96
Page 1 User Manual LVRSys™ - 3-phase Systems Low-Voltage-Regulation-System TM Systems of the series: 180.1000.2xxx Delivery from 2017

User Manual - A. Eberle€¦ · 9.4.2 System overview 110 kVA to 400 kVA ... 11.11.3 CT ratio (current transformer ratio) ... This User Manual is a summary of the information needed

  • Upload
    others

  • View
    4

  • Download
    0

Embed Size (px)

Citation preview

  • Page 1

    User Manual LVRSys™ - 3-phase Systems

    Low-Voltage-Regulation-SystemTM

    Systems of the series: 180.1000.2xxx

    Delivery from 2017

  • Page 1

    Content

    1. User guidance ................................................................................................................ 6

    1.1 Target group ..............................................................................................................................6

    1.2 Warnings ...................................................................................................................................6

    1.3 Tips ............................................................................................................................................6

    1.4 Other symbols ...........................................................................................................................7

    1.5 Applicable documentation ........................................................................................................7

    1.6 Keeping .....................................................................................................................................7

    2. Scope of Delivery/Options .............................................................................................. 8

    2.1 LVRSys™ control unit for 3-phase systems ...............................................................................8

    2.2 Transformer block for 3-phase systems....................................................................................8

    2.3 LVRSys™ 1-phase systems for pole mount ...............................................................................9

    2.4 Grid system ...............................................................................................................................9

    2.5 Regulation range/step size .......................................................................................................9

    2.6 Design ..................................................................................................................................... 10

    2.7 Base ........................................................................................................................................ 10

    2.8 Connection ............................................................................................................................. 10

    2.9 Fuse protection ...................................................................................................................... 11

    2.10 Connection and BYPASS operation ........................................................................................ 11

    2.11 Additional NH fuse-switch-disconnectors (B11-B14) ............................................................. 11

    2.12 Control speed ......................................................................................................................... 11

    2.13 Voltage range ......................................................................................................................... 11

    2.14 Communication/Scada protocols ........................................................................................... 12

    2.15 Voltage measurement ........................................................................................................... 12

    2.16 Current/power measurement incl. converter terminals 4- fold ............................................ 12

    2.17 Service socket......................................................................................................................... 12

    2.18 Locking system ....................................................................................................................... 13

    2.19 Integration of other devices .................................................................................................. 13

    2.20 Operation manual & connection diagram ............................................................................. 13

    2.21 Language of the display ......................................................................................................... 13

    3. Safety instructions ........................................................................................................ 14

    4. Technical Data .............................................................................................................. 15

    5. Intended use ................................................................................................................. 16

    6. Description and Principle of Operation .......................................................................... 17

    7. Packaging ...................................................................................................................... 20

    7.1 3-phase systems outdoor ....................................................................................................... 20

  • Page 2

    We take care of it.

    Cabinet .................................................................................................................................... 20 7.1.1

    Transformer block ................................................................................................................... 21 7.1.2

    Concrete Base ......................................................................................................................... 21 7.1.3

    8. Transport ..................................................................................................................... 22

    8.1 3-phase systems outdoor ....................................................................................................... 22

    Switch cabinet transport on pallet ......................................................................................... 22 8.1.1

    Switch cabinet transport by crane .......................................................................................... 22 8.1.2

    Transformer block transport with pallet ................................................................................ 24 8.1.3

    Transformer block transport by crane .................................................................................... 25 8.1.4

    Transport Concrete Base ........................................................................................................ 25 8.1.5

    8.2 3-phase systems indoor .......................................................................................................... 26

    Switch cabinet transport on pallet ......................................................................................... 26 8.2.1

    Switch cabinet transport by crane .......................................................................................... 27 8.2.2

    9. Installation ................................................................................................................... 29

    9.1 3-phase Systems for Outdoor ................................................................................................. 29

    System overview 22 kVA to 70 kVA ........................................................................................ 29 9.1.1

    System overview 110 kVA to 250 kVA 8 % ............................................................................. 30 9.1.2

    System overview 250 kVA 10 % to 630 kVA 10 % ................................................................... 31 9.1.3

    Fuse protection ....................................................................................................................... 32 9.1.4

    Requirement outdoor ............................................................................................................. 32 9.1.5

    9.2 Mounting 3-phase systems outdoor ....................................................................................... 33

    Base hole for concrete base ................................................................................................... 33 9.2.1

    Mounting of the concrete base .............................................................................................. 33 9.2.2

    Insertion of the transformers block ........................................................................................ 35 9.2.3

    Fill layer in base ...................................................................................................................... 35 9.2.4

    Mounting the LVRSys™ on a concrete base ............................................................................ 36 9.2.5

    Closure .................................................................................................................................... 36 9.2.6

    9.3 Electrical connection of the LVRSys™ cabinet and the transformer block ............................. 37

    Transformer contact plug (systems 22 kVA 6 % to 70 kVA 10 %) ........................................... 37 9.3.1

    Transformer contact plug (systems 100 kVA 6 % to 250 kVA 8 %) ......................................... 38 9.3.2

    Transformer contact plug (systems 250 kVA 10 % to 630 kVA 6 %) ....................................... 38 9.3.3

    Secondary cables transformer block ...................................................................................... 38 9.3.4

    Deviating bus bar system & extensions on customer side ..................................................... 40 9.3.5

    PEN and local grounding point ............................................................................................... 40 9.3.6

    Connecting the low-voltage cable .......................................................................................... 41 9.3.7

    9.4 3-phase systems indoor .......................................................................................................... 42

    System overview 22 kVA to 70 kVA ........................................................................................ 42 9.4.1

  • Page 3

    System overview 110 kVA to 400 kVA ................................................................................... 43 9.4.2

    Fuse protection ...................................................................................................................... 44 9.4.3

    Closure ................................................................................................................................... 44 9.4.4

    PEN and local grounding point ............................................................................................... 44 9.4.5

    Requirement indoor ............................................................................................................... 44 9.4.6

    9.5 Handling systems with circuit breaker (up to 70 kVA) ........................................................... 45

    9.6 Handling systems with NH-switch disconnectors (110 kVA to 630 kVA) ............................... 46

    10. Commissioning and Decommissioning LVRSys™ ............................................................. 49

    10.1 Indicator lamps & system switch ........................................................................................... 49

    10.2 Control & first commissioning LVRSys™ ................................................................................ 49

    Control ................................................................................................................................... 49 10.2.1

    First commissioning ............................................................................................................... 49 10.2.2

    10.3 Put the LVRSys™ into operation............................................................................................. 50

    10.4 Take LVRSys™ out of operation and BYPASS mode ............................................................... 51

    11. Operation/Regulator operation ..................................................................................... 52

    11.1 Indicator lamps – control cabinet .......................................................................................... 52

    11.2 Indicator lamps & switch – CPU-board .................................................................................. 52

    11.3 Indicator lamps ...................................................................................................................... 53

    11.4 Switches ................................................................................................................................. 53

    11.5 Boot process .......................................................................................................................... 54

    11.6 Menu navigation .................................................................................................................... 54

    11.7 Automatic mode .................................................................................................................... 55

    11.8 Manual mode ......................................................................................................................... 55

    11.9 Overview of the displays ........................................................................................................ 56

    11.10 Parameters ............................................................................................................................. 57

    Set point ................................................................................................................................. 58 11.10.1

    Tolerance band + and tolerance band - ................................................................................. 58 11.10.2

    Reaction time ......................................................................................................................... 59 11.10.3

    Grid impedance ...................................................................................................................... 60 11.10.4

    11.11 Setup ...................................................................................................................................... 61

    Phase spacing ......................................................................................................................... 62 11.11.1

    Net frequency ........................................................................................................................ 62 11.11.2

    CT ratio (current transformer ratio) ....................................................................................... 62 11.11.3

    Communication ...................................................................................................................... 62 11.11.4

    NTP Time Synchronization ..................................................................................................... 62 11.11.5

    Safety ..................................................................................................................................... 62 11.11.6

    Language ................................................................................................................................ 62 11.11.7

  • Page 4

    We take care of it.

    Delete statistics ....................................................................................................................... 63 11.11.8

    11.12 Drag indicator ......................................................................................................................... 63

    11.13 Info/Update ............................................................................................................................ 63

    Firmware update .................................................................................................................... 63 11.13.1

    LOG ERR .................................................................................................................................. 65 11.13.2

    Firmware-Version ................................................................................................................... 65 11.13.3

    Type number ........................................................................................................................... 65 11.13.4

    Archive log book ..................................................................................................................... 66 11.13.5

    Evaluate logbook (Measurement data) with Microsoft Excel ................................................ 67 11.13.6

    Evaluate logbook (Event data) in Notepad++ ......................................................................... 70 11.13.7

    11.14 Communication ....................................................................................................................... 71

    Overview of the communication settings ............................................................................... 71 11.14.1

    Modbus ................................................................................................................................... 72 11.14.2

    IEC 60870-5-104 ...................................................................................................................... 74 11.14.3

    NTP Time Synchronization ...................................................................................................... 80 11.14.4

    Additional communication protocols ..................................................................................... 80 11.14.5

    12. Safety .......................................................................................................................... 81

    13. Controls and Power stage ............................................................................................. 82

    13.1 Controls for systems up to 70 kVA .......................................................................................... 82

    13.2 Controls for systems from 110 kVA 6 % up to 250 kVA 8 % ................................................... 83

    13.3 Controls for systems from 250 kVA 6 % up to 630 kVA 10 % ................................................. 84

    13.4 Interfaces ................................................................................................................................ 85

    USB .......................................................................................................................................... 85 13.4.1

    Ethernet .................................................................................................................................. 85 13.4.2

    13.5 Power stage ............................................................................................................................ 85

    Systems up to 70 kVA ............................................................................................................. 85 13.5.1

    Systems from 110 kVA 6 % up to 250 kVA 8 % ....................................................................... 86 13.5.2

    Systems from 250 kVA 10 % up to 630 kVA 10 % ................................................................... 86 13.5.3

    13.6 Current transformers .............................................................................................................. 86

    13.7 Fuses Power stage .................................................................................................................. 87

    13.8 Microfuses .............................................................................................................................. 88

    13.9 Lightning protection ............................................................................................................... 89

    13.10 Transformer protection module ............................................................................................. 89

    14. External devices and modifications ............................................................................... 90

    14.1 External devices ...................................................................................................................... 90

    14.2 PQI-DA smart .......................................................................................................................... 90

    15. Servicing/Cleaning/Spare parts ..................................................................................... 91

  • Page 5

    16. Standards and Laws....................................................................................................... 91

    17. Disassembly and disposal .............................................................................................. 91

    18. Warranty ...................................................................................................................... 92

  • Page 6

    We take care of it.

    1. User guidance

    This User Manual is a summary of the information needed for the installation, putting into operation and operation of the low-voltage regulator.

    Read the User Manual in its entirety and do not use the product unless you have understood the User Manual.

    1.1 Target group

    The User Manual is intended for skilled technicians as well trained and certified operators.

    The contents of this User Manual must be accessible to people tasked with the installation and operation of the system.

    1.2 Warnings

    Structure of the warnings

    Warnings are structured as follows:

    SIGNAL WORD

    Nature and source of the danger.

    Consequences in the event of non-observance.

    Actions to avoid the danger.

    Types of warnings

    Warnings are distinguished by the type of danger they are warning against:

    DANGER! Warns of an immediately impending danger that can result in death or serious injuries when not avoided.

    WARNING! Warns of a potentially dangerous situation that can result in death or serious injuries when not avoided.

    CAUTION! Warns of a potentially dangerous situation that can result in fairly serious or light injuries when not avoided.

    NOTICE: Warns of a potentially dangerous situation that results in material or environmental damage when not avoided.

    1.3 Tips

    Tips on the appropriate device use and recommendations.

  • Page 7

    1.4 Other symbols

    Instructions

    Structure of the instructions:

    Instructions for an action.

    Indication of an outcome, if necessary.

    Lists

    Structure of unnumbered lists:

    0 List level 1

    – List level 2

    Structure of numbered lists:

    1) List level 1

    2) List level 1

    1. List level 2

    2. List level 2

    1.5 Applicable documentation

    For the safe and correct use of the product, observe the additional documentation that is delivered with the system as well as the relevant standards and laws.

    1.6 Keeping

    Keep the user manual, including the supplied documentation, readily accessible near the system.

  • Page 8

    We take care of it.

    2. Scope of Delivery/Options

    The systems are to be assembled via modular modules. The main components and documents are:

    0 LVRSys™ control unit

    0 Transformer block

    0 Switch cabinet for out- or indoor installation or pole mount

    0 LVRSys™ user manual

    0 LVRSys™ mounting instructions

    0 Circuit diagram LVRSys™ switch cabinet

    0 LVRSys™ test certificate

    2.1 LVRSys™ control unit for 3-phase systems

    2.2 Transformer block for 3-phase systems

    Transformer block Code

    Transformer block 400 kVA TB400

    Transformer block 250 kVA TB250

    Transformer block 175 kVA TB175

    Transformer block 144 kVA TB144

    Transformer block 110 kVA TB110

    Transformer block 70 kVA TB70

    Transformer block 44 kVA TB44

    Transformer block 22 kVA TB22

    Other choices on request TB9

    Control unit Code

    LVRSys 400-3/230 LVRSys 400-3/230

    LVRSys 250-3/230 LVRSys 250-3/230

    LVRSys 175-3/230 LVRSys 175-3/230

    LVRSys 144-3/230 LVRSys 144-3/230

    LVRSys 110-3/230 LVRSys 110-3/230

    LVRSys 70-3/230 LVRSys 70-3/230

    LVRSys 44-3/230 LVRSys 44-3/230

    LVRSys 22-3/230 LVRSys 22-3/230

    Other choices on request LVRSys9-3

  • Page 9

    2.3 LVRSys™ 1-phase systems for pole mount

    2.4 Grid system

    2.5 Regulation range/step size

    Control unit Code

    LVRSys control unit + transformer block 50 kVA LVRSys 50-1/230+TB

    LVRSys control unit + transformer block 35 kVA LVRSys 35-1/230+TB

    LVRSys control unit + transformer block 15 kVA LVRSys 15-1/230+TB

    LVRSys control unit + transformer block 7,5 kVA LVRSys 7,5-1/230+TB

    Other choices on request LVRSys9-1

    Grid Code

    TN-C System (3-phase) or 1-phase (standard) GS1

    TN-S System (3-phase) GS2

    IT System (3-phase) GS3

    Other choices on request GS9

    3-phase Code

    ± 6% in 1,5% steps (standard) S1

    ± 8% in 2% steps (22 - 70 kVA) S21

    ± 8% in 2% steps (110 - 250 kVA) S22

    ± 8% in 2% steps (400 kVA ) S23

    ± 10% in 2,5% steps (22 - 70 kVA) S31

    ± 10% in 2,5% steps (110 - 250 kVA) S32

    ± 10% in 2,5% steps (400 kVA) S33

    1-phase

    ± 6% in 1,5% steps (standard) S1

    ± 8% in 2% steps S21

    ± 10% in 2,5% steps S31

    Other choices on request

  • Page 10

    We take care of it.

    2.6 Design

    2.7 Base

    2.8 Connection

    Cabinet Code

    Only control unit IP66 for integration in external cabinet B0

    Fixed cabinet outdoor (22 - 70 kVA) B11

    Fixed cabinet outdoor (110 - 250 kVA) B12

    Fixed cabinet outdoor (400 kVA) B13

    Fixed cabinet outdoor 160 cm B14

    Fixed cabinet indoor (22 – 70 kVA) B21

    Fixed cabinet indoor (110 - 400 kVA) B22

    Pole mount 1-phase outdoor B31

    Cabinet outdoor GRP (22 - 70 kVA) B41

    Cabinet outdoor GRP (110 - 250 kVA) B42

    Other choices on request B9

    Base Code

    Without base C0

    Concrete base outdoor (22 - 70 kVA) C11

    Concrete base outdoor (110 - 250 kVA) C12

    Concrete base outdoor (400 kVA) C13

    Concrete base outdoor 160 cm C14

    Steel base indoor (22 - 70 kVA) C21

    Steel base indoor (110 - 400 kVA) C22

    GRP base outdoor systems (22 - 70 kVA) C41

    GRP base outdoor systems (110 - 250 kVA) C42

    Other choices on request C9

    Connection Code

    Connection strands 2m (only with the selection B0) D0

    Flat terminal M12 25 mm² - 240 mm² (systems from 110 kVA) D1

    Steel-frame clamp 25 mm² - 300 mm² (systems from 110 kVA) D2

    Box terminal 25 mm² - 150 mm² (systems up to 70 kVA) D3

    Direct connection isolater (included in the option B31 & B41) D4

    Other choices on request D9

  • Page 11

    2.9 Fuse protection

    2.10 Connection and BYPASS operation

    2.11 Additional NH fuse-switch-disconnectors (B11-B14)

    Fixed cabinet is widened by additional switch-disconnectors. A different base and a different design must be chosen.

    2.12 Control speed

    2.13 Voltage range

    Fuse protection Code

    Input and output fuse protection for rated power (standard) Q0

    No fuse protection (fuse protection by operators) Q1

    Other choices on request Q9

    Connection and Bypass Code

    No strip (only in combination with B0) J00

    1 input and 1 output (standard 22 - 44 kVA) circuit breaker J11

    1 input and 1 output (standard 70 kVA) circuit breaker J12

    1 input and 1 output (standard 110 - 250 kVA) switch-disconnector NH2 J13

    1 input and 1 output (standard 400 kVA) switch-disconnector NH3 J14

    Other choices on request J9

    Additional fuse-switch-disconnectors Code

    Without additional fuse-switch-disconnectors JS0

    NH 00 input unregulated (per fuse-switch-disconnector 5 cm ) JS1

    NH 00 output regulated (per fuse-switch-disconnector 5 cm) JS2

    NH 2 input unregulated (per fuse-switch-disconnector 10 cm) JS3

    NH 2 output regulated (per fuse-switch-disconnector 10 cm) JS4

    NH 3 input unregulated (per fuse-switch-disconnector 10 cm) JS5

    NH 3 output regulated (per fuse-switch-disconnector 10 cm) JS6

    Additional fuse-switch-disconnector combination JS9

    Control speed Code

    < 1 s (standard) E1

    < 30 ms E2

    Voltage range Code

    50 Hz 100 V-264 V Voltage range (standard) H1

    60 Hz 100 V-264 V Voltage range H2

  • Page 12

    We take care of it.

    2.14 Communication/Scada protocols

    2.15 Voltage measurement

    2.16 Current/power measurement incl. converter terminals 4- fold

    2.17 Service socket

    Other choices on request H9

    Communciation/Scada protocols Code

    Modbus TCP/IP (standard) L1

    IEC 60870-104 L2

    DNP 3:00 TCP/IP L3

    Other choices on request L9

    Voltage measurement Code

    Voltage measurement output (standard) U0

    Voltage measurement for external devices 3-phase input U1

    Voltage measurement for external devices 3-phase output U2

    Voltage measurement for external devices 1-phase input U3

    Voltage measurement for external devices 1-phase output U4

    Other choices on request U9

    Current measurement Code

    Without current/power measurement M0

    Current measurement (only wiring for external converters 4- fold) M1

    Current/power measurement LVRSys 3-phase (22 - 70 kVA) incl. converter M11

    Current/power measurement LVRSys 3-phase (110 - 250 kVA) incl. converter M12

    Current/power measurement LVRSys 3-phase (630 kVA) incl. converter M13

    Current/power measurement LVRSys 1-phase (7,5 - 50 kVA) incl. converter M21

    Current/power measurement LVRSys and selected PQI-DA smart M5

    Other choices on request M9

    Service socket Code

    Without socket K0

    Socket + GFCI (CEE 7/4) Schuko 16A (Deutschland) K1

    Socket + GFCI (SEV 1011) Typ 13 16A (Schweiz) K2

    Other choices on request K9

  • Page 13

    2.18 Locking system

    2.19 Integration of other devices

    2.20 Operation manual & connection diagram

    2.21 Language of the display

    Locking system Code

    Cabinet key (only in combination with B0) N0

    Profile cylinder DIN 18254 N1

    Profile cylinder pivot lever Ø 22 N2

    Other choices on request N9

    Integration of other devices Code

    Without extern devices P0

    Mounting and wiring-test of communication device P1

    Other choices on request P9

    Language Code

    German G1

    English G2

    French G3

    Italian G4

    Spanish G5

    Polish G6

    Dutch G7

    Other choices on request G9

    Language Code

    German A1

    English A2

    French A3

    Italian A4

    Spanish A5

    Polish A6

    Dutch A7

    Other choices available on request A9

  • Page 14

    We take care of it.

    3. Safety instructions

    Observe the operating instructions

    Always keep the operating instructions with the unit.

    Make sure that the device is operated only in perfect condition.

    Make sure that only specialized personnel are operating the unit.

    Connect the device only according to the instructions.

    Make sure that the device is not operated over the rated data (see chapter 4, Technical

    Data)

    Do not operate the unit in an environment where explosive gases, dust or fumes occur.

    Ensure that protective covers are in place and are functional

    Ensure that the five safety regulations according to DIN VDE 0105 are always observed.

    Clean the appliance only with commercially available detergents.

  • Page 15

    4. Technical Data

    Rated data

    Rated voltage 𝐔𝐍 400 V / 230 V ±20 % (L-L/LE)

    Rated current 𝐈𝐍 3-phase/1-phase 3-phase

    32 A (22 kVA system)

    63 A (44 kVA system)

    100 A (70 kVA system)

    160 A (110 kVA system)

    200 A (144 kVA system)

    250 A (175 kVA system)

    355 A (250 kVA system)

    577 A (400 kVA system)

    909 A (630 kVA system)

    1-phase

    32 A (7,5 kVA system)

    63 A (15 kVA system)

    100 A (25 kVA system)

    125 A (30 kVA system)

    160 A (40 kVA system)

    200 A (50 kVA system)

    Rated frequency 𝐟𝐍 50 Hz / 60 Hz

    Efficiency 99.4 % – 99.8 %

    Maximum regulation time 30 ms

    Regulation area

    ± 6 % from UN in 9 steps á 1.5 %

    ± 8 % from UN in 9 steps á 2.0 %

    ± 10 % from UN in 9 steps á 2.5 %

    up to ± 24 % from UN (special design)

    Ambient temperature - 40 °C to + 40 °C (to + 50 °C special design)

    Maximum permissible air temperature in the cabinet

    70 °C

    Height of installation (NN) < 2000 m

    Protection class IP44- IP55/ electronic IP 66

    Maximum current consumption sec-ondary electronics

    200 mA (230 V)

    Short-circuit impedance 𝐮𝐤 ca. 0,3 %

    Cooling passive (Convection via cabinet housing)

    Limits

    Rated impulse voltage 𝐔𝐈𝐦𝐩 6 kV

    Rated short-circuit current resistance 𝐈𝐜𝐰 ( 1 s)

    5 kA (to 70 kVA)

    15 kA (110 kVA to 630 kVA)

    Conditional rated short-circuit current 𝐈𝐜𝐜

    20 kA (to 70 kVA)

    50 kA (110 kVA to 630 kVA)

    Rated short-circuit current 𝐈𝐜𝐟 protected by fuse

    3 kA (22 kVA)

    5 kA (44 kVA)

    10 kA (70 kVA)

    14 kA (110 kVA)

    16 kA (144 kVA)

    20k A (175 kVA)

    30 kA (250 kVA)

    50 kA (400 kVA)

    50 kA (630 kVA)

  • Page 16

    We take care of it.

    Rated impulse withstand current 𝐈𝐩𝐤 20 kA (to 70 kVA)

    50 kA (110 to 630 kVA)

    Measurements and weight

    Measurements cabinet B/T/H

    80 cm/40 cm/135 cm

    120 cm/40 cm/135 cm

    140 cm/50 cm/145 cm

    (22 kVA – 70 kVA)

    (110 kVA – 250 kVA 8 %)

    (250 kVA 10 % – 630 kVA)

    Weight cabinet 100 kg

    150 kg

    220 kg

    (22 kVA – 70 kVA)

    (110 kVA – 250 kVA 8 %)

    (250 kVA 10 % – 630 kVA)

    Measurement base B/T/H

    80 cm/40 cm/100 cm

    120 cm/40 cm/100 cm

    140 cm/50 cm/100 cm

    (22 kVA – 70 kVA)

    (110 kVA – 250 kVA 8 %)

    (250 kVA 10 % – 630 kVA)

    Weight base

    200 kg

    260 kg

    290 kg

    (22 kVA – 70 kVA)

    (110 kVA – 250 kVA 8 %)

    (250 kVA 10 % – 630 kVA)

    Measurement transformer block B/T/H – 3-phase

    40 cm/28 cm/100 cm

    50 cm/28 cm/100 cm

    70 cm/35 cm/100 cm

    (22 kVA – 70 kVA)

    (110 kVA – 250 kVA 8 %)

    (250 kVA 10 % – 630 kVA)

    Weight transformer block – 3-phase

    60 kg ( 22 kVA)

    100 kg( 44 kVA)

    120 kg ( 70 kVA)

    150 kg (110 kVA)

    170 kg (144 kVA)

    200 kg (175 kVA)

    250 kg (250 kVA)

    450 kg (400 kVA)

    550 kg (630 kVA)

    Fulfilled guidelines

    EMC Immunity DIN EN 61000-6-1

    EMC emissions DIN EN 61000-6-3

    Installation instructions DIN EN 61439-1/5

    Low voltage directive 2014/35/EU

    Noise emission < 37 dB(A)

    Table 4-1 Technical data

    5. Intended use

    This product is designed exclusively to regulate voltage at the low voltage level (400V L-L).

  • Page 17

    6. Description and Principle of Operation

    The LVRSys™ regulator concept is based on a linear regulator. By coupling and uncoupling two transformers with a selected transfer ratio, the output voltage can be regulated in several (e.g. 9) steps. The maximum control range depends on the version (e.g. from ±6% up to ±20%).

    The transformers are controlled by thyristors. The stages of the transformers are determined by the thyristors' switching settings.

    Step Transformer 1.5% Transformer 4.5%

    +6 % +1.5 % +4.5 %

    +4.5 % 0 % +4.5 %

    +3 % -1.5 % +4.5 %

    +1.5 % +1.5 % 0 %

    0 % 0 % 0 %

    -1,5 % -1,5 % 0 %

    -3 % +1.5 % -4.5 %

    -4.5 %/ 0 % -4.5 %

    -6 % -1.5 % -4.5 %

    Table 6-1 Generation of the voltage levels in steps

    The control signals for the thyristors are generated by driver circuits that switch them intelligently. By monitoring the magnetic flux in the transformers, the transformers can be switched without voltage dips, current increases or generating harmonics.

    The step change required is output by the controller. The controller can determine the step based on the bus bar voltage or the output currents.

    All three phases are regulated independently of one another. This helps improve the symmetry of the grids.

    In the event of a failure the safety contactor activates automatically. This ensures that the transformers are shorted and as such the low-voltage grid will operate unregulated.

  • Description and Principle of Operation

    Page 18

    We take care of it.

    Figure 6-1 Single-phase functional diagram

    Trafo 1 Additional transformer 1

    Trafo 2 Additional transformer 2

    F1, F2 Fuse

    S Safety contactor (NCC principle)

    R Switching resistor

    T Thyristor

    TC Thyristor control

    V_in Unregulated input voltage

    V_out Regulated output voltage

    Table 6-2 Explanation of the abbreviations

  • Page 19

    Figure 6-2 Example of 3% voltage reduction

    In the example shown in Figure 6-2, the output voltage is reduced by 3% compared with the input voltage. The transformer Trafo 1 (-4.5%) converts the primary voltage, which is switched by thyristors, in a negative direction and subtracts 10.35 V (4.5% of 230 V) from the output voltage. The transformer Trafo 2 (1.5%) converts the primary voltage in a positive direction and adds 3.45 V (1.5% of 230 V) to the output voltage.

  • Packaging

    Page 20

    We take care of it.

    7. Packaging

    7.1 3-phase systems outdoor

    Figure 7-1: LVRSysTM Outdoorsystem with transformer block and concrete socket

    Cabinet 7.1.1

    Figure 7-2 Cabinet packed using wood panels

  • Page 21

    Figure 7-3 Packaging & Shock Stickers

    To protect the system the packaging consists of OSB plates.

    Check the shock stickers before opening.

    NOTICE With red colored sticker:

    Do not remove the packaging.

    Contact A. Eberle GmbH & Co. KG

    Transformer block 7.1.2

    The transformer block is standing packed and secured on a pallet. The transport packaging is a foil.

    Concrete Base 7.1.3

    The concrete base is packed in individual parts on a pallet.

  • Transport

    Page 22

    We take care of it.

    8. Transport

    8.1 3-phase systems outdoor

    Switch cabinet transport on pallet 8.1.1

    CAUTION! Switch cabinet can be damaged if handled incorrectly during transport!

    Only transport LVRSys™ in an upright position.

    Make sure the switch cabinet cannot topple over.

    Fasten mounting devices on the board wall.

    Figure 8-1 Transport the cabinet by lorry

    Switch cabinet transport by crane 8.1.2

    DANGER! Falling switch cabinet is a danger to life!

    Make sure no one is below a hanging load.

  • Page 23

    CAUTION! Falling switch cabinet can damage the system!

    Secure the LVRSys™ with all of the transport lugs.

    Load the transport lugs only with vertical load (maximum devia-tion 60°).

    Do not lift the LVRSys™ with a jolt.

    Transport lugs are located under the weather protection roof.

    Removing the hood:

    Loosen the screws at the front (1).

    Lift the hood at the front (2).

    Push the hood to the back (3).

    Lift the hood upward (4).

    Installing the hood:

    Lower the hood from above (5).

    Push the hood to the front (6).

    Fasten the screws at the front (7).

    1 2

    3 4 5

  • Transport

    Page 24

    We take care of it.

    Figure 8-2 Installing and removing the hood

    The screws can be loosened and fastened with a TX 25 screwdriver. The tightening torque may not exceed 6 Nm.

    Use all four transport lugs.

    Figure 8-3 Transport lugs

    Transformer block transport with pallet 8.1.3

    CAUTION! Transformer block can be damaged if handled incorrectly during transport!

    Only transport transformer block in an upright position.

    Make sure the transformer block cannot topple over.

    Fasten mounting devices on the board wall.

    6

    1 2

    7

  • Page 25

    Transformer block transport by crane 8.1.4

    DANGER! A falling transformer block represents a danger to life!

    Make sure no one is below a hanging load.

    CAUTION! Falling transformer block can damage the system!

    Secure the transformer block with all of the transport lugs.

    Load the transport lugs only with vertical load (maximum devia-tion 60°).

    Do not lift the transformer block with a jolt.

    3.

    Figure 8-4 Transformer block with 4 crane lugs

    Use all four transport lugs.

    Transport Concrete Base 8.1.5No special transport sensitivities.

  • Transport

    Page 26

    We take care of it.

    8.2 3-phase systems indoor

    Switch cabinet transport on pallet 8.2.1

    CAUTION! Switch cabinet can be damaged if handled incorrectly during transport!

    Only transport LVRSys™ in an upright position.

    Make sure the switch cabinet cannot topple over.

    Fasten mounting devices on the board wall.

    Figure 8-5 Transport the cabinet by lorry

  • Page 27

    Figure 8-6 Transport with forklift or pallet truck

    Switch cabinet transport by crane 8.2.2

    DANGER! Falling switch cabinet is a danger to life!

    Make sure no one is below a hanging load.

  • Transport

    Page 28

    We take care of it.

    Figure 8-7 Transport lugs power distribution

    CAUTION! Falling switch cabinet can damage the system!

    Secure the LVRSys™ with all of the transport lugs.

    Load the transport lugs only with vertical load (maximum devia-tion 60°).

    Do not lift the LVRSys™ with a jolt.

    400 & 630 kVA systems are allowed only to be loaded with a ver-tical load

    VORSICHT! Damaging the system by dropping the switch cabinet!

    Always transport the LVRSysTM switch cabinet evenly.

  • Page 29

    9. Installation

    9.1 3-phase Systems for Outdoor

    System overview 22 kVA to 70 kVA 9.1.1

    PEN

    1

    23

    4

    5

    6

    7

    8

    Figure 9-1 System overview LVRSysTM 22 to 70 kVA

    1 LVRSys™ switch cabinet

    2 Concrete base

    3 Transformer block

    4 Switch cabinet for electronic IP 66

    5 Circuit breaker for manual BYPASS operation

    6 PEN bus bar with injection nuts M12 and M8

    7 C-profile bus bar for cable interception

    8 Connection input and output with box terminals 35 mm² to 240 mm²

    Table 9-1 Explanation of Figure 9-1 listed numbers

  • Installation

    Page 30

    We take care of it.

    System overview 110 kVA to 250 kVA 8 % 9.1.2

    PEN

    1

    23

    4

    5

    6

    7

    Figure 9-2 System overview LVRSys™ 110 to 250 kVA 8%

    1 LVRSys™ switch cabinet

    2 Concrete base

    3 Transformer block

    4 Switch cabinet for electronics IP 66

    5 NH-switch disconnectors for connection to the low voltage grid and BYPASS

    6 PEN bus bar with injection nuts M12 und M8

    7 C-profile bus bar for cable interception

    Table 9-2 Explanation of Figure 9-2 listed numbers

  • Page 31

    System overview 250 kVA 10 % to 630 kVA 10 % 9.1.3

    PEN

    1

    23

    4

    5

    6

    7

    Figure 9-3 System overview LVRSys™ 250 kVA 10% to 630 kVA 10%

    1 LVRSys™ switch cabinet

    2 Concrete base

    3 Transformer block

    4 Switch cabinet for electronic IP 66

    5 NH-switch disconnectors for connection to the low voltage grid and BYPASS

    6 PEN bus bar with injection nuts M12 und M8

    7 C-profile bus bar for cable interception

    Table 9-3 Explanation of Figure 9-3 listed numbers

  • Installation

    Page 32

    We take care of it.

    Fuse protection 9.1.4

    The LVRSysTM must be protected against short circuit and continuous overcurrent. All systems are designed with a safety equipment according to Table 9-4.

    In consultation with the A. Eberle GmbH & Co. KG Support Team larger fuses may be

    used as indicated.

    Protection Matched fuse protection

    Circuit breaker C

    32 A (22 kVA system)

    63 A (44 kVA system)

    100 A (70 kVA system)

    NH-fuse gG NH2

    160 A (110 kVA system)

    200 A (144 kVA system)

    250 A (175 kVA system)

    355 A (250 kVA system)

    NH-fuse gTr NH3 400 kVA (400 kVA system)

    630 kVA (630 kVA system)

    Table 9-4 Protection of the systems input load bar

    Requirement outdoor 9.1.5

    Ensure that heat is dissipated through adequate air circulation.

    Observe the following minimum distances:

    – 50 cm to the ceiling.

    – 100 cm to 120 cm in the door area.

    Avoid direct sunshine.

  • Page 33

    9.2 Mounting 3-phase systems outdoor

    Base hole for concrete base 9.2.1

    Work to be performed:

    Cut out a base hole that is 110 cm to 130 cm deep.

    Found it with 30 cm of broken stones and gravel.

    Pave foundation.

    Install the grounding base.

    Figure 9-4 Founding

    Mounting of the concrete base 9.2.2

    Two people are needed to set up the base.

    Required tools:

    0 Spirit level.

    0 Wrench 13 and 19, 25 Nm.

    When edging the base with flagging or similar material, a minimum distance to the base of 5 cm must be observed as an expansion gap.

    Do not bring vibratory equipment in contact with the base.

    The concrete base is made of light-weight concrete and consists of:

    0 Foundation plate

    0 Two side components

    0 Two split base plates

    0 Installation material

    0 Fastening screws.

    To give the sides more stability, support them with earth-moist concrete.

  • Installation

    Page 34

    We take care of it.

    Align the foundation plate with recesses facing upward.

    Place the side components with notches facing upward on the foundation plate.

    Fasten the rear panel:

    Connect the larger plate at the bottom with two screws and brackets to the side components.

    Connect the smaller plate at the top with two screws and brackets to the side components.

    Pull through the wiring.

    Of the two-part front panel, first fasten the larger plate at the bot-tom with two screws and brackets to the side components.

    Then connect the smaller plate at the top with two screws and brackets to the side components.

    Installation depth of the concrete base ca. 70 cm

    Figure 9-5 Installing the concrete base

  • Page 35

    Insertion of the transformers block 9.2.3

    Insert the transformer block into the base on the left (viewed from the front).

    Transformer block with fuse-switch-disconnector(thick cables) on the left and connec-tion cable control electronics (thin cable with plug) on the right.

    Correct the transformer block that no walls are touched.

    Figure 9-6 : Top view concrete base and transformer block

    1 Transformer block

    2 Connection cable load bar (thick cables)

    3 Connection cable control electronics (thin cable with plugs)

    4 Concrete base

    5 Switch cabinet doors opened

    Table 9-5 Explanation of Figure 9-6 listed numbers

    Fill layer in base 9.2.4

    To avoid condensation in the base area, seal the final filling layer in the base with a

    suitable material.

    The filling height should be amount 200 mm – 300 mm.

    Material recommendation fill layer in base:

    0 Dry fine gravel as base layer

    0 Dry river sand as middle layer

    0 Lean concrete, expanded concrete or styrofoam as finishing layer

  • Installation

    Page 36

    We take care of it.

    Mounting the LVRSys™ on a concrete base 9.2.5

    Figure 9-7 Mounting ducts

    Connect the switch cabinet through four mounting ducts with the concrete base.

    Only use the provided screws M 12 x 25 mm.

    Closure 9.2.6

    Installing and removing the locking cylinder:

    Turn the cover cap to the right to open it (1).

    Insert the key in the locking cylinder and turn right to open (2).

    Unscrew fastening screw (M5) from the locking cylinder (3).

    Pull out the locking cylinder towards the switch cabinet (4).

    Slide in the new locking cylinder (5).

    Screw fastening screw (M5) into the locking cylinder (6).

    Insert the key in the locking cylinder and turn left to lock (7).

    Turn cover cap left to close (8).

    1 2

  • Page 37

    Figure 9-8 Installing and removing the locking cylinder

    9.3 Electrical connection of the LVRSys™ cabinet and the trans-

    former block

    For outdoor systems the LVRSysTM the transformer block and switch cabinet must be connected. For complete indoor systems the connections already exist.

    Transformer contact plug (systems 22 kVA 6 % to 70 kVA 10 %) 9.3.1

    Place the coded plug at the bottom of the case.

    Lock the connector. Fix the cables with cable clamps.

    Figure 9-9 Transformer contact plug 22 kVA 6% bis 70 kVA 10%

    3 4 5

    6

    1 2

    7 8

  • Installation

    Page 38

    We take care of it.

    Transformer contact plug (systems 100 kVA 6 % to 250 kVA 8 %) 9.3.2

    Place the coded plug at the bottom of the case.

    Lock the connector. Fix the cables with cable clamps.

    Figure 9-10 Transformer contact plug 110 kVA 6% bis 250 kVA 8%

    Transformer contact plug (systems 250 kVA 10 % to 630 kVA 6 %) 9.3.3

    Place the coded plug at the bottom of the case.

    Lock the connector. Fix the cables with cable clamps.

    Figure 9-11 Transformer contact plug 250 kVA10 % bis 630 kVA 6%

    Secondary cables transformer block 9.3.4

    Connect the secondary cables of the transformer block (L1IN / L2IN / L3IN) to the NH-

    switch disconnectors or the circuit breaker LVRSysIN (F2).

    Connect the secondary cables of the transformer block (L1OUT / L2OUT / L3OUT) to the

    NH-switch disconnectors or the circuit breaker LVRSysOUT (F4).

    Connect the PEN cable of the transformer block to the PEN busbar.

    Fix the cables with cable clamps.

    Connection via circuit breakers:

  • Page 39

    Figure 9-12 Circuit breaker

    Torque circuit breaker min. 3 / max. 4 Nm.

    Connection via switch disconnectors

    Figure 9-13 NH-switch disconnectors

    NH-switch disconnectors must be connected via cable lugs (see cross section below).

    For torques see chapter 9.3.7.

  • Installation

    Page 40

    We take care of it.

    Cable cross sections of the transformer blocks

    System Cable cross section secondary cable Cable cross section PEN-cable

    22 kVA 4 mm² 2,5 mm²

    44 kVA 10 mm² 6 mm²

    70 kVA 16 mm² 10 mm²

    110 kVA 35 mm² 16 mm²

    144 kVA 50 mm² 25 mm²

    175 kVA 70 mm² 35 mm²

    250 kVA 120 mm² 70 mm²

    400 kVA 2 x 120 mm² 120 mm²

    630 kVA 2 x 185 mm² 185 mm²

    Table 9-6 Cable cross section of the transformer blocks

    Deviating bus bar system & extensions on customer side 9.3.5

    In case of deviations from the standard (5 NH-switch disconnectors) the following conditions apply:

    0 Busbar system 2-part (input and output) is coupled by a BYPASS load bar which is designed for the rated current of the system.

    0 The load bar for LVRSysIN is connected to the secondary cables of the transformer block (L1IN / L2IN / L3IN).

    0 The load bar for LVRSysOUT is connected to the secondary cables of the transformers (L1OUT / L2OUT / L3OUT).

    0 System voltage of the control must be clamped on the load bar LVRSysOUT.

    0 PEN connection of the control unit must be connected to the PEN busbar.

    PEN and local grounding point 9.3.6

    The operator of the installation must ensure that the local grounding point is conform with DIN 18014 or DIN EN 62305-3.

    Connect the local grounding point to the PEN bus bar.

    Connect PEN input (grid connection transformer) with PEN bus bar.

    Connect PEN output (grid connection load) with PEN bus bar.

    Figure 9-14 Connection of the PEN busbar with insert nut M12 and M8

  • Page 41

    Connecting the low-voltage cable 9.3.7

    DANGER! Danger of electric shock!

    Make sure the LVRSys™ is de-energized before connecting it.

    CAUTION! Destruction of components due to overload!

    Use cable clasps in the LVRSys™ system's inputs and outputs.

    CAUTION! Destruction of components due to overload!

    Only switch on the low voltage grid in BYPASS mode. (See Section 11.4)

    Sequence connection to the low voltage grid:

    Isolate the low voltage grid.

    Clamp L1/L2/L3 input (grid connection transformer) according to DIN EN 61439.

    Clamp L1/L2/L3 output (grid connection load) according to DIN EN 61439.

    Install the cable clips on C profile bus bars under input and output.

    Couple the low voltage grid.

    Figure 9-15 Installation of low voltage cables with flat connector

  • Installation

    Page 42

    We take care of it.

    For Aluminum wires the oxide layer must be mechanically removed and the con-

    duction must be treated with acid and alkali free fat before contacting the cables.

    System Flat terminals (Nm)

    feature D1

    Box terminals (Nm)

    feature D2/D3

    Up to 70 kVA 10 % 3,5

    110 kVA 6 % up to 250 kVA 8 % (NH2)

    35 - 40 32

    250 kVA 10 % up to 630 kVA 10 % (NH3)

    35 - 40 32

    Table 9-7 Torque table connection LVRSys™

    9.4 3-phase systems indoor

    System overview 22 kVA to 70 kVA 9.4.1

    Figure 9-16 System overview LVRSys™ 22 kVA to 70 kVA

    1 LVRSys™ Switch cabinet

    2 Transformer block

    3 Switch cabinet for electronic IP 66

  • Page 43

    4 Circuit breaker for manual BYPASS operation & connection clamps

    5 PEN bus bar with injection nuts M12 und M8

    6 C-profile bus bar for cable interception

    Table 9-8 Explanation of Figure 9-16 listed numbers

    System overview 110 kVA to 400 kVA 9.4.2

    Figure 9-17 System overview LVRSys™ 110kVA to 250 kVA

    1 LVRSys™ switch cabinet

    2 Transformer block

    3 Switch cabinet for electronic IP 66

    4 NH-switch disconnectors for connection to the low voltage grid and BYPASS

    5 PEN bus bar with injection nuts M12 und M8

    6 C-profile bus bar for cable interception

    7 Fuse-switch-disconnectorfor LVRSysIN (intern/transformer block secondary cable input) NH2

    Table 9-9 Explanation of Figure 9-17 listed numbers

  • Installation

    Page 44

    We take care of it.

    Fuse protection 9.4.3

    See Section 9.1.4.

    Closure 9.4.4

    See Section 9.2.6.

    PEN and local grounding point 9.4.5

    See Section 9.3.6.

    Requirement indoor 9.4.6

    Ensure that heat is dissipated through adequate air circulation.

    Observe the following minimum distances:

    – 50 cm to the ceiling.

    – 100 cm to 120 cm in the door area.

    Avoid direct sunshine.

  • Page 45

    9.5 Handling systems with circuit breaker (up to 70 kVA)

    The following must be observed when switching devices:

    Ensure that commissioning, decommissioning and operation are carried out exclusively

    by qualified electricians or by persons with electro technical knowledge, in accordance

    with VDE 0105-100.

    Press the circuit breaker exclusively on the operating handle.

    Press the circuit breaker quickly.

    21 3

    4 5

    Figure 9-18 Connection and BYPASS operation

    1 Circuit breaker for LVRSysIN (intern/transformer block secondary cables input)

    2 BYPASS fuse element

    3 Circuit breaker for LVRSysOUT (intern/transformer block secondary cables out-put)

    4 Connection block for input external cables (grid connection transformer)

    5 Connection block for output external cables (grid connection load)

    Table 9-10 Explanation of Figure 9-18 listed numbers

  • Installation

    Page 46

    We take care of it.

    Figure 9-19 Circuit breaker status OFF

    9.6 Handling systems with NH-switch disconnectors (110 kVA to

    630 kVA)

    DANGER! Danger of electric shock!

    Never open the NH load bar partially.

    Always use the handle to open the load bar.

    NH fuses are intended exclusively for use by skilled electricians or people trained in electrotechnical work, see IEC 60269-2.

    The following must be observed when switching devices:

    Ensure that commissioning, decommissioning and operation are carried out exclusively

    by qualified electricians or by persons with electro technical knowledge, in accordance

    with VDE 0105-100.

    Make sure that only fuse links with silver-plated knives or silver-plated knives are used.

    Press the NH-switch disconnectors exclusively on the operating handle.

    Use NH-switch disconnectors quickly

  • Page 47

    Figure 9-20 NH-switch disconnectors

    1 2 3 4 5

    Figure 9-21: NH-switch disconnectors

  • Installation

    Page 48

    We take care of it.

    CAUTION! Voltage interruption in the low voltage grid!

    (2) Fuse-switch-disconnector LV-grid input. Do not switch at any time!

    (4) Fuse-switch-disconnector LV-grid output. Do not switch at any time!

    1 Fuse-switch-disconnector for LVRSysIN (intern/transformer block secondary

    cable input)

    2 Fuse-switch-disconnector for input external cables (grid connection transform-

    er)

    3 BYPASS load bar

    4 Fuse-switch-disconnector for output external cables (grid connection load)

    5 Fuse-switch-disconnector for LVRSysOUT (intern/transformer block secondary

    cable output)

    Table 9-11 Explanation of listed numbers

  • Page 49

    10. Commissioning and Decommissioning LVRSys™

    10.1 Indicator lamps & system switch

    Error Operation System switch

    Figure 10-1 Indicator lamps and system switch

    State off State on

    Figure 10-2 Switch position

    10.2 Control & first commissioning LVRSys™

    Control 10.2.1

    Ensure the PEN connections are running properly

    Ensure that the primary cables are installed according to the circuit diagram

    Ensure that the secondary cables are installed according to the circuit diagram

    First commissioning 10.2.2

    The initial position is:

    0 Closed BYPASS.

    0 Open input (LVRSys-IN).

    0 Open output (LVRSys-OUT).

    0 The regulator in position Off.

    CAUTION! Destruction of components due to overload!

    Only switch on the LVRSys™ according to the described process.

  • Commissioning and Decommissioning LVRSys™

    Page 50

    We take care of it.

    Close LVRSys-IN.

    Switch regulator to ON position (See Section Fehler! Verweisquelle konnte nicht ge-

    funden werden.).

    Regulator automatically moves up.

    LVRSys™ is active.

    Local network is regulated over LVRSys™.

    Change to manual mode (See Section 11.8).

    Set all levels.

    All stages must be reached. The voltage of the controller must change in the corresponding direction after each step of the step.

    If the voltage does not change as expected, the wiring must be checked again. The system must not be put into operation under any circumstances.

    10.3 Put the LVRSys™ into operation

    The initial position is:

    0 Closed BYPASS.

    0 Open input (LVRSys-IN).

    0 Open output (LVRSys-OUT).

    0 The regulator in position Off.

    CAUTION! Destruction of components due to overload!

    Only switch on the LVRSys™ according to the described process.

    Close LVRSys-IN.

    Close LVRSys-OUT.

    Open LVRSys-BYPASS.

    Switch regulator to ON position (See Section Fehler! Verweisquelle konnte nicht ge-

    funden werden.).

    Regulator automatically moves up.

    LVRSys™ is active.

    Local network is regulated over LVRSys™.

  • Page 51

    10.4 Take LVRSys™ out of operation and BYPASS mode

    The initial position is:

    0 Closed input (LVRSys-IN).

    0 Closed output (LVRSys-OUT).

    0 The regulator in position ON.

    0 Open BYPASS.

    CAUTION! Destruction of components due to overload!

    Isolate the LVRSys™ only according to the described process.

    Switch regulator to OFF position

    Electronics (regulator/actuator/contactors) are de-energized.

    Transformers are short-circuited through opener contactors.

    Close LVRSys-BYPASS.

    Open LVRSys-OUT.

    Open LVRSys-IN.

    LVRSys™ is isolated from the grid.

    BYPASS is active.

    The local grid is supplied through the BYPASS.

  • Operation/Regulator operation

    Page 52

    We take care of it.

    11. Operation/Regulator operation

    11.1 Indicator lamps – control cabinet

    Figure 11-1: Description – lamps control cabninet

    1) Indicator lamp Error

    2) Indicator lamp Operation

    3) System-switch

    11.2 Indicator lamps & switch – CPU-board

    Figure 11-2: Description - lamps & switch CPU-board

    Description:

    1) Service switch

    2) Status lamp

    3) Status contactor lamp (first from left) and status service switch lamp (second from left)

  • Page 53

    11.3 Indicator lamps

    The red and green indicator lamps show that state the system is in:

    0 Red: Error mode

    0 Green: Operating mode; system is operating without failure.

    Follow the instructions when an indicator lamp illuminates red.

    Note the error code (Sec. 11.13.2).

    When the error cannot be corrected, you have to contact the A. Eberle support team.

    11.4 Switches

    The switch settings create the following states:

    0 Switch system on:

    – Switch to the right: System on

    – Switch upward: System off

    0 Slide switch service switch:

    Figure 11-3: Slide switch service switch

    – Switch position on: Switch service active

    – Switch position off: Switch service inactive

    Switch position on sets the red indicator lamp off and the green indicator lamp

    on.

    Status switch lamp and status lamp turn from green to red with switch position

    on. Both lamps are found on the CPU-board (see Cap. 11.2).

    Automatic bypass-function is active, Regulator without any function.

    The use of the service switch is reserved for firmware updates.

  • Operation/Regulator operation

    Page 54

    We take care of it.

    11.5 Boot process

    Activating the System on switch automatically starts the regulator's boot process.

    After 25 seconds, the display shows Boot....

    After completing the boot process (ca. 45 sec), the regulator is in 'Automatic'

    mode.

    The boot process must be completed in order to perform all other activities such as configuration, changing the display pages, etc.

    11.6 Menu navigation

    By default, the regulator is in Automatic mode when operating error free.

    The main display shows the external conductor's three phase voltages and the current tap for each phase.

    Figure 11-4 Regulator display

    1 Mode

    2 Browse up (only in the user menu or active manual mode)

    3 Enter key (confirm)

    4 Browse right

    5 Browse down (only in the user menu or active manual mode)

    6 Browse left

    Table 11-1 Explanation of listed numbers

    1

    2

    3 4

    5

    6

  • Page 55

    11.7 Automatic mode

    The regulator is active in Automatic mode. After the boot process (connecting the supply voltage) has finished, the regulator switches into Automatic mode.

    Figure 11-5 Automatic mode

    The display shows:

    0 three phase voltages

    0 the phases' current tap position

    11.8 Manual mode

    The regulator is not active in Manual mode. A tap change per second is possible.

    Changing taps manually:

    Select Manual mode, press Enter in Automatic mode. (See Section 11.9).

    To switch to a lower tap, press the down key.

    To switch to a high tap, press the up key.

    Figure 11-6 Manual mode display

  • Operation/Regulator operation

    Page 56

    We take care of it.

    11.9 Overview of the displays

    To control Parameter

    ...

    To Auto / Manual

    Figure 11-7 Navigation menu overview

  • Page 57

    11.10 Parameters

    Each parameter is described below:

    Figure 11-8 Configuring the regulator

    Select the Parameter menu (See Section 11.9 Overview of the displays).

    To select the items submenu, press the up or down key.

    Press the Enter key.

    Configuration:

    PIN input by pressing the up/down and left/right keys.

    Press Enter to confirm the PIN.

    The parameters are set by pressing the up/down and left/right keys.

    Press Enter to confirm the selection.

    Delivery state of the PIN is 0000 (four times zero)

    The PIN can be changed in accordance with Sec. 12 Safety.

  • Operation/Regulator operation

    Page 58

    We take care of it.

    Set point 11.10.1

    The default is 230 V.

    Set the set point.

    Tolerance band + and tolerance band - 11.10.2

    The defaults are:

    0 98% for tolerance band – (Tolerance -)

    0 102% for tolerance band + (Tolerance +)

    Set the tolerance bands.

    Figure 11-9 Tolerance band zone

    1 Regulator active

    2 Phasing process

    3 Regulator inactive

    4 Set point

    5 Tolerance band +

    6 Tolerance band -

    Tabelle 11-2 Explanation of listed numbers

    The regulator is inactive if the voltage lies within the area between the tolerance bands. When the tolerance bands are exceeded, the regulator is activated and as such it will switch the phases according to the parameter settings.

  • Page 59

    Reaction time 11.10.3

    The default is 1 VS.

    Reaction time from 1 Vs to 100 Vs adjustable in 0.1 steps

    The control speed of the system can be parameterized on the basis of the reaction time.

    Example: Injury of the tolerance band by reaction time 1 Vs.

    (see Figure 11-10 Toleran)

    Exceed tolerance band + by 1 V -> Step down after 1 s (2.1).

    Drop below tolerance band + by 0.5 -> Step up after 2 s (2.2).

    The reaction time is the time delay between the measurement value of the exceeding tol-

    erance band and the step (see Section. Fehler! Verweisquelle konnte nicht gefunden

    werden.).

    Figure 11-10 Tolerance band zone reaction time

    1 Regulator active

    2.1 Phasing process exceed tolerance band + by 1 V

    2.2 Phasing process drop below tolerance band - by 0.5 V

    3 Regulator inactive

    4 Set point

    5 Tolerance band +

    6 Tolerance band -

    Table 11-3 Explanation of figure

  • Operation/Regulator operation

    Page 60

    We take care of it.

    Grid impedance 11.10.4

    The Grid impedance function can only be used if the Current measurement option is integrated (Sec. 2.16 Current/power measurement incl. converter terminals 4- fold).

    The default is grid impedance is 0 Ω:

    Grid impedance is deactivated.

    Grid impedance from 0 Ω to 0.5 Ω adjustable in 0.01 steps.

    Max. Influence on local voltage measurement 5 V.

    When the impedance is deactivated:

    Current-dependent regulation is deactivated.

    When the impedance is activated:

    Current values are included in regulation.

    Resistance symbol displays in the status window.

    Figure 11-11 Active Impedance display

    The configuration of the grid impedance takes into account the load current in the regulator algorithm.

    Example:

    0.4kV

    PV Feeder

    KV

    LVRSys™ DT

    Figure 11-12 Example network branch with a 500 m cable section

    Cable data Values

    Cable NA2X2Y 4 x 150 mm²

    Cable length 500 m

    Cable resistance 0.5 km x 0.206 Ω/km = 0.05 Ω

    Table 11-4 Cable data

    500 m

  • Page 61

    In the example, the voltage value at the end of the cable would deviate from the regulator's voltage value by 100 A x 0.05 Ω = 5 V, at a current flow of 100 A.

    When configuring the grid impedance, the regulator constantly calculates the voltage from the voltage value in the regulator + grid impedance x grid current.

    𝑈𝐼𝑚𝑝 = 𝑈𝑅𝑒𝑔𝑢𝑙𝑎𝑡𝑜𝑟 + 𝑍𝐺𝑟𝑖𝑑 ∗ 𝐼𝐺𝑟𝑖𝑑

    Type of wire spec. cable resistance Ω/km

    NAYY-J 4 x 70 mm² 0.453

    NAYY-J 4 x 95 mm² 0.321

    NAYY-J 4 x 120 mm² 0.255

    NAYY-J 4 x 150 mm² 0.208

    NAYY-J 4 x 185 mm² 0.167

    NAYY-J 4 x 240 mm² 0.131

    Overhead line AL 4 x 50 mm² 0.662

    Overhead line AL 4 x 70 mm² 0.519

    Overhead line AL 4 x 95 mm² 0.432

    Table 11-5: Specification of cable resistance

    11.11 Setup

    Figure 11-13 Setup

  • Operation/Regulator operation

    Page 62

    We take care of it.

    Select the Setup menu (See Section 11.9).

    To select the item submenu, press the up or down key.

    Press the Enter key.

    Configuration:

    PIN input by pressing the up/down and left/right keys.

    Press Enter to confirm the PIN.

    The parameters are set by pressing the up/down and left/right keys.

    Press Enter to confirm the selection.

    Phase spacing 11.11.1

    Phase spacing is set at the factory.

    Do not change the phase spacing.

    Net frequency 11.11.2

    Net frequency is set at the factory

    Do not change the net frequency.

    CT ratio (current transformer ratio) 11.11.3

    For A. Eberle GmbH & Co. KG. current transformers, the transfer ratio is set at the factory.

    When external current transformers are used:

    Enter the conversion ratio.

    Communication 11.11.4

    See Cap. Fehler! Verweisquelle konnte nicht gefunden werden.Fehler! Verweisquelle konnte nicht gefunden werden..

    NTP Time Synchronization 11.11.5

    See Cap. Fehler! Verweisquelle konnte nicht gefunden werden. Fehler! Verweisquelle konnte nicht gefunden werden..

    Safety 11.11.6

    See Cap. 12

    Language 11.11.7

    Possible languages:

    0 German

    0 English

  • Page 63

    Delete statistics 11.11.8

    Delete individual statistics:

    Select.

    PIN input by pressing the up/down and left/right keys.

    Press Enter to confirm the PIN.

    Confirm selection.

    Selected statistic is deleted.

    11.12 Drag indicator

    Drag indicator contains 15 min average values for the:

    0 maximum voltages (Ph 1-3)

    0 maximum currents (Ph 1-3)

    0 maximum output values

    0 maximum and minimum temperature in switch cabinet in °C (T).

    Values can be reset individually.

    Resetting the current values also resets the output values.

    11.13 Info/Update

    The menu item Info/Update contains:

    0 Time

    0 Date

    0 Firmware version

    0 Logbook error entries

    0 Run Firmware update

    0 Store logbook event.

    Firmware update 11.13.1

    CAUTION! Destruction of components due to overload!

    Make sure the service switch is active before starting the update process.

    Activating the service switch isolates the thyristors from the mains voltage and short-circuits the transformers. The control function is out of order. A secure update process can be started.

    Copy Update file to USB stick

    Unzip the zip file (from email of download).

  • Operation/Regulator operation

    Page 64

    We take care of it.

    Save the files on a FAT32 formatted USB stick

    The folder structure below is mandatory, no superordinate folder on the USB stick

    (USB-stick:\unzipped files; e.g. E:\...).

    Figure 11-14 Folder structure for the update via the USB stick

    Full update procedure:

    Activate the service switch. (See Section Fehler! Verweisquelle konnte nicht gefunden

    werden.)

    Regulator goes into error mode.

    Insert USB stick.

    Select menu item Firmware update.

    PIN input by pressing the up/down and left/right keys.

    Press Enter to confirm the PIN.

    Press Yes to confirm the selection.

    Please wait displays.

    Do not press any buttons or activate the service switch during the update process.

    Regulator needs about 5 minutes for the update process to complete.

    The regulator reinitializes.

    The regulator stays in error mode while the update is completed.

    Deactivate the service switch.

    Remove the USB stick.

    Regulator goes into automatic mode.

    The update procedure is finished.

  • Page 65

    LOG ERR 11.13.2

    The last error is displayed.

    Note the error if the installation/update is malfunctioning or is not complete.

    Contact the A. Eberle GmbH & Co. KG. Support team.

    Error Error code

    Contactor 0x001

    Overvoltage 0x002

    Under voltage 0x004

    Internal control error 0x008, 0x010, 0x040, 0x080, 0x100, 0x400, 0x1000

    EEPROM 0x020

    Service switch 0x200

    Invalid serial number 0x800

    Table 11-6 The error code table

    Firmware-Version 11.13.3

    Menu item FW-Version contains information about:

    0 Firmware - version

    0 Cortex-firmware - version

    0 Kernel - version

    0 Filesystem – version

    The version number is determined automatically.

    No change possible.

    Type number 11.13.4

    Menu item Type number contains information about:

    0 Device number

    0 Type number CPU board

    0 Type number Thyristor board

    Device number is set at the factory.

    Do not change the device number.

    The type number of CPU board and thyristor board is determined automatically.

    No change possible.

  • Operation/Regulator operation

    Page 66

    We take care of it.

    Archive log book 11.13.5

    Insert USB stick.

    Select menu item Logbook.

    Select submenu item Start time.

    Data are archived from the start time.

    The data Event data, measurement data, service data must be activated to archive them.

    0 ( ) Selection inactive

    0 (x) Selection active

    Select the submenu item Event data, measurement data and service data.

    Select with the up or down key.

    PIN input by pressing the up/down and left/right keys.

    Press Enter to confirm the PIN.

    Press Yes to confirm the selection.

    Select the submenu item Archive data.

    Press Yes to confirm the selection.

    Please wait displays.

    Regulator writes data to the USB stick.

    Event data

    Event data list contains:

    0 Parameters

    0 Reparameterization

    0 State (Automatic/Manual/Blocked)

    0 State changes (Automatic-Manual)

    0 Error

    Measurement data

    Measurement data list contains:

    0 U1 to U3 (10 minutes average values in V)

    0 U1Z to U3Z (10 minutes average values in V, only with option current transformer and

    0 I1 to I3 (10 minutes average values in A; only for option Current transformer)

    0 P1 to P3 (10 minutes average values in kW; only for option Current transformer)

    0 Q1 to Q3 (10 minutes average values in kvar; only for option Current transformer)

    0 S1 to S3 (10 minutes average values in kVA; only for option Current transformer)

    0 T1 to T3 (10 minutes average values in °C)

    0 Tap 1 to Tap 3 (current tap position Ph1-Ph3 at the time)

  • Page 67

    0 Taps/Period 1-3 (10 minutes average values of tap position Ph1-Ph3).

    Service data

    Service data are intended only for the A. Eberle GmbH & Co. KG. support team to perform evaluations.

    Evaluate logbook (Measurement data) with Microsoft Excel 11.13.6

    (other spreadsheet software can also be used).

    Open the Measurement data in Excel.

    Select the first column (A).

    Figure 11-15 Selecting the first column

    Under Data, press Text to Columns.

  • Operation/Regulator operation

    Page 68

    We take care of it.

    Figure 11-16 Selecting data and text in columns

    Convert Text to Columns Wizard - Step 1 of 3 select Delimited.

    Press Next to confirm

    Figure 11-17 Text conversion wizard - Step 1 of 3

    Convert Text to Columns Wizard - Step 2 of 3 select Space.

    Press Next to confirm

  • Page 69

    Figure 11-18 Text conversion wizard - Step 2 of 3

    Convert Text to Columns Wizard - Step 3 of 3 presses on Advanced...

    Figure 11-19 Text conversion wizard - Step 3 of 3

    Decimal separator: Select Point.

    Press OK to confirm

  • Operation/Regulator operation

    Page 70

    We take care of it.

    Press Finish in the Convert Text to Columns Wizard to confirm.

    Figure 11-20 Other text import settings

    Splitting measurement data across columns.

    Evaluate logbook (Event data) in Notepad++ 11.13.7

    (other text processing software can also be used).

    Figure 11-21 Event data opened in Notepad++

  • Page 71

    11.14 Communication

    Overview of the communication settings 11.14.1

    Figure 11-22 Overview of the communication settings

  • Operation/Regulator operation

    Page 72

    We take care of it.

    Modbus 11.14.2

    11.14.2.1 Modbus Setup

    Select the submenu Communication to configure the parameters for the communica-

    tion interfaces.

    Available communication interfaces:

    0 Ethernet TCP/IP

    Select menu communication (See Section. Fehler! Verweisquelle konnte nicht gefun-

    den werden.)

    To select submenu items, press the up or down key

    Press the Enter key.

    Configuration:

    The parameters are set by pressing the up/down and left/right keys.

    PIN input by pressing the up/down and left/right keys.

    Press Enter to confirm the PIN.

    Press Enter to confirm the selection.

    Standard parameters for the Modbus Communication are:

    0 TCP-Port 502

    11.14.2.2 Modbus Register mapping

    Input register (16-Bit data, read only)

    Name permitted values Standard Addressing

    Status 2 - Operation, 1 - Error 2 101

    Table 11-7 Status

    Input register (16-Bit data, read only)

    Name permitted values Standard Addressing

    LOG-ERR 0 - 65000 0 (Hex) 102

    Table 11-8 Log error

    Input register (16-Bit data, read only)

    Name permitted values Standard Addressing

    Firmware 0 - 999999 1 (float) 103

    Table 11-9 Firmware version

    Holding registers (16-Bit data, read and write)

    Name permitted values Standard Addressing

    Operating status 0 - Auto, 1 - Manual, 2 - Blocked 0 201

  • Page 73

    Holding registers (16-Bit data, read and write)

    Name permitted values Standard Addressing

    Ph1 Step up 0/1 1 - Command Step up 0 202

    Ph2 Step up 0/1 1 - Command Step up 0 203

    Ph3 Step up 0/1 1 - Command Step up 0 204

    Ph1 Step up 0/1 1 - Command Step down 0 205

    Ph2 Step down 0/1 1 - Command Step down 0 206

    Ph3 Step down 0/1 1 - Command Step down 0 207

    Reset Drag indicator 0/1 1 - Command Reset Drag indicator

    0 208

    Table 11-10 Operating status and regulator commands

    Input register (16-Bit data, read only)

    Name permitted values Unit Addressing

    Phase spacing 0 - 1000 0.01 301

    Step phase 1 0 - 8 1 302

    Step phase 2 0 - 8 1 303

    Step phase 3 0 - 8 1 304

    Voltage phase 1 0 - 65000 0.1 V 305

    Voltage phase 2 0 - 65000 0.1 V 306

    Voltage phase 3 0 - 65000 0.1 V 307

    Current phase 1 0 - 65000 0.1 A 308

    Current phase 2 0 - 65000 0.1 A 309

    Current phase 3 0 - 65000 0.1 A 310

    Active power phase 1 -32500 - 0 - 32500 0.1 kW 311

    Active power phase 2 -32500 - 0 - 32500 0.1 kW 312

    Active power phase 3 -32500 - 0 - 32500 0.1 kW 313

    Apparent power phase 1 0 - 65000 0.1 kVA 314

    Apparent power phase 2 0 - 65000 0.1 kVA 315

    Apparent power phase 3 0 - 65000 0.1 kVA 316

    Reactive power phase 1 -32500 - 0 - 32500 0.1 kVar 317

    Reactive power phase 2 -32500 - 0 - 32500 0.1 kVar 318

    Reactive power phase 3 -32500 - 0 - 32500 0.1 kVar 319

    Step number Day Ph1 0 - 99999999 1 320

    Step number Day Ph2 0 - 99999999 1 321

    Step number Day Ph3 0 - 99999999 1 322

    Step number Week Ph1 0 - 99999999 1 323

    Step number Week Ph2 0 - 99999999 1 324

    Step number Week Ph3 0 - 99999999 1 325

    Step number Month Ph1 0 - 99999999 1 326

    Step number Month Ph2 0 - 99999999 1 327

    Step number Month Ph3 0 - 99999999 1 328

  • Operation/Regulator operation

    Page 74

    We take care of it.

    Input register (16-Bit data, read only)

    Name permitted values Unit Addressing

    Step number Year Ph1 0 - 99999999 1 329

    Step number Year Ph2 0 - 99999999 1 330

    Step number Year Ph3 0 - 99999999 1 331

    Temperature cabinet 0 - 65000 0.1°C 332

    Drag indicator U1 max. 0 - 65000 0.1 V 333

    Drag indicator U2 max. 0 - 65000 0.1 V 334

    Drag indicator U3 max. 0 - 65000 0.1 V 335

    Drag indicator I1 max. 0 - 65000 0.1 A 336

    Drag indicator I2 max. 0 - 65000 0.1 A 337

    Drag indicator I3 max. 0 - 65000 0.1 A 338

    Drag indicator P1 max. 0 - 65000 0.1 kW 339

    Drag indicator P2 max. 0 - 65000 0.1 kW 340

    Drag indicator P3 max. 0 - 65000 0.1 kW 341

    Drag indicator T max. 0 - 65000 0.1°C 342

    Drag indicator T min. 0 - 65000 0.1°C 343

    Table 11-11 Measurement and informational value registers

    Holding registers (16-Bit data, read and write)

    Name permitted values Standard Unit Addressing

    Set point 18000 - 30000 23000 0,01 V 401

    Tolerance band + 10000 - 13000 10200 0,01 % 402

    Tolerance band - 7000 – 10000 9800 0,01 % 403

    Grid impedance 0 - 500 0 0,001 Ω 404

    Reaction Time 10 - 1000 10 0,1 Vs 405

    Table 11-12 Parameter registers

    IEC 60870-5-104 11.14.3

    The IEC 60870-5-104 is a communication protocol that communicates over the TCP/IP interface. The IEC Protocol has to be unlocked via a license. If this communication is required, contact the A. Eberle suppport team.

    11.14.3.1 License IEC 60870-5-104 unlock

    The licensce file will be transmitted by the A. Eberle Support Team and is linked to the serial number of the system.

    Save License file on FAT32 formatted USB stick.

    Connect USB stick to LVRSys™.

    Select menu item License File.

    Confirm with Yes.

  • Page 75

    IEC 60870-5-104 is unlocked.

    11.14.3.2 CSV configuration of the IEC 60870-5-104 Slave

    The LVRSys™ IEC 60870-5-104 Slave can be configurd by using a CSV file. When starting the system, the CSV file will be loaded and the IEC 60870-5-104 slave is then ready for use.

    In the standard lvrsys_t104_target.csv all possible configurations are described. The desirec changes must be made directly in the file, using the following steps:

    Get CSV-File lvrsys_t104_target.csv from A. Eberle Support-Team.

    Adjust CSV-File as desired with Notepad or MS Excel.

    Save CSV-File as lvrsys_t104_target.csv (MS-DOS File if MS Excel is used) on a FAT32

    formatted USB stick.

    Connect USB stick to LVRSys™.

    Select menu item Communication->IEC60870-5-104->T104 CSV load.

    IEC 60870-5-104 configuration adapted.

    11.14.3.3 IEC 60870-5-104 Parameter

    0 T104 active (disabled – all configurations 0 / activated – configurations are loaded)

    The new configurations of IEC 60870-5-104 Slave will be changed from disabled -

    > activated.

    0 T104 Station CA is the IP address of the allowed station (ASDU)

    0 Default is 1 (Each station allowed).

    0 T104 TCP/IP Port Address of the 1st. instance of the T104

    0 Default is 2404.

    0 Timeout (T104 Timeout. Param.)

    0

    Parameter Default Notice

    t0 30 s Timeout of the connection establishment

    t1 15 s Timeout of transmission or testing-ASDUs

    t2 10 s Timeout for acknowledgments without data telegrams

    t2 < t1

    t3 20 s Timeout for sending test frames with long time delays

    Table 11-13 Timeout parameter

    0 T104 IP Bind (enabled only in redundant systems)

    0 LVRSys™ IEC 60870-5-104 slave can be linked in the first instance to a system IP. This is useful if redundancy systems are used to communicate or there is an additional connection via other networks such as WLAN or UMTS. LVRSys™ IEC 60870-5-104 slave reads only the first instance.

    In redundant systems with different IP addresses and the same port address

    T104 IP Bind must be activated.

  • Operation/Regulator operation

    Page 76

    We take care of it.

    0 T104 redundancy

    Figure 11-23 Parameter overview IEC 60