45
University of Saskatchewan University of Saskatchewan Geological Engineering Geological Engineering GEOE 498.3 GEOE 498.3 Introduction to Mineral Engineering Introduction to Mineral Engineering

University of Saskatchewan Geological Engineering GEOE 498.3 Introduction to Mineral Engineering

  • Upload
    masako

  • View
    51

  • Download
    0

Embed Size (px)

DESCRIPTION

University of Saskatchewan Geological Engineering GEOE 498.3 Introduction to Mineral Engineering. Lecture # 3. Production Rate Productivity Stope Production Mine Production U/G Infrastructure. Productivity vs. Production. - PowerPoint PPT Presentation

Citation preview

Page 1: University of Saskatchewan Geological Engineering GEOE 498.3 Introduction to Mineral Engineering

University of SaskatchewanUniversity of Saskatchewan

Geological EngineeringGeological EngineeringGEOE 498.3GEOE 498.3

Introduction to Mineral EngineeringIntroduction to Mineral Engineering

Page 2: University of Saskatchewan Geological Engineering GEOE 498.3 Introduction to Mineral Engineering

Lecture # 3Lecture # 3

Production RateProduction RateProductivityProductivityStope ProductionStope ProductionMine ProductionMine Production

U/G InfrastructureU/G Infrastructure

Page 3: University of Saskatchewan Geological Engineering GEOE 498.3 Introduction to Mineral Engineering

Productivity vs. ProductionProductivity vs. Production Productivity is the rate at which a task is Productivity is the rate at which a task is

completed or ore is produced. In mining it is completed or ore is produced. In mining it is usually reported in units per machine or man usually reported in units per machine or man hour.hour.Drilling: metres per drill - HourDrilling: metres per drill - HourMucking: Tonnes per LHD - HourMucking: Tonnes per LHD - HourDevelopment: metres per man-shift.Development: metres per man-shift.

Production is the total amount produced. In Production is the total amount produced. In mining it is usually the total production per day, mining it is usually the total production per day, week, month or year.week, month or year.

Page 4: University of Saskatchewan Geological Engineering GEOE 498.3 Introduction to Mineral Engineering

Determining Productivity and ProductionDetermining Productivity and Production

Rule’s of ThumbRule’s of Thumb

Benchmarking Benchmarking

Historical DataHistorical Data

Equipment SpecificationsEquipment Specifications

First Principle CalculationsFirst Principle Calculations

Page 5: University of Saskatchewan Geological Engineering GEOE 498.3 Introduction to Mineral Engineering

Rule of Thumb

Rule of Thumb – An easy to remember guide that falls somewhere between an engineered solution and an experienced or educated guess.

Are the Rules always correct? Absolutely no. Can they provide a quick answer or a starting place? Absolutely yes.

The primary usage of Rules of Thumb should be in the development of conceptual designs and feasibility studies or, when a quick decision is required in the solution of an operating problem.

When the time arrives for final design and actual construction, Rules of Thumb are no substitute for sound engineering practices.

Page 6: University of Saskatchewan Geological Engineering GEOE 498.3 Introduction to Mineral Engineering

Productivity - Rule’s of ThumbProductivity - Rule’s of ThumbActivity Measurement ProductivitySink timber shaft m/day 2 - 2.8Sink bald concrete shaft m/day 3 - 4Sink equipped concrete shaft m/day 2.4 - 3.6Equip concrete shaft m/day 10 - 15Cut shaft stations - slusher cu m/day 50 - 65Cut shaft stations – LHD 65 - 95Drive raw raises up to 10 m m/m-sh 0.5 - 0.7Drive timbered raises m/m-sh 0.45 - 0.6Drive alimak raises m/m-sh 0.75 - 1.0Raise bore drill

Set up days 2 - 5Drill Pilot m/day 20 - 25Ream m/day 7 - 10

Track drift m/m-sh 0.5 - 0.75Trackless Drift m/m-sh 0.65 - 1.0Ramp m/m-sh 0.55 - 0.8Drill and Install Rock Bolts (stoper) m/m-sh 45 - 60Drill and Install Rock Bolts (mobile) m/m-sh 100 - 125Drill Jack Leg m/m-sh 10 - 15Drill Stoper m/m-sh 8 - 12Drill Jumbo m/m-sh 75 - 100Drill Tophammer (small diameter < 76mm) m/machine-shift 75 - 120Drill Tophammer (large diameter > 105mm) m/machine-shift 25 - 50Drill ITH m/machine-shift 25 - 50

Page 7: University of Saskatchewan Geological Engineering GEOE 498.3 Introduction to Mineral Engineering

Mucking Mucking ProductivityProductivity

Page 8: University of Saskatchewan Geological Engineering GEOE 498.3 Introduction to Mineral Engineering

Productivity - DrillingProductivity - Drilling

Page 9: University of Saskatchewan Geological Engineering GEOE 498.3 Introduction to Mineral Engineering

Productivity - DrillingProductivity - Drilling

Page 10: University of Saskatchewan Geological Engineering GEOE 498.3 Introduction to Mineral Engineering

Mucking Productivity - TruckingMucking Productivity - Trucking

Page 11: University of Saskatchewan Geological Engineering GEOE 498.3 Introduction to Mineral Engineering

Mucking Productivity Large ScoopMucking Productivity Large Scoop

Page 12: University of Saskatchewan Geological Engineering GEOE 498.3 Introduction to Mineral Engineering

BenchmarkingBenchmarking

Gathering information and statistically analyzing Gathering information and statistically analyzing how other similar operation are performing.how other similar operation are performing.ProductionProductionProductivityProductivityCostCostSafetySafety

Information is not always readily available.Information is not always readily available.

Must ensure that orebody, skill of labour, work Must ensure that orebody, skill of labour, work organization, consumable costs, etc. are in fact organization, consumable costs, etc. are in fact similar.similar.

Page 13: University of Saskatchewan Geological Engineering GEOE 498.3 Introduction to Mineral Engineering

BenchmarkingBenchmarking

Page 14: University of Saskatchewan Geological Engineering GEOE 498.3 Introduction to Mineral Engineering

First Principle CalculationsFirst Principle Calculations

Zero based calculations where the Zero based calculations where the production or productivity estimate is production or productivity estimate is created by the mine engineer.created by the mine engineer.

Typically used at the detailed design Typically used at the detailed design stage.stage.

Equipment specifications, quotations, Equipment specifications, quotations, detailed drawings, established detailed drawings, established engineering practices form the bases.engineering practices form the bases.

Page 15: University of Saskatchewan Geological Engineering GEOE 498.3 Introduction to Mineral Engineering

Equipment ManufacturerEquipment Manufacturer

Equipment Manufacturers have detailed Equipment Manufacturers have detailed specifications for their equipment that specifications for their equipment that will provide data on:will provide data on:ProductivityProductivityEnergy consumptionEnergy consumptionWater ConsumptionWater ConsumptionCompressed AirCompressed AirSize of OpeningsSize of OpeningsWeightsWeights

Page 16: University of Saskatchewan Geological Engineering GEOE 498.3 Introduction to Mineral Engineering

Equipment ManufacturerEquipment Manufacturer

The specifications are typically derived under The specifications are typically derived under ideal conditions.ideal conditions.

The mine engineer must factor in site specific The mine engineer must factor in site specific conditions such as:conditions such as:Skill of work forceSkill of work forceEnvironment (heat, depth, humidity)Environment (heat, depth, humidity)Condition of openingsCondition of openingsHardness of rockHardness of rockMaintenanceMaintenanceAvailability and UtilizationAvailability and Utilization

Play LHD VideoPlay LHD Video

Page 17: University of Saskatchewan Geological Engineering GEOE 498.3 Introduction to Mineral Engineering

First Principle First Principle Shotcrete Shotcrete

CalculationCalculation

Input Data

Arch back is assumed. 20%Roughage Factor 20%Rebound Factor 20%Overlap Factor 0.5 mDrift width 4.5 mDrift height 4.5 mRound length 3.2 mShotcrete thickness 3.0 inShotcrete Height from Floor 1.5 m

Calculated DataShoulder Height 3.60 mBack Arc Length ... 4.97 mPerimeter Coverage of Shotcrete 9.2 mShotcrete thickness 0.0762 m

Results

Theoretical volume 2.58 m^3Actual volume considering overlap, surface roughness and rebound 3.72 m^3

Page 18: University of Saskatchewan Geological Engineering GEOE 498.3 Introduction to Mineral Engineering

Productivity Mucking EquipmentProductivity Mucking Equipment

Page 19: University of Saskatchewan Geological Engineering GEOE 498.3 Introduction to Mineral Engineering

Mucking Productivity - TruckingMucking Productivity - Trucking

Page 20: University of Saskatchewan Geological Engineering GEOE 498.3 Introduction to Mineral Engineering

Productivity Drill EquipmentProductivity Drill Equipment

Page 21: University of Saskatchewan Geological Engineering GEOE 498.3 Introduction to Mineral Engineering

Tunneling EquipmentTunneling Equipment

Page 22: University of Saskatchewan Geological Engineering GEOE 498.3 Introduction to Mineral Engineering

Historical DataHistorical Data

Usually applies to existing operations and Usually applies to existing operations and is used to forecast production and create is used to forecast production and create annual operating budgets.annual operating budgets.If a site does things the way they If a site does things the way they

always did, can expect the same always did, can expect the same results.results.

Data gathered from time studies.Data gathered from time studies.

May also be used when estimating May also be used when estimating productivity, production and costs for an productivity, production and costs for an expansion.expansion.

Page 23: University of Saskatchewan Geological Engineering GEOE 498.3 Introduction to Mineral Engineering

SummarySummary In most estimating situations a combination of In most estimating situations a combination of

history, benchmarking, rule of thumb and first history, benchmarking, rule of thumb and first principle calculations are used.principle calculations are used.

CAUTION: in mining CAUTION: in mining “stuff happens”“stuff happens” It is important It is important to build efficiency factors and reality into the estimate.to build efficiency factors and reality into the estimate.Types of Delays:Types of Delays:

• Gas Check• Equipment down• Ground Conditions• No Materials• Surveying• Air, water, vent, power• Travel and Breaks

Page 24: University of Saskatchewan Geological Engineering GEOE 498.3 Introduction to Mineral Engineering

Equipment AvailabilityEquipment AvailabilityAvailability (Operational Availability) It is the probability that an item will operate satisfactorily at a given point in time when used in

an actual or realistic operating environment. Includes all sources of downtime, (administrative, logistic as well as actual time to repair) Operational availability is used to isolate the effectiveness and efficiency of maintenance

operations. Operational availability can be calculated on a calendar basis or on a scheduled work basis. Uptime Equipment is available to the operators Total Time Based on 24-7, i.e. 168 hours in a week Scheduled Time Based on work schedule, i.e. 2x10hr shifts per day 7 days per week = 140

hours /week

AOT = Total Operational Availability = uptime/total time AOE = Effective Operational Availability = uptime/scheduled time Rule of Thumb - New and/or well maintained equipment will have 80-

90% effective availability

Page 25: University of Saskatchewan Geological Engineering GEOE 498.3 Introduction to Mineral Engineering

Equipment UtilizationEquipment Utilization

Utilization Utilization is defined as the percentage of time in which equipment is in production. In other

words production is not prevented by equipment malfunction, operating delays, or scheduled downtimes.

Utilization is used to isolate the effectiveness and efficiency of mine operations.

UT = Total Utilization = equipment operating time/total time US = Effective Utilization = equipment operating time/scheduled time UA = Actual Utilization = equipment operating time/uptime

Rule of Thumb - New and/or well maintained equipment should have 60-70% effective utilization

Page 26: University of Saskatchewan Geological Engineering GEOE 498.3 Introduction to Mineral Engineering

Equipment ReliabilityEquipment Reliability

ReliabilityReliability: is the probability that a piece of equipment or : is the probability that a piece of equipment or system will perform its required function under stated system will perform its required function under stated conditions for a stated period of time.conditions for a stated period of time.

MTBF: Mean Time Between Failures – how long a piece of MTBF: Mean Time Between Failures – how long a piece of equipment or system will operate before it fails.equipment or system will operate before it fails.

TTR : Time to repairTTR : Time to repair

Preventative Maintenance : routinely schedule equipment Preventative Maintenance : routinely schedule equipment for service and inspection of key componentsfor service and inspection of key components

Predictive Maintenance : Schedule changeout of key Predictive Maintenance : Schedule changeout of key components and major overhauls or rebuilds prior to components and major overhauls or rebuilds prior to equipment failure.equipment failure.

Page 27: University of Saskatchewan Geological Engineering GEOE 498.3 Introduction to Mineral Engineering

Example 1Example 1

Estimate development advance and metres per Estimate development advance and metres per manshift in a typical developmentmanshift in a typical development

Assumptions:Assumptions:RMR : Very StrongRMR : Very Strong2 man Crew,2 man Crew,2 boom Jumbo, stoper for ground support, 2 boom Jumbo, stoper for ground support,

med sized scoopmed sized scoopRound size is 5x5x3.5Round size is 5x5x3.5Drill pattern requires 65 holesDrill pattern requires 65 holesBolting pattern is 1.5x1.5 and 2m long boltsBolting pattern is 1.5x1.5 and 2m long bolts

Page 28: University of Saskatchewan Geological Engineering GEOE 498.3 Introduction to Mineral Engineering

Example 1Example 1

Page 29: University of Saskatchewan Geological Engineering GEOE 498.3 Introduction to Mineral Engineering

Estimating Mine ProductionEstimating Mine Production

Taylor’s Rule is a means of estimating Mine Life Taylor’s Rule is a means of estimating Mine Life and Daily Production. It has been calibrated and Daily Production. It has been calibrated against many mines over several years and is against many mines over several years and is adequate for pre-feasibility level estimates.adequate for pre-feasibility level estimates.

L=0.2TL=0.2T0.250.25

PR=T/(LxDPY) PR=T/(LxDPY) Where

L=Mine LifeT=Resource (inc. Dilution and Recovery)

PR=Daily ProductionDPY=Scheduled Days Per Year

Page 30: University of Saskatchewan Geological Engineering GEOE 498.3 Introduction to Mineral Engineering

Example 2Example 2

Orebody A is 2 000 000 tOrebody A is 2 000 000 t The expected Recovery is 90% and dilution is The expected Recovery is 90% and dilution is

estimated at 20%, therefore the Resource = 2mt estimated at 20%, therefore the Resource = 2mt x .9 x 1.2 = 2.16 mtx .9 x 1.2 = 2.16 mt

L=0.2TL=0.2T0.250.25

L = 0.2 x (2 160 000)L = 0.2 x (2 160 000)0.250.25

L = 7.7 yearsL = 7.7 years If the mine is scheduled to operate 350 days per If the mine is scheduled to operate 350 days per

year, then the daily production is year, then the daily production is PR=T/(LxDPY)PR=T/(LxDPY)PR=2 160 000/(7.7 x 350)PR=2 160 000/(7.7 x 350)PR ~ 800 tpdPR ~ 800 tpd

Page 31: University of Saskatchewan Geological Engineering GEOE 498.3 Introduction to Mineral Engineering

Example 3Example 3

Orebody B is 20 000 000 tOrebody B is 20 000 000 t The expected Recovery is 80% and dilution is The expected Recovery is 80% and dilution is

estimated at 10%, therefore the Resource = 20mt estimated at 10%, therefore the Resource = 20mt x 0.8 x 1.1 = 17.6 mtx 0.8 x 1.1 = 17.6 mt

L=0.2TL=0.2T0.250.25

L = 0.2 x (17 600 000)L = 0.2 x (17 600 000)0.250.25

L = 12.95 yearsL = 12.95 years If the mine is scheduled to operate 350 days per If the mine is scheduled to operate 350 days per

year, then the daily production is year, then the daily production is PR=T/(LxDPY)PR=T/(LxDPY)PR=17 600 000/(12.95 x 350)PR=17 600 000/(12.95 x 350)PR ~ 3900 tpdPR ~ 3900 tpd

Page 32: University of Saskatchewan Geological Engineering GEOE 498.3 Introduction to Mineral Engineering

Example 4Example 4

Orebody A is a nearly vertical quartz vein Orebody A is a nearly vertical quartz vein containing 0.25 oz gold per tonne (insitu). It is a containing 0.25 oz gold per tonne (insitu). It is a tabular, deposit that measures 215 metres on tabular, deposit that measures 215 metres on strike, 240 m high and 15m thick. It has a strong strike, 240 m high and 15m thick. It has a strong ore and f/w and a week h/w. The top of the ore and f/w and a week h/w. The top of the orebody is 200 metres below surface and the orebody is 200 metres below surface and the bottom is 440 metres below surface. Both ore bottom is 440 metres below surface. Both ore and waste have a SG of 2.6 t/mand waste have a SG of 2.6 t/m33

The chosen mining method is Transverse The chosen mining method is Transverse Mechanized Cut and Fill.Mechanized Cut and Fill.

Stope dimensions Have been established as 7m Stope dimensions Have been established as 7m wide x 24m high x 15 m longwide x 24m high x 15 m long

Page 33: University of Saskatchewan Geological Engineering GEOE 498.3 Introduction to Mineral Engineering

Example 4Example 4

Determine:Determine:Average tonnes per day per stope of Average tonnes per day per stope of

ore and waste.ore and waste.Number of stopes required to meet Number of stopes required to meet

daily production target.daily production target.The truck fleet size.The truck fleet size.

Page 34: University of Saskatchewan Geological Engineering GEOE 498.3 Introduction to Mineral Engineering

Example 5Example 5

Orebody B is a thick, tabular steeply dipping Orebody B is a thick, tabular steeply dipping Nickel deposit with a diluted grade of 3% Ni. It Nickel deposit with a diluted grade of 3% Ni. It averages 330 metres on strike, 400 m high and averages 330 metres on strike, 400 m high and 40m thick. It has a strong ore and h/w and a 40m thick. It has a strong ore and h/w and a moderate f/w. The top of the orebody is 100 moderate f/w. The top of the orebody is 100 metres below surface and the bottom is 500 metres below surface and the bottom is 500 metres below surface. The recovered ore has an metres below surface. The recovered ore has an S.G. of 3.8 and the waste has an SG of 2.6 t/mS.G. of 3.8 and the waste has an SG of 2.6 t/m33

The chosen mining method blasthole stoping The chosen mining method blasthole stoping with paste fillwith paste fill

Stope dimensions Have been established as 15m Stope dimensions Have been established as 15m wide x 32.5m high x 20m longwide x 32.5m high x 20m long

Page 35: University of Saskatchewan Geological Engineering GEOE 498.3 Introduction to Mineral Engineering

Example 5Example 5

Determine:Determine:Average tonnes per day per stope of Average tonnes per day per stope of

oreoreNumber of stopes required to meet Number of stopes required to meet

daily production target.daily production target.If 30 metres of development is If 30 metres of development is

required to access each stope, required to access each stope, calculate tonnes of waste per daycalculate tonnes of waste per day

Page 36: University of Saskatchewan Geological Engineering GEOE 498.3 Introduction to Mineral Engineering

SequencingSequencing

Once the number of stopes are Once the number of stopes are determined, they need to be sequenceddetermined, they need to be sequenced

Considerations:Considerations:StressStressVoidsVoidsFill Cure TimeFill Cure TimeLogistics (congestion on a level)Logistics (congestion on a level)VentilationVentilationCapital or access developementCapital or access developement

Page 37: University of Saskatchewan Geological Engineering GEOE 498.3 Introduction to Mineral Engineering

Chevron & Primary/Secondary Mining Chevron & Primary/Secondary Mining

2

3

78

11

2

8

Primary Stopes

Secondary Stopes 6

7

9

12

17

1 5

4 1011

13

14

15

16

STRIKE

Page 38: University of Saskatchewan Geological Engineering GEOE 498.3 Introduction to Mineral Engineering

Mining SequenceMining Sequence

Sill level

1

Sill level P PP S S

Page 39: University of Saskatchewan Geological Engineering GEOE 498.3 Introduction to Mineral Engineering

Mining SequenceMining Sequence

Sill level

1

Sill level P PP S S

2

Page 40: University of Saskatchewan Geological Engineering GEOE 498.3 Introduction to Mineral Engineering

Mining SequenceMining Sequence

Sill level

1

Sill level P PP S S

2

33

Page 41: University of Saskatchewan Geological Engineering GEOE 498.3 Introduction to Mineral Engineering

Mining SequenceMining Sequence

Sill level

1

Sill level P PP S S

2

33

4

Page 42: University of Saskatchewan Geological Engineering GEOE 498.3 Introduction to Mineral Engineering

Mining SequenceMining Sequence

Sill level

1

Sill level P PP S S

2

33

4

5 5

Page 43: University of Saskatchewan Geological Engineering GEOE 498.3 Introduction to Mineral Engineering

Mining SequenceMining Sequence

Sill level

1

Sill level P PP S S

2

33

4

5 5

66

Page 44: University of Saskatchewan Geological Engineering GEOE 498.3 Introduction to Mineral Engineering

SequencingSequencing

86

87

88

90

91

92

94

122

120

S38

968 948

S48

S28S18S08

125 105 085 066 988

102

100

082

080

062

967 9472011

987

006 986 966 946

060

042

040

025022

005002001

123 103 084 065 045 028 008

985982981

965962961

945942941

905

S49S39S29S19

S17S07

S09

123121

103101

S47 S48926 S27 S28

083081

063 S27002964

943061 041 021 001

043044

025024

005

122 102 082 064 044 027 007

004

043 023

044

984983982981

985 965

963962961

945944

2007

2008

2009

902

S26

S06

S25

S05

121

104103

945

S26948947946

967

922

942941

987 966

S06S16S36

984983 961 941

985 965 946984 964 945 925

103 084 064 026 006 946964 944 924963 943

969968

121 101 081 063 S17

S37 S38S27 S28S17

923

S18

122 083 063 007

962

989988987

986

003

008

121 101 081 061 043

S08

S18

S49S39S29

S07

009008

961 941 921 S07080 062 981

029

023022

S49S39S29

026023

009

102101

084083082

067

064

049047

2010

045043041

029028027 007

006003

989988987986

041

068067066

060

048047046043

966965

946945

969

967949947

086085084083

S48S38S28S18S08

S57S47S27

S49S39S29S19S09

080

106105104101

S27125123143

2006

S49

S29S19S09

S27

S58

S28S18

949948947946945

989988

984

969968967

005

029028

025

009008

006

068067066

049045044043

085

107106105

087086

123

144143

127126124

925

Page 45: University of Saskatchewan Geological Engineering GEOE 498.3 Introduction to Mineral Engineering

Mine D - Schematic Longitudinal SectionPanels

Levels

68 68-SL4 68-SL3 68-SL268-SL168-GW1b 68-GW1a

69

70

71

73H1 2007

H2 2007

74 H1 2008

919 H2 2008918 897917 896 H1 2009

75

77

78

79

80

82

0 GW81 GW723

83 4

84

86

87

88

H1 2007

H2 200790

H1 2008

H2 2008

91 H1 2009

GW4

S46S36

GW6

GW2

074

012015 976

073072

055

071

074093092

073

S0FS0Y

936 877 857 S35 S25

GW5GW4

GW6

GW5

GW5

GW6B

S14

GW3

S14s24s34

S15

S0I

GW4

GW6GW5GW4S0ES0X

GW6

GW4

S23 s24

s44/54

S25S35

GW4

12A

120

10A082

101 083

04A

041006007

026027

004005

966967

989988987986

948947

964965

s34s44

10A100101103

081082083

048065066

04B04A041047

008

021022025026027

005006007

988

964

966967

948947946

946945

923924

924925

S32

S00SAS01S10

S02S12S22

S02S12S22

s24s34s44

S03S13S23S33

s44/54

S15S25S35

S45

S45/S55

S12 S14

S13S23

S05

S43 S45/S55

S14

S0J/S0B

S15S25055

012 992 975

S43/S53S03

956 917 897

S13S23

S0A

S0H

033

S45

S35

S46S56

917 898074

976 956093

054015 995

S56

GW6

S35

S26 S16

S46

S35S45

S25

S45

957 937S45

877S35

977 S55

936

897

977 917

956976 936

030

035

032993

011031

034994

981

961

924

864

862

901

882861

014 993 976977

918936

897

958

976992013

034

032035031 011

997

993012

GW9GW8

S15 S05GW6 GW7 GW8 GW9

GW7 GW8 GW9

S31 GW6GW5

GW5 GW6 GW7

GW5 GW6

GW8 GW9GW7

GW8 GW9GW6 GW7

S35 S25 GW6S15

905

917916

916

918

981

903943944

961

GW6

GW2 GW3 GW4 GW5

GW2 GW3 GW4

944943942

866/867

865904828

821

101

906

901

887

849

849

847/848

843841/842

primary

827

primary

809

829

827

primary

844944886

100 98 96

primaryprimary primary

885

847886

867846

868

866902

927

868

863/864861/862

887

885881

NIR

961

925

927943

926942

113

107109111

071070

092093

105 103

8082 7894 92 90 88 8486

845

847

848

826825

846

S33

S33

S13S23S22

S32

GW3S44 S45

GW1

112 106108110 GW7GW1 GW2 GW3 GW4 GW5102104 GW9

GW5GW4

GW5

GW8

GW7GW1

GW1

GW7GW3 GW4 GW5 GW6

GW8GW7

GW6

S48

GW2

101

942981

935934

956

957

99 97

917

994

977 957 938

S55

898

S55939

87

897

915

915

91 89

916

937

95

937

935

957

93

936

938

937

936

937

937

938

961 941

927943 887

S45

846866

906

906868

886

S36

857

865885

GW2S34

S13S23

865 825

886 866/867

S47863 845/846

848827828

S46

805

828

826825

S45

S37 S38903

829

926 822883

902926

863 842

788

785805806

808807

848

843

867

864

GW8GW7GW6S25 S05S15 GW5

S05S15S25

S55 S45

033

S65

994977 957 938 S26

993

994

956 905

877

055 015 976 957

015S55

S05S15

055017

055

072

014 993015

993

006

014

9899810

956

926

004

006007

009/10003/4

007009

0010

968969

986987988989

006007008009

9899810

003

008009

924925

9699610

966967

945946947

946

928929

923

948949

9699610

947

9499410

968

965

94

948949

9410946947948

102 100 98 96110 108 106 104 92 90 88 86112 84

966967968969

946947

988989

005

987

005008009

062

067/068065/066

064063

085086

969

049

023/024025026

105106126

105106107 087

061/062063064067068

083084085086

093 075994

S05

0290210

043044045048

053 033

044045

024025

029

023

005 947 927

066 049

103104105 085

066080082083084

023026027028029

041

048

043044046048049

028029106

082083084085086

103104105

085086087

104105106107

066067

043S03S13

S00SAS01

968

984

986987

12A

S43

946

986

S13S23S33

988989 Block 3

Block 4a

Block 2

Block 1