Upload 1Desig n an d operatio n perspectiv e o f a Britis h UH V laborator

Embed Size (px)

Citation preview

  • 8/10/2019 Upload 1Desig n an d operatio n perspectiv e o f a Britis h UH V laborator

    1/21

    Design and operation perspective o f a

    British UHV laboratory

    Prof. H.M. Ryan. B.Sc, Ph.D., C.Eng., F.I.E.E., F.lnst.P.,

    and J. Wh iskard, B.Sc. Eng .), C.Eng., M.I.E.E.

    Indexing terms: Design, Instrumentation and measuring science, Reviews of progress

    Abstract: The authors have, in the past, been directly involved in the design, planning and supervision of the

    construction, of a new ultra-high-voltage laboratory. The main purpose of the laboratory was to provide a

    major facility in the UK for the development of switchgear rated up to 765 kV and in the dielectric research

    required for such an undertaking. Following the opening of the laboratory in 1970, the authors have in recent

    years been closely connected in the development of new ranges of open terminal and metalclad SF

    6

    switchgear

    rated up to 525 kV and for fault currents up to 63 kA. These activities have been supported by extensive

    dielectric research studies, which have enabled the major factors influencing the insulation integrity of practical

    equipment to be determined. First, this paper outlines the criteria used in designing the laboratory and presents

    a critical appraisal of the facilities during the first 15 years of operation. Secondly, consideration is given to

    illustrating some significant laboratory activities. Examples are given of various switchgear and nonswitchgear

    components for systems =765 kV, which have been subjected to rigorous dielectric proving tests in the main

    test hall. The use of specific high-voltage test procedures (e.g. climatic, artificial rainfall, mixed voltage testing)

    are described, and important technical factors which have influenced the dielectric design of apparatus are

    considered.

    1 Introduction

    In the 1920s, switchgear manufacturers were mainly

    engaged in exploring the problem of protecting oil-

    immersed switchgear by means of surge arresters, for

    which the impulse generators and the test cages then avail-

    able were adequate for the purpo se.

    The problem of damage to station equipment due to

    lightning strokes was, however, becoming an important

    issue during the 1930s, and the necessity to learn more

    about the behaviour of dielectric materials and electrical

    equipment when subjected to lightning voltages, was

    becoming urgent. The outcome of these requirements was

    the establishment of a whole generation of high-voltage

    laboratories in this country and abroad. These labor-

    atories provided a major factor in the development of

    switchgear rated up to 400 kV, and the accumulation of

    knowledge in the related problems of high-voltage impulse

    wave behaviour.

    The laboratories established in the late 1930s continued

    to prove their usefulness even though additions in testing

    equipment, increases in test area and even in the height of

    the laboratories, were required from time to time. This

    state of affairs continued until the early 1960s, during

    which time the establishment of the British National Super

    Grid, and the use of air-blast circuit breakers were taking

    place.

    It was becoming evident by this time (early 1960s) that

    with the foreseeable development of transmission voltages

    in excess of 400 kV, much more knowledge in the behav-

    iour of impulse and switching voltage waves was required

    for the development of higher voltage rated air-blast gear

    and the rapidly developing technology of pressurised gases

    (SF

    6

    ).

    A new generation of ultra-high-voltage laboratories was

    initiated in the UK and abroad, particularly in Italy,

    France, Germany, USA, Canada and Ja pan.

    Paper 4889A

    (S3),first

    eceived 19th July

    1985

    and in revised form 7th April 1986

    The authors were formerly with NEI Reyrolle Ltd. Professor Ryan is now at the

    Department of Electrical, Electronic and Control Engineering, Sunderland Poly-

    technic, Edinburgh Building, Chester Road, Sunderland SRI 3SD, United

    Kingdom. Mr. Whiskard is now retired and can be contacted at 28 Briardene Drive,

    Gateshead, Tyne and Wear NE10 8AN, United Kingdom

    As a major switchgear manufacturer in this country, it

    was imperative to develop our own ultra-high-voltage

    facilities. The possibility however, had not been ignored of

    sending equipment for tests to already existing laboratories

    abroad, but the cost of testing and of transportation of

    large and heavy equipment, the lengthy processing of test

    results and data at considerable distance from the parent

    company, all proved a major drawback to this course of

    action. The decision was taken towards the end of the

    1960s period to go ahead in the design and construction of

    the laboratory which is the subject of the present paper.

    This paper describes the criteria used in designing the

    new UHV laboratory, outlines the finalised design and

    provides an app raisal of

    i)

    the effectiveness of major labor-

    atory test equipment and (ii) the salient work carried out

    in the laboratory during the past 15 years. In this

    appraisal, particular attention is given to problems

    encountered with the test equipment and ways in which

    some of them were overcome are considered. Difficulties in

    the test work are also described and some of the many

    successes achieved are highlighted. Where appropriate, the

    paper will 'position' the UK state of the art, by describing

    laboratory achievements and activities of this industrial

    laboratory complex and comparing with related work

    carried out elsewhere particularly at three other UHV

    test laboratories in the UK, France and Canada operated

    by national supply utilities.

    2 Criteria used in designing the labora tory

    As usual in engineering design, the criteria used are a

    mixture of technical reasoning, economic considerations

    and time scales. Preliminary considerations started about

    the middle of 1963 regarding the feasibility of such a

    project an d b roadly covered the following g rou nds :

    (a) Enlarging existing high-voltage laboratory building

    and uprating existing test equipment such as AC trans-

    former, impulse generator, high-voltage measuring devices

    etc.

    b) Survey of available land with the possible purpose of

    creating a new high-voltage test site.

    (c) Determination of maximum rating of switchgear to

    IEE PROCEEDINGS, Vol. 133, Pt. A, No. 8, NOVEMBER 1986

    501

  • 8/10/2019 Upload 1Desig n an d operatio n perspectiv e o f a Britis h UH V laborator

    2/21

    be developed and therefore tested in the foreseeable future

    with a test voltage margin above this for future develop-

    ment and research. Evaluation of the probable physical

    size of future switchgear at the maximum rating con-

    sidered.

    d) Evaluation of the size of the test hall based on the

    maximum foreseeable size of test piece and on clearances

    derived from switching impulse data associated with point-

    to-plane airgaps.

    e) Con sidera tion was given to the following alterna-

    tives

    :

    (i) test area completely outdoors, with or without

    some protection for main test equipment

    (ii) test area indoors, to maximum ideal dimensions,

    with all major test equipment in fixed positions

    (iii) test area indoors, but with additional facility for

    outdoor testing

    (iv) test hall of reduced dimensions (economical size),

    but with major test equipment mobile.

    3 Finalised labo rator y design

    In 1963, when the projected design of the laboratory was

    first under review and its potential role was being con-

    sidered the natural steps of circuit-breaker ratings

    beyon d the 420 kV level already o perating in the UK , were

    750-765 kV and 1100-1200 kV. Although serious doubts

    remained that any progress upwards towards transmis-

    sion systems >420 kV would be made in the home

    market within the next twenty to thirty years, there were

    definite indications that overseas the rating in certain pro-

    jects e.g. Ontario/Quebec Hydro (Canada), El-Chocon

    (Argentina) etc., would reach 765 kV and, in the foresee-

    able future, 1200 kV was likely. This prediction would

    obviously identify and quantify the laboratory test volt-

    ages and air clearances which would be necessary to

    undertake dielectric research, development and ultimately

    type tests associated with any new switchgear.

    The other prediction was to evaluate what form future

    switchgear designs would take. On the one hand, it was

    logical to think that the principle of air-blast interruption

    (see Fig. 1) and comp ressed-air insulation would prevail

    and all that would be required was to scale up the known

    parameters, at the existing statutory ratings, while at the

    same time anticipating future EHV dielectric test specifi-

    cations, customer requirements etc. On the other hand,

    there was a general realisation that circuit breakers using

    sulphurhexafluoride gas (SF

    6

    ) for interruption and dielec-

    tric duties represented an alternative possibility at

    EHV/UHV levels in which case, fewer series interrupter

    breaks per phase might be possible and any future trend

    towards 'compact' SF

    6

    metalclad switchgear installations

    would obviously result in a significantly reduced labor-

    atory test hall dimensional requirement. In general terms,

    if a 275 kV air-blast circuit breaker was associated with a

    test object of length 5.2 m in the test hall, 420 kV with

    about 11.3 m, for 1.1-1.2 MV rated gear, a length of about

    18.3 m would be a reasonable assumption.

    Since the most onerous test condition is imposed by the

    application of the positive-polarity switching impulse

    F i g . 1

    Earlier designs of 420 kV air-blast circuit breakers

    c

    Recent labo ratory tests have involved UHV system co-ordination studies

    a

    Single phase of

    afirst-generation

    breaker (12 breaks/phase)

    b

    Single phase of

    a

    second-generation breaker

    6

    breaks/phase)

    502

    Part schematic diagram of

    b

    IE E

    PROCEEDINGS,

    Vol.

    133,

    Pt. A,

    No.

    8,NOVEMBER

    1986

  • 8/10/2019 Upload 1Desig n an d operatio n perspectiv e o f a Britis h UH V laborator

    3/21

    15.2 m

    door height

    18 9

    m

    width 5.7m

    Mr

    heig ht 18.9m

    w id th 11.7m

    48.8 m

    B C

    c

    IEE

    PROCEEDINGS,

    Vol.

    133,

    Pt.A ,

    No.

    8,NOVEMBER

    1986

    D A

    Fig.

    2 UHVlaboratory layout

    a Plan

    bElevation

    c

    External view looking north

    d

    View of test hall and equipment

    A

    2 MV

    AC

    transformer, overall height 18.3 m

    B

    4 MV impulse generator, overall height 13.2

    m

    C 4 MV capacitor divider, overall height 14.7 m

    D Test specimens

    E Mobile oil-filled test tank

    Internal diameter 5.5 m

    Depth 5.5 m

    Additional supplementary facilities were located

    within the original laboratory building following

    reorganisation in 1980. They are illustrated in

    Figs. 25-31 and their locations identified by

    letters F-L

    503

  • 8/10/2019 Upload 1Desig n an d operatio n perspectiv e o f a Britis h UH V laborator

    4/21

    waves, it was necessary to establish the minimum air clear-

    ance for this test plus a comfortable margin above this

    level for research and to take into account the unpredict-

    ability of switching impulses and proximity effects with

    large practical air gaps, when values of 1.8 MV peak are

    reached and exceeded.

    Studies at the time in other laboratories gave extreme

    examples of flashover paths of (i) 8.75 m for 1.4 MV peak

    positive switching impulse SI wet with a clearance of

    7 m to the building, (ii) broken paths equivalent in one

    case to 8.78 m for 1.9 MV positive SI dry and, in another

    example, to 9.28 m for 1.9 MV peak positive SI dry. For

    1.1-1.2 MV rated gear, switching impulse voltages of up to

    2.3 MV could be required for insulation coordination

    evaluation, for which a laboratory clearance of 15.3 m was

    estimated.

    The dimensions of the labora tory, denned as the work-

    ing clearance, were then estimated to be 33.5 m (110 feet)

    wide x 32 m (105 feet) high x 82.3 m (270 feet) long.

    However, since the cost of building is roughly propo rtional

    to the volume, a worthwhile economy could be effected by

    reducing the length of the building and, in compensation,

    ensuring that all test equipment would be mobile.

    The resultant laboratory length selected was a reduction

    from 82.3 m (270 feet) to 48.8 m (160 feet), but an outdoor

    test pad was provided which could be serviced readily

    because of the mobility of test equipment, so as to mini-

    mise the disadvantage of reduced internal space. The

    general layout of the labo ratory is illustrated in Fig. 2. The

    main items of test equipment are shown in Figs. 2 and 3

    and described elsewhere [1 , 2] . They include:

    (i) 2 MV RM S 50 Hz test transformer (Figs.Id and 3a)

    (ii) 4 MV lightning impulse 2.8 MV switching surge gen-

    erator (Figs.

    2d

    and 3b)

    (iii) 4 MV potential divider (Figs.2dand 3c)

    (iv) artificial rain equipment capable of continuous rain

    oper ation (Fig. 5)

    (v) two large oil tanks (Figs. 3c and 5c)

    (vi) various high-voltage measuring devices other than

    (iii) abo ve.

    A full list of equipment with technical data is given in

    Appendix 10.2.

    Historically, it should be recalled that the laboratory

    was officially opened on 15th May 1970, by the then Min-

    ister of Technology, the Rt. Hon. Anthony Wedgwood

    Benn and was named, the Clothier Laboratory to honour

    an earlier eminent engineer Henry William Clothier, 1872

    1938,

    remembered for his pioneer work in furthering the

    expansion of the electricity supply industry. From the

    outset, it was intended to make these laboratory facilities

    available to the supply industry and to manufacturers, uni-

    versities, polytechnics and HEI for high-voltage research

    and development.

    4 Critical operational appraisal of facilities

    4.1 Rating ofequipment tested

    Prior to the completion of the new facility in May 1970,

    laboratory facilities existed in an old EHV laboratory,

    located in the Hebburn main works area, suitable for high-

    voltage type testing of switchgear of up to 420 kV rating

    with certain clearance restrictions. The original design

    philosophy was a new UHV test facility to cater mainly for

    transmission switchgear equipment etc. rated 765 kV and

    above with adequate provision for increasing the test

    capacity to levels appropriate to 1.1 MV transmission

    systems. Moreover, the new facility would enable overvol-

    tage insulation co ordination studies to be made o n 420 kV

    switchgear at impulse test voltages >

    2

    MV.

    Contrary to expectations however, during its first 15

    years of operation the extent of UHV laboratory testing

    devoted to gear rated at 765 kV, and above, was mainly

    concerned with bushings with only one sample at 1.1

    MV, and with in-depth testing of tower-window per-

    formance for 765 kV ratings. The majority of work has

    involved testing equipment rated at 420 or 525 kV (see

    Figs.1, 6-14, 17-20, 23, 24 and 31).

    The prediction that air-blast gear would develop to

    higher rating s than 420 kV was not fulfilled and the labo r-

    atory was involved in research work and development of

    the alternative range of SF

    6

    insulated open-type and

    metalclad switchgear and in proving tests for this type of

    gear at levels of = 525 kV as illustrated in Figs. 17-20.

    In general, this change in technical development from

    pressurised-air to SF

    6

    insulation meant that the laboratory

    area was more than adequate (i.e. there was a surplus of

    floor area), because of the smaller size of SF

    6

    equipment

    compared to air-blast gear and this resulted in a consider-

    able saving of time which would have been spent in

    moving the major test equipment. For example, the 2 MV

    transformer was kept in one position most of the time (see

    Figs.Id and 17).

    For economic reasons, it was decided in 1980 to close

    down all the dielectric laboratories in the old works. A

    careful appraisal was made of the test equipment most of

    which was scrapped and only items in very good condition

    were retained. By making full use of this equipment, it was

    possible to establish three test areas within the main hall of

    the UHV laboratory, without effectively reducing the effi-

    ciency and usefulness of the main area (see Appendix 10.1,

    Figs.25, 28 and 30). At the same time, the usefulness of the

    erection bay was reconsidered since little effective use had

    been made of it. A multipurpose mechanical/thermal/

    dielectric area was therefore established in the erection bay

    (Figs.

    29 and 31a), thus considerably enlarging the scope of

    the laboratory. The dielectric area included facilities for

    research into insulation materials, including endurance

    and accelerated frequency testing (see Appendix 10.1, Figs.

    26

    and 27).

    4.2 EffectivenessofUHV laboratory equipment

    4.2.1 2 MV RMS-50 Hz test transformer see Fig. 3c):

    This has been electrically satisfactory with a constant

    partial-discharge performance of about 5 pC at 1 MV

    Fig . 3 Major items of laboratory equipment

    a 2

    MV transformer positioned for outdoor use

    b4 MV impulse generator

    c

    Standard laboratory setup for power factor and partial internal discharge testing

    of bushings. 950 kV bushing (courtesy Bushing Co. Ltd.)

    d

    View of

    2

    M spheregaps, control room and galleries

    eMain control room

    /Screened room

    Clothier Laboratory:

    Dimensions of test hall for electrical clearance: length 49 m, width 33.5 m, height

    32 m

    Size of outdoor test pad : width

    15.3

    m, length 24.4 m

    Size of

    main

    access door to test pad: width 11.7 m clear, height

    19

    m clear

    Impulse generator for outdoor and indoor use: maximum nominal voltage 4 MV

    peak, maximum nominal energy

    150

    kJ, height

    13

    m

    test transformer for outdoor and indoor use: maximum nominal voltage 2 MV

    RMS,

    primary input 2.7 kV RMS, nominal rating 3.2 MVA, high-voltage maximum

    current rating 1.6 A, maximum kVA demand on supply system 750 kVA, height

    18.3 m

    Capacitive voltage divider: maximum voltage for impulse waves 4 MV peak, for

    switching surges 2.8 MV peak, for 50 Hz 2.8 MV peak, height 15 m

    Oil test tank: Internal diameter 5.5 m, internal height 5.5 m, suitable for vacuum

    impregnation with 0.133 Pa l/s maximum leakage rate, number of inspection ports

    12,maximum weight of test piece on top cover 10.2 tonnes, mobile by means of air

    cushion

    IEE

    PROCEEDINGS,

    Vol.

    133,

    Pt.A,

    No .

    8,NOVEMBER

    1986

  • 8/10/2019 Upload 1Desig n an d operatio n perspectiv e o f a Britis h UH V laborator

    5/21

    IEEPROCEEDINGS,

    Vol.

    133,Pt. A, No .

    8,

    NOVEMBER 1986

    505

  • 8/10/2019 Upload 1Desig n an d operatio n perspectiv e o f a Britis h UH V laborator

    6/21

    Fig. 4

    Shielding and earthing details

    [ /]

    a

    Interconnecting copp er straps

    dPlan view of earthing box, earth rod and water hole

    b

    Copper earth rod

    e

    Earthing connection

    c Earthing box with to p cover

    /Co ppe r mesh and copper tapes

    RMS. Mechanically, however, the considerable weight of

    the transformer (203 tonnes) borne by railway type wheels

    travelling on rails, resulted in appreciable wear and distor-

    tion of the wheels which had to be replaced with a better

    grade of steel.

    4.2.2 4 MV impulse generator see Fig. 2d):

    This in

    general was satisfactory, but the following experiences

    were noted:

    (a) The maximum charge voltage of 200 kV DC per

    stage was not achievable due to interstage flashover gener-

    ated by corona (at about 180 kV DC). One of the main

    reasons for this problem was the substantial mechanical

    reinforcing incorporated into the finalised design to make

    the generator suitable for outdoor use, even under severe

    wind conditions. In compensation, two additional stages

    were added (bringing the total to 22 stages).

    b) Irregularities were experienced in firing the generator

    and to counter these it was found necessary to circulate

    dry air through the 'polytron' gaps 24 hours a day. To

    improve performance of the gaps and reduce maintenance,

    all original gaps were modified gradually with graphite

    tips.

    (c) The generator was fitted with front and tail resistors

    to provide nominal standard waves of 1.2/50microseconds

    and 250/2500 microseconds. It has been recognised that

    additional resistor sets should be obtained for greater ver-

    satility. Nevertheless, by careful arrangement of the exist-

    ing resistors, it was still possible to obtain nonstandard

    waves such as 1/40, 20/1600 microseconds and others for

    certain co-ordination work on 420 kV live-tank

    SF

    6

    -insulated circuit breakers etc.

    4.2.3 Capacitor-resistive potential divider see Fig. 2d):

    This has given excellent service. The divider is calibrated

    routinely at intervals of six months against a pure resistive

    divider, and checked for impulse waves with uniform field

    gaps,

    and for power-frequency voltages against a 1 MV

    standard capacitor of 109.09 pF (shown in foreground of

    Fig.3c).

    506

    This divider is normally used for all tests which require

    voltage measurements and recording. The two-metre

    sphere gaps (Fig.

    3d )

    which are available in the laboratory

    are not used for accurate voltage measurements, due to

    flashover inconsistencies which can introduce errors of up

    to 10%.

    4.2.4 WOO pF capacitor: For RIV and partial discharge

    testing, a capacitor C (see Fig. 17), of approximately

    1000 pF, was built by stacking in vertical construction

    existing capacitor units taken from surplus 400 kV CV

    transformers. Adequate anticorona buns and shields were

    incorporated into the design, the whole structure being

    made fully mobile. It is capable of operating up to 1 MV

    RMS.

    4.2.5 Double-beam type 72 Haefely transient recorders-

    Three recorders are available (see Fig. 3e). These instru-

    ments, which are calibrated at regular intervals, have been

    fairly reliable. Records are taken with 35 mm cameras with

    automatic frame advance operation, which facilitates the

    enormous output required in statistical research studies.

    Special table projectors with enlargement up to

    254 x 203 mm (10 x 8 inches) of the 35 mm records aid

    accurate measurements and observation of anomalies in

    the wave shapes.

    4.2.6 Screening: Although the laboratory control room is

    screened from the test hall, the screening is not adequate

    when operating equipment for the observation of flashover

    phenomena and image enhancing. A completely screened

    room was designed and manufactured for this purpose. It

    can be deposited at any convenient location within the test

    hall on an insulated sheet, so that one-point earthing can

    be applied (Fig. 3/). So far, some difficulties with electrical

    interference have not been completely resolved.

    4.3 Earthing system

    The earthing system is based on an underfloor copper

    mesh linking a multirod arrangement in the subsoil, access

    IEE PROCEEDINGS Vol. 133 Pt. A No. 8 NOVEM BER 1986

  • 8/10/2019 Upload 1Desig n an d operatio n perspectiv e o f a Britis h UH V laborator

    7/21

    being obtained by screwing in connectors at the head of

    the rods. The earth system is tied to the metal walls of the

    building [1-3] forming a gigantic Faraday cage. Some of

    the details of copper mesh, rod connections, intercon-

    nections to the building walls etc. are shown in Fig. 4 and

    discussed in Reference 1.

    It has been found that with flashover in SF

    6

    -insulated

    gear, due to the steep collapse of voltage (

    x 1

    MV//is)

    multisparkover of the earthed points has been consistently

    experienced. This has led to problems in laboratory pro-

    tective circuits. Because of the variety of test objects to be

    handled in the test hall, it was not thought practical to

    obviate these sparkover phenomena by mounting all

    equipment on large thick aluminium plates.

    4.4 Outdoo r test facility

    An outdoor test pad was provided outside the main door

    opposite the control room for the following reas ons:

    (a) additional electrical clearance not obtainable within

    the building for testing at higher ratings than 765 kV

    {b) additional test area facility when the main hall was

    engaged in long-term testing

    (c) its close proximity to adjacent high-power short-

    circuit test facilities.

    Earlier prevailing weather studies had indicated the fea-

    sability of outdoor testing. In the first few years, this

    facility has only been used infrequently since the internal

    laboratory clearances have been more than adequate for

    the work undertaken with particular reference to metalclad

    SF

    6

    equipment. Its usefulness, however, for the future

    remains for possible application to ultra-high-voltage

    transmission-line hardware and experimental lengths of

    transmission line for which there is adequate room to

    accommodate up to 150 m. Further application is possible

    to special situations when the combined facilities of the

    short-circuit station and ultra-high-voltage laboratory may

    be deployed.

    The outdoor test facility has been used extensively

    during the past five years for combined mechanical/

    electrical operational proving tests on 420 kV metalclad

    switchgear. This is clearly illustrated in Appen dix 10.1 by

    the example presented in Fig.

    3

    Id and

    e .

    4.5 Artificial-rainequipment

    4.5.1 Fixed standard equipment: To date , the design

    philosophy of the rain-water equipment has been fully jus-

    tified. The design incorporated:

    Fig . 5 General view of wet-testing assemblies

    Improved nozzle assembly

    b

    View of artificial rain catchment area: for circuit breaker, surge arrester or discon- area

    nect isolator tests [2]

    Set up for bushing wet tests showing oil-tank wet-test assembly and catchment

    IEEPROCEEDINGS,

    Vol.

    133,

    Pt.

    A,No .

    8,

    NOVEMBER1986

  • 8/10/2019 Upload 1Desig n an d operatio n perspectiv e o f a Britis h UH V laborator

    8/21

    (i) automatic mixing of the tap water and deionised

    water to provide any requ ired resistivity

    (ii) possibility of storing water with two different values

    of resistivity separately in the storage vessels, for alterna-

    tive imme diate use

    (iii) collection of the rain water from the test piece and

    return at high pressure and high speed to the pressurised

    storage vessels via an intermediate open vessel.

    The nozzles comply with IEC 60-1 regulations regard-

    ing the mandatory dimensions. The rear chamber of the

    nozzle assembly has been designed to give a better water

    flow; restriction has been imposed on the angular move-

    ment of the stem to prevent cutoff and obstruction of the

    water flow. The frames supporting the nozzle assemblies

    allow each row of nozzles to be rotated by up to 90 (see

    Fig. 5a).

    The catchment basin at the base of the test pieces is

    built up with sheets of polythene for each test programme

    since the floor cannot be used for this purpose, as it was

    kept flat for air-cushion transportation. This disadvantage

    was pa rtly justified by the flexibility afforded by this tech-

    nique in placing the test objects anywhere in the test hall

    (see Fig.5band c).

    4.5.2 Special rain equipment: The rain equipme nt just

    described forms the fixed installation, and is located o n the

    wall opposite the control room. There are occasions when

    such a standard installation is unsuitable, and special

    arrangements have been devised. In the case of bushings,

    mounted in the oil tanks, a nozzle frame has been mounted

    on a mobile 'beanstalk', where the height is controlled

    hydraulically. The frame is ideally dimensioned to produce

    the required rainfall on such a narrow and long test piece

    as a bushing (see Fig. 5c). In the case of a tower window, a

    frame was built along the top of the tower with nozzles

    pointing upwards so that the required even rainfall could

    be produced (see Figs.15band15d).

    4.6 Oil test

    equipment

    The oil system, which comprises underground storage

    tanks (127 m

    3

    (28000 gallons)), pumping station, stream-

    line purifier and conditioner, and delivery pipes to outlets

    in the centre of the laboratory floor area, has been satisfac-

    tory.

    There are two test tanks, mainly used for testing bush-

    ings. The first one is of 127 m

    3

    (28000 gallons) capacity

    (Fig. 3c) and can be sealed for vacuum impregnation (if

    required); it is mobile with skirted air cushion. The second

    tank (Fig. 5c) has been acquired in recent years and

    although smaller than the first, can be used for bushings

    up to 765 kV rating. The advantage of this tank is that in

    the case of transformer bushings, the smaller test tank

    reproduced more accurately the stresses existing in actual

    power transformers.

    4.7 General movemento fobjectsand cranage

    All the floors in the test hall, erection bay and on the

    outside test pad, were constructed flat to close tolerances,

    so that objects, test pieces etc., could be moved about

    using air-cushion-skirt principles (see Fig. 3c). In practice,

    when moving objects, the following difficulties were experi-

    enced

    :

    instability of large or high structures causing oscil-

    lations of the air pads, failure of the air cushion and

    bottoming of the load onto the floor.

    The crane is of

    7

    ton capacity and runs the whole length

    of the test hall with a beam equal to the width of the hall

    at a height just below the

    roof.

    The crane is adequate for

    the work required but suffers from pendulum oscillations

    due to the 30.5 m drop of the crane hook, and is normally

    supplemented with mobile cranes.

    5 Scope and range of dielectric activities

    While the modern UHV laboratory facilities outlined in

    this paper are mainly devoted to switchgear product

    research, development, quality control and certification,

    many of the experimental techniques involved are equally

    applicable to testing equipment for commercial operations

    Fig . 6

    Transportable metaldad switchgear assemblies prior to routine

    dielectric testing

    a

    Assembly mounted on trailer

    b

    Circuit breaker assembly, with temporary 800 kVfibre-glass est bushing, being

    moved into works test area using multipalette systems

    508

    IE EPROCEEDINGS,

    Vol.

    133,

    Pt.

    A,No .

    8,

    NOVEMBER1986

  • 8/10/2019 Upload 1Desig n an d operatio n perspectiv e o f a Britis h UH V laborator

    9/21

    not connected with switchgear. The laboratory and test

    facilities, including consultancy services and an extensive

    library of electrostatic field and power-system computer

    programs have been made available to outside clients on a

    confidential contractual basis for many years.

    An indication of the scope of dielectric activities under-

    taken within the present integrated UHV complex during

    the past 15 years can be seen from the following group-

    ings:

    (i) barrier flashover characteristics [8, 13]

    (ii) GIS site installation, quality and testing procedures

    [9, 10]

    (iii) particle-initiated breakdown [11, 13]

    (iv) insulation coordination [14-1 8]

    (v) laboratory testing techniques [1,2, 19-21]

    (vi) GIS backparts and interrupter developments

    [23-28]

    (vii) general contractual testing [22, 29-32]

    (viii) insulation materials evaluation [33-37]

    (ix) gas breakdown characteristics for large practical

    electrode systems [4-7].

    Extensive use was made of established field analysis and

    breakdown estimation techniques [26]. Technical details

    relating to most of these aspects are fully covered in the

    original reference publications and only a brief general

    appraisal of some salient work carried out in the UHV

    laboratory area is given in Section 6.

    6 Appraisal of salient examples of UHV laboratory

    utilisation

    6.1 Dielectric properties of pressurised SF

    6

    As illustrated in Section 5, the insulation group of

    researchers in the authors company have been actively

    involved in many aspects of dielectric research and devel-

    opment work during the past 20 years. The emphasis has

    been on determining the breakdown and flashover charac-

    teristics of gas gaps and support insulation, the work being

    directly relevant to the design of gas insulated switchgear

    equipment (GIS). The laboratory work, which involved the

    use of large test rigs (e.g. Figs. 6-9), had five main objec-

    tives :

    (a) Before the first 300/420 kV GIS equipment was pro-

    duced in the UK it was vital to establish reliable clear-

    ances. Consequently, it was necessary to embark on

    research programmes to provide comprehensive design

    da ta; reproduced in Figs. 10-12 [7, 13].

    b)It was also important to carry out a considerable

    amount of testing, using video techniques, to gain an

    appreciation of the influence of particulate contamination

    Fig. 7

    General view of 2.6 MV test rig and SF,,gas recovery plant

    [7 ]

    Fig. 8 400/525 kV development rig for SF

    6

    metalclad switchgear

    on the attainable withstand capabilities of GIS (see Fig.

    12).

    (c) In addition, to carrying out short-term studies it was

    necessary to determine projected in-service or long-term

    characteristics ofGIS.

    Fig . 9 Typical schematic of a 420/525 kV GIS

    IEE PROCEEDINGS, Vol. 133,Pt. A, No. 8, NOVEMBER 1986

    509

  • 8/10/2019 Upload 1Desig n an d operatio n perspectiv e o f a Britis h UH V laborator

    10/21

    d) The b roa d q uestion of insulation coordina tion for

    GIS had also to be resolved by studying the interrela-

    tionship between GIS voltage/time [13, 15-18] character-

    istics and those of line gaps and surge arresters (see Fig.

    13).

    e)Fin ally, effective factory quality control, work s and

    site erection testing procedures had to be established. Elec-

    trically, each GIS subassembly unit was subjected to a

    2.0

    0.1 0.2 0.3 0 .4 0.5

    p r e s s u r e , M P a

    0 . 6

    F i g . 1 0

    Lightning and switching impulse V

    50

    levels in SF

    6

    for perturbed

    cylinder configuration

    0.1 0.6

    .2 0.3 0.4 0.5

    a pressure,MPa

    b

    F i g . 1 1 A Withstand characteristics of epoxy resin support insulator in

    Fig . 11 B

    Surface flashover marks on a 400/525 kV cast-resin insulator

    after extensive laboratory testing

    1000

    600

    1600

    >

    400

    20 0

    SF

    6

    0.55 MPa

    420 kV

    -phas.e

    system

    vol tage

    44

    1

    jclean withstandfl min)J

    630KV works test level

    520 kV routine test level

    , ^ 4 2 0 ^

    site test level

    typical particle 1

    lift off voltage

    0 2 4 6 8 10 12

    part icle size,mm

    F i g . 1 2

    50 Hz flashover characteristics of epoxy resin conical spacers

    under varying degree of metallic contamination [ / i ]

    high-voltage test of one minute duration in the works,

    before despatch to site; this test was repeated on site prior

    to commissioning. Extensive laboratory studies have been

    .2.1 m gap

    .2.5m gap

    0.1

    1 10 100

    t ime, us

    Fig . 13

    Insulation co-ordination diagram

    [ / J ]

    A

    Typical V/t characteristics of

    420

    kV GIS

    BRepresentative characteristics of

    396

    kV ZnO arrester

    C

    Lower limit curve of

    a

    line gap for specific gap settings

    (i) upper limit 40

    kA

    amplitude

    (ii) lower limit 3 kA am plitude

    carried out by the authors to evaluate the effectiveness of

    various site-commissioning test procedures for large GIS

    installations [9]. In addition, various on-line monitoring

    techniques have been under development in recent years

    which should result in still further improvements in service

    reliability in SF

    6

    -insulated switchgear.f

    One on-line monitoring technique examined in the

    laboratory by the authors recently [10], related to a

    chemical SO

    2

    detection method. If flashover occurs during

    any test in SF

    6

    -insulated GIS, it is important to be able to

    distinguish between a nonself-restoring surface flashover

    of the cast-resin support barriers and self-restoring flash-

    over across gas gaps. Examples of experimental tests based

    on this chemical approach are shown in Fig. I4a-e.

    Preliminary 50 Hz studies involved full-scale laboratory

    experiments which were established on GIS assemblies

    (Fig. 14a-/) to assess the comparative sensitivity of this

    SO

    2

    detection technique. These tests, without absorbent,

    indicated the possibility of clearly differentiating between

    gas-gap and insulator gas-to-surface flashover, with an

    SO

    2

    concentration differing by a factor

    x

    1000 (e.g. Fig.

    14a).

    Using an SF

    6

    test volume of 350

    1

    at 0.55 MPa, with

    molecular sieves fitted, a family of curves was produced

    (Fig.

    He)

    giving the time taken to obtain readings of SO

    2

    concentrations against time elapsed after flashover [10]. It

    was noted that even after 14 hours had elapsed following a

    single 50 Hz spacer flashover, significant concentrations of

    SO

    2

    were detectable.

    Three controlled-energy impulse studies were also

    reported using different energies and chamber volumes.

    For purposes of direct comparison, results from these

    impulse studies are shown in Fig. 14/, curves 2, 3 and 4

    respectively, together with the 50 Hz results reproduced in

    curve 1. All results refer to SO

    2

    detection reading of 15.

    These curves clearly demonstrate the relationship of gas

    volume, arc energy and disposition of the arc relative to

    the gas sampling points, in the presence of a molecular

    sieve absorbent, against elapsed time following flashover

    event [10]. These controlled-energy impulse tests sup-

    ported by TNA studies provided a useful means of assess-

    ing the sensitivity of the simple SO

    2

    detection method. The

    f B.F. Hampton (CERL ) is currently at the forefront of novel developments relating

    to site testing of GIS

    51 0

    IEE PROCEE DINGS, Vol. 133, Pt. A, No. 8, NOVEMBER 1986

  • 8/10/2019 Upload 1Desig n an d operatio n perspectiv e o f a Britis h UH V laborator

    11/21

    experiments demonstrated that the technique is clearly

    able to differentiate between a gas-gap or spacer flashover

    in GIS assemblies. The authors point out that further

    work is necessary to confirm the effectiveness of this test

    technique when referred and applied to larger GIS gas

    zones under site conditions [10 ],

    Special purpose-built large test rigs and associated

    bushings were designed to be used for much of the above

    studies [7]; these, together with digital programs to facili-

    tate correlation of test data and gas handling equipment

    (Fig. 7) enabled essential technical information to be

    acquired. The recent introduction of video library and

    recording techniques, to augment standard and high-speed

    cameras, has provided a valuable new diagnostic monitor-

    ing capability which can be used to study in detail the

    influence of particles in GIS and correlate particle position

    with partial discharge level etc. [13].

    6.2 Switchingimpulse strengthof 765 kVtower

    window

    For the tower-window study (Fig. 15), sponsored by the

    combined efforts of ERA UK Manu facturers/Con-

    sultants [30], it was necessary to build a structure 19.5 m

    high with a window width of 15 m (18 m width overall).

    The corresponding laboratory height and width dimen-

    sions are 32 and 34 m, showing that there were no diffi-

    culties in accommodating such structures. The frame

    sections were preassembled elsewhere, so that the time of

    erection in the test hall could be minimised, effectively

    reducing costs because of the high charges of occupation.

    To increase stability of the structure, which could not be

    bolted to the laboratory floor, (a precaution used to pre-

    serve the integrity of the underlying earth mat), ties to the

    building stanchions were used.

    An additional moveable box trusss was added to vary

    2 S 10 IS 202 5 30

    F i g . 1 4

    Results from a recent S0

    2

    detection study [Iff]

    a

    Gastec SO

    2

    detector tube

    (i) after repeated gas gap flashovers

    (ii) after o ne flashover across solid insulation

    b, c,dLaboratory GIS test arranagements (SF

    6

    al 0.55 MPa)

    B bauxite spacer

    SP sampling point

    O observation port

    M molecular sieve containe r

    Sg position of

    Al

    spike gas breakdown

    Ss position ofAlspikes spacer flashover

    Relationship between time and SO

    2

    concentration O (arbitrary scale)

    4

    epoxy/alumina spacer, vol. 650

    I,

    energy 712 J, impulse

    I

    5

    0

    tim

    ( 5 ) @ @ (20) (25) (30

    - -

    - * -

    ,30)

    tubeG

    60 120

    tube C

    tube B

    tube A

    8 12 16 20

    e required to obtain reading,minutes

    10 15 20

    time after f lashover, h ours

    IEE PROCEEDINGS, Vol. 133, Pt. A, No. 8, NOVEMBER 1986

    511

  • 8/10/2019 Upload 1Desig n an d operatio n perspectiv e o f a Britis h UH V laborator

    12/21

    /

    /

    S

    S.

    \

    \

    \2

    /\/\/\/\/\/\/\

    1 5 m

    \

    S ,

    S

    3

    MV)

    bduring preapplied pollution tests using sail/clay mixture (voltage 250 kV RMS)

    much better 'feel' for the complex arc-interruption pheno-

    mena [27] in the SF

    6

    interrupter units, ably assisted by the

    adoption of effective dielectric principles using analytical

    field analysis and breakdown estimation techniques. Con-

    siderable progress has been made in both arc-interruption

    and dielectric modelling techniques in recent years as more

    reliable experim ental d ata beco mes available [7, 13, 27,

    28].

    F i g . 1 9 View of 420 kV SP D 2 break) metalclad circuit breaker

    assembled in main UHV hall for type testing

    Two vertically mounted porcelain inlet bushings and horizontal connecting busbar

    are also shown which enables complete type and conjunctive bias testing to be

    carried out on this vertically-mounted metalclad switchgear assembly. The pho-

    tograph indicates the size of main hall which provides adequate air clearances for

    more than one test object to be assembled at the same time so minimising erec-

    tion delays.

    51 4

    Recent changes in dielectric specifications have resulted

    in the need for more sophisticated test procedures such as

    phase-phase and bias-testing techniques.

    Laboratory staff have participated in IEC (TC28) and

    BSI deliberations on revision to relevant specifications.

    6-break 4-break 3-break 2-break

    1-break

    (1976) (end 1976) (1979) (1981) (1985)

    Fig . 20

    Stages in the evolution of a 420 kV dead-lank circuit breaker

    1281

    For bias testing, simultaneous application of power-

    frequency and lightning impulse voltage to circuit breakers

    or gas-insulated substation equipment (GIS) is required. A

    typical circuit for bias testing is shown in Fig. 21. Here

    again, the generous clearances available in the test hall,

    together with the mobility of test equipment (e.g. 2 MV

    transformer and 4 MV impulse generator) have enabled

    these tests to be performed effectively. Obviously, special

    care is required to ensure adequate protection of test

    transformer from impulse test voltages.

    impulse

    generator

    DC

    charger

    ha

    test object X

    differential voltmeter

    protective

    T

    transformer.

    point-on-

    wave

    selector tran sien t recorder

    50 Hz

    sample voltage

    Fig. 21 Test circuit for bias testing GIS

    1EE PROCEEDINGS, Vol. 133, Pt. A, No. 8, NOVEMBER 1986

  • 8/10/2019 Upload 1Desig n an d operatio n perspectiv e o f a Britis h UH V laborator

    15/21

    6.5 Impulse -voltage measuring system

    6.5.1 Analysis:

    With the increasing amount ofdevelop-

    ment and basic research work being undertake n at all

    transmission voltages from UHV downwards, the require-

    ments ofthe impulse-voltage measuring systems usedare

    becoming necessarily more stringent.

    In

    order

    to

    obtain

    maximum information about the impulse wave,theaccu-

    racy limitations of themeasuring system must first be

    established andunderstood. Some general points can be

    made first:

    (a) Measuring tasks may vary from the relatively simple

    on e of recording with lowerror a full or tail-chopped

    1.2/50fi simpulse wave (see Fig. 22a, waveforms (i), (ii))to

    the more difficult problems involving a front-chopped

    impulse or onehaving partial (layer) break dow n of the

    solid insulation under test, usually about thepeak ofthe

    impulse (waveforms (iii), (iv)).

    b)A further difficult measurem ent tobe mad e,is ofthe

    extent and magnitude of any oscillations occurring at the

    test object. The occurrence of these voltage wave shapes

    in

    high-voltage development work is quite common, espe-

    cially

    the

    full

    and

    tail-chopped waves. Fro nt-chopp ed

    waves down

    to

    chopping times

    of

    about only

    0.4[is are

    often met, particularly when testing equipment per-

    formance for insulation coordination.

    (c) Partial breakdown ofinsulation unde r test (Fig. 22a

    waveform (iv))canoccur ontest objects having multiple-

    layer insulation (e.g. bushings, current transformers, capac-

    itors etc.).

    d) Almost all impulse waves recorded exhibit oscil-

    lations whose significance must be analysed with regardto

    compliance with the relevant specification anderrorsin

    peak voltage and waveshape measurements.

    e) Particular problems can beencountered with UH V

    impulse measuring systems, suitablefor themeasurement

    of fast transients, due to the large dimensions involved.

    (/) 'Response time' and step responseofany measuring

    system are two major criteria

    in

    determining its suitability

    for fast-transient measurement [38-41].

    During thepast 20years, authoritative work on UHV

    divider response have been undertaken elsewhere by Creed

    and Collins and also Zaengl. However, for the purposes of

    the present paper it isadequate to highlight someofthe

    early work undertaken by Richardson.

    Richardson and Ryan [21] reported on the general con-

    struction and described the testing techniquetoassess the

    step response ofthe 4 MV impulse measuring systemin

    the authors' UHV laboratory. An equivalent circuit, repro-

    duced inFig.22b,was evolved, upon which the analytical

    method was based and comp utational aspects of the

    digital technique were briefly discussed. Although

    the

    influence of several circuit parameters were consideredit is

    sufficient topickouttwo aspectsatpresent; the effectsof

    (i) high-voltage lead damping resistor R

    D

    and (ii)high-

    voltage lead length / and surge impedance Z

    o

    on step

    response. Atypical set of response curves for Z

    o

    =300,

    /

    = 9 m and a

    terminating capacitance

    C

    p

    =

    7.5

    pF are

    shown inFig. 22c.It can be seen thatit isprincipallythe

    area of the first overshoot

    T

    2

    ,

    which determines the

    response time T where,asillustratedin the insert to Fig.

    22c

    100 200 300 400 0 100 200 300

    d ns ns

    0 100 200 300 400 0 100 200 300

    F i g .

    22 Study of response of impulse voltage measuring system [ 2 / ]

    a Typical voltage shapes to be measu red

    b Equivalent circuit of impulse measuring system

    c Effect ofHV lead damping res i s to r onstep respo nse

    Z

    o

    = 300 n, C

    p

    = 7.5

    p F ,

    / = 9 m

    T = T,

    -

    T

    2

    +

    T

    3

    - T

    4

    d Effect of HV lead strength on step response RJZ

    0

    = 0.5)

    Z

    o

    = 300 n, C , = 250 pF

    init ial response referred to 3 mlead

    (, Response parame ters ,ns

    metres

    T, T

    2

    T

    3

    39.5 3.5 36.0

    6 40.6 8.4 32.2

    9 42.7 10.9 31.8

    e Effect of HV lead lengtho n step response R

    D

    /Z

    0

    =0.167)

    Z

    o

    = 300fi C

    r

    = 250 pF

    init ial response referred to 3 mlead

    I , Response parame ters ,

    n s

    metres

    3 23.2 24.1 6.35

    6 27.9 34.3 11.25

    9 34.0 42.5

    /Effect ofHV lead surge impedance on step response (S

    D

    /Z

    0

    = 1.0)

    /= 9 m, C, = 7.5 pF

    Z

    o

    ,

    1 Response time

    T,ns

    30 0 24.3

    50 0 25.4

    58 0

    26.5

    g Effect ofHV lead su rge impedanc eo n step response (R

    o

    / Z

    0

    = 0.5)

    / = 9 m, C

    p

    = 7.5 pF

    Z

    o

    , n Response t ime T,ns

    30 0 9.2

    50 0 17.8

    58 0 19.2

    1EE PROCEEDINGS, Vol. 133, Pt. A, No. 8, NOVEMBER 1986

  • 8/10/2019 Upload 1Desig n an d operatio n perspectiv e o f a Britis h UH V laborator

    16/21

    Briefly, with fast-response voltage dividers, the response

    time can be significantly affected by R

    D

    .

    Fig. 22d, e and /, g, respectively, illustrate interesting

    results obtained by Richardson due to (i) effects of HV lead

    length on step response for different values of damping

    resistor R

    D

    )and (ii) effects of HV lead surge impedance on

    the step response for different values of damping resistor.

    The results of this computer-aided analysis [21] were vali-

    dated by laboratory testing and such characteristics were

    subsequently well documented in laboratory test manuals

    for future reference.

    6.5.2 Practical considerations:

    Hav ing mad e a full

    appraisal of the theoretical measuring system and the pre-

    ferred layout of measurement equipment, it is important to

    determine the long-term reliability and accuracy of one sel-

    ected measuring system to avoid the necessity of frequent

    and even daily repeated calibrations, which would inter-

    rupt a series of tests or even cause postponement of them,

    a procedure very costly in time and money.

    The particular measuring system selected always com-

    prises a combination of the ASEA 4 MV-capacitor-

    resistive divider in conjunction with denned low-voltage

    arm(s),

    coaxial cable and Haefely CR O.

    Other methods of measurement in the laboratory

    included 2-metre sphere gaps for checking and measuring

    high-voltage peak values, but du e to erra tic fiashover char-

    acteristics up to 10% errors were experienced. Very little

    improvement was obtained by UV ionising procedures.

    Eventually, uniform field gaps of 4 feet diameter were

    installed with which an accuracy of better than 1% was

    achieved. A pure resistance divider (Haefely) with capac-

    itance grading is used for calibrating the ASEA divider,

    which is supplemented by cross referencing to the uniform

    field gaps.

    Finally, it must be stressed that theoretical consider-

    ations cannot be divorced from the practical reality of long

    leads connecting the impulse generator with the test piece

    and the potential divider. Also, the practical problem exists

    of reducing the inductive effects of loops whilst retaining

    adequate clearances and dealing with physically large test

    components and test pieces which occupy considerable

    areas of the UHV laboratory floor.

    6.6 General and contractual H V testing

    In addition to extended investigations of the types

    described in Sections 6.1-6.4, there has been considerable

    activity in type testing, proving tests and routine pro-

    duction testing. In the case of routine testing, either the

    work could not be done in the works' extensive high-

    voltage test facilities, due to technical reasons or during

    periods of high production.

    The regular practice of routine testing in the UHV

    laboratory cannot be fully defended on economic grounds,

    but when necessary, the costs can be considerably reduced

    by erecting a number of similar test pieces contemporan-

    eously (for which there is ample floor space and electrical

    clearance) and testing them in quick succession.

    Another advantage of the available floorspace was the

    fact that providing operating voltages are not too high

    tests could be interrupted on one particular test piece,

    and work continued on another which had been suitably

    erected on the floor. Fig. 19 shows, in fact an arrangement

    for testing a 420 kV dead-tank SF

    6

    circuit breaker, whilst

    phases of a live-tank 420 kV circuit breaker, placed else-

    where, were awaiting tests. At the same time, a rig was also

    erected on the floor for routine testing of cast-resin

    support barriers.

    With regard to contractual work, a considerable

    amount of type and routine testing has been carried out on

    500 kV and 765 kV bushings, and in particular trans-

    former bushings. For the latter, test requirements for the

    oil are stringent (less than 10 parts in 10

    6

    of moisture,

    usually 4 parts in 10

    6

    and test-cell breakdown in excess of

    60 kV) and can be more readily achieved by using the

    smaller of the two oil test tanks available (Fig. 5c). The

    smaller tank could be sealed more effectively against mois-

    ture ingress durin g the artificial rain tests.

    Although the laboratory was designed specifically for

    testing power-engineering equipment, it has been used

    because of its lightning voltage capability for the con-

    tractual testing with electrogeometric models of aircraft

    (Fig. 23). After proving the validity of the scale techniques,

    and contributing to a better understanding of the physics

    Fig . 23

    Aircraft lightning studies using simplified models

    [29]

    Fig . 24 BAC Nimrod lightning strike studies laboratory impulse tests on front radome

    Laboratory tests on aircraft to evaluate the probability of lightning strike have underlined the importance of

    multicamera operation to obtain a three dimensional picture of the exact point of strike. Similar techniques

    have also been used in assessing voltage coordination in GIS and live-tank circuit breakers, line gaps etc.

    51 6

    1EEPROCEEDINGS,

    Vol.

    133,

    Pt.A,

    N o.

    8,NOVEMBER

    1986

  • 8/10/2019 Upload 1Desig n an d operatio n perspectiv e o f a Britis h UH V laborator

    17/21

    of long sparks and lightning discharges [29]. Later work

    was carried out on full-size aircraft radomes as fitted fore

    and aft to AEW Nimrods (UKAEA Culham being the

    main project contractor) to evaluate lightning protection

    (see Fig. 24). Further studies have recently been reported

    [31,32].

    For the economic accountability of an UHV laboratory,

    it is necessary to operate test programmes with very tight

    schedules leaving only very limited opportunity for investi-

    gating new testing techniques or carrying out maintenance.

    Preferably the latter should be carried out outside normal

    working hours. Nevertheless, new techniques must be

    regularly explored to keep the facilities competitive.

    For this reason, considerable laboratory time has been

    set aside recently for conjunctive impulse and power-

    frequency testing. After designing the necessary equipment

    for point-on-wave operation the following cases have been

    successfully studied:

    (a) AC and impulse applied to the same pole as for

    bushing CTs etc.

    b)

    AC and impulse applied to oppo site poles as with

    open breaks of a circuit breaker.

    7 Final comments and conclusions

    In recent years, the major emphasis in research and devel-

    opment has shifted from air blast to SF

    6

    -insulated live-

    tank and metalclad switchgear. This has been illustrated

    by the more fundamental work carried out during this

    period of SF

    6

    breakdown phenomena and on particulate

    initiated breakdown in SF

    6

    /solid insulation systems [7, 13,

    27, 28]. In addition, preparatory to new designs, extensive

    insulation co-ordination studies have been undertaken

    within this UHV laboratory and in collaboration with

    power-systems specialists.

    Because of the trend towards compact SF

    6

    switchgear,

    the electrical clearances available within the laboratory

    have been more than adequate. Consequently, it has

    proved possible to introduce additional dielectric facilities

    within the UHV laboratory complex for research,

    distribution equipment testing, insulation material evalu-

    ation with necessary ancillary mechanical/thermal proving

    capabilities [25, 36, 37]. This change from the original

    UHV laboratory design philosophy has resulted in estab-

    lishing a complete dielectric complex on one site, covering

    all ratings from distribution up to UHV transmission

    levels. These supplementary test facilities are illustrated in

    Appendix 10.1 with app ropriate explanatory captions.

    As discussed in Section 4, numerous technical problems

    have been encountered with laboratory test equipment,

    but the difficulties experienced have been of a minor

    nature rather than of fundamental importance. Moreover,

    the effectiveness of the laboratory has to be judged in rela-

    tion to what has been accomplished in the first 15 years

    approximately of its life, and the following achievements

    are here sum marised.

    (a) A major contribution to the fundamental develop-

    ment of 300, 420 and 525 kV SF

    6

    -rated switchgear by the

    dielectric evaluation of representative electrode arrange-

    ments of practical GIS.

    b)

    Type and proving tests on air-blast and SF

    6

    switch-

    gear, bushings etc. by extensive test programmes. Investi-

    gations into particulate contamination and potential

    causes of breakdown in SF

    6

    GIS.

    (c) Evaluation, backed up by computer techniques, of

    the high-voltage measurements carried out in the labor-

    atory. This work was necessary for establishing confidence

    in the high-voltage work undertaken and in the results

    obtained.

    d) Development of test equipment and test methods for

    RIV and partial discharge investigations and testing at

    very high voltages up to

    1

    MV RMS.

    e) Experimental techniques: design and fabrication of

    nozzles, support frames, automatic mixing plant for artifi-

    cial rain testing which can operate under continuous

    testing conditions and diversified test objects and develop-

    ment of conjunctive-impulse/power-frequency test pro -

    cedures and techniques.

    (/) Considerable diversification in the extensive work

    undertaken for outside customers has included:

    (i) tests on transmission-line hardware

    (ii) tower window for 765 kV transm ission lines

    (iii) performance of porcelain bushings etc. (inclined

    at various angles to the vertical) typical of outdoor

    transformers, subjected to rain and washing pro-

    grammes (or preapplied pollution)

    (iv) Lightning-strike studies on simulated scaled air-

    craft models followed by studies on full-scale radomes,

    as fitted to aircraft.

    In conclusion, the laboratory has been a very effective

    'tool' in the research, development and routine testing

    undertaken. The design of the laboratory layout has made

    it possible, in the last few years, to make useful additions

    to the facilities thus considerably increasing and extending

    the testing potential of the laboratory complex.

    From a national point of view, it is to be noted that this

    laboratory, and that at CERL Leatherhead represent in

    1986 the only UHV testing facilities available in the UK.

    This disappointing state of affairs, with consequential

    reduction in personnel expertise, compares very unfavour-

    ably with the testing and manpower resources available

    especially in Japan, Canada, France, Italy, Germany and

    the USSR.

    8 Acknowledgments

    The authors wish to thank the Directors of NEI Reyrolle

    Ltd., for permission to publish this paper. Thanks are also

    due to their former colleagues for their continued support

    and assistance over the years. The au tho rs gratefully

    acknowledge permission to reproduce extensively from

    laboratory contractual research studies undertaken for

    various organisations over the years and fully acknowl-

    edged in the original publication sources.

    9 References

    1 LEGG, D., RYAN, H.M., and WHISKARD, J. : 'A new Bri t ish ul t ra-

    high voltage laboratory'. Presented at IEEE Winter Power Meeting,

    New York, 1972, Paper C72 224-9. Also reviewed in

    Reyrolle Parsons

    Rev., summer 1971,1,(1), pp. 11-16

    2 R YAN, H.M., and WH ISKA RD , J. : 'Recent studies in the Clothier

    Labora tory ' , Reyrolle Parsons Rev.,winter 1974/75, 2, (2), pp. 2 4-28

    3 KARADY, G., HYLTEN-CAVALLIUS, N.: 'Electromagnet ic shield-

    ing of high voltage laboratories'. IEEE Trans. Paper 70 TP 604-PWR

    (1970).

    4 RYAN, H.M., and W ATS ON, W.L.: 'Electr ical breakd own and

    voltage-time characteristics in SF

    6

    at high pressures'. Presented at

    IEEE PES Summer Power Meet ing, Por t land Oregon, 1976, Paper

    F76 390-5. Based on paper presented at the Internatio nal High

    Voltage Symposium, Zurich, September 1975, pp. 12-18 (Annexe).

    Also reviewed in Reyrolle Parsons Rev., winter 1975/76, 2, (4), pp.

    24-28

    5 RYAN, H.M., WA TSO N, W.L., DAL E, S.J., TE DF OR D , D.J. ,

    KU RIM OT O, A., BAN FORD , H.M., and HA MP TO N, B.F.:

    'Factors affecting the insulation strength of SF

    6

    filled systems'.

    CIG RE , 1976, Pap er 15.02

    6 WAT SON , W.L., and RY AN, H.M.: 'Breakdown and vol tage- t ime

    IEE PROCEEDINGS, Vol. 133, Pt. A, No. 8, NOVEMBER 1986

    517

  • 8/10/2019 Upload 1Desig n an d operatio n perspectiv e o f a Britis h UH V laborator

    18/21

    character ist ics in SF

    6

    for voltages in the range 0.62M V , IEE Conf.

    Publ. 143,

    1976, pp. 153-156

    7 RYAN, H.M., and WATSON, W.L.: ' Impulse breakdown character-

    istics in SF

    6

    for non-uniform field gaps'. CIGRE, 1978, Paper 15.01

    8 RYAN, H.M., and WATSON, W.L.: 'Breakdown character ist ics in

    S F

    6

    for non-uniform field gaps and support insulation for voltages in

    the range 0.8-2 M V . Presented at 1976 IEEE Conference on Com mu-

    nicat ion and Power , M ontreal , October 1976, pp. 501-504

    9 RYAN, H.M., and MILNE, D.: 'Dielectr ic test ing of GIS: Review of

    test procedures and evaluat ion of test resul ts ' . CIGRE Colloquium,

    Edinburgh, 1983,

    SC33,

    Paper 33-83

    10 R YAN, H.M., M ILN E, D., and P OW EL L, C.W.: 'Si te testing and the

    evaluation of a technique to differentiate between a gas or spacer

    flashover in SF

    6

    GIS'. Presented at Symposium on Gas Insulated

    Substat ion Tech nology and Pract ice, Toro nto, Can ada, Septembe r

    1985,

    Paper K2

    11 RYAN, H.M., and MILNE, D.: 'Breakdown performance studies in

    S F

    6

    under clean and contaminated condi t ions' ,

    4th Int. Symp. HV

    Eng.,

    Athens , 1983, Pap er 34-12

    12 RYAN, H.M., ALI, S.M.G., and POWELL, C.W.: 'Field computat ion

    relating to switchgear design',

    Ibid.,

    Pape r 12-12

    13 RYAN , H.M., LIGH TL E, D., and M ILN E, D.: 'Factors influencing

    dielectric performance of SF

    6

    insulated GIS', IEEE Trans., 1985,

    PAS-104 (6), pp. 1527-1535

    14 RYAN , H.M., and PO WE LL , C.W.: '50 Hz breakdown character-

    istics of long air gaps'.

    IEE Conf. Publ. 90,

    1972, pp. 30-32

    15 RYAN, H.M. , WATSO N, W.L. , HO GG , W.D. , and RITC HIE, W .M.:

    'Effects of system overvoltages on insulation coordination require-

    ments for EHV open type and metalclad installations'. Presented at

    Internat ional Conference on the Design and Appl icat ion of EHV Sub-

    stat ions, London, 22-24th November 1977

    16 WATSON, W. , HOWIE, R.B. , RYAN, H.M. , IRWIN, T . , HOGG,

    W.D., and PETTY, H.C.: ' Insulat ion coordinat ion of a 420 kV SF

    6

    insulated substat ion in the UK'. CIGRE, 1984, Paper 33.05

    17 RYAN, H.M., FLYNN, A, and WATSON, W.: 'Vol tage- t ime charac-

    teristics of long air-gaps'. Presented at 8th International GDC,

    Oxford, Septemb er 1985, pp. 368-373

    18 W AT SON , W., FL YN N, A., IRW IN, T., and RYAN , H.M .: 'Determi-

    nation of the voltage/time characteristics of rod gaps etc.'. CIGRE,

    1986,

    Pa pe r 15.05

    19 RYAN, H.M., and MATT1NGLEY, J.M.: 'Salt-fog artificial pollution

    val idat ion studies' , Proc. IEE, 1970, 117 (7), pp. 1389-1392

    20 ELLIS, N.S. , LU GT ON , W.T., POWEL L, C.W. , and RYAN , H.M. :

    'Special spark-gap switches for use in synthetic test circuits'. Presented

    at IEEE Winter Power Meet ing, New York, 1972, Paper T72 051-6.

    Subsequent ly publ ished in

    IEEE Trans.,

    1972,PAS-91 pp. 2020-2025

    21 RIC HA RD SO N, A.V., and RYA N, H.M .: 'Comp uter aided analysis

    of an impulse voltage measuring system'. Presented at International

    Sym posiu m: High Vol tage Technology, Munich, March 1972, pp.

    245-251. Also presented at IEEE PES Summer Meet ing, Vancouver ,

    Canada, 1973, Paper C73 345-6

    22 RYA N, H.M., EL LIS, N.S., and B ELL, W.R.: 'Case for a UK co l labo-

    rative research strategy using major industrial laboratory facilities'.

    Presented at 17th Universities Power Engineering Conference,

    UMIST, Manchester , 30th March 1982-1 Apri l 1982

    23 RYAN, H.M. : 'SF

    6

    switchgear further developments', Reyrolle

    Parsons Rev.,

    sum mer 1977, 3, (1), pp. 1-8

    24 BALL, E.H., RICHARDSON, A.V., and RYAN, H.M.: 'Terminat ions

    used in EHV metalclad substations'. Presented at IEE International

    Conference on the Design and Application of EHV Substations,

    Londo n, 22-24 th Novem ber 1977, pp. 134-139

    25 RYAN, H.M., LIGH TLE , D., HEA DLE Y, P. , and K ELSE Y, T.:

    'Engineering considerations relating to EHV metalclad switchgear for

    currents up to 63 kA'. CIGRE, 1980, Paper 13.02

    26 RYAN, H.M.: 'Applications of gaseous insulants'. Presented at IEE

    Summer School on Electrical insulation-measurements design and

    materials for power engineering, University of Salford,

    5-8th

    Septem-

    ber 1983, Chap. 6. Also in B RAD WE LL , A. (Ed.): 'Electrical insula -

    tion'(Peter Peregrinus Ltd., UK, 1983)

    27 ALI, S.M.G., RYAN, H .M., LIG HT LE , D., SHIM MIN , D.,

    TAYLOR, S., and JONES, G.R.: 'High power short circuit studies on

    a commercial 420 kV, 60 kA puffer circuit breaker',

    IEEE Trans.,

    1985,PAS-104 (2), pp. 459-* 68

    28 RYAN, H.M., and JONES, G.R.: IEE Review on SF

    6

    Switchgear

    (Paper in preparation, commissioned by IEE)

    29 PH ILL POT T, J. , LITTLE , P. , WHIT E, E.L., RYAN, H .M.,

    POWELL, C.W., DALE, S.J. , AKED, A., TEDFORD, D.J. , and

    WATERS, R.T.: 'Lightning strike point location studies on scale

    models'. Presented at International Lightning and Static Electricity

    Conference, Culham Laboratory, United Kingdom, April 1975

    30 POWELL, C.W., and RYAN, H.M.: 'Switching impulse strength of a

    765 kV simulated tow er window with V-string insulators under artifi-

    cial rain'. Presented at 3rd International Symposium on High Voltage

    Engineering, Milan, August 1979, Paper 52.11

    31 BISHO P, J. , AK ED , A., PO WE LL , C.W., and RYAN, H.M.: 'Aspects

    of lightning protection schemes for radomes'. Presented to Interna-

    tional Aerospace and Group Conference on Lightning and Static

    Electricity, Paris, Franc e, 1 0-1 lth J une 1985, pp. 499-507

    32 AKED, A., POWELL, C.W., RYAN, H.M., and BISHOP, J. : 'Aspects

    of lightning protection schemes for radomes'. Presented at 8th Inter-

    national GD C, Oxford, Septemb er 1985, pp. 372-375

    33 GREENWAY, R., and RYAN, H.M.: 'Modern developments in the

    insulation of switchgear components'.

    IEE Conf. Publ. 83,

    (I), pp. 122-

    127.Also D iscussion (2), pp . 54 -55

    34 RYAN, H.M., WAUGH, R.A., and GREENWAY, R.: 'An appraisal

    of realistic discharge levels for high voltage switchgear'. Presented

    at BEAMA 2nd International Electrical Insulation Conference,

    Brighton, May 1974, pp. 271 -280

    35 RYAN, H.M., GREENWAY, R., and POWELL, C.W.: 'Inst rument

    transformers for modern EHV substations'. Presented at BEAMA 3rd

    International Conference, Brighton, Ma y 1978, pp. 170-180

    36 POWELL, C.W., MILNE, D., and RYAN, H.M.: 'The appl icat ion of

    RBGF and solid dielectric materials in modern switchgear'. Presented

    at BEAMA Insulation Conference, Brighton, May 10th-13th 1982

    37 MILNE, D., and RYAN, H.M.: 'The evaluation of solid dielectric

    systems for use in high voltage switchgear',

    IEE Conf. Publ. 239,

    1984,

    pp .76-79

    38 ZAENGL, W.: The impulse voltage divider with h.t. lead', Bull. ASE,

    1970,61, (12), pp. 1003-1017

    39 ZAENGL, W., and FESER, K.: 'Contr ibut ion to the calculat ion of

    the transmission behaviour of impulse voltage dividers',

    ibid.,

    1964, 55,

    (25),p . 1249

    40 ZAENGL, W.: 'A new divider for steep impulse voltages',

    ibid.,

    1965,

    56 ,p . 23 2

    41 Working Group

    33.03:

    'Record of performance of voltage and current

    measuring systems',

    Electro,

    1981, 78, pp. 35-69

    F i g . 2 5 Views of insulation research test facilities installed in main XJHV hall south wall F )

    518

    IEE PROCEEDINGS, Vol. 133, Pt. A, No. 8, NOVEMBER 1986

  • 8/10/2019 Upload 1Desig n an d operatio n perspectiv e o f a Britis h UH V laborator

    19/21

    Fig . 27

    View of insulation materials evaluation laboratory showing

    ovens and samples prior to test G)

    Fig . 26

    Endurance/accelerated frequency test area

    (/)

    Fig . 28

    Views of 250 kV discharge test area K)

    Fig . 29

    Mechanical and thermal test area

    (L)

    IEE PROCEEDINGS, Vol. 133, Pt. A, No. 8, NOVEMBER 1986

    Fig. 30 500

    kV im pulse test laboratory H)

    519

  • 8/10/2019 Upload 1Desig n an d operatio n perspectiv e o f a Britis h UH V laborator

    20/21

    10 Appendix

    10.1

    Supplementary

    test facilities

    Following laboratory reorganisation in 1980 three addi-

    tional test areas were established within the main hall of

    the UHV laboratory, without effectively reducing the effi-

    ciency and usefulness of the main area. In addition, a

    multipurpose mechanical/thermal/dielectric area was

    established in the erection bay; insulation material

    research areas, suitable for endurance and accelerated fre-

    quency testing, were also established within the UHV

    laboratory precinct. Examples of these supplementary

    facilities are given in Figs.2531.Identification letters F -L

    refer to Fig.2a .

    10.2

    High voltage

    facilities

    a t

    NEI

    Reyrolle Hebburn

    10.2.1 Laboratory dimensions and facility data: Th e

    main test plant and equipment are detailed below and

    illustrated in Figs. 2, 3, 5-8, 17 -19.

    Fig. 31 Examples of thermal, mechanical and dielectric testing

    a View of SF

    6

    insulated mctalclad switchgear assembled for thermal testing (L).

    Close proximity of main UHV hall makes it very convenient to carry out dielectric

    tests on the thermal test arrangement if required.

    b

    Modern 420 kV SPD (4 break) metalclad circuit breaker set up in mechanical/

    electrical test hall for mechanical endurance type testing. Vertically mounted por-

    celain inlet bushing and voltage transformer are shown connected to the circuit

    breaker for these tests.

    c 420 kV SPD (2 break) circuit breaker inside an environmental test chamber with

    range 40 to 50C (L). Studies also included power-frequency dielectric testing

    and video filming

    for particulate count.

    d, e Views of 420 kV (2 break) dead-tank circuit-breaker assembly (mounted for

    outdoor mechanical type testing) (2000 operations). Studies also included power-

    frequency dielectric testing and video filming

    for particulate count.

    1EE PROCEEDINGS, Vol. 133, Pt. A, No. 8, NOVEMBER 1986

  • 8/10/2019 Upload 1Desig n an d operatio n perspectiv e o f a Britis h UH V laborator

    21/21

    JO.2.1.1

    Indoor laboratory:

    (i) Maximum internal clearance 48.7 m x 33.5 m x 32

    m (high) (provision/space to extend southern facing wall by

    at least 24.4 m)

    (ii) do or openin g 11.7 m x 18.9 m (high)

    (iii) overhead cran e 7.1 tonnes (7 tons)

    (iv) mobile cra nes

    (v) floor loading 21.9 tonnes/m

    2

    (2 ton/sq. ft.)

    (vi) Maximum tension for overhead line and insulator

    tests 10.1 tonnes

    (vii) Underground oil storage tanks (136 m

    3

    (30000

    gallons)), pumping station, streamline purifier and condi-

    tioner

    (viii) main oil test tank (127 m

    3

    (28000 gallons)) suit-

    able for oil impregnation and testing of transformer insula-

    tion and for complete bushings, testing up to 765 kV

    rating

    (ix) wet test equipment. Testing in accordance with IEC

    60 etc. on complete assemblies of 420/525 kV open termin-

    al and metalclad switchgear, disconnectors, transformer

    bushings transmission towers/lines and hardware etc. (e.g.

    Figs.

    5,15)

    (x) compressed air supplies

    (xi) SF

    6

    handling equipment

    (xii) various compressed-gas test vessels for GIS studies

    at voltages 2.8 MV and pressures up to 8 x 10

    5

    N /m

    2

    (gauge).

    10.2.1.2 Erectionbay:(Figs. 2, 29, 31a)

    (i) maximum internal clearance 10.5 m x 15 ra x 15.6 m

    (high)

    (ii) various transformers for thermal testing switchgear

    panels, GIS or for cables etc. for AC and DC type testing

    (iii) mechanical/thermal test capability in this area with

    ready access to HV supplies from main test hall.

    10.2.1.3 Outdoor laboratory:(see Figs. 2, 3a, 3Id,e)

    (i) concrete are a 15.3 m x 24.4 m.

    (ii) Flat grass/concrete area adjacent to both high-

    voltage and short-circu it facilities 150 m x 60 m

    approx imately (see Figs. 2c, 31c).

    10.2.2

    High

    voltage

    equipment:

    10.2.2.1 Directvoltage tests:

    (i)

    1

    MV generator

    (ii) 2 MV generator capability produced from exist-

    ing 4 MV impulse generator

    (iii)

    1

    MV wire-wound resistor divider

    (iv) electrometers for low current measurements etc.

    10.2.2.2 Power-frequency

    tests:

    (i) 2 MV, 3.2 MVA transformers (see Figs.

    2d,

    3)

    (ii) 2 x 0.5 MV, 500 kVA transformer (cascaded units)

    (iii) 250 kV, 100 kVA transformer

    (iv) 200 kV, 20 kVA transformer

    (v) various shielded gas capacitors up to 1.2 M V

    (vi) compensated capacitor divider up to 2.0 MV

    (vii) various Schering bridges (up to 200 kV)

    (viii) RIV test set

    (ix) partial discharge detectors.

    10.2.2.3Impulsevoltagetests:

    (i) 4 MV, 150 kJ generator (see Figs. 2d , 3) (could be

    extended to 5.6 MV)

    (ii) 800 kV, 9.5 kJ generator

    (iii) 600 kV, 4.2 kJ generator

    (iv) bias (impulse/AC) test con trols

    (v) 4 MV compensated capacitor divider with series-

    distributed resistors (see Figs.Id ,3c)

    (vi) 1.2 MV capacitive graded resistor divider

    (vii) impulse oscilloscopes

    (viii) digital transien t recorders

    (ix) various uniform field and sphere gaps

    (x) pressurised measuring spark gaps

    (xi) specialised screened room, suitable for detailed gas

    prebreakdown studies

    (xii) Digital support: programs for statistical analysis of

    test results, for electric field evaluation of test objects, and

    for step response evaluation of laboratory test circuits.

    Also a suite of power-system analysis programs available

    for analysing laboratory switching studies involving surge

    arresters, switchgear etc.

    1EE PROCEEDINGS Vol. 133 Pt. A No. 8 NO VEMBER 1986