridges. VDC allows Sundt to design the
best construction solutions for project owners by facilitating communications, reducing change
orders and requests for information, eliminating rework, increasing productivity and quality,
shortening schedules, creating computerized as-built drawings and specifications, and most
importantly reducing costs.
Sundt led the industry in applying Building Information Modeling (BIM) to vertical construction
projects like office buildings, and is now transferring the lessons learned in that arena to
horizontal projects. Although the principles, methods, software, hardware, and equipment
involved in VDC and BIM are similar, participants in horizontal projects are wary of the BIM
acronym because they believe that it applies exclusively to buildings. Therefore, Sundt uses the
more neutral designation of VDC when referring to the creation and use of intelligent,
parametric, interactive computer models in the realm of horizontal projects.
Process
VDC is not simply an improved tool it is an improvedprocessaimed at facilitating
communication between participants at all levels. VDC improves the process and experience for
owners, architects, engineers, general contractors, subcontractors, suppliers, and the public in thedesign and construction of complex, expensive, and time-consuming horizontal construction
projects, regardless of the delivery method whether its design-bid-build, design-build, or
construction manager at risk. When different portions of the improved process are executed
under the right conditions at the right time, the process enhancements are seen and felt by
everyone on the project team.
Sundt began applying VDC to horizontal construction projects by asking questions about current
construction methods and looking for technologies that improve capability, efficiency, and
quality. Since the initial use of BIM, Sundt began searching for technologies to enhance specific
horizontal construction processes. After a year of research, development, and testing, Sundt,along with other stakeholders, are reaping the benefits.
Sundt first recognized the link between BIM and VDC as applied to horizontal projects while
working on light rail projects. Similar to clash detection on HVAC and other systems in
vertical building projects, VDC allowed Sundt to model and detect clashes between
underground utilities like sewers and water lines. However, clash detection on horizontal projects
7/29/2019 Virtual Design and Construction in Horizontal Construction-05!03!12
2/11
2
is arguably more critical because of the inherent differences between most vertical and horizontal
construction projects. Unlike vertical projects, which are usually unoccupied until completed,
builders of many horizontal projects must accommodate traffic during construction and VDC
helps with the process.
Sundt plans to create construction-ready VDC models during preconstruction of most horizontalprojects and believes that the models have the potential to transform all phases of the
construction process from surveying to paving to recording as-built information and everything
in between including excavation and forming. Since VDC is in its infancy, Sundt continues to
evaluate enhancements.
Differences between Vertical and Horizontal Construction
Construction processes in the world of vertical buildings are often repeated and repeatable. For
instance, builders may use the exact same formwork when placing concrete decks on two
separate buildings. The same trusses and supports used to support one deck can be used on thefloor above as well as on a deck at a project across town. Horizontal projects are different. The
design and construction of highways, bridges, roads, and associated utilities are more complex
due to changing surface conditions and the need to tie into existing infrastructure elements. VDC
allows Sundt to cope with complexity while improving efficiency and meeting contractual
requirements.
When building roads, bridges or utility projects, builders must deal with the variable contours of
the land, site conditions, and the need to coordinate traffic during construction. In view of these
factors, the software and methods used in VDC often have to be more flexible than those used in
BIM. In contrast to the deck example cited earlier, the inherent complexity of horizontal projectsprevents the creation and use of single static elements of a model over the entire scope of a
project. A single section of a road can easily have more than ten different conditions that can
change in a short span.
VDC on Horizontal Projects
The VDC process may begin by
obtaining a 3D laser scan of the project
site that is accurate to within a
millimeter. A 3D laser scan measures
any visible objects by timing how long
it takes light to bounce back. This
method creates millions of very precise
measurements that together create a
point cloud. Figure 1 shows the millions of
points as white dots that represent real structures and objects. This model can be navigated in 3D
and the user can take measurements directly in the program. This allows estimators to
Fi ure1
7/29/2019 Virtual Design and Construction in Horizontal Construction-05!03!12
3/11
3
incorporate the laser scan into a preliminary VDC model based on the design that allows them to
explore existing conditions and evaluate proposed construction methods such as project phasing,
traffic control, excavation sequencing, and material selection. Figure 2 demonstrates how an
estimating team reconstructed an existing
bridge.
Estimates created within the context of
VDC can require more time and effort at the
beginning, but the resulting models are
accurate and flexible enough to handle
many project variables and alternative
scenarios. Because the models are created
within a 3D virtual environment, estimators
can evaluate different construction methods
without incurring the costs of mockups or prototypes.For instance, at the click of the mouse, an estimator can
change a Type A Shored Trench, to a Type B Single
Bench Trench, or even a Type C Multiple Bench
Trench in an effort to explore quantity, productivity, and
cost impacts. Figure 3 shows sample options that an
estimator can select. Beyond selecting general shapes such
as vertical or stepped sides, they can also specify
parameters like slopes and distances. Instead of spending
time calculating quantities by hand, estimators may focus
their efforts on adding value by delivering the best solutions
to project owners. As the VDC model evolves, project
teams can identify and resolve coordination issues before
construction begins and costs are incurred. For instance,
Sundt is able to model existing and new utilities and to rectify clashes before encountering the
conditions in the field. Figures 4, 5, and 6 are taken from a three-mile-long light rail project
through the heart of Phoenix, Ariz. Being able to see underground was critical to ensuring all
costs were captured and accounted for in the estimate. Not only can this process uncover
Figure2
Figure4 Figure5 Figure6
Figure3
7/29/2019 Virtual Design and Construction in Horizontal Construction-05!03!12
4/11
4
coordination issues, it can also reveal construction issues because methods such as trenching are
incorporated in the model. In VDC software, common trench styles, such as those in Figure 3,
are simplified down to basic and specific instructions regarding distances and angles, such as
the trench bottom is six inches below the invert elevation, or the trench width is five feet.
VDC software approaches instructions like these with packets of commands called
subassemblies.
Subassemblies
Subassemblies are small, intelligent sets of instructions that electronically depict road surfaces,
retaining walls, typical road details, bridges, grading standards, rail tracks, utilities, trenching
methods and more. Subassemblies are stored in libraries within the VDC software and inserted
where appropriate. Figure 7 represents a small sample of instructions that are used in a
subassembly. It shows starting from a specific point and moving a certain distance horizontally
and vertically based on input from the user. Subassemblies are parametric in that they allow the
components to stretch inappropriate ways to
accommodate the specific
application. Imagine a
stretchy piece of paper: if
it were parametric, it could
stretch to 11 x 17, 24 x 36, or even 5 x 3, all while still being
the same piece of paper. Similar stretching is accomplished through
parametric subassemblies. For instance, a road subassembly can
stretch to accommodate various road widths, thicknesses of aggregate
base course or asphaltic concrete, or changes to the slope of the
shoulder.
Owners, including departments of transportation, often define these
types of instructions in their standard specifications. For example, a
Type I retaining wall subassembly may contain consistent
dimensions for the footings, specific requirements for the footing toe,
and adjustable dimensions for the height of the footing wall. To
model these features, subassemblies contain variables such as footing
width, wall thickness, and wall height along with rules or algorithms
to define slopes and other features. Based on specific input, subassemblies calculate physically
accurate shapes. These shapes contain information about quantities, survey points, and guide
machines in conjunction with total stations or the global positioning system.
VDC models are often able to implement subassemblies by reading the types of spreadsheets that
estimators have traditionally created. For instance, when estimators take off a retaining wall, they
Figure7
Figure8
7/29/2019 Virtual Design and Construction in Horizontal Construction-05!03!12
5/11
5
typically generate a spreadsheet with cells that represent the top of wall profile, top of footing
profile, and the structural type of the wall.
Figure 8 is a typical department of transportation retaining wall. It defines the shape of a
retaining wall similar to a subassembly. The standard defines the thickness of the footing from
the top of footing point down a distance of B as the first instruction. The second instruction ofa subassembly might be to go W units over, creating the width of the footing. Now the
subassembly knows the shape and size of the footing. Figure 9 is a sample showing the values
for all of the variables associated with the retaining wall. Figure 10 shows the final result: a
subassembly based on the logic from Figure 8 and the dimensions from Figure 9. The diagonal
lines on the left represent a decision made by the subassembly. The spreadsheet, along with a 3D
topographical file or laser scan, can provide the
input needed for a subassembly to create
retaining walls based on real world information,
not guesses or assumptions.
In contrast to relying solely on spreadsheets,
models also incorporate real world coordinates to
calculate existing and finished grades and
provide more accurate takeoffs of cut and fill
quantities. An excellent example is a 45-foot
trench on a site improvement project that Sundt
was recently awarded. Traditionally, an estimator
would have reviewed the plans to figure out the
average existing surface elevation and the average trench
depth. He or she would plug those numbers into a spreadsheet to calculate the excavation
quantities. The same is also true for calculating volumes of shapes that curve, for example, a
retaining wall that bends as it approaches an intersection. VDC software can calculate volumes
on a curve just as easily as volumes on a straight
section of road.
By using a VDC model, estimators can calculate
every foot of the trench from exact existing
elevations and exact trench depths and apply a slope
formula to figure out the exact amount of excavation
required. The set of commands in the subassembly
can incorporate intelligent commands like, start at
the invert elevation of the pipe at the current
station, and the next command can be if the
existing grade is more than twenty feet, build trench
A. If it is less than twenty feet, build trench B.
Figure9
Figure10
7/29/2019 Virtual Design and Construction in Horizontal Construction-05!03!12
6/11
6
Laser scanning improves the process further since it provides up-to-date information on the
existing terrain instead of relying on outdated data. Other examples are bridges that typically
follow standard tub, stem, or beam designs promulgated by departments of transportation with
the profile and slope information applied. Using estimators spreadsheets, VDC models can
generate quantities of materials needed along with the capability to plan the work. An estimator
can utilize this same file to generate survey quality data on specific points or surfaces of the
bridge.
Fourth and Fifth Dimensions
Modeling projects properly during the estimating process allows construction teams to link the
schedule the fourth dimension (4D) and budget the fifth dimension (5D) to the three
dimensional model and to begin
construction immediately after receipt of
the notice to proceed. A detailed phasing
plan for complex steel arches is shown inFigure 11. Not only does this model
include the physical pieces to install, it
shows the order and the phasing of the
scaffolding.Sending VDC models tosubcontractors facilitates the development
of shop drawings and allows the
incorporation of subsidiary models
prepared by subcontractors for their scopes
of work. VDC can be used as a platform
for communication of the huge volumes of information contained in a project, as opposed to a
CAD file that only contains line work. VDC also facilitates the creation of animations that
dramatically demonstrate the construction process over time and allows Sundt to identify the
most efficient means of construction.Recently, Sundt self-performed deep
excavations with shoring subcontractors by
creating a VDC model that showed the
volumes to be excavated for an
underground structure. Sundt was able to
calculate the surface area that required
shoring at the end of each shift. This
process allowed Sundt and its
subcontractors to communicate better as
well as reduce costs and possible time
impacts of miscalculated quantities. Having specific quantities for each shift ensured that
proper crews and equipment were onsite based on each days need. Figure 12 is an excavation pit
Figure11
Figure12
7/29/2019 Virtual Design and Construction in Horizontal Construction-05!03!12
7/11
7
for a basement thirty feet underground. The model was not only able to calculate specific dirt
volume quantities, but also the area exposed when the volumes were removed.
Ancillary Benefits of VDC
Other benefits flow from VDC models. For instance, project managers and superintendents mayuse quantity information generated by VDC models to create work plans as shown in Figure 12,
generate daily reports, and provide feedback on the status of construction. In addition, the public
may view models in order to visualize and monitor construction activities and coordinate travel
and work plans.
In Portland, Ore., Multnomah County instituted a public relations program on the Sellwood
Bridge project that allowed Sundt to publish construction models suitable to the needs of the
public. A series of videos atwww.sellwoodbridge.orgshows construction phasing for this
complex bridge project that
involves moving an existingbridge almost sixty feet to
carry traffic while a new
bridge is built. Figure 13
shows the bridge after the
move to its temporary
location. The object in red is
the original bridge pier.
Traffic flow is represented
with green arrows.Another example illustrates the advantages of VDC. Traditionally, surveyors have calculated the
points needed to define the location of roads by plugging numbers into as many as six different
formulas. Since the complexity of roads varies considerably, it is difficult to define the typical
amount of time and expense of using traditional
methods. Nevertheless, to demonstrate the
advantages of VDC, Figure 14 illustrates a
typical 20-step process for calculating bridge
points. A surveyor following traditional
processes might spend 20 hours calculating the
1,400 points needed to define a complex sectionof road, if we assume that each point takes an
average of one minute to calculate (a
conservative assumption).
Figure13
Figure14
7/29/2019 Virtual Design and Construction in Horizontal Construction-05!03!12
8/11
8
In contrast, by using VDC and creating models of typical road sections, surveyors can
visualize the project, understand the requirements, and avoid spending large blocks of time
solving math problems that computers can solve instantaneously. Based on Sundts experience,
using this method can easily reduce calculation time by up to thirty percent. If discrepancies
arise, the survey crew can use the construction documents to verify features and components in
the model.
VDC and Equipment
After the participants on a horizontal construction project verify the VDC model and set the
controls on the jobsite, operators can upload files containing the alignment and 3D surface of the
road to computers in heavy equipment like graders or excavators. The surface model provides
operators with information needed to grade roads or dig trenches. A computer screen in the
grader or excavator displays exactly where to cut or fill based on the location of the blade or
bucket. When work has progressed to the point of the final pass, operators can turn on automated
machine guidance and allow computers to make the millions of micro adjustments needed toachieve a perfect grade.
For example, when lowering the profile of an existing 5,000-foot stretch of Interstate-17 in
Arizona, Sundt used this process to ensure proper survey calculations and loaded the model
directly into computerized monitors on heavy civil equipment. Not only did it save time by
eliminating the need for a two-man survey crew to spend two weeks blue topping the road
(placing wooden stakes to define the top of the grade), the productivity rate of Sundts equipment
and crews increased significantly since there was constant and direct communication via
automated machine guidance. Sundt was able to deliver a quality product to the owner without
need for rework.
Other efficiencies that flow from VDC include less wear and tear on equipment, reduced fuel
consumption, and fewer injuries. In addition, VDC models can adjust to changes in elevation,
baseline, superelevated roadways, and drainage conditions as well as blending finished grades
into other construction elements. For instance, one segment of roadway might daylight at a 4:1
grade while ten feet way it might daylight at 3:1. Figure 15 shows an intelligent model with five
different road scenarios on
the left, and a standard option
on the right. The model is
able to read conditions anddecide which scenario to use.
VDC also allows surveyors to
establish elevations for specific points on concrete bridges in a one-step process, instead of the
traditional two-step process. By using a 3D model of the proposed deck surface, computerized
equipment is able to calculate real time cut and fill dimensions for any spot on the bridge. They
Figure15
7/29/2019 Virtual Design and Construction in Horizontal Construction-05!03!12
9/11
9
no longer have to collect 3D points in the field and then return to the office to calculate the
corresponding proposed elevations by hand. The model computes the required coordinates by
comparing real world data uploaded into the model against the design coordinates in real time
out in the field. The surveyors equipment uses the same process as the grader to display real
time information showing existing conditions compared to proposed conditions. As a result,
surveyors can give instant feedback about any given point on a bridge and no office calculation
time is required.
One of the greatest benefits of VDC is that it facilitates the discovery of clashes and coordination
issues within the virtual environment of the computer not in the field and consequently
reduces requests for information and change orders along with the associated health and safety
risks. On a recent project involving a complex trenching method, Sundt utilized VDCs accurate
dimensional modeling capabilities to comply with OSHA regulations that stipulate that if the
bottom of a trench is more than twenty feet deep, it needs to have a bench in the sidewall to
prevent the walls from caving in and potentially injuring workers. VDC leads to solutions by
enhancing communications between participants by allowing them to visualize challenges in an
intuitive environment that may be manipulated to illustrate problems and create solutions.VDC also improves quantity calculations and reduces raw material costs. For example, models
allow builders to know instantly whether they have placed the proper quantities of materials like
aggregate base course because the model is linked directly to computers in the cabs of heavy
equipment. Traditionally, builders erred on the side of placing too much material rather than too
little in order to meet or exceed specifications. In short, teams using VDC experience fewer
communication problems due to the wealth of information communicated via virtual design and
construction software. When a designer specifies a road width or structural thickness, it is
communicated to every stakeholder through VDC software on demand and the designers intent
is not hidden in hundreds of pages of project plans and specifications.
Case Study
Recently, Sundt submitted a
bid on a medical hospital
project for the U.S. Army that
included placing a sewer pipe
forty-five feet below grade.
Traditionally, on this type ofproject estimators would have
used an Excel spreadsheet
similar to the one showed in
Figure 16 that includes
information about depth and the existing grade with the concomitant potential for errors. In
contrast, a VDC model allowed the estimator to evaluate the process quickly and efficiently.
Figure16
7/29/2019 Virtual Design and Construction in Horizontal Construction-05!03!12
10/11
10
By analyzing different scenarios with a VDC model, the estimator analyzed daylight slopes on
the side of the trench, which allowed Sundt to make an informed decision regarding the best
method of construction. The VDC model allowed the estimator to evaluate three scenarios:
digging the entire trench in one pass and moving all of the dirt elsewhere on the site; a two-pass
method that involved moving excavated dirt two times; and a two-pass method that involved
moving the dirt once. Each scenario implied different quantities and costs. The model allowed
Sundt to visualize the sections of the trench based on the alignment and profile of the pipe.
Using VDC, the estimator explored a two-step process to install the sewer pipe at a lower cost
than using traditional methods. The first step analyzed using a scraper to plough out a flat area
twenty-five feet below the existing grade. The area excavated followed the slopes of the existing
parcel as well as the alignment and profile
of the proposed sewer pipe while
automatically displaying offset and
elevation information.
To reduce construction costs, the scraper
will dig the trench wide enough to hold
the dirt excavated from the twenty-foot
trench required for installation of the pipe
at forty-five feet below grade. This
innovative method avoids the costs and
delays associated with placing the dirt in
trucks, hauling it to another location
during construction, and then hauling itback to fill the trench. Figure 17 is a
section through the proposed trench. The
orange area illustrates the first scraper
pass, the light green the excavator pass,
and the dark green where the extra dirt
was placed. Figure 18 is the 3D model
showing a section every twenty-five feet.
In addition, the VDC model of the trench
was loaded directly onto scrapers andexcavators with automated machine guidance. This provided instant feedback to the operators
and ensured that the trench precisely followed the model used to estimate the project. As a
bonus, during construction Sundt generated as-built information at no additional cost using the
GPS features on the excavator.
Figure17
Figure18
7/29/2019 Virtual Design and Construction in Horizontal Construction-05!03!12
11/11
11
Contrary to the concerns of current industry professionals, participants do not necessarily need to
become experts on using VDC software because subassemblies or templates can read
spreadsheets that provide the information needed by models. After the information is loaded and
checked, intelligent templates or subassemblies can precisely calculate angles, elevations, grade
breaks, and volumes. Estimators may then use the resulting model to take off quantities and to
plan the project since the model is a byproduct of the estimate.
Conclusion
Lagging productivity and adversarial relationships plague the construction industry. As part of its
commitment to deliver quality horizontal projects to owners on time and within budget, Sundt
has demonstrated that VDC improves the constructionprocessand frees skilled professionals to
concentrate on creating solutions instead of calculating quantities or fixing problems in the field.
VDC enables all participants in a horizontal construction project owners, architects, engineers,
general contractors, subcontractors, suppliers, and the public to visualize the entireprocess in a
seamless, holistic way and to create innovative techniques to meet increasingly constrainedbudgets and deadlines. Sundt invites all participants to join us as we explore the possibilities.