OR212: UPRR - US26 PRESERVATION PROJECT
Project updates coming soon at:
WWW.OR212IMPROVEMENTS.ORGODOT Project Manager – Tom Hamstra
K18772OR212: UPRR - US26
K18772OR212: UPRR - US26
Project SnapshotKey project improvements
• Rehabilitation and repaving of OR212.
• ADA-compliant sidewalk curb ramps and signal modifications to update pedestrian push buttons.
• A new environmentally-friendly bridge will accommodate North Fork Deep Creek, currently carried under OR212 via three corrugated pipe.
Anticipated schedule
• Design: now through December 2018
• Right-of-way acquisition: now – May 2019
• Construction: Aug 2019 to Nov 2020
• Bridge construction will require a multiday closure with a detour between July 15th and August 31st 2020.
• Contractor will be restricted from impacting Hood-to-Coast Relay Race August 28-29, 2020
K18772OR212: UPRR - US26
Replacement Structure – 42ft Bridge
Plan view
K18772OR212: UPRR - US26
Proposed Detour during OR212 Closure Detour to utilize 282nd and Orient Drive
K18772OR212: UPRR - US26
Replacement Structure – Using Accelerated Bridge Construction (ABC)
Single 7 day roadway closure and detour (as proposed at 3/20/18 MAC meeting)
Excavate, drive piles, install pile caps, install wingwalls, place precast deck panels, back fill structure, install bridge rail, place aggregate base, pave ACP and stripe
K18772OR212: UPRR - US26
Replacement Structure – Cost Savings Proposal
Cast in place deck design could save the project $190k but requires
a 12 day closure of OR212
K18772OR212: UPRR - US26
Replacement Structure – Cost Savings Proposal
Single 12 day roadway closure and detour
Excavate, drive piles, install pile caps, install wingwalls, back fill structure, install bridge rail, cure cast-in-place deck with water, place aggregate base, paving and striping
K18772OR212: UPRR - US26
ODOT Project Manager – Tom HamstraProject updates coming soon at:
WWW.OR212IMPROVEMENTS.ORG
Questions?