    S T A T U S O F W O R K P R O G R E S S

    A S O N

    1 2 / 0 7 / 2 0 1 4

  • BLOCK BLOCK BLOCK BLOCK AAAA

  • BLOCK BLOCK BLOCK BLOCK BBBB

  • BLOCK BLOCK BLOCK BLOCK CCCC

  • BLOCK BLOCK BLOCK BLOCK DDDD

  • BLOCK BLOCK BLOCK BLOCK EEEE

  • BLOCK BLOCK BLOCK BLOCK FFFF

  • BLOCK BLOCK BLOCK BLOCK GGGG

  • AMENITIES BLOCK AMENITIES BLOCK AMENITIES BLOCK AMENITIES BLOCK GROUND & FIRST FLOOR BLOCK WORKS & GROUND & FIRST FLOOR BLOCK WORKS & GROUND & FIRST FLOOR BLOCK WORKS & GROUND & FIRST FLOOR BLOCK WORKS &

    PLASTERING FINISHES PLASTERING FINISHES PLASTERING FINISHES PLASTERING FINISHES IN PROGRESSIN PROGRESSIN PROGRESSIN PROGRESS

    AMENITIES BLOCK AMENITIES BLOCK AMENITIES BLOCK AMENITIES BLOCK BLOCK WORKS & PLASTERING FINISHES BLOCK WORKS & PLASTERING FINISHES BLOCK WORKS & PLASTERING FINISHES BLOCK WORKS & PLASTERING FINISHES IN IN IN IN

    PROGRESSPROGRESSPROGRESSPROGRESS

  • RAMP SIDE R.C WALL WORKS & COMPOUND WALL PAINTING WORKS RAMP SIDE R.C WALL WORKS & COMPOUND WALL PAINTING WORKS RAMP SIDE R.C WALL WORKS & COMPOUND WALL PAINTING WORKS RAMP SIDE R.C WALL WORKS & COMPOUND WALL PAINTING WORKS

    IN PROGRESSIN PROGRESSIN PROGRESSIN PROGRESS

  • COMPOUND WALL PAINTING WORKS & PERIPHERAL LANDSCAPE COMPOUND WALL PAINTING WORKS & PERIPHERAL LANDSCAPE COMPOUND WALL PAINTING WORKS & PERIPHERAL LANDSCAPE COMPOUND WALL PAINTING WORKS & PERIPHERAL LANDSCAPE

    WORKS WORKS WORKS WORKS IN PROGRESSIN PROGRESSIN PROGRESSIN PROGRESS

  • CENTRE COURT YARD CENTRE COURT YARD CENTRE COURT YARD CENTRE COURT YARD WATER FEATURE BODY WORKS WATER FEATURE BODY WORKS WATER FEATURE BODY WORKS WATER FEATURE BODY WORKS IN PROGRESS IN PROGRESS IN PROGRESS IN PROGRESS

  • STATUS OF FINISHING WORKS

    AMIGO BLOCK

    INTERNAL 1ST COAT PAINTING COMPLETED

    DOOR FRAMES FIXING COMPLETED

    DOOR SHUTTERS FIXING IN PROGRESS

    MARBLE 3RD AND 4TH COAT POLISH IN PROGRESS

    TILING WORKS IN ALL BATH ROOMS COMPLETED

    TILING WORKS IN KITCHEN & UTILITY COMPLETED

    CORNICE WORKS COMPLETED

    WINDOWS FIXING COMPLETED

    TOILET FALSE CEILING WORKS GRID CEILING WORKS COMPLETED

    KITCHEN GRANITE COUNTER FIXING IN PROGRESS

    LIFT LOBBY FINISHING WORKS - IN PROGRESS

    LIFT INSTALLATION IN PROGRESS

    EXTERNAL TEXTURE PAINTING - IST COAT COMPLETED

    BELLAMY BLOCK

    TERRACE OVER HEAD TANK FINISHING WORKS - COMPLETED

    EXTERNAL PLASTERING WORK - UNDER PROGRESS. 90% COMPLETED

    MARBLE LAYING WORKS COMPLETED UPTO 14TH FLOOR, PENTHOUSE IS IN PROGRESS

    BATHROOM/KITCHEN TILING WORKS ARE IN PROGRESS

    CEILING PAINTING WORKS ARE IN PROGRESS

    STAIRS GRANITE FLOOR WORKS COMPLETED

    STAIRS M.S RAILING WORKS - COMPLETED

    TOILETS MARBLE COUNTER FIXING IN PROGRESS

    UNITS ELECTRICAL WIRING STARTED

    FIRE SAFETY WORKS COMPLETED UPTO 11TH FLOOR

    WINDOWS FIXING IN PROGRESS

    BALCONY S.S RAILING FIXING & GRANITE COPING WORKS - IN PROGRESS

  • RAYA BLOCK

    INTERNAL 1ST COAT PAINTING COMPLETED

    DOOR FRAMES FIXING COMPLETED

    DOOR SHUTTERS FIXING IN PROGRESS

    TILING WORKS AT ALL THE BATH ROOMS COMPLETED

    TILING WORKS AT KITCHEN & UTILITY COMPLETED

    CORNICE WORKS COMPLETED

    WINDOWS FIXING COMPLETED

    TOILET FALSE CEILING WORKS GRID CEILING WORKS COMPLETED

    LIFT LOBBY FINISHING WORKS ARE IN PROGRESS

    LIFT INSTALLATION IN PROGRESS

    BONARO BLOCK

    TERRACE OVER HEAD TANK FINISHING WORKS - COMPLETED

    EXTERNAL PLASTERING WORK - UNDER PROGRESS. 93% COMPLETED

    MARBLE LAYING WORKS COMPLETED UPTO 14TH FLOOR, PENTHOUSE IS IN PROGRESS

    BATHROOM/KITCHEN TILING WORKS ARE IN PROGRESS

    CEILING PAINTING WORKS ARE IN PROGRESS

    STAIRS GRANITE FLOOR WORKS COMPLETED

    STAIRS M.S RAILING WORKS - COMPLETED

    TOILETS MARBLE COUNTER FIXING IN PROGRESS

    UNITS ELECTRICAL WIRING STARTED

    FIRE SAFETY WORKS COMPLETED UPTO 14TH FLOOR

    WINDOWS FIXING IN PROGRESS

    BALCONY S.S RAILING FIXING & GRANITE COPING WORKS - IN PROGRESS

    TERRACE WATERPROOFING WORKS ARE IN PROGRESS

  • KADIN BLOCK

    INTERNAL 1ST COAT PAINTING COMPLETED

    DOOR FRAMES FIXING COMPLETED

    DOOR SHUTTERS FIXING IN PROGRESS

    MARBLE 3RD AND 4TH COAT POLISH IN PROGRESS

    TILING WORKS AT ALL THE BATH ROOMS COMPLETED

    TILING WORKS AT KITCHEN & UTILITY COMPLETED

    CORNICE WORKS COMPLETED

    WINDOWS FIXING COMPLETED

    TOILET FALSE CEILING WORKS GRID CEILING WORKS COMPLETED

    KITCHEN GRANITE COUNTER FIXING IN PROGRESS

    LIFT LOBBY FINISHING WORKS ARE IN PROGRESS

    LIFT INSTALLATION IN PROGRESS

    EXTERNAL TEXTURE PAINTING 1ST COAT IN PROGRESS

    CARA BLOCK

    TERRACE OVER HEAD TANK FINISHING WORKS - COMPLETED

    EXTERNAL PLASTERING WORK COMPLETED

    MARBLE LAYING WORKS COMPLETED UPTO 14TH FLOOR, PENTHOUSE IS IN PROGRESS

    BATHROOM/KITCHEN TILING WORKS ARE IN PROGRESS 90% COMPLETED

    CEILING PAINTING WORKS ARE IN PROGRESS

    STAIRS GRANITE FLOOR WORKS COMPLETED

    STAIRS M.S RAILING WORKS - COMPLETED

    TOILETS MARBLE COUNTER FIXING IN PROGRESS

    UNITS ELECTRICAL WIRING IN PROGRESS

    FIRE SAFETY WORKS COMPLETED UPTO 14TH FLOOR

    WINDOWS FIXING IN PROGRESS

    EXTERNAL PAINTING WORKS IN PROGRESS

    BALCONY S.S RAILING BASE PLATES FIXING & GRANITE COPING - IN PROGRESS

  • SUHUBA BLOCK

    INTERNAL 1ST COAT PAINTING COMPLETED

    DOOR FRAMES FIXING COMPLETED

    DOOR SHUTTERS FIXING IN PROGRESS

    MARBLE 3RD AND 4TH COAT POLISH IN PROGRESS

    TILING WORKS AT ALL THE BATH ROOMS COMPLETED

    TILING WORKS AT KITCHEN & UTILITY COMPLETED

    CORNICE WORKS COMPLETED

    WINDOWS FIXING COMPLETED

    TOILET FALSE CEILING WORKS AND GRID CEILING WORKS COPMLETED

    KITCHEN GRANITE COUNTER FIXING IN PROGRESS

    LIFT LOBBY FINISHING WORKS ARE IN PROGRESS

    LIFT INSTALLATION IN PROGRESS

    EXTERNAL TEXTURE PAINTING IST COAT COMPLETED.

    PODIUM

    PODIUM CENTRE COURTYARD FOCAL TREE YARD RETAINING WALL COMPLETED

    OTHER EXTERNAL DEVELOPMENT WORKS:

    SEWERAGE TREATMENT PLANT STRUCTURE WORKS - COMPLETED

    COMPOUND WALL WORK - ON SOUTH & EAST SIDE - COMPLETED

    BASEMENT RAINWATER COLLECTION PITS 4 NOS. - COMPLETED

    BASEMENT FLOOR ANTI TERMITE TREATMENT WORKS, SOLING WORKS & PCC WORKS

    ARE COMPLETED

    BASEMENT FLOOR DRAIN WORKS ARE IN PROGRESS

    BASEMENT ELECTRICAL CABLE TRAY WORKS IN PROGRESS

    BASEMENT FIRE SAFETY RING MAIN WORKS ARE IN PROGRESS

    AMENITY BLOCK STRUCTURAL WORKS COMPLETED UPTO TERRACE,

    BLOCK WORKS AND PLASTER FINISHES ARE IN PROGRESS

    CLUB HOUSE FIRST FLOOR SLAB SHUTTERING WORKS ARE IN PROGRESS

    SWIMMING POOL- R.C BASE SLAB AND SIDE WALL CONSTRUCTION IN PROGRESS

    PODIUM WATERPROOING WORKS AND LANDSCAPE WORKS IN PROGRESS