US 26–BORING ROAD BRIDGE RAISING PROJECT 26 212 212 26 Stone Rd. Closure area: SE 282nd Avenue/ Boring Road overpass Compton Rd. Orient Dr. Orient Dr. NORTHBOUND DETOUR SOUTHBOUND DETOUR Gresham Boring NEWSLETTER #1 SUMMER 2016 The SE 282nd Avenue/Boring Road overpass will be raised, repaired, and resurfaced in 2018 ODOT is working to improve the Boring Road overpass at US 26 by raising it to accommodate over-height vehicles. Additional clearance will allow large vehicles to stay on US 26 instead of being detoured onto Orient Drive and Kelso Road. Project details The project includes these key elements: • Raise SE 282nd Avenue/Boring Road overpass at US 26 by more than two feet • Repair and resurface the roadway on the overpass • Build new storm water ponds Construction impacts and detours The project will require an extended full closure of SE 282nd Avenue/Boring Road where it crosses US 26. Detours will be in place while the overpass is closed (see detour map). US 26 will remain open during construction. ODOT is talking to area stakeholders to determine when the closure will be least impactful. We want to hear from you. We are hosting an online open house where you can get more information on the timing of the closure and provide your feedback. Detours during overpass closure We want to hear from you! Visit the online open house at www.BoringRdBridge.org through September 15, 2016 to learn more and provide feedback. Anticipated project schedule Design Now – December 2017 Construction Spring/Summer 2018 – Fall 2018 While the SE 282nd Avenue/Boring Road overpass is closed, northbound travelers will take OR 212/Compton Road to US 26 westbound to Stone Road. Southbound travelers will take Orient Drive to Compton Road and back to SE 282nd Avenue/Boring Road.

US 26–BORING ROAD BRIDGE RAISING PROJECTopenhouse.jla.us.com/files/odot/us26boringroad/us26-boringrd... · The SE 282nd Avenue/Boring Road project will raise and repair the overpass

  • Upload
    others

  • View
    3

  • Download
    0

Embed Size (px)

Citation preview

Page 1: US 26–BORING ROAD BRIDGE RAISING PROJECTopenhouse.jla.us.com/files/odot/us26boringroad/us26-boringrd... · The SE 282nd Avenue/Boring Road project will raise and repair the overpass

US 26–BORING ROAD BRIDGE RAISING PROJECT

26

212

212

26Stone Rd.

Closure area:SE 282nd Avenue/Boring Road overpass

Compton Rd.

Orient Dr.

Orient Dr.

NORTHBOUNDDETOUR

SOUTHBOUND

DETOUR

Gresham

Boring

NEWSLETTER #1SUMMER 2016

The SE 282nd Avenue/Boring Road overpass will be raised, repaired, and resurfaced in 2018ODOT is working to improve the Boring Road overpass at US 26 by raising it to accommodate over-height vehicles. Additional clearance will allow large vehicles to stay on US 26 instead of being detoured onto Orient Drive and Kelso Road.

Project detailsThe project includes these key elements:

• Raise SE 282nd Avenue/Boring Road overpass at US 26 by more than two feet

• Repair and resurface the roadway on the overpass • Build new storm water ponds

Construction impacts and detours The project will require an extended full closure of SE 282nd Avenue/Boring Road where it crosses US 26. Detours will be in place while the overpass is closed (see detour map). US 26 will remain open during construction.

ODOT is talking to area stakeholders to determine when the closure will be least impactful. We want to hear from you. We are hosting an online open house where you can get more information on the timing of the closure and provide your feedback.

Detours during overpass closure

We want to hear from you!Visit the online open house at

www.BoringRdBridge.org through September 15, 2016

to learn more and provide feedback.

Anticipated project schedule Design Now – December 2017Construction Spring/Summer 2018 – Fall 2018

While the SE 282nd Avenue/Boring Road overpass is closed, northbound travelers will take OR 212/Compton Road to US 26 westbound to Stone Road. Southbound travelers will take Orient Drive to Compton Road and back to SE 282nd Avenue/Boring Road.

Page 2: US 26–BORING ROAD BRIDGE RAISING PROJECTopenhouse.jla.us.com/files/odot/us26boringroad/us26-boringrd... · The SE 282nd Avenue/Boring Road project will raise and repair the overpass

Oregon Department of Transportation Region 1 Headquarters 123 NW Flanders St.Portland, OR 97209

For ADA Title II or Civil Rights Title VI accommodations, translation/interpretation services or for additional information call (503) 731-4128, TTY (800) 735-2900 or use the statewide Oregon Relay Service: 7-1-1.¿Habla usted español? Podemos proporcionar la información en esta publicación en español. Para recibir la información en español, por favor llame al (503) 731-4128.Вы говорите по-русски? Мы можем предоставить информацию в этой публикации на русском языке. Для получения информации звоните по тел (503) 731-4128 или посетите веб-сайт.

Online open house is now live!

US 26–BORING RD.BRIDGE RAISING

PROJECT

www.BoringRdBridge.org

Visit our online open house!www.BoringRdBridge.org

Contact Kimberly Dinwiddie(503)731-8281 [email protected]

The SE 282nd Avenue/Boring Road project will raise and repair the overpass at US 26. This work will require an extended closure of SE 282nd Avenue/Boring Road in 2018. The closure is necessary to raise the overpass more than two feet to allow for over-height vehicles to stay on US 26. Learn more about the project and provide your feedback on the closure. Visit the online open house at www.BoringRdBridge.org between now and September 15, 2016.

Overpass improvements• Raise deck

height 2+ feet• Repair and

resurface

New stormwater ponds

New stormwater ponds

Gresham

Boring

SE 2

82nd

Ave

./Bor

ing

Rd.

US 26

US 26

Kelly Hawley(503)[email protected]