79
Mekong Delta Water Management for Rural Development Project Environmental Management Plan (EMP) for Hau Giang Rural Water Supply And Sanitation Subproject

vi. environment management plan (emp)

  • Upload
    vandung

  • View
    217

  • Download
    1

Embed Size (px)

Citation preview

Mekong Delta Water Management for Rural Development Project

Environmental Management Plan (EMP) for Hau Giang Rural Water Supply And Sanitation

Subproject

Hau Giang, 2012

TABLE OF CONTENTSEXECUTIVE SUMMARY ......................................................................................................1I. INTRODUCTION ............................................................................................................3II. POLICY, REGULATIONS, AND INSTITUTIONALFRAMEWORKS ............................4

2.1 Government’s EIA Regulations ......................................................................................42.2 WB’s Safeguard Policy Applicable to the Subproject ...................................................6

III. SUBPROJECT DESCRIPTION ........................................................................................63.1 Objectives ........................................................................................................................63.2 Subproject location ..........................................................................................................63.3 Works’s descriptions .......................................................................................................83.4 Water Treatment Process ...............................................................................................103.5 Distribution Network .....................................................................................................12

IV. ENVIRONMENTAL BACKGROUND ...........................................................................124.1 General Characteristics ..................................................................................................124.2 Water, air and soil quality. ............................................................................................124.3 Land and water uses ......................................................................................................144.4 Socio-economic conditions ...........................................................................................17

V. POTENTIAL IMPACTS AND MITIGATION MEASURES ...........................................185.1. Summary of subproject impact. ....................................................................................185.2 Screening and Identification of Issues ...........................................................................185.3. Potential Negative Impacts and Proposed Mitigation Measures ..................................19

VI. ENVIRONMENT MANAGEMENT PLAN (EMP) .......................................................216.1 Mitigation Measures during Construction .....................................................................216.2 Mitigation Measures during Operation .........................................................................216.3 Water monitoring and EMP cost ...................................................................................21

VII. IMPLEMENTATION ARRANGEMENT .....................................................................247.1 Organization and Responsibilities .................................................................................247.2 Monitoring and Reporting. ............................................................................................267.3 Work Plan, Schedule, and Cost. ....................................................................................26

VIII.CONSULTATION AND INFORMATION DISCLOSURE ...........................................288.1 Objective of public consultations ..................................................................................288.2 Consultation procedure ..................................................................................................298.3 Public consultation results .............................................................................................298.4 Information disclosure ...................................................................................................30

ANNEX 1:Environmental Code of Practice (ECOP) for Hau Giang rural water supply and sanitation subproject ...............................................................................................................31Chapter 1: Introduction ..........................................................................................................32Chapter 2: Responsibilities .....................................................................................................32Chapter 3: ECOP Part A: General Provisions ........................................................................33Chapter 4-ECOP PART B: Construction Management ........................................................36Chapter 5-ECOP PART C: Environmental Guidelines for Protection of groundwater source ................................................................................................................................................42ANNEX 2: Photos, list of participants, minutes of the consultation meetings .....................44

i. iiiiii.

EXECUTIVE SUMMARY ...........................................................................................................4I. ........................................................................................................................INTRODUCTION .......................................................................................................................................................6II. POLICY, REGULATIONS, AND INSTITUTIONALFRAMEWORKS ................................72.1 Government’s EIA Regulations ..............................................................................................72.2 WB’s Safeguard Policy Applicable to the Subproject ...........................................................9III. SUBPROJECT DESCRIPTION .............................................................................................93.1 Objectives ...............................................................................................................................93.2 Subproject location .................................................................................................................93.4 Water Treatment Process .......................................................................................................133.5 Distribution Network ............................................................................................................15IV. ENVIRONMENTAL BACKGROUND ...............................................................................154.1 General Characteristics .........................................................................................................154.2 Water, air and soil quality. .....................................................................................................154.3 Land and water uses ..............................................................................................................174.4 Socio-economic conditions ...................................................................................................20V. POTENTIAL IMPACTS AND MITIGATION MEASURES ................................................215.1. Summary of subproject impact. ...........................................................................................215.2 Screening and Identification of Issues ..................................................................................215.3. Potential Negative Impacts and Proposed Mitigation Measures .........................................22VI. ENVIRONMENT MANAGEMENT PLAN (EMP) ............................................................246.1 Mitigation Measures during Construction ............................................................................246.2 Mitigation Measures during Operation .................................................................................24VII. IMPLEMENTATION ARRANGEMENT .........................................................................277.1 Organization and Responsibilities ........................................................................................27VIII.CONSULTATION AND INFORMATION DISCLOSURE ...............................................318.1 Objective of public consultations ..........................................................................................318.2 Consultation procedure .........................................................................................................328.3 Public consultation results ....................................................................................................328.4 Information disclosure ..........................................................................................................33ANNEX 1:Environmental Code of Practice (ECOP) for Hau Giang rural water supply and sanitation subproject ...................................................................................................................34Chapter 1: Introduction ...............................................................................................................35Chapter 2: Responsibilities .........................................................................................................35Chapter 3: ECOP Part A: General Provisions .............................................................................36Chapter 4-ECOP PART B: Construction Management ............................................................39Chapter 5-ECOP PART C: Environmental Guidelines for Protection of groundwater source . .46ANNEX 2: Photos, list of participants, minutes of the consultation meetings ..........................48EXECUTIVE SUMMARY ...........................................................................................................4I. INTRODUCTION ............................................................................................................6II. POLICY, REGULATIONS, AND INSTITUTIONALFRAMEWORKS ................................72.1 Government’s EIA Regulations ...............................................................................................72.2 WB’s Safeguard Policy Applicable to the Subproject ............................................................9

i. iiiiiiii.

III. SUBPROJECT DESCRIPTION .............................................................................................93.1 Objectives ................................................................................................................................93.2 Subproject location ..................................................................................................................93.4 Water Treatment Process .......................................................................................................133.5 Distribution Network .............................................................................................................15IV. ENVIRONMENTAL BACKGROUND ...............................................................................154.1 General Characteristics ..........................................................................................................154.2 Water, air and soil quality. .....................................................................................................154.3 Land and water uses ...............................................................................................................174.4 Socio-economic conditions ....................................................................................................20V. POTENTIAL IMPACTS AND MITIGATION MEASURES ................................................215.1. Summary of subproject impact. ............................................................................................215.2 Screening and Identification of Issues ...................................................................................215.3. Potential Negative Impacts and Proposed Mitigation Measures ..........................................22VI. ENVIRONMENT MANAGEMENT PLAN (EMP) ............................................................236.1 Mitigation Measures during Construction .............................................................................236.2 Mitigation Measures during Operation ..................................................................................24VII. IMPLEMENTATION ARRANGEMENT .........................................................................277.1 Organization and Responsibilities .........................................................................................27VIII.CONSULTATION AND INFORMATION DISCLOSURE ...............................................318.1 Objective of public consultations ..........................................................................................318.2 Consultation procedure ..........................................................................................................328.3 Public consultation results .....................................................................................................328.4 Information disclosure ...........................................................................................................33ANNEX 1:Environmental Code of Practice (ECOP) for Hau Giang rural water supply and sanitation subproject ...................................................................................................................34Chapter 1: Introduction ...............................................................................................................35Chapter 2: Responsibilities .........................................................................................................35Chapter 3: ECOP Part A: General Provisions .............................................................................36Chapter 4-ECOP PART B: Construction Management ............................................................39Chapter 5-ECOP PART C: Environmental Guidelines for Protection of groundwater source . .46ANNEX 2: Photos, list of participants , minutes of the consultation meetings .........................48

List of tablesTable 3.1 Design capacity, land requirements, and length of the distribution pipeline… 118Table 4.1: Ground water quality at a well in Mr Tha house near Phung Hiep CPC…. …...1613Table 4.2: Surface water quality (of a sample taken at Nang Mau canal)……………...1714

i. ivivii.

Table 5.1 Result of safeguard screening ……………………………………………….. 202118Table 5.2 Potential negative impacts and proposed mitigation measures .…………… 222320Table 6.1: Water quality (WQ) monitoring for safety of water sources………………. 2522Table 6.2: Estimated cost for water analysis per sample……………………………… 2623 Table 7.1: Institutional responsibilities for Hau Giang rural water supply subproject.. 27285Table 7.2 Work schedule for Hau Giang rural water supply subproject……………… 3027Table 7.3 Estimated Cost for EMP……………………………………………………..….….3128Table 8.1 Detail information of public consultation meeting…………………………. ..3229

List of figureFigure 3.1 Location of water supply systems in Hau Giang province ………………. 107Figure 3.2 Water treatment process for underground water source ………………… ..1411Figure 3.3. Water treatment process for surface water source ……………………… ..1411Figure 4.1 Chart of Land use of Hau province……………………………………… ..16174Figure 4.2 Land use map of subproject......................................................................... ......... 171916

ABBREVIATIONS AND ACRONYMSBOD Biochemical Oxygen DemandCPMU Central Project Management UnitDONRE Department of Natural Resources and EnvironmentCPO Central Project Office

DARD (Provincial) Department of Agriculture and Rural Development

DPC District People’s CommitteeECOP Environmental Code of PracticesEIA Environmental Impact AssessmentEMP Environment Management Plan EMDP Ethnic Minority Development PlanEMPF Ethnic Minority Policy FrameworkESMF Environment and Social Management Framework GOV Government of VietnamMONRE Ministry of Natural Resources and Environment

PCERWASS(s) Provincial Center(d) for Rural Water Supply and Sanitation

PMU Project Management UnitPPMU Provincial Project Management UnitPPC Provincial People’s CommitteeQCVN National Technical RegulationsRAP Resettlement Action Plan RWSS Rural Water Supply and SanitationTCVN National Environmental StandardWSS Water Supply and SanitationWB World Bank

i. vvii.

EXECUTIVE SUMMARY

Background: The subproject comprises construction of 6 new water supply systems with a total treatment capacity to serve about 47.716 people. The subproject is located in Long Binh commune- Long My district, Tan Binh commune-Phung Hiep district, Phung Hiep commune –Phung Hiep district, Truong Long A commune- Chau Thanh A district, and Vi Thủy commune- Vi Thuy district. The major land use is for rural residential area and the risk related to UXO is not expected. Water treatment capacity of the systems would range from 750 m3/day to 980 m3/day while serving 47.716 people. Surface and groundwater will be used as the water sources and current water quality appear suitable while the water quantity of groundwater is expected to be adequate. All the water treatment plants will be located near the rural residential area to be served and will not involve any ethnic minorities. The Hau Giang Provincial Center(d) for Rural Water Supply and Sanitation (PCERWAS) will be the subproject owner.

Impacts and mitigations: The project will create positive impacts to rural population. Potential negative impacts during site clearance and construction will be minor, temporary, and localized due to small size of the water supply systems and the nature of rural resident (low population density, low traffic volume). The impacts will be limited to increasing dust, noise, and traffic at the subproject site due to transportation of construction materials which will be small amount. The increase in the waste water from the proposed subproject would be minor and could be managed through the household sanitation to be supported by the project. Total affected households by land acquisition are 10 hhs with 56 people .Total land will be acquired are 7.855 m2. Of which, 203 m2 of residential land, 3394 m2 of garden land, 4058 m2 of agricultural land and 200 m2 of aquacuture land.

Mitigation measures:

To mitigate the impacts due to land acquisition the RAP will prepared and implemented

To mitigate the minor impacts during site clearance and construction the following measures will be carried out in close consultation with local authority and communities;

(1) During preparation of bidding and contract documents PCERWAS of Hau Giang will include the environmental code of practice (ECOP) for construction (Part A and B) in the bidding and contract documents and ensure that contractor is aware of safeguard obligation and commit to comply;

(2) During construction, the PCERWAS will assign field engineer to closely supervise and monitor safeguard performance of contractor and safeguard training will be provided to the staff; In addition a group of national consultant to be hired to assist PCERWAS in implementation of other water supply project will provide technical guidance and training to staff; and

(3) After completion of construction, the PCERWAS will monitor water quantity and quality of groundwater on a monthly basis at least for the first year of the system

operation. Training will be provided to the operation staff as part of normal operation.

Responsibility: The Hau Giang PCERWAS will be responsible for ensuring effective implementation of the mitigation measures, including reporting the implementation progress. The PCERWAS will set up an environment and social unit (ESU) comprising at least one full time staff to be responsible for forging effective implementation of safeguard measures. A group of national consultant will be hired to assist the ESU in performing the safeguard activities under the responsibility of PCERWAS. The Central Project Management Unit (CPMU) and its safeguard consultant will be responsible for periodical monitoring of safeguard measures for the subproject, including providing clarification on issues related to safeguard policies and requirements and safeguard training to the subproject staff.

Budget: - Cost for abbreviated RAP- Cost for implementation of mitigation measures during site clearance and

construction, including consultation with local communities and environmental monitoring as agreed with the local authorities and communities and/or compensation to damage (if any) will be part of the subproject construction cost.

- Cost for supervision of contractor performance will be part of the subproject supervision cost.

- Budget for safeguard training of staff will be part of the subproject management.

iii. 22iv.

I. INTRODUCTION

The Government of Vietnam (GOV) is implementing the Mekong Delta Water Resources Management for Rural Development Project (the Project) during 2011-2016 with financial support from the World Bank (WB or the Bank).  The Project will support technical assistance as well as physical investment through a number of subprojects designed to achieve the Project Development Objectives1 through the following components: (1) Water Management Planning and Efficient Utilization, including measures to strengthen institutional capacities at sub-regional and provincial levels, promote effective operations and maintenance, and promote on-farm water use efficiency through pilot schemes; (2) Improvement and Rehabilitation of Water Resources Infrastructure, with emphasis on rehabilitation and minor improvement through canal dredging, and embankment reinforcement, as well as the installation of secondary control sluice gates; (3) Rural Water Supply and Sanitation, aiming to extend reliable services to about 60,000 households in the project area; and (4) Project Management and Implementation Support, supporting incremental operating costs to implement the project and the monitoring and evaluation of project outcomes and impacts. To ensure that the Project activities will not create adverse impacts on local community and local environment three safeguard policy instruments have been established and they will be applied to all the subprojects. These safeguard instruments are (a) the Environment and Social Management Framework (ESMF), (b) the Resettlement Policy Framework (RPF), and (c) the Ethnic Minority Policy Framework (EMPF). The ESMF has been designed to comprise 4 key steps: (a) safeguard screening and impacts assessment, including consultation and preparation of an EIA or environmental commitment as required by the Government; (b) preparation of mitigation measures and documentation; (c) WB clearance; and (d) implementation, monitoring, and reporting.

As part of the Component 3 "Rural Water Supply and Sanitation", about 59 small water supply systems will be built and/or rehabilitated in Can Tho City and the 6 Project provinces. Of these systems 5 new water supply systems will be implemented in Hau Giang province to serve 47.716 people in 6 communes. These six systems have been combined as a subproject Phase 2 and through a safeguard screening (ESMF step1) this subproject is eligible for Project financing. To secure WB’s safeguard clearance, an Environmental Management Plan (EMP) has been prepared (this report) by the subproject owner (the Hau Giang Provincial Center(d) for Rural Water Supply and Sanitation (PCERWAS)) with assistance from a national consultant firm. Implementation of the subproject will require GOV approval of the Environmental Protection Commitment (EPC) and the GOV approval process is on-going.

1The project development objective (PDO) is to protect and enhance the utilization of water resources in the project provinces of the

Mekong Delta Region in order to sustain prior gains in agricultural productivity, provide access to water supply for rural households, and contribute to climate change adaptation.

iii. 33iv.

II. POLICY, REGULATIONS, AND INSTITUTIONALFRAMEWORKS

2.1 Government’s EIA RegulationsGiven the small size of the water supply systems, an EIA is not required However, the owner of the subproject must undertake to execute environmental protection for each water supply system and be approved by local District People’s Committee (DPC). In the construction stage, contractors must abide regulations, criterions and quality of Vietnam government, etc on environment and safety related to construction. The regulations are listed below:* Environmental protection Aspect- Law of environmental protection ref. 52/2005/QH11 dated November 29th 2005;- Decree No. 80/2006/NĐ-CP of the Government dated August 9 th 2006 about detail stipulation on instructing to execute clauses in Law of Environmental Protection;- Decree No. 21/2008/NĐ-CP of the Government dated February 28th 2008 about changing and adding clauses of Decree ref. 80/2006/NĐ-CP of the Government dated August 9 th 2006 about detail stipulation on instructing to execute clauses in Law of Environmental Protection;- Decree No. 29/2011/NĐ-CP of the Government dated April 18 th 2011 regulating assessing strategic environment, environment impact and undertaking to environmental protection;- Decree No. 149/2004/NĐ-CP dated July 27th 2004 regulating issuing licenses for exploring, exploiting, using water resources and letting out wastewater into water source;- Circular No.. 26/2011/TT-BTNMT of the Minister of Natural Resources and Environment dated July 18th 2011 regulating detail clauses in Decree ref. 29/2011/NĐ-CP of the Government dated April 18th 2011 regulating assessing strategic environment, environment impact and undertaking to environmental protection;* Regarding construction aspect:- Law of Construction ref. 16/2003/QH11- Decree No.. 12/2009/NĐ-CP dated February 10th 2009 about managing constructing investment project.- Decree No. 209/2004/NĐ-CP dated December 16th 2004 about managing constructing work quality.* Regarding land acquisition and resettlement- Law of Land ref. 13/2003/QH11 dated November 26th 2003, replacing Law in enforced issued in 1987 and 1993.- Decree No.181/2004/NĐ-CP about instructing to execute Law of Land in 2003- Decree No. 197/2004/NĐ-CP about assisting, compensating, resettling when the government re-purchases land.- Decree No. 17/2006/NĐ-CP about changing clauses in Decree ref. 181/2004/NĐ-CP and Decree ref. 197/2004/NĐ-CP.- Circular No. 116/2004/TT-BTC about instructing to execute Decree ref. 197/2004/NĐ-CP- Decree No.. 188/2004/NĐ-CP about how to determine land price and price frame for land types.* Regarding environmental criterions:Ministry of Natural Resources and Environment and Ministry of Health have responsibility to promulgate environmental criterions based on promulgated Vietnam technique regulations. Decision rNo.. 22/2006/QD-BTNMT by Ministry of Natural Resources and Environment dated December 18th 2006 about strictly applying environment criterions. The following Vietnam environmental criterions will be strictly complied for executing environmental assessment research, including:Water environment: - QCVN 01:2009/BYT: National technique regulations on drinking-water quality- QCVN 02:2009/BYT: National technique regulations on running water quality

iii. 44iv.

- QCVN 08:2008/BTNMT: National technique regulations on water surface quality- QCVN 09:2008/BTNMT: National technique regulations on underground water quality- QCVN 10:2008/BTNMT: National technique regulations on water quality in coastal areas- QCVN 11:2008/BTNMT: National technique regulations on industrial wastewater quality- QCVN 14:2008/BTNMT: National technique regulations on wastewater quality in water source.- QCVN 24:2008/BTNMT: National technique regulations on industrial wastewater.- TCVN 5502:2003: Supplying water – Quality request- TCVN 6773:2000: Water quality – Water quality for irrigation purpose- TCVN 6774:2000: Water quality – Protection water quality for aquaculture- TCVN 7222:2002: Water quality – Water quality for gathered water in water source.Land environment: - QCVN 03:2008/BTNMT – National technique regulations on permitted limit of hard metal in land- QCVN 15:2008/BTNMT – National technique regulations on pesticide existence in land.- Decision ref. 27/2008/QĐ – BXD by Minister of Construction dated on September 11 th

2004 about enforcing TCXDVN 320:2004 “harmful waste garbage – design criterions”Air environment:- QCVN 05:2008: Air quality – Surrounding air quality criterions- QCVN 06:2008: Air quality – maximum permitted concentration of noxious substances in the surrounding air.- QCVN 07:2008: Air quality – Threatening of noxious substances in the air- TCVN 6438:2001: Maximum permission limit of discarding exhausted gases. Solid waste management: - TCVN 6438:2001 – Maximum permission limit of discarding dismissed gases. - TCVN 6696:2009: Solid waste – garbage cleaning. Common requirements for environmental protection.- QCVN 07:2009: National technique regulations on clarifying harmful waste.- QCVN 25:2009: National technique regulations on wastewater and solid waste.Vibration and noise - QCVN 27:2010/BTNMT – National technique regulations on vibration (replacing TCVN 6962:2001 – Vibration caused by construction work and factories – maximum permitted level in environment in public areas and residence zones). QCVN 26:2010/BTNMT – National technique regulations on noise (replacing TCVN 5948:1999 Acoustics – Noise caused by transportation moving when speeding up – permitted calculation level).- TCVN 5949:1998 Acoustics – Noise in public areas and residence zones – permitted calculation level.Health and labor safety:Decision No. 3733/2002/QĐ-BYT of Ministry of Health dated October 10th 2002 about applying article 21 on labor health and relating safety criterions for microclimate, noise, vibration, chemicals – permitted level in work place.Moreover, about programming for infrastructure design, managing water supply system and selecting water source to serve domestic water supply system are based on the following criterions:- Decision ref. 628/BXD-CSXD of Ministry of Construction dated December 14th 1996: Vietnam criterions and regulations.- Forming criterion ref. 20TCN-33-85 for water supply project.- TCXDVN 33:2006 relating to water supply – Pipe system and work – design criterions.- Instructing to prepare and approving the city construction programming by Ministry of Construction in 1998- Using criterion TCXD 66:1991 in the operation of water supply and drainage system

iii. 55iv.

- Making criterion TCXD 76:1979 technique management process in the operation of water supply system.- Making criterion TCXD 233:1999 on criteria which are used for selecting water surface, underground water source in order to serve water supply system.

2.2 WB’s Safeguard Policy Applicable to the SubprojectWorld Bank (WB) classified the Project to be the project “ type B”, more than ten protection policies and fiveThe following policies are striggged: Environmental assessment (operation policies of WBNHTG 4.01); Integrated Pest Management (operation policies of NHTG 4.09); Ethnic minority groups (operation policies of NHTG 4.10); involuntarily resettlement (operation policies of WBNHTG 4.12)), and international waterway (operation policies of NHTG 7.50. To execute these policies, the following protection instruments are prepared:

(a) Summary of Regional environment assessment (REA) for the whole project;(b) Integrated Pest Management (IPM);(c) Ethnic minority development framework (EMDF);(d) Ethnic minority plan (EMPs);Environmental Management Plan (EMP);(e) Resettlement policy frame (RPF);(f) Resettlement Action plan (RAP).; and(g) Engineering Code for Environment Practices (ECEPs) for all civil works.

The EMP provides a brief summary of the subproject description and the environmental background and describes the potential negative impacts and the proposed mitigation measures to be carry out during preconstruction, construction, and operation stages, including the implementation arrangement. The EMP also describes the Environmental Codes of Practices (ECOP) to be included in the bidding and contract documents.

III. SUBPROJECT DESCRIPTION

3.1 ObjectivesThe subproject is designed to provide water supply for about 47,716 people in 6 communes of 4 districts in Hau Giang province. This effort will support the Government policy to increase rural water supply service in Hau Giang province.

3.2 Subproject locationThe subproject comprises 6 new water supply systems located in the following 6 communes of the Hau Giang province (see Figure 3.1 for locations):

+Phung Hiep commune –Phung Hiep district;+Truong Long A commune- Chau Thanh A district;+Long Binh commune- Long My district;+Tan Binh commune-Phung Hiep district; and+Vi Thủy Thuy commune- Vi Thuy district.+Vinh Vien commune- Long My district.

iii. 66iv.

Figure 3.1 Location of water supply systems in Hau Giang province

iii. 77iv.

Phung Hiep water supply

Tan Binh water supply

Truong Long A water supply

Long Binh water supply

Vi Thuy water supply

Vinh Vien water supply

3.3 Works’s descriptions Of the 6 water supply systems, 3 systems use groundwater and 3 systems use surface water as raw water. Design capacity, land requirements, and length of the distribution pipeline are summarized in Table 3.1 , details are as below.

Table 3.1 Design capacity, land requirements, and length of the distribution pipeline No Works Design

capacity (m3/day)

Land Area (m2)

Total length of distribution pipeline (m)

Population served (people)

Water sources

1 Phung Hiep water supply system

750 900 11226 7.052 Groundwater (2 wells, about 180 m)

2 Truong Long A water supply system

980 560 6636 9.248 Groundwater (2 wells, about 180 m)

3 Long Binh water supply system

840 2000 13882 7.936 Surface water from Xang Xa No canal

4 Tan Binh water supply system

960 1500 17691 9.080 Surface water from Cau Dinh canal

5 Vi Thuy water supply system

800 1000 6093 7.584 Surface water from Nang Mau canal

6 Vinh Vien water supply system

720 1600 6574 6.816 Groundwater (2 wells, about 180 m)Nước ngầm (2 giếng khoảng 180m sâu)

b1.Phung Hiep water supply system (groundwater)oDrilled well: 02 wells (1 operation, 1 standby); Exploitation depth: 180 meters (m); D

Diameter of standing pipes: 250 millimeters (mm) made of PVC, 48m in length; Exploitation pipe made of PVC with diameter 114 mm, 108 m in length; and there are 02 submersible pump: Q=30-40m3/hr, H=55-45m.

oClarifier: 01 tank, Reinforced concrete, size WxLxH=3x6x4.7moGravity Sand filter: 02 reinforced concrete tanks, size WxLxH=1.5x3x4.5moClean water storage: Volume of 150m3, reinforced concrete, size WxLxH= 10x6.5x3.8moAdministrative house: reinforced concrete, brick wall, area=52.8m2.oChemical room: 04 tanks for chemical solution, 04 mixers, 04 dosing pumps with

capacity of 50l/h.

iii. 88iv.

oPumping station: reinforced concrete, brick wall, size WxL=1.5x6m; 02 water pump, Q=45m3/h; H=35m.

oWater tower: reinforced concrete, 30m3, H=22m.oDistribution network: To be installed with total length of 11,226m with diameter from 40

to 150 mm.

b2. Truong Long A water supply system (groundwater)oDrilled well: 02 wells (1 operation, 1 standby); the exploitation depth: 180 meters (m);Diameter of standing pipes: 250 millimeters (mm) made of PVC, 48m in length;Exploitation pipe made of PVC with diameter 114 mm, 108 m in length. There are 02 submersible pump: Q=30-40m3/h, H=55-45moClarifier: 01 tank, Reinforced concrete, size WxLxH=3x6x4.7moGravity Sand filter: 02 reinforced concrete tanks, size WxLxH=2x3x4.25 moClean water storage: Volume of 200m3, reinforced concrete, size WxLxH=11x6.5x3.8moAdministrative house: reinforced concrete, brick wall, area=76.8m2oChemical room: 04 tanks for chemical solution, 04 mixers, 04 dosing pumps with

capacity of 50 l/h.oPumping station: reinforced concrete, brick wall, sized WxL =4.5x6m; 02 water

pumpswith Q=60m3/h, H=35m.oWater tower: reinforced concrete, 30m3, H=22m.oDistribution network: To be installed with total length of 6636m with diameter from 40 to 150 mm.

b3.Long Binh water supply system (surface water)oWater intake: Reinforced concrete, feed water pipe with diameter of 150mm.oClarifier: 01 tank, Reinforced concrete, size WxLxH=3x6x4.7moGravity Sand filter: 02 reinforced concrete tanks, size WxLxH=1.5x3x4.25moClean water storage: Volume of 180m3 ,reinforced concrete , size WxLxH=11x6.5x3.8moAdministrative house: reinforced concrete, brick wall, area=76.8m2oChemical room: 04 tanks for chemical solution, 04 mixers, 04 dosing pumps with

capacity of 50l/h.oSludge lagoon : size WxL=15.4x7.4moPumping station: reinforced concrete, brick wall, sized WxL =7.1x6; 02 raw water

pumps with Q=35m3/h, H=15m; 02 clean water pumps with Q=50m3/hr, H=35m;oWater tower: reinforced concrete, 30m3, H=22m.oDistribution network: To be installed with total length of 13,882m with diameter from 40

to 150 mm.

b4. Tan Binh water supply system (surface water)oWater intake: Reinforced concrete, feed water pipe with diameter of 150mm.oClarifier: 01 tank, Reinforced concrete, size WxLxH =3x6x4.7 m

iii. 99iv.

oGravity Sand filter: 02 reinforced concrete tanks, size WxLxH=2x3x4.25 moClean water storage: Volume of 200m3, reinforced concrete , size

WxLxH=11x6.5x3.8m.oAdministrative house: reinforced concrete, brick wall, area=76.8m2oChemical room: 04 tanks for chemical solution, 04 mixers, 04 dosing pumps with

capacity of 50l/hr.oPumping station: reinforced concrete, brick wall, size WxL =6x7.1m; 02 raw water

pumps with Q=40m3/hr, H=15m; 02 clean water pumps with Q=60m3/h, H=35m;oWater tower: reinforced concrete, 30m3, H=22m.oDistribution network: To be installed with total length of 17,691m with diameter from 40

to 150 mm.b5. Vi Thuy water supply system (surface water)oWater intake: Reinforced concrete, feed water pipe with diameter of 150mm.oClarifier: 01 tank, Reinforced concrete, size WxLxH=3x6x4.7 moGravity Sand filter: 02 reinforced concrete tanks, size WxLxH=1.5x3x4.25 m.oClean water storage: Volume of 150m3, reinforced concrete, size WxLxH=10x6.5x3.8m.oAdministrative house: reinforced concrete, brick wall, area=76.8m2oChemical room: 04 tanks for chemical solution, 04 mixers, 04 dosing pumps with

capacity of 50l/hr.oSludge lagoon: size WxL=15.4x7.4m.oPumping station: reinforced concrete, brick wall, size WxL =6x6m; 02 raw water.o pumps with Q=30m3/hr, H=15m; 02 clean water pumps with Q=45m3/hr, H=35m;oWater tower: reinforced concrete, 30m3, H=22m.oDistribution network: To be installed with total length of 6,093m with diameter from 40

to 100 mm.b6.Vinh Vien water supply system (groundwater)oDrilled well: 02 wells ( 1 operation, 1 standby) The exploited depth: 180 meters (m);

diameter of standing pipes: 250 millimeters (mm) made of PVC, 48m in length; exploitation pipe made of PVC with diameter 114 mm, 108 m in length.There are 02 submersible pump: Q=30-40m3/h, H=55-45m.

oClarifier: 01 tank ,Reinforced concrete, sized WxLxH=3x6x4.7m.oGravity Sand filter: 02 reinforced concrete tanks, sized WxLxH=1.5x3x4.25m.oCleanwater storage:Volume of 150m3 ,reinforced concrete , sized WxLxH=10x6.5x3.8moAdministrative house: reinforced concrete, brick wall, area=76.8m2.oChimical room: 04 tanks for chemical solution, 04 mixers, 04 dosing pumps with

capacity of 50l/h.o Sludge lagoon: sized BxL=6.6x9.6moPumping station: reinforced concrete, brick wall, sized WxL=4.5x6m; 02 water pump, Q=45m3/h; H=35m.oWater tower: reinforced concrete, 30m3, H=22m.oDistribution network: To be installed with total length of 6574m with diameter from 40

iii. 1010iv.

to 150 mm.

3.4 Water Treatment ProcessBelow shows the schematic diagrams for the design for the water treatment plant usingGrounddwater (Figure 3.2) and surface water (Figure 3.3) as the water sources:

Figure 3.2 Water treatment process for underground water source

iii. 1111iv.

Wells +Submersible

pump

Aeration tower Mixing+ Clarifier

Aquazur sand filter Clean water Storage

Pumping

station

chlorine 

Water tower

Distribution network

Chlorine Na2CO3

Figure 3.3. Water treatment process for surface water source

3.5 Distribution NetworkMaterials and pipelines are selected, calculated and designed for the optimal option regarding economic and technical conditions. Pipes shall be installed mainly along the existing roads so that resettlement is not necessary.

IV. ENVIRONMENTAL BACKGROUND

4.1 General Characteristics

Location: Hau Giang province is located in the center of the Mekong Delta. It is 45km from Can Tho city. It’s provincial boundary is connected to Can Tho city in the North ,with Soc Trang province in the south, with Vinh Long province in the east, and with Kien Giang and Bac lieu provinces in the west Geographical coordinates:from 9030'35 "to10019'17"North latitude and from105014'03" to 106017'57" East longitude.  The provincial area is1601.14km2, representing about 4% of the Mekong Delta of Vietnam. Hau Giang has seven administrative units, comprises five districts: Phung Hiep, Long My, Vi Thuy and Chau Thanh, Chau Thanh A, one town of Nga Bay, one provincial city of Vi Thanh.

Climate: Hau Giang Province is located in the inner ring the Northern Hemisphere tropics,near the equator. It has a tropical monsoon climate which can be divided into two distinct seasons i.e. the Southwest rainy season from May to November and the dry northeast season

iii. 1212iv.

River Pump Mixing+ Clarifier

Aquazur sand filter Clean water Storage

Pumping

station

chlorine 

Water tower

Distribution network

Chlorine Al2(SO4)3.18H2O

from December to April. The average temperature is 270C. Warmest month (350C) is in April and the lowest (300C) month is in December. The rainy season is from May to November accounting for 92-97% of the annual rainfall. Rainfall in Hau Giang has an average of about 1,800mm/year in which the highest rainfall occurs in September (250.1 mm). Relative humidity varies significantly with an average of about 82%.

4.2 Water, air and soil quality.Groundwater: There are 4 layers of aquifers in Hau Giang, in which the second aquifer (Pleistocene) which occurs at depths of about 80-190 m has a large capacity and the quality of water is quite good. Table 4.1presents the result of ground water quality in the project area. The results show that almost all parameters are whithin permitted levels of QCVN 09:2008/BTNMT. However, some parameters, such asturbidity and iron) are 12 times and 7 times, respectively, higher than permitted threshold pursuant to QCVN 01:2009/BYT. (National technical regulation on underground water quality).

Table 4.1: Ground water quality at a the well in Mr Tha house near Phung Hiep CPC

No Parameter Unit Testing Method

Analysed Result

QCVN 0109:2009200

8/BYT BTNMT

1 pH   TCVN 6194 – 1996 6.2 65.5 - 8.5

2 NH4 (ammonia)Color

Mg/lTCU

TCVN 5998 – 1995TCVN 6185 – 1996

010 0.115

3Mn2+ (Manganese)Turbidity

mg/lNTU

TCVN 6002 - 1995 (ISO 6333 -

1986)ISO 7027 - 1990

0.3524 0.52

4As (Arsenic)TDS (Total dissolved Solid)

Mg/lmg/l

TCVN 6626 – 2000SMEWW 2540 C

0420 0.051,000

5 FluorideNH4 (ammonia)

Mg/lMg/

l

TCVN 6195 – 1996TCVN 5998 – 1995

00 1.53

iii. 1313iv.

6 Fe (iron)Mn2+ (Manganese)

Mg/lmg/l

TCVN 6177 – 1996TCVN 6002 - 1995 (ISO 6333 - 1986)

2.20.35 50.3

7Total Coliform bacteriaAs (Arsenic)

MPN/

100mlMg/l

TCVN 6187 - 1996 ISO 9308 - 1 –

1990TCVN 6626 – 2000

00 30.01

8 E.Coli bacteriaFluoride

MPN/

100mlMg/l

TCVN 6187 - 1996 ISO 9308 - 1 –

1990TCVN 6195 – 1996

00 01.5

9 Fe (iron) Mg/l TCVN 6177 – 1996 2.2 0.3

10 Total Coliform bacteria

MPN/

100ml

TCVN 6187 - 1996 ISO 9308 - 1 –

1990

0 0

11 E.Coli bacteria

MPN/

100ml

TCVN 6187 - 1996 ISO 9308 - 1 –

1990

0 0

-Surface water: Hau River and Cai Lon River provide water all year round, but the quality is slightly polluted. There are some parameters in surface water which are higher than drinking water standards such as turbidity, color, coliform … Therefore water needs to treated to meet the standards. The water quality at the areas proposed as the water sources is presented in Table 4.2

Table 4.2: Surface water quality (of a sample taken at Nang Mau canal, 300m away from Vi

iii. 1414iv.

Thuy CPC)

No Parameter Unit Testing Method

AnalysedResult

QCVN 08:2008/BTN

MT cột A2

1 pH   SMEWW 2130-98 6.48 6 - 8.5

2 DO mg/l O2 KMnO4 1.8 2

3 NO2- mg/l  TCVN 6178-96 0.03 0.02

4 NO3- mg/l  –TCVN 6180-

96 6 5

5 CL- mg/l TCVN 6194-96 18 400

6 Total Iron mg/l  TCVN –6177-96 0.8 1

7 Ecoli MPN/ 100ml

TCVN 6187 - 1996 ISO 9308

- 1 - 199010 50

The results show that 02 parameters are slightly respectively higher than permitted standards. Special attention should be paid to treatment those ones.-Air quality: In general, air quality of the subproject area is quite good, concentration ofpollutants in the air is smaller than permitted limitation according to QCVN 05:2009/BTNMT: National Technical Regulation on Ambient Air Quality. -Soil quality: pH of soil is low, acidity of soil from medium to slightly; Concentration of total nitrogen in soil at fair to rich level, concentration of total phosphorus quite poor. The soil wasn’t polluted by heavy metals including zinc (Zn), lead (Pb), arsenic (As), cadmium (Cd), copper (Cu), their concentration in soil all met QCVN 03/2008/BTNMT (National technical regulation on heavy metals in soil/sediment.

4.3 Land and water uses

Figure 4.1 Chart of Land use of Hau Giang province

a.Land use

iii. 1515iv.

Land use in Hau Giang Province

82.72%

3.19%1.11%

2.61%10.24%0.12%

Agricultural Forestry Aquacultural Housing Mutipurposes Non-use

Total area of Hau Giang is 160,114 ha .It is located in the region of biggest food growing, approximately 80.72 % land is used for farming. Double rice cropping are applied in the area. Detail of land use is as below:

-Agricultural land 132,443 ha;

-Forestry land 5,114 ha;

-Aquacultural land 1,781 ha;

-Housing land 4,177 ha;

-For Mutipurposes 16,402 ha and

-Non-use land 197 ha.

b. Water use:In late 2011, the rate of people in Hau Giang province assessing hygienically was 91%, of which in rural erea area 83%.National target program on clean water and rural environmental sanitation has been improved but lack of clean water still happened in many areas especially in dry season. Using water from rivers and canals within subproject site for domestic use was very common.

Figure 4.2 Landuse map of subproject

iii. 1616iv.

Fige 4.2 Land use map of subproject

iii. 1717iv.

Truong Long A water supply

Phung Hiệp water supply

Tan Binh water supply

Long Binh water supply

Vi Thuy water supply

Vinh Vien water supply

4.4 Socio-economic conditionsPopulation and ethnic minoritiesAccording to 2007’s statistical yearbook, the population in subproject area up to 2007 was 802.797, including 49.5 % of males and 50.5% of females. The majority of the population belongs to the Kinh (95.6%), while other ethnic groups make up the small remain (4.4% ) including Khmer 2.18,Chinese 1.18%, and others 1.04%. Household size in the Sub-project is about 4.9.Economy

The ecomomy economy of Hau Giang is mainly based on agriculture. Despite persistent difficulties, challenges and restrictions, the economic growth rate of Hau Giang in 2011 was 14.12%GDP per capita will reach US$942, production value of agriculture, forestry and fishery sectors grew 5 - 5.5 percent; industrial and construction climbed 17.5 - 18 percent , service value grew 18 - 18.5 percent; total budget revenues reached to VND 4,560 billion .Education & HealthRecently Hau Giang has gained a positive achievement in education. According to the statistic in 2011, the total pupils going to school are 148.028, the rate of pupils giving up studying is only 1.46%.The health care service is more and more improved, there are 4.8 doctors per 10.,000 people .

iii. 1818iv.

Nguyen Loan, 11/03/12,
Bổ sung các thông tin này

V. POTENTIAL IMPACTS AND MITIGATION MEASURES

5.1. Summary of subproject impact.Positive:

-Implementation of the subproject will serve 47.716 people. At present, there is no water supply service in the project area, so people cannot access to clean water.

-Implementation of the subproject will increase the number of rural population served by clean water and improve the living condition of local residents as well as reduce the risk for exposing to water born diseases (such as eye diseases, diarrhea, petechial fever).

Negative:-The potential negative impacts will be minor due to small size of the water supply systems and nature of rural land use and population density.

-Social impacts (land acquisition, construction, and operation): 10 households will be affected by land acquisition for constructing civil works including residential , garden and agricultural land, the total area 9455.2 m2

-Impacts during construction will be limited to increasing dust, noise, and traffic at the subproject site due to transportation of construction materials which will be small amount.

-The increase in waste water is not considered to be substantial, and would be mitigated adequately through household level sanitation.

5.2 Screening and Identification of Issuesa) Eligibility screening The subproject activities as proposed do not fall into the negative list and therefore eligible for project funding. (b) Identification of issuesThe subproject conducted the technical screening for safeguard issues in line with the criteria provided in the ESMF (Table 5.1) and the results are shown as follows:Table 5.1 Results of screening Safeguard issues likely to be involved

Nature and scale of the impacts

Safeguard document prepared

Remarks

(1)Permanent or temporary loss of land or resources for any family

The land area will be acquired for the

six systems is 9455.2 m2

Abbreviated RAP 10 affected households

(9) Impact due to construction of new water supply systems

Construction and operation of new

five six water treatment plants and distribution

pipelines

EMP The subproject located in existing community areas

iii. 1919iv.

5.3. Potential Negative Impacts and Proposed Mitigation Measures

Table 5.2 summarizes the potential impacts and proposed mitigation measures for the subproject. Minor land acquisition and relocation will be required for construction of water treatment plants (WTPs).The total area is 9455.2 m2, of which Vi Thuy WTP 997.4 m2 , Long Binh WTP 3006.8 m2 , Phung Hiep WTP 1100 m2 ,Tan Binh WTP 1700 m2 , Truong Long A 1051 m2 , Vinh Vien WTP 1600 m2 . This will affect 10 households in the subproject areas However Ethnic minority will not be affected. Construction of water distribution pipeline systems will be made along the existing roads. Detail of six pipeline systems are as below: -Phung Hiep pipeline: total length of 11,226m, uPVC diameter from 40 to 150 mm.-Truong Long A pipeline: total length of 6636m, uPVC diameter from 40 to 150 mm.-Long Binh pipeline: total length of 13,882m, uPVC diameter from 40 to 150 mm.-Tan Binh pipeline: total length of 17,691m, uPVC diameter from 40 to 150 mm.-Vi Thuy pipeline: total length of 6,093m, uPVC diameter from 40 to 100 mm.-Vinh Vien pipeline: total length of 6574m , uPVC diameter from 40to 150 mm.

Extent and nature of the impacts during site clearance and construction will be minor and limited to generation of wastes, dust, noise, and vibration at the construction sites and adverse impact on water pollution, social issues and possible disruption of water supply are not anticipated. All these impacts could be mitigated through the application of an Environmental Code of Practice (ECOP) Parts A and B that has been adjusted for the subproject (Annex 1) with close supervision of field engineer and in close consultation with local authority and community.

The potential impacts during operation of the subproject will be limited to waste generation (treatment sludge) and safety of operators during the water treatment process however the extent of the impacts will be small and can be managed through good housekeeping and training of operators. Potential increase in wastewater generation in the service area would be minor however priority will be given to improve the sanitary condition at household level and/or in the service area through the planning of the sanitation program to be implemented under the project. As part of the system operation, water quality monitoring will be carried out to ensure effectiveness of the water treatment process and safety to the water users, including water quality monitoring at the water source intake.

iii. 2020iv.

Table 5.2 Potential negative impacts and proposed mitigation measures – it will be the same for all the subproject sites

Key Activities Potential Negative Impact Impact Level Proposed Mitigation Measures

1. Pre-construction PhaseLand acquisition and relocation of local residents

The area of land required, is 1100. Only 1 household is affected .

Small, short term, unavoidable, controllable

Prepare and ImplementResettlement Action Plan (RAP) to provide compensation and/or assistance following the Resettlement Policy Framework (RPF)

2. Construction Phase

Site clearance and construction of the water treatment plant, intake station, and distribution system.

Increase safety risk and obstruction of local traffic; Increase dust, noise, vibration, and other nuisance to local residents; Water and land pollution due to leakage of waste oil and toxic materials, disposal of solid wastes and wastewater, etc.

Small, short term, unavoidable, controllable

Apply ECOP Parts A and B (Annex 1)

Activities of construction workers, including work camp

Generation of solid and liquid wastes; Conflicts between workers and workers and workers and local people; Health and safety issues.

Small, short term, unavoidable, controllable

Apply ECOP Parts A and B (Annex 1)

3. Operation phase

Operation of water treatment plant

Generation of wastes and safety of workers during the treatment process; Safety to water users; and potential increase in wastewater generation in the service area.

Small, short term, unavoidable, controllable

Proper disposal of treatment sludge and other wastes; Training of staff; monitoring of water quality; and provide high priority for improve sanitation conditions.

The distribution pipeline network is leaked in the joints, or broken pipes due to the collision or neighboring works construction affecting the pipelines, as a result, flooding, insufficient pressures and unreliable in flow for the area in case of

Small, short term, unavoidable, controllable

Pressure and flow of the pipelines network are permanently inspected to find leakages, and the broken pipes will be promptly repaired and overcome.

iii. 2121iv.

problems.

Coordinate with people in pipelines protection and inform in case of any problems.

VI. ENVIRONMENT MANAGEMENT PLAN (EMP)

6.1 Mitigation Measures during Construction To mitigate the negative impacts during construction, during detailed design, ECOP Parts A and B (Annex 1) will be included in the bidding and contract documents and the contractor will be informed to the need to comply with the safeguard requirements. Hau Giang CERWASS will assign field engineer to closely supervise and monitor safeguard performance of contractor and safeguard training will be provided to the staff. In addition a group of national consultant will be hired to monitor performance of the contractor.

During construction, Hau Giang CERWASS assisted by consultant will ensure that the contractor complies with the ECOP given due attention to the following areas:

- Management and control of sanitary condition of campsite, safety of workers, and worker behaviors; - Management of construction site including covering material transport truck and watering to suppress dust generation, and reduction and noise and vibration; and - Cooperation with local residents and local authorities, especially during planning and construction of the distribution network, and be responsive to their requests related to mitigation of potential negative impacts. Due attention will be given to ensure public safety and disruption of local access and businesses.

6.2 Mitigation Measures during Operation During operation, training of operational staff and water quality will be monitored periodically as part of the system operation. ECOP part C should be to apply to protect ground water source

6.3 Water monitoring and EMP costTable 6.1 provides some guidance on water quality monitoring parameters and locations while Table 6.2 provides an estimate unit cost for the analysis, respectively. These costs will be part of the system operation cost. During the planning of sanitation improvement program, Hau Giang CERWASS will receive technical assistance for improving sanitation at household and service area level.

iii. 2222iv.

iii. 2323iv.

Table 6.1: Water quality (WQ) monitoring for safety of water sources WQ Parameters Location of

samplesFrequency Compared

StandardsOr Regulations

An estimated

cost/samplepH, BOD, COD, SS, coliform bacteria, E. coli bacteria, As, Fe, DO

In wells or water intakes

Water quality (when it is used for raw water) Both wet and dry season:Monthly for the first year; This frequency can be reduced if justified.

Government standard for surface water domestic uses (QCVN 08:2008/BTNMT column A1)

Monitoring cost will be part of the system operating cost. Below provides an estimate cost for analysis/sample

pH, BOD, COD, SS, coliform bacteria, As, Fe, DO Cl-

At storage tanks (after treatment and chlorination)

Water quality from the treatment after chlorination (before sending for distribution). (1 year after the works finish and begin operation) Atleast one per quarter

Government standard for drinking water(QCVN 01 and 02/BYT)

Samples will be taken at household level Key parameters are pH, BOD, COD, SS, coliform bacteria, As, Fe, DO, Cl-

At households at the beginning point of pipeline and at the farthest end of pipeline of each system to determine the quality of treated water at dítributiondistribution

Water quality from the households(1 year after the works finish and begin operation )At least one per quarter

Government standard for drinking water (QCVN 01 and 02/BYT)

iii. 2424iv.

Table 6.2: Estimated cost for water analysis per sample

TT Parameter Unit

Unit cost (VND) for each sample

According to Circular No.232/2009/TT/BTC dated on 9/12/2009 of

MOF

1 pH - 40,000

2 Metals (6) mg/l 480,000

3 TSS mg/l 50,000

4 DO mg/l 80,000

5 COD mg/l 100,000

6 E. Coli bacteria mg/l 80,000

7 Coliform bacteria MPN/100ml 80,000

 8 Cl- Pptppt 80,000

  Total   880,000

iii. 2525iv.

VII. IMPLEMENTATION ARRANGEMENT

7.1 Organization and ResponsibilitiesThe subproject owner: The Hau Giang CERWASS is the subproject owner and will be responsible for ensuring effective implementation of safeguard measures and timely reporting the implementation progress. The Hau Giang CERWASS will set up an environment and social unit (ESU) comprising at least one full time staff to be responsible for effective implementation of safeguard measures. The Construction Supervision Consultant (CSC) and/or field engineer will be assigned to be responsible for day-to-day supervision of safeguard performance of contractor in close coordination with local authorities and communities. As required in the EMP, the CSC and/of field engineer is responsible for ensuring full compliance with the agreed Contractor environmental management plan (CEMP). The CSC and/or field engineer will also include the safeguard performance of contractor into the subproject progress report. The safeguard consultant: To ensure effective implementation of safeguard measures, a team of qualified national consultant (Environmental Management Consultant or EMC) will be hired to assist Hau Giang CERWASS during the implementation of safeguard activities for all the subprojects to be implemented by Hau Giang CESWASS under the subproject, including providing guidance on supervision and monitoring of contractors as well as safeguard training to ESU staff and field engineers.

The Central Project Management Unit (CPMU): CPMU and its safeguard consultant will be responsible for periodic monitoring of safeguard measures for the subproject, including providing clarification on issues related to safeguard policies and requirements and safeguard training to the subproject staff/consultant. Qualified national consultants will be hired to assist CPMU in performing this task.

Other entities: The Hau Giang People Committees and the Department of Natural Resources and Environment and (DONRE) are responsible for ensuring full compliance of GOV's regulations. It is also a normal practice in Vietnam that local community and/or social entities will also monitor the contractor performance as well as actual environmental and social impacts.

Key responsibilities of these stakeholders are listed in Table 7.1.

iii. 2626iv.

Table 7.1: Institutional responsibilities for Hau Giang rural water supply subproject

Community/Agencies Responsibilities.

CPMU

-Periodically monitor performance of the subproject and include the safeguard performance in the project progress report and be the overall contact point with the World Bank.

Hau Giang CERWASS

-As the subproject owner, it is responsible for implementation of all EMP activities including the mitigation measures during construction and operation, including fostering effective coordination and cooperation between contractor, local authorities, and local communities during construction phase. CERWASS will be assisted by a team of qualified consultant, the environmental staff, and/or field engineer.

Supervision engineer-Assist Hau Giang CERWASS in the routine supervision of contractor performance in line with the EMP, including reporting and Supervision engineer maintain close coordination with local community.

Contractor

-Take actions to mitigate all potential negative impacts in line with the objective described in the ECOP -Actively communicate with local residents and take actions to prevent disturbance during construction. -Ensure all the construction activities having sufficient documents from the related organization. -Ensure that all staff and workers understand the procedure and their tasks in the environmental management program. -Report to the Hau Giang CERWASS on any difficulties and their solutions -Report to local authority and Hau Giang CERWASS if environmental accidents occur and coordinate with agencies and keys stakeholders to resolve these issues.

Local NGOs and affected groups

-These organizations could play a role as a bridge between the Provincial and/District People's Committee, communities, contractors, and Hau Giang CERWASS by assisting in community monitoring, -Mobilizing communities participation in the subproject, providing training to communities, and -Participating in solving environmental problems if any.

Hau Giang People's Committee

-Oversee the implementation of the subproject under the recommendations of the DONRE and the Hau Giang CERWASS to ensure compliance of GOV policy and regulations

Hau Giang DONRE -DONRE represents Hau Giang PPC for environmental management. It

iii. 2727iv.

is responsible for monitoring the compliance with the GOV's environmental requirements.

iii. 2828iv.

7.2 Monitoring and Reporting.Field engineer will report the safeguard performance of the contractor as part of the contract's progress report to Hau Giang PCERWASS. The PCERWASS will submit a progress report to CPMU periodically, including the progress on the implementation of the EMP and safeguard performance of the contractor. CPMU will submit the following reports to WB: (a) Semiannual progress report, including; (b) Mid-term Review Report; and annual Environmental and Social Safeguard Monitoring Report, and the reports will also include the progress on safeguard implementation and performance of contractors.

7.3 Work Plan, Schedule, and Cost. Table 7.2 summarizes work plan and schedule of the EMP.

iii. 2929iv.

Table 7.2 Work schedule for Hau Giang rural water supply subproject

Activities Responsible agency

Work schedule Remarks

1.Set up safeguard capacity 1. Set up ESU Hau Giang

CERWASSSeptember 2012 Assume WB

clearance of subproject in October 2012

1.2 Provide safeguard training to subproject staff

CPMU/ Hau Giang CERWASS

December 2012

2. Consultation and detailed design 2.1 Inform local authorities and communities on the EMP and adjust the plan as appropriate

Hau Giang CERWASS

September 2012

2.2 Include the ECOP for the subproject in bidding document and contract document and inform all the bidders of the safeguard requirement

Hau Giang CERWASS

Before finalize bidding and contract documents and the bidding process

2.3 Assign EMC and field engineers to supervise contractor on a daily basis

Hau Giang CERWASS

Before the contractor is on board

EMC also assist in other subproject under Hau Giang PCERWAS responsibility

3. Site clearance and construction management3.1 Prepare CSEP and implement the activities as indicated in the EMP

Contractor During construction

3.4 Monitor and report on contractor performance and actual impact including consultation activities with local resident

Hau Giang PCERWAS /field engineer, consultant

4. WQM program4.1 Monitor water quality as part of normal operation

Hau Giang PCERWAS /consultant

Periodically as planned

iii. 3030iv.

The cost for implementation of EMP includes water quality monitoring cost , training cost is presented in Table 7.3.

Table 7.3 Estimated Cost for EMP

Description ResponsibilityEstimated Cost

(VND)I Construction stage 60,560, 0001 Water quality monitoring program

(880,000đ x 2 samples x 6 systems)

PPMU 10,560,000

2 Expense on ability to execute Environment Protection and Safety

PPMU 50,000,000

II Operation stage 41,120,0001 Cost to analyze water quality in 2

years(880,000đ x 2 samples x 6 systems x 2 years)

PPMU 21,120,000

2 Cost to execute Environment Activities and Security in the first year

PPMU 20,000,000

Total (I, II) 101,680,000

The total cost is 101,680,000 VND equivalent to 4,914 USD

• Cost for mitigation measures during the site clearance and construction process (including monitoring environmental quality) will be included in construction costs.• Cost for monitoring and control of contractors will be included in the cost of contract monitoring;• Cost of testing water quality during operation will be part of the operating costs of the system and paid by Hau Giang CERWASS.

VIII.CONSULTATION AND INFORMATION DISCLOSURE

8.1 Objective of public consultations

Public consultation for the subproject is required during preparation of the subproject so that concerns and comments could be incorporated into the EMP.The public involvement and consultation had been conducted in order to:

Provides useful information, a better understanding of the project and its potential impacts and possible improvements to the project;

Allows potentially controversial issues to emerge at an early stage;

Creates opportunities for early resolution of the issues; and

Helps to build transparent procedures for carrying out proposed project, and to create accountability and a sense of local ownership during project implementation.

iii. 3131iv.

The World Bank’s Operational Policy (OP 4.01) on Environmental Assessment requires that affected groups and local NGOs to be informed

Participation is enabled during project preparation under certain conditions and is generally recommended as part of implementation.

8.2 Consultation procedure

-The Project owner shall coordinate with district/commune People committee PPC, Design Consultant, and Environment Consultant to organize community meetings in the project area. - During that consultation meeting, the project owner and design consultant shall inform people about the project activities, schedule and locations. The Environment Consultant shall present the environmental potential impacts of the project activities and the respective mitigation measures - The community shall give comments on the project schedule, and additional environmental potential impacts the during the actual implementation and mitigation measures suitable for the local conditions.

8.3 Public consultation results

Table 8.1 Detail information of public consultation meetingDate and venue Participants Contents

Dated 29th,30th 31st

Oct1st Nov,2012

Venue: CPCs of 6 subproject communes

Number 138Female:29Male:109

chairman/vice chairman of PPCs, women’s union, Youth union, PCERWASS’s staff, Environment Consultant ,representatives of beneficiaries/affected households of the subproject

1. Local authority introduce participants 2. Environmental consultant describe:- Summary of Subproject- Potential negative impact- Proposed mitigation 3. Questions from participants4. Response from the Project’s owner

Results of public consultationa. Opinions from local people-Most participants said that there was a high demand of clean water in their area. They were expecting to have a water supply system so that they could access to clean water for their domestic need. This would also contribute to promoting local economic growth.-They agreed with PCERWASS about construction schedule proposed, agreed with Environment Consultant on environmental potential impacts of the subproject activities and the respective mitigation measures. -They suggested some measures to minimize impacts that suitable with local condition such as : prohibiting heavy traffic to carry construction materials, encouraging of using slow boat with little noise emitting, watering roads frequently to prevent dust from polluting the air, restriction of construction activities in night time to not disturb local residents nearby.

iii. 3232iv.

b. Responses from Project OwnerPCERWASS committed to put the participant’s suggestions and requirements relating to environmental impact mitigations into bidding document so that the contractor shall have to carry out the work accordingly.PCERWASS also committed to try his best to cooperate with other relevant authorities to speed up the progress to meet the schedule.

8.4 Information disclosure

The EMP will be disclosed in the country at CPMU and Hau Giang PPMU as well as in the subproject districts and communes

The English version of EMP report of subproject will be disclosed at Vietnam Development Information Center (VDIC), Floor 2- No.63 Ly Thai To, Hanoi.

iii. 3333iv.

ANNEX 1:Environmental Code of Practice (ECOP) for Hau Giang rural water supply and sanitation subproject

Table of Contents

Chapter 1 Introduction

Chapter 2 Responsibilities

Chapter 3 -ECOP Part A: General Provisions A 1 Contract Specific Environmental Plan (CSEP) A2 Non-compliance Reporting Procedure A3 Liaising with Authorities and the Public A4 Community Relations A5 Mitigation Objective A6 Implementation of "Chance Find" Procedures A7. Prohibitions

Chapter 4- ECOP Part B: Management of Construction Bl Management of Construction Sites B2 Management of Environmental Quality B3 Management of Work Camp B4 Monitoring of Potential Impacts

Chapter 5- ECOP Part C : Environmental Guidelines for Protection of groundwater source

iii. 3434iv.

Chapter 1: Introduction

1. This ECOP will be included in the bidding and contract documents of the subproject as an annex to the contract specification and the contractor will be informed of this obligation. The ECOP comprises two three parts: Part A (General Provisions) describing basic requirements for implementation and supervision of works while Part B (Construction Management) describing basic requirements for all Contractors carrying out construction. Part C (Environmental Protection Guide groundwater ).For the sake of clarification, "construction" in this document includes all site preparation, demolition of structures, spoil disposal, materials and waste removal and all related engineering and construction activities.

2. Below describes responsibilities and safeguard requirements during the construction stage, including closure of all construction sites and work camps.

Chapter 2: Responsibilities

3. The subproject owner (Hau Giang PCERWASS) and the Contractor are the key entities responsible for implementation of this ECOP. Key responsibilities of the subproject owners and the contractors are as follows:

(a) Subproject owner -General: The subproject owner on behalf of the Central Project Management Unit (CPMU) is responsible for ensuring that the ECOP is effectively implemented. The subproject owner will create a safeguard unit and assign a group of qualified staff to be responsible for preparation and management of environmental and social safeguard of the subproject throughout its life, including supervision of contractors. The subproject owner is responsible for preparing the safeguard reports and submitting to the CPMU.

-During construction, the subproject owner will recruit an Environmental Management Consultant (EMC) to monitor the compliance of the contractor to fulfill the agreed Contract Specific Environmental Plan (CSEP). (see Al below). Responsibilities of the EMC would include the following: (a) monitoring the contractors' compliance with the environmental plan, (b) taking remedial actions in the event of noncompliance and/or adverse impacts occur, (c) investigating complaints, evaluating and identifying corrective measures; (d) advising to the Contractor on environment improvement, awareness, proactive pollution prevention measures; (f) supervising the Contractor's activities in responding to the complaints; (g) providing guidance and on-the-job training to field engineers on various aspects to avoid/mitigate potential negative impacts to local environment and communities during construction.

(b) Contractor -Contractor has the responsibility of carrying out contracted works through fulfilling the agreed CESEP. In doing so, the contactor will establish and maintain contact with the subproject owner and local residents, and keep them informed of construction matters likely to affect them. This may include regular and frequent distribution of newsletters and attendance at meetings at the request of the subproject owner with representatives of local residents groups.

- Contractor will provide information and reporting telephone "Hot Line", staffed at all "" times during working hours. Contact details should be prominently displayed at the sites. Information on the construction progress, including the projected activities that might require closure of traffic or may cause safety risk should be timely provided.

iii. 3535iv.

- Contractor has the duty to secure appropriate permits and licenses before undertaking the works or moving heavy equipment. .It is the responsibility of the Contractor to monitor the development and implementation of new environmental legislation and regulation and to use the appropriate standards prevailing at the time of awarding contracts. Contractor must comply with all prevailing legislation at the time of construction, including any requirements under health and safety.

Chapter 3: ECOP Part A: General Provisions

A 1.Contract Specific Environmental Plan (CSEP)

4. Contractor will be required to prepare a CSEP describing how the Contractor intends to operate construction at works sites as well as other specific measures necessary to avoid and/or reduce the potential negative impacts as required in the ECOP, especially those related to management of the construction site; transportation of construction materials, especially dredge materials; control of dust, noise, and vibration; solid and liquid waste management; and public health. Given different scope and nature of civil works, scope and nature of the CSEP could be differ and all the CSEP will be reviewed and approved by the EMC to be assigned by the subproject owner.

A2. Non-compliance Reporting Procedures

45. -Contractor must comply with the CSEP, and must ensure that their Sub-Contractors (if any) also comply with it. To ensure that necessary action has been undertaken and that steps to avoid recurrence have been implemented, the EMCs and/or Contractor must advise the subproject owner within 24 hours of any serious incidents of non-compliance with the CSEP that may have serious consequence. In the event of working practices being deemed dangerous either by the subproject owners, the local authorities, or the other concerned agencies, immediate remedial action must be taken by the Contractors. The Contractor must keep records of any incidents and any ameliorative action taken. The records on non-compliance that could be practically

56. The Contractor will be responsible for dealing with any reports forwarded by the subproject owner, Police or other agencies by (following instruction from the subproject -owner representative as appropriate) as soon as practicable, preferably within one hour but always within 24 hours of receipt by either the Contractor. The EMCs will monitor and ensure that the Contractor has taken appropriate action. Where appropriate, approval remedial actions may require an agreement from the local authorities and/or other GoV agencies. Procedures should be put in place to ensure, as far as is reasonably practical, that necessary actions can be undertaken to avoid recurrence and/or serious damage.

A3. Liaising with Authorities and the Public

67. Prior to the commencement of subproject activities and throughout the construction duration, the Contractors will work closely with the local authorities and other agencies to ensure full compliance with GOV regulations and will also provide adequate information on the Project to the General Public, especially those that may cause public safety, nuisance, and sensitive areas and the locations of storage and special handling areas.78. The Contractor will provide information and reporting telephone "Hot Line" staffed at all times during working hours. Information on this facility shall be prominently displayed on site hoardings.

iii. 3636iv.

A4. Community Relations 89. -Contractor will assign a community-relation personnel, who will be focused on engaging with the community to provide appropriate information and to be the first line of response to resolve issues of concern. Contractor will take reasonable steps to engage with residents of ethnic minority backgrounds and residents with disabilities (or other priority groups as appropriate), who may be differentially affected by construction impacts.910. -Contractor will ensure that local residents nearby the construction sites will be informed in advance of works taking place, including the estimated duration. In the case of work required in response to an emergency, local residents shall be advised as soon as reasonably practicable that emergency work is taking place. Potentially affected residents will also be notified of the 'Hotline' number, which will operate during working hours. The "Hotline" will be maintained to handle enquiries regarding construction activities from the public as well as to act as a first point of contact and information in the case of any emergency. All calls will be logged, together with the responses given and the callers' concerns action and a response provided promptly. The hotline will be widely advertised and displayed on site signboards.

1011.The Contractor respond quickly to emergencies, complaints or other contacts made via the 'Hotline' or any other recognized means and liaise closely with the emergency services, local authority officers and other agencies (based on established contacts) who may be involved in incidents or emergency situations.1112.The Contractor will manage the work sites, work camps, and workers in a way that is acceptable to local residents and will not create any social impacts due to workers. Any construction workers, office staff, Contractor's employees, or any other person related to the Project found violating the "prohibitions" activities listed in Section A2 below may be subject to disciplinary actions that can range from a simple reprimand to termination of his/her employment depending on the seriousness of his/her employment depending on the seriousness of the violation.

A5. Mitigation Objectives

1213.Main objective of this ECOP is to minimize the potential negative impacts during construction on local environment, local community, and human and environmental safety and disturbance. The Contractor is expected to implement the activities in line with the following approach as much as possible in close consultation with the supervision and/or field engineers who will be assigned by PPMU to supervise the contract. Key approaches include, but not limited, to:

- Minimize impacts and restore damages;

- Replanting trees in project areas;

- Control erosion and sedimentation during construction;

- Proper control of runoff and erosion from acid sulphate soil (ASS) and contaminated sediments through special protection and management;

- Use main roads when possible;

- Heavy traffic restrictions;

- Control (collection, disposal) of wastes (solid and liquid);

iii. 3737iv.

- Minimize disturbance to local population; Frequent meetings with local people and provision of timely and adequate information to the project affected peoples (PAPs) so that their living and production conditions could be managed;

- Engage and provide labour opportunity for local population;

- Application of proper safety and warning measures in the construction sites, especially in dredging canals;

- Provision of temporary crossings and bridges during construction of bridges; Application of proper safety and warning measures;

- Conduct public information campaign and outreach program, including training and capacity building.

A6. Implementation of “Chance Find” Procedures

1314. If Contractors discovers archeological sites, historical sites, remains and objects, including graveyards and/or individual graves during excavation or construction, the Contractors will carry out the following steps:

- Stop the construction activities in the area of the chance find;

- Delineate the discovered site or area;

- Secure the site to prevent any damage or loss of removable objects. In cases of removable antiquities or sensitive remains, a night guard shall be arranged until the responsible local authorities or the National Culture Administration take over;

- Notify the supervisory Project Environmental Officer and Project Engineer who in turn will notify the responsible local authorities and the Culture Department of Province immediately (within 24 hours or less);

- Responsible local authorities and the Culture Department of Province would be in charge of protecting and preserving the site before deciding on subsequent appropriate procedures. This would require a preliminary evaluation of the findings to be performed by the archeologists of National Culture Administration. The significance and importance of the findings should be assessed according to the various criteria relevant to cultural heritage; those include the aesthetic, historic, scientific or research, social and economic values;

- Decisions on how to handle the finding shall be taken by the responsible authorities and Culture Department of Province. This could include changes in the layout (such as when finding an irremovable remain of cultural or archeological importance) conservation, preservation, restoration and salvage;

- Implementation for the authority decision concerning the management of the finding shall be communicated in writing by relevant local authorities; and

- Construction work could resume only after permission is given from the responsible local authorities or Culture Department of Province concerning safeguard of the heritage.

A7. Prohibitions iii. 3838

iv.

1415.The following activities are prohibited on or near the Project sites:

- Cutting of trees for any reason outside the approved construction area; Hunting, fishing, wildlife capture, or plant collection; Buying of wild animals for food; Having caged wild animals (especially birds) in camps; Poaching of any description; Explosive and chemical fishing; Disturbance to anything with architectural or historical value;

- Building of fires; Use of unapproved toxic materials, including lead-based paints, asbestos, etc.; Use of firearms (except authorized security guards); Use of alcohol by workers in office hours; Driving in an unsafe manner in local roads;

- Washing cars or machinery in streams or creeks; Maintenance (change of oils and filters) of cars and equipment outside authorized areas: Creating nuisances and disturbances in or near communities; Disposing garbage in unauthorized places; Indiscriminate disposal of rubbish or construction wastes; Littering the site; Spillage of potential pollutants, such as petroleum products; Collection of firewood; Urinating or defecating outside the designated facilities; and Burning of wastes and/or cleared vegetation.

Chapter 4-ECOP PART B: Construction Management

B1. Construction Site Management

1516. This section outlines the requirements related to management activities that place should be made in the operation site. These related to working hours, location and layout appearance and good hygiene as well as the operation of the equipment and facilities. Monthly inspection / meeting must be conducted to ensure that these procedures are respected. Contractor must comply with "good housekeeping" a policy at all times. This site should be cleared by the contractor on completion of construction.

1617. The contractor is required to minimize, as far as practicable, any adverse environmental impact of their construction activities. All appropriate permits and consent to the operation site will be promptly secured. The main measures are as follows:

- Hours: Core hours will be 0800-1800 on weekdays and 0800-1300 on Saturday. Location requests that individuals other than the above will be considered on a site in each location. Noisy activities not take place outside these hours without prior approval from ESA or PPMU. All construction related traffic will comply with the agreed working hours for each location. Any exemption would require an agreement with ESA, PPMU, and / or local governments.

- Good hygiene: The Contractor shall comply with "good housekeeping" a policy at all times. This will include, but not necessarily limited to the following: Make sure the location considerate behavior employees of the contractor is forbidden to open fire; Ensure that appropriate regulations to control road dust and clean made; Remove garbage at regular intervals, leaving the place clean tidy ; Remove food waste; Prevent insects, other destructive; regular inspection, repair and repaint if necessary hoardings all locations to comply with local conditions and local

iii. 3939iv.

regulations method, all flights / vessels will be removed as soon as reasonably practical and within 24 hours notice of the ESA; Maintain toilets and other welfare facilities for their employees, often do vehicle washing facilities clean and perform all the loading and unloading highway vehicles wherever this is practical.

- Public access to information and locations: As a minimum, the Contractor will provide public information on the location of the program (start and end date), plus the phone to contact public and / or request. Although limited access to dredging locations, dyking , and construction of culverts will be very difficult, the effort will be made as much as possible to ensure safety for employees as well as for the (special especially in children). Things left to enter exit from the location to be controlled as much as possible- The layout and facilities location: The location of huts, houses offices, restrooms and public welfare should be accommodated within the boundaries of the site.- Emergency Procedures: The Contractor shall ensure that emergency procedures are developed to facilitate the effective action in case of medical emergency fire / as well as environmental pollution (mainly gas , used oil, and / or toxic chemicals, etc.). Further guidelines will be provided by the responsible agencies. The emergency procedures will include emergency telephone number and method of notification to the authorities according to law. Contact phone number for the key personnel of the contractor will also be included.- Fire prevention and control: all relevant locations and housing construction or welfare facilities will have in place appropriate planning and management control to prevent fires. The location of fire plan will be prepared and will be led by the Government of Vietnam regulations. During operation and maintenance equipment, vehicles, contractors will ensure that its workers are well aware of the procedures and have enough knowledge to fit them. The specification of non-flammable materials, products and packaging will be pursued wherever reasonably practical. The project will also be made at the request of the Government of Vietnam as may be appropriate in the particular location.- Pest Control: The Contractor shall ensure that the risk of destructive or parasitic disease is minimized. Order enough for handling food waste or other material attractive to the pests must be done. If infection occurs the Contractor must act so as to deal with it as required.- Operation of Equipment: The Contractor shall make all reasonable precautions to ensure that the device is operated in a manner so as not to cause a safety risk and / or cause problems for people around and occupation. Operation of cranes and other large equipment will be closely monitored. License may be required in accordance with the Government of Vietnam.- Unexploded Ordnance (UXO): Although this risk is unlikely in most of the existing project area, however, in the project area in Hau Giang, the Contractor will be responsible for ensuring safety of construction. Process that should be included in the emergency procedure. An emergency procedure will be prepared and implemented if the risk is high.- Site clearance and rehabilitation of the building upon completion: After the completion of works, the contractor will remove and discard all the materials and rubbish and temporary works of every form. This site will be left clean and in a condition to the satisfaction of the PPMU. Any defects which may cause danger to the highway will be done well, before long-term recovery.

iii. 4040iv.

B2.Environmental Quality(a) Water quality1718. The Contractor shall make all efforts to prevent the waste (solid and liquid) discharged into the river channel and protect surface and ground water pollution and other adverse effects including water level changes, flow and water quality in general. Drain engine oil and waste oil from dredgers and construction machines for the canals will be strictly prohibited. Engine oil, used oil, and other toxic substances and hazardous wastes must be collected, stored, processed, and / or the reduction. The main measures are as follows:

- Used oil / engine oil: The oil tank at the construction site (especially when the venue is located less than 10 meters from waterways) must have sufficient strength to ensure to prevent leakage. Container must be located in a secondary prevention systems (bunded) , which will prevent the release of any oil leak. The Contractor shall make provisions to ensure that all hazardous substances including oil drums or contained on the site are labeled and stored correctly and no oil or other contaminants are allowed to access courses water or groundwater study.- Wastewater from these locations: Whenever possible, the contractor shall reduce the amount of waste water is discharged and needs to find alternative means of handling. The Contractor shall ensure that any leaks and wastewater from the farm buildings and must be collected and discharged through a settlement tank. The standards for wastewater treatment before discharge to be agreed in advance with ESA .Contaminated water or water of a certain quality to be discharged into the sewer system of the tanker, other means approved of the disposal.

-Drainage. Drainage must be designed to avoid stagnation can create odors and unsanitary conditions. Contractor must agree with previous ESA, details of the method used, before

starting construction. Particular attention must be treated regularly for pest control (especially rats and

flies) remove mud and other debris after drainage, reduce odors from the sludge and algae by measures including deodorant, hosing down v .. v .. safety measures must be taken to protect both the public and employees and to prevent fly-peak access and illegal in the development process works.- Water quality monitoring: The Contractor shall ensure continuous compliance with all

of the above condition monitoring of ESA / FE, including performance monitoring water quality at

- specific locations and in accordance with government regulations related to wastewater

- management and water quality monitoring.

iii. 4141iv.

(b) Dust, Noise, Vibration1819. The Contractor shall make all efforts to control dust, noise and vibration from the site, as far as is reasonably practical. Too much noise / vibration generating activities must conform to the standards the Government of Vietnam. For critical areas, many contractors are required to measure noise in close consultation with local residents and set the appropriate measures to control and manage noise levels. Measures to reduce dust and other air pollution, noise, vibration is defined as follows:

- Announcement of the People: Before beginning work at any location, the Contractor shall notify local authorities and people on the planning and construction noise and vibration could potentially occur from the construction activities, including measures to reduce noise and vibration- Dust Control: Contractors will happen that no burning of waste materials on site, adequate water supply available on site; dry sweeping of large areas is not allowed; Cover all trucks Bulk materials or potentially dust (soil, mud, v .. v ..) to and from construction sites; water or sprinkle the construction area periodically, especially at the site located near residential areas avoid over loading of trucks, regular cleaning of public roads and access routes, means to ensure that work on site has been exhausted position such that the risk of re-suspension is reduced dust (fine emission should point up), but actual, reasonable driving speed control on un-surfaced roads and the work area; ensure bulk cement and powdered materials other smooth assigned in enclosed tankers and stored in silos with suitable emission control systems to prevent escape of material and overfilling during delivery; Mix a large amount of cement, bentonite , mortars and other similar materials in specified areas; Store materials have the potential to produce dust out of the boundaries where practical, reasonable minimize the number of excavated material is held in the local points; Sheet, seal or damp down unavoidable stockpiles of excavated material is held in place where required; Seal, re-vegetate Earthworks completed as soon as possible reasonable after completion.- Care must be taken in the transport of dredged or damage to and from the construction

site;- damage should be covered at all times. Fly tipping, will not be allowed. Download

only be sent at the specified location (SDA). The Contractor will be responsible for all the trucks assigned to, or exit the workplace and will clean up all the possible damage to public roads and other public

iii. 4242iv.

- works. Be careful when loading and unloading vehicles or dismantling scaffolding or moving

- materials to reduce noise impact. Loading and unloading bays can be placed in suitable enclosures sound.

- The installation of sheet piling with a diesel engine or control air or drop hammer impact cannot be accepted on a number of locations. Using hydraulic hammer or vibrating operation may be necessary in these cases driving and extracting sheet piling, providing the soil strata is suitable for such devices. Where practical, rotary and bursters actuated by hydraulic or electrical energy is used for excavating hard material. Noisy plant and equipment will be sited as far away as practical from noise sensitive buildings. The use of barriers, (egg, mound), huts, sheds audio or partitions to deflect noise away from noise sensitive areas should be used wherever done be.- The contractor will be required to comply with the vibration level established under an agreement with ESA on a location in each location are due attention to minimize exposure to humans (1 Hz to 80 Hz) and protect damage to nearby structures.(c) Traffic and transport

1920. Contractors will be required to use the roads are built as directed by the local authorities and police. The number of truck movements, hours of operation and any area to keep the truck will be agreed in advance with local authorities and police. The plan will be required for each location showing the location of the entrances / exits and access roads agreed to use to the nearest main road, and the routes used by trucks to and from the strategic road network.

- The contractor will maintain up to date log of all drivers will include a written commitment to comply with their local government roads approved for construction traffic. In case of non-compliance, the contractor and / or their subcontractor (s) would be breach of contract, there should be disciplinary action against the individual driver.- The Contractor may request the supply truck stickers only determines the kind of buildings included in each contract, details of which are submitted to local government approval. For identification purposes the contractor will fix this in a prominent position on all trucks serving regular construction. The determination will need to be large enough to be readable from a distance of 20 meters. Trucks waiting to enter or leave the place to turn off their engines to avoid engine noise and emissions is not necessary. The limited size and weight of the vehicle to reach each location can be applied depending on the route to reach agreement.- For construction of interference with a road or footway, the Contractor shall notify local authorities, the responsible agency, and local residents before starting work and measures proposed to minimize safety risks and inconvenience to the public. All necessary and agreed to obtain a license before. The safety of the public must be assured. In the case of temporary footways, reasonable access will be provided to people under the following requirements: (a) any road transport temporary and will be built with the reasonable requests of local government and should have a uniform surface as much as possible; (b) a clear sign to be provided at all times for pedestrian routes with minimum number of changes for all temporary arrangement to reduce the

iii. 4343iv.

confusion. Forewarned should, if possible, the only alternative route is wheelchair, (c) Upon completion of construction materials arising from the works will be leaving the highway in a situation similar clean and tidy condition to the reasonable request of local authorities, and (d) The Contractor shall be responsible for damages caused by their activities to the streets and public buildings in the area around the workplace. Any defects caused by the contractor must be corrected immediately if dangerous or otherwise within 24 hours.- Any street furniture (power or no power) cannot be removed or relocated by the contractor or any of its subcontractors without the written agreement of the responsible agencies.(d) Handling, reuse, recycle waste2021.. The Contractor shall make an effort to minimize waste and storage and handling of hazardous waste (such as used oil, batteries, v .. v) and this should be clearly defined in the SEMP. Opportunities for reuse or recycling construction waste and demolition should be explored and implemented. Where contaminated wastes were found to be present, handling and processing procedures have been proposed by the contractor and agreed upon by the ESA. Contractor shall follow the procedures in the process of development locations. The Contractor will not be allowed to transport the contaminated material on the canals, unless the appropriate treatment facilities and infrastructure agreement with the responsible agencies.(e) Materials of construction2122. Excavation must be handled carefully to reduce dust and congestion and may cause nuisanceand health effects for local residents. Training affects the way public transport (such as pipelines and bridges) must be planned in consultation with local authorities and inform people in advance. All of the damage as well as dredged material excavated will be re-used for road building dikes / and / or land at or near the work site. Care must be taken to excavate, transport and handling / or acid sulfate soil and / or contaminated land.(f) demolition materials2223. Demolition materials must be handled before. The Contractor shall consult with ESA on the final selection of processing sites and methods. If the work involves asbestos removal or destruction of facilities containing asbestos, the contractor shall comply with the provisions of the relevant government.(g) Protection of natural population2324.  Contractor must comply with national regulations and local policies related to protected areas / species, conservation of wildlife, and conservation of natural landscapes for tourism development and control strong disturbance to these areas. Where species are protected by specific legislation contractors must follow the instructions to follow the requirements and allow enough time to get the license, agrees. No trees in this area will be cut without prior agreement with the authorities.

B3. Management of farm work2425. The Contractor shall consult with local agencies in the farm work placement and will provide appropriate water supply systems, waste collection, toilets, mosquito control

iii. 4444iv.

measures, and measures to protect health for all other officers and employees. Prohibited activities fishing, hunting wild animals and affecting the lives of local communities. Conduct training of workers on safety, hygiene and other activities are prohibited (Section A7).

B4. Monitoring the potential impact2526. Contractors will be required to perform the monitoring program as follows:

INFLUENCE PARAMETERS SAMPLING LOCATIONS FREQUENCY

Emissions Dust concentrations Vicinity clearing works In windy weather conditions

Noise and vibration arising

Noise levels meet standards TCVN / QCVN

Vicinity to the receiving vulnerable

Respond to the complaint

Erosion and sedimentation

Impact of erosion control and sedimentation

control erosion and sedimentation

After heavy rains

Toxic contamination of soil

Pesticides and heavy metals in sedimentsAcid concentrations in sediments

The contaminated area was known or acid sulphate soil (ASS) will be tested

Before you cancel prior to reuse

Reduce the value of surface water quality

TSS, pH, BOD,Salinity, coliform meet standards TCVN 5942

Downstream of the dredging works, especially when the ASS and / or sludge contaminated soil be tested and / or been released into the water

Frequently in the course of construction (refer to Part C, C3)

iii. 4545iv.

Chapter 5-ECOP PART C: Environmental Guidelines for Protection of groundwater source

This part is the guidelines during selection of the well. If the selection has been made it should be described in the EMP

2627.Because groundwater is used as a water supply need to be evaluated as to ensure safe levels of water quality.  Here are some guidelines in selecting environmentally appropriate locations. Water quality should comply with WHO standards and / or national standards.

(a) The environmental impacts and mitigation measures applied to the wellsActivity Potential influence These mitigation

measures can be appliedSite Selection Soil loss, soil degradation, and 

toxic effects on aestheticPublic consultation, land relocation, construction landscape (trees / crops)

Bore The disturbance of the flow, aquatic animal populations, disrupting social structures due to the construction workers and the occurrence of disease (STD) Execution risk

Re-planting of vegetation, the establishment of settlements for workers outside the village to minimize the social interaction

Construction pumping station

Pollution of surface water and groundwater by oil…

Only hire an experienced driller to use, implement standard safety procedures

operationOperation

The reservoir may be the regeneration area for the disease by insects / water (mosquitoes, worms), water may be contaminated during transport or storage; spill or leakage of water; water quality problems due to decomposition; excessive groundwater pumping to lower the water makes groundwater hydrology disruption downstream

Organizing programs and health and hygiene, ensuring the provision appropriate management and operation and maintenance of equipment facilities (including training staff and community)

(a) Requirement of space for deep wells (> 30m)The rate of withdrawal (l/s) The minimum distance between wells (m)

2-10 200in 10 –20 400in 20 – 40 600

in 40- 1,000 1000

iii. 4646iv.

(b) The guidelines on minimum land acquisition for water resource protection

water Resources

Requirements Minimum land acquisition outside the  residential areas

Land acquisitionrequirements within the minimum residential

notes

wells 20-50 m2 around wells Inappropriate Need to protect the watershed more

deep wells 10-20 m2 around wells 30 50 m2 around wells

Frenchmen should have additional protection for water storage areas (see section 0)

Surface water intake

The size of intake and treatment plant

The size of intake and treatment plant

Need comprehensive monitoring of water quality upstream to control pollution sources

sludge Removal 1,000-2000 m2 Not acceptable

(d) Examples of guidelines for groundwater protection areaReception areas directly Protection zone The remaining

volume of water area

Delay time or distance to the wells

60 days and over 30 meters 10 and 25 years or 2km

The safeguardsPrevent pathogenic bacteria and viruses, chemical pollution sources

Prevention of chemical decomposition up. The principles and operation of soil and groundwater protection

The principles and operation of soil and groundwater protection

The activitiesallowed

Only activities related water supply

Not permitted:

•Transportation and storage of dangerous goods; industrial waste dumps, construction• The military activities, intensive farming and livestock; mine quartz sand or limestone ;waste water

iii. 4747iv.

iii. 4848iv.

ANNEX 2: Photos, list of participants , minutes of the consultation meetings

iii. 4949iv.