209
Chapter 1 Overview of Hardware Installation 1-1 ............................................... 1.1 About This Chapter 1-1 ................................................................................ 1.2 Hardware Installation Procedure 1-1 ............................................................ 1.3 Overview of Hardware Installation Steps 1-3 ............................................... 1.3.1 Installation Preparations 1-3 ................................................................ 1.3.2 Installing Cabling Rack or Cabling Trough 1-3 ..................................... 1.3.3 Installing Supports and Slide Rails 1-3 ................................................ 1.3.4 Installing Cabinets 1-3 .......................................................................... 1.3.5 Installing Internal Components 1-3 ...................................................... 1.3.6 Installing Power Cables and Protection Grounding Cables 1-3 ........... 1.3.7 Installing Signal Cables 1-4 .................................................................. 1.3.8 Installing Cabinet Fittings 1-4 ............................................................... 1.3.9 Installing Peripherals 1-4 ...................................................................... 1.3.10 Hardware Installation Check 1-4 ........................................................ 1.4 Hardware Installation Notices 1-4 ................................................................. Chapter 2 Installation Preparations 2-1 ............................................................... 2.1 About This Chapter 2-1 ................................................................................ 2.2 Preparation of Technical Documents 2-1 ..................................................... 2.3 Personnel Preparation 2-2 ............................................................................ 2.4 Preparation of Mounting Tools and Instruments 2-2 .................................... 2.5 Installation Environment Check 2-3 .............................................................. 2.5.1 Checking Building Conditions of Equipment Room 2-3 ....................... 2.5.2 Checking Environment Conditions 2-3 ................................................. 2.5.3 Checking Power Supply Conditions 2-4 ............................................... 2.5.4 Checking Grounding Conditions 2-4 .................................................... 2.5.5 Checking Auxiliary Devices 2-4 ............................................................ 2.5.6 Checking Other Facilities 2-5 ............................................................... 2.6 Unpacking and Inspection 2-5 ...................................................................... 2.6.1 Unpacking Wooden Crate 2-6 .............................................................. 2.6.2 Unpacking Carton 2-7 .......................................................................... 2.6.3 Acceptance and Handover 2-8 ............................................................. Chapter 3 Installing Cabinets 3-1 ......................................................................... 3.1 About This Chapter 3-1 ................................................................................ 3.2 Introduction to Cabinet 3-1 ........................................................................... 3.3 Installing Cabinets on ESD-Preventive Floor 3-1 ......................................... 3.3.1 Introduction to Supports and Floor Holder-Slide Rail Assemblies 3-1 .............................................................................................. 3.3.2 Amount of Supports, Floor Holders, and Slide Rails 3-3 ...................... 3.3.3 Installation Procedure on ESD-Preventive Floor 3-4 ...........................

UMG8900 Installation Manual-Hardware Installation

Embed Size (px)

Citation preview

Page 1: UMG8900 Installation Manual-Hardware Installation

Chapter 1 Overview of Hardware Installation 1-1...............................................

1.1 About This Chapter 1-1................................................................................1.2 Hardware Installation Procedure 1-1............................................................1.3 Overview of Hardware Installation Steps 1-3...............................................

1.3.1 Installation Preparations 1-3................................................................1.3.2 Installing Cabling Rack or Cabling Trough 1-3.....................................1.3.3 Installing Supports and Slide Rails 1-3................................................1.3.4 Installing Cabinets 1-3..........................................................................1.3.5 Installing Internal Components 1-3......................................................1.3.6 Installing Power Cables and Protection Grounding Cables 1-3...........1.3.7 Installing Signal Cables 1-4..................................................................1.3.8 Installing Cabinet Fittings 1-4...............................................................1.3.9 Installing Peripherals 1-4......................................................................1.3.10 Hardware Installation Check 1-4........................................................

1.4 Hardware Installation Notices 1-4.................................................................

Chapter 2 Installation Preparations 2-1...............................................................

2.1 About This Chapter 2-1................................................................................2.2 Preparation of Technical Documents 2-1.....................................................2.3 Personnel Preparation 2-2............................................................................2.4 Preparation of Mounting Tools and Instruments 2-2....................................2.5 Installation Environment Check 2-3..............................................................

2.5.1 Checking Building Conditions of Equipment Room 2-3.......................2.5.2 Checking Environment Conditions 2-3.................................................2.5.3 Checking Power Supply Conditions 2-4...............................................2.5.4 Checking Grounding Conditions 2-4....................................................2.5.5 Checking Auxiliary Devices 2-4............................................................2.5.6 Checking Other Facilities 2-5...............................................................

2.6 Unpacking and Inspection 2-5......................................................................2.6.1 Unpacking Wooden Crate 2-6..............................................................2.6.2 Unpacking Carton 2-7..........................................................................2.6.3 Acceptance and Handover 2-8.............................................................

Chapter 3 Installing Cabinets 3-1.........................................................................

3.1 About This Chapter 3-1................................................................................3.2 Introduction to Cabinet 3-1...........................................................................3.3 Installing Cabinets on ESD-Preventive Floor 3-1.........................................

3.3.1 Introduction to Supports and Floor Holder-Slide RailAssemblies 3-1..............................................................................................3.3.2 Amount of Supports, Floor Holders, and Slide Rails 3-3......................3.3.3 Installation Procedure on ESD-Preventive Floor 3-4...........................

Page 2: UMG8900 Installation Manual-Hardware Installation

3.3.4 Planning Support Positions 3-5............................................................3.3.5 Installing Supports and Slide Rails 3-9................................................3.3.6 Installing Floor Holder Fixing Components 3-13....................................3.3.7 Leveling Cabinets 3-14..........................................................................3.3.8 Fixing Cabinets 3-15..............................................................................3.3.9 Performing Insulation Test 3-16.............................................................

3.4 Installing Cabinets on Cement Floor 3-17......................................................3.4.1 Installation Procedure on Cement Floor 3-17........................................3.4.2 Planning Cabinet Positions 3-18............................................................3.4.3 Leveling Cabinets 3-22..........................................................................3.4.4 Fixing Cabinets 3-23..............................................................................3.4.5 Performing Insulation Test 3-25.............................................................

Chapter 4 Installing Internal Components 4-1....................................................

4.1 About This Chapter 4-1................................................................................4.2 Introduction to Internal Components and Installation 4-1.............................

4.2.1 Introduction to Internal Components 4-1..............................................4.2.2 Introduction to Internal Component Installation 4-2.............................

4.3 Installing Internal Components 4-3...............................................................4.3.1 Installing MGW Frames 4-3.................................................................4.3.2 Installing Boards 4-3............................................................................

Chapter 5 Installing Power Cables and Protection Grounding Cables 5-1......

5.1 About This Chapter 5-1................................................................................5.2 Installation Procedure 5-1.............................................................................5.3 Installation Notices 5-3.................................................................................5.4 Installing Power Cables for Internal Components 5-3..................................

5.4.1 Introduction to Power Cables for Internal Components 5-3.................5.4.2 Installing Power Cables from Power Distribution Frame toMGW Frame 5-5...........................................................................................5.4.3 Installing Power Cables for Fan Boxes in MGW Frames 5-6...............

5.5 Installing Protection Grounding Cables for Cabinets 5-7..............................5.5.1 Introduction to Protection Grounding System 5-7................................5.5.2 Installing Protection Grounding Cables for Cabinet Body 5-7..............5.5.3 Installing Protection Grounding Cables for MGW Frames 5-9.............5.5.4 Installing Protection Grounding Cables between AdjacentCabinets 5-10..................................................................................................

5.6 Installing Power Cables and Protection Grounding Cables betweenDC Power Distribution Cabinet to N68-22 Cabinet 5-11......................................

5.6.1 Introduction to Installing Power Cables and ProtectionGrounding Cables for Cabinets 5-11...............................................................5.6.2 Core Areas of Power Cables and Protection Grounding Cables 5-12...5.6.3 Installing Power Cables and Protection Grounding Cables 5-13...........

Page 3: UMG8900 Installation Manual-Hardware Installation

5.6.4 Requirements for Installing Power Cables and ProtectionGrounding Cables 5-15...................................................................................

5.7 Installing Power Bus Cables between DC Power DistributionCabinet and DC Switchboard 5-16.......................................................................

5.7.1 Introduction to Power Bus Cables 5-16..................................................5.7.2 Connecting Power Bus Cables 5-16......................................................5.7.3 Requirements for Installing Power Bus Cables 5-18..............................5.7.4 Requirements for Laying Cables Inside DC Power DistributionCabinet 5-20....................................................................................................

5.8 Engineering Labels for Cables 5-21...............................................................

Chapter 6 Installing Signal Cables 6-1.................................................................

6.1 About This Chapter 6-1................................................................................6.2 Introduction to Signal Cables 6-1.................................................................

6.2.1 Category of Signal Cables 6-1.............................................................6.2.2 Introduction to Internal Signal Cables 6-1............................................6.2.3 Introduction to External Signal Cables 6-2...........................................

6.3 Introduction to Installation Procedure 6-2.....................................................6.3.1 Procedure of Installing Internal Signal Cables 6-2...............................6.3.2 Procedure of Installing External Signal Cables 6-3..............................

6.4 Requirements for Installing Signal Cables 6-3.............................................6.4.1 General Requirements 6-3...................................................................6.4.2 Method of Using Fiber Coiler 6-4.........................................................6.4.3 Method of Installing Cables In and Out of Cabinets 6-5.......................

6.5 Installing Internal Signal Cables 6-6.............................................................6.5.1 Installing Internal Clock Cables 6-6......................................................6.5.2 Installing Monitoring Cables 6-10...........................................................6.5.3 Installing Cascading Cables 6-13...........................................................6.5.4 Installing Internal E1/T1 Cables 6-18.....................................................

6.6 Installing External Signal Cables 6-21............................................................6.6.1 Installing Trunk Cables 6-21..................................................................6.6.2 Installing External Clock Cables 6-22....................................................6.6.3 Installing External Network Cables 6-23................................................6.6.4 Installing External Optical Fibers 6-24...................................................

Chapter 7 Installing Cabinet Fittings 7-1.............................................................

7.1 About This Chapter 7-1................................................................................7.2 Installing ESD-Preventive Floor Holders and Recovering Floor 7-1.............

7.2.1 Installing ESD-Preventive Floor Holders 7-1........................................7.2.2 Adjusting Holder Height 7-2.................................................................7.2.3 Cutting and Recovering ESD-Preventive Floor 7-2..............................

7.3 Installing Door Lintels 7-2.............................................................................

Page 4: UMG8900 Installation Manual-Hardware Installation

7.4 Installing Cabinet Side Panels 7-4................................................................7.5 Installing Front and Back Doors 7-5.............................................................

Chapter 8 Installing Peripherals 8-1.....................................................................

8.1 About This Chapter 8-1................................................................................8.2 Introduction to UMG8900 Peripherals 8-1....................................................8.3 Connecting to the LMT 8-1...........................................................................

8.3.1 Connecting Network Cables between the LMT and UMG8900 8-1.....8.3.2 Installing Protection Grounding Cables for the LMT 8-2......................8.3.3 Connecting Protection Grounding Cables between the LMTand UMG8900 8-2.........................................................................................

8.4 Connecting to the Alarm System 8-2............................................................8.4.1 Introduction to the Alarm Box 8-2.........................................................8.4.2 Connecting to the Alarm Box 8-3.........................................................

8.5 Laying Cables for Peripherals 8-4................................................................

Chapter 9 Hardware Installation Check 9-1.........................................................

9.1 About This Chapter 9-1................................................................................9.2 Checking Appearance of Hardware Components 9-1..................................

9.2.1 Checking Cabinets 9-1.........................................................................9.2.2 Checking Cable Distribution 9-1...........................................................9.2.3 Checking Connectors and Sockets 9-2................................................9.2.4 Other Checks 9-3.................................................................................

9.3 Checking Power Supplies for Cabinets and Frames 9-3..............................9.4 Performing Board Power-On Test 9-4..........................................................

Appendix A Installing Cabling Rack A-1..............................................................

A.1 About This Appendix A-1..............................................................................A.2 Introduction to the Cabling Rack A-1............................................................

A.2.1 Functions of the Cabling Rack A-1.......................................................A.2.2 Components of Cabling Rack A-1........................................................A.2.3 Installation Modes A-7..........................................................................A.2.4 Cabling Rack Specifications A-7..........................................................

A.3 Installing Cabling Rack A-7..........................................................................A.3.1 Installation Procedure A-7....................................................................A.3.2 Assembling Cabling Ladder A-8...........................................................A.3.3 Connecting and Installing Cabling Troughs A-10...................................A.3.4 Installing Turning Cabling Rack A-11.....................................................A.3.5 Installing Cabling Rack in Suspension Mounting Mode orGround Supporting Mode A-13........................................................................A.3.6 Installing Triangular Support A-14..........................................................A.3.7 Installing Cabling Rack over Cabinet A-16.............................................

Page 5: UMG8900 Installation Manual-Hardware Installation

A.3.8 Installing Accessories A-17....................................................................

Appendix B Engineering Labels for Cables B-1..................................................

B.1 Introduction to the Appendix B-1..................................................................B.2 Introduction to Labels B-1.............................................................................

B.2.1 Functions of Engineering Labels B-1...................................................B.2.2 Label Material Specifications B-1.........................................................B.2.3 Type and Shape of Labels B-2.............................................................B.2.4 Printing Labels B-3...............................................................................B.2.5 Writing Labels B-5................................................................................B.2.6 Affixing Labels B-6...............................................................................B.2.7 Information Carried on Labels B-9.......................................................B.2.8 Remarks B-9........................................................................................

B.3 Engineering Labels for External Cables of Alarm Box B-10...........................B.4 Engineering Labels for Ethernet Cables B-11................................................

B.4.1 Introduction to the Labels B-11..............................................................B.4.2 Label Information Meanings B-11..........................................................B.4.3 Label Example B-12...............................................................................

B.5 Engineering Labels for Optical Fibers B-13....................................................B.5.1 Introduction to the Labels B-13..............................................................B.5.2 Labels for Fiber that Connects Two Devices B-13.................................B.5.3 Labels for Fiber that Connects the Device and the ODF B-15...............

B.6 Engineering Labels for Trunk Cables B-16.....................................................B.6.1 Introduction to the Labels B-16..............................................................B.6.2 Labels for Trunk Cable that Connects Two Devices B-16.....................B.6.3 Labels for Trunk Cable that Connects the Device and the DDF B-17....

B.7 Engineering Labels for Subscriber Cables B-19.............................................B.7.1 Introduction to the Labels B-19..............................................................B.7.2 Label Information Meanings B-19..........................................................B.7.3 Label Example B-19...............................................................................

B.8 Engineering Labels for Power Cables B-20....................................................B.8.1 Labels for DC Power Cables B-20.........................................................B.8.2 Labels for AC Power Cables B-22.........................................................

Appendix C Installing Antenna System C-1.........................................................

C.1 Introduction to the Appendix C-1..................................................................C.2 Introduction to Antenna System C-1.............................................................C.3 Installation Preparations C-2........................................................................

C.3.1 Planning Grounding Points C-2............................................................C.3.2 Planning Antenna Installation Positions C-3........................................

C.4 Installing Antenna System C-3.....................................................................

Page 6: UMG8900 Installation Manual-Hardware Installation

C.4.1 Installation Procedure C-3....................................................................C.4.2 Fixing Antenna Support C-4.................................................................C.4.3 Installing Antenna C-7..........................................................................C.4.4 Installing Lightning Arrester C-9...........................................................C.4.5 Making N Connector of 1/2" Super Flexible Feeder Cable C-10...........C.4.6 Connecting Cables C-12........................................................................C.4.7 Grounding Feeder with Grounding Clip C-16.........................................C.4.8 Requirements for Installing Antenna Feeder System C-17....................

Appendix D Connecting the UAM D-1..................................................................

D.1 Connecting the SSM with the Main Frame D-1............................................D.1.1 Connecting the SSM with the Rear Access PV8 Main Frame D-1.......D.1.2 Connecting the SSM with the Front Access UAFM Frame D-2...........

D.2 Connecting the Main Frame and Sub Frame D-4.........................................D.3 Connecting the SSM with the Direct Frame D-5...........................................

D.3.1 Connecting the RSP Frame D-5..........................................................D.3.2 Connecting the RSB Frame D-6..........................................................

D.4 Connecting the SSM with the RSA Frame D-7.............................................D.5 Connecting the RSA Frame with the RSA Sub Frame D-8..........................

Appendix E Requirements for Equipment Operating Environment E-1............

E.1 Introduction to the Chapter E-1....................................................................E.2 Site Requirements E-1.................................................................................E.3 Building Requirements E-2...........................................................................E.4 Humidity and Temperature Requirements E-4.............................................E.5 Air Cleanness Requirements E-4.................................................................E.6 Erosive Gas Condition Requirements E-5....................................................E.7 Electromagnetic Requirements E-6..............................................................E.8 ESD-Preventive Requirements E-6..............................................................E.9 Lightning Protection Requirements E-7........................................................E.10 Requirements for Power Supply E-9..........................................................

E.10.1 Requirements for AC Power Supply E-9............................................E.10.2 Requirements for DC Power Supply E-10............................................

Appendix F List of Abbreviations and Acronyms F-1........................................

Index .................................................................................................................

Page 7: UMG8900 Installation Manual-Hardware Installation

Huawei Technologies Proprietary

HUAWEI

U-SYS UMG8900 Universal Media Gateway Installation Manual - Hardware Installation

V100R003

Page 8: UMG8900 Installation Manual-Hardware Installation

Huawei Technologies Proprietary

U-SYS UMG8900 Universal Media Gateway

Installation Manual

Volume Hardware Installation

Manual Version T2-010473-20050315-C-1.33

Product Version V100R003

BOM 31041573

Huawei Technologies Co., Ltd. provides customers with comprehensive technical support and service. Please feel free to contact our local office or company headquarters.

Huawei Technologies Co., Ltd.

Address: Administration Building, Huawei Technologies Co., Ltd.,

Bantian, Longgang District, Shenzhen, P. R. China

Postal Code: 518129

Website: http://www.huawei.com

Email: [email protected]

Page 9: UMG8900 Installation Manual-Hardware Installation

Huawei Technologies Proprietary

Copyright © 2005 Huawei Technologies Co., Ltd.

All Rights Reserved

No part of this manual may be reproduced or transmitted in any form or by any means without prior written consent of Huawei Technologies Co., Ltd.

Trademarks

, HUAWEI, C&C08, EAST8000, HONET, , ViewPoint, INtess, ETS, DMC,

TELLIN, InfoLink, Netkey, Quidway, SYNLOCK, Radium, M900/M1800, TELESIGHT, Quidview, Musa, Airbridge, Tellwin, Inmedia, VRP, DOPRA, iTELLIN, HUAWEI OptiX, C&C08 iNET, NETENGINE, OptiX, iSite, U-SYS, iMUSE, OpenEye, Lansway, SmartAX, infoX, TopEng are trademarks of Huawei Technologies Co., Ltd.

All other trademarks mentioned in this manual are the property of their respective holders.

Notice

The information in this manual is subject to change without notice. Every effort has been made in the preparation of this manual to ensure accuracy of the contents, but all statements, information, and recommendations in this manual do not constitute the warranty of any kind, express or implied.

Page 10: UMG8900 Installation Manual-Hardware Installation

Huawei Technologies Proprietary

Summary of Updates

This section provides an update history of this manual and introduces the updates of contents.

Update History

Manual Version Notes

T2-010473-20041015-C-1.30 Initial field trial release

T2-010473-20041116-C-1.31 Initial commercial release

T2-010473-20041222-C-1.32 Second commercial release

T2-010473-20050315-C-1.33 Third commercial release

Updates of Contents

Updates between manual versions are cumulative. Therefore, the latest manual version contains all updates made to previous versions.

Updates in Manual Version 1.33

The modification for bugs is incorporated. The figure for installing the clock distribution cable is optimized.

Updates in Manual Version 1.32

Chapter 2 is amended. Appendix E “Requirements for Equipment Operating Environment” is added for

engineers’ reference. Figure 5-5 is updated. Figure 6-5 is updated to replace the clips on the connector by the bolts due to the

change of hardware.

Updates in Manual Version 1.31

This version incorporates modifications for bugs.

Page 11: UMG8900 Installation Manual-Hardware Installation

Huawei Technologies Proprietary

About This Manual

Release Notes

The manual applies to U-SYS UMG8900 Universal Media Gateway V100R003.

Organization

This manual presents the hardware installation, component installation and installation check for U-SYS UMG8900 Universal Media Gateway (hereinafter referred to as UMG8900).

There are nine chapters and five appendixes in the manual.

Chapter 1 Overview of Hardware Installation profiles the overall procedure of installing hardware components of the UMG8900.

Chapter 2 Installation Preparations lists the pre-installation tasks, including preparing technical documents, tools and meters, and checking installation conditions in the equipment room.

Chapter 3 Installing Cabinets guides you through planning, adjusting and fixing a single cabinet and combining adjacent cabinets based on the actual conditions of the equipment room.

Chapter 4 Installing Internal Components introduces the categories of the internal components in a cabinet and the installation requirements.

Chapter 5 Installing Power Cables and Protection Grounding Cables presents the connection and cabling of power cables and protection grounding cables pertaining to the equipment.

Chapter 6 Installing Signal Cables covers the categories, appearance, connection and cabling of signal cables of the equipment.

Chapter 7 Installing Cabinet Fittings presents the installation of door lintel, front and back doors and side panels of the cabinet.

Chapter 8 Installing Peripherals describes the installation of terminal devices, alarm devices and auxiliary cables.

Chapter 9 Hardware Installation Check defines the points to check after hardware installation completes.

Appendix A Installing Cabling Rack introduces the components of the cabling rack as well as the installation of the cabling rack.

Appendix B Engineering Labels for Cables introduces the materials and specifications of the engineering labels and the usage methods.

Page 12: UMG8900 Installation Manual-Hardware Installation

Huawei Technologies Proprietary

Appendix C Installing Antenna System introduces the installation of global positioning system (GPS) antenna system, including the installation of accessory lightning arresters and the connection of cables.

Appendix D Connecting the UAM introduces the connection of the UAM module.

Appendix E Requirements for Equipment Operating Environment describes the requirements of the UMG8900 for running conditions.

Appendix F List of Acronyms and Abbreviations lists abbreviations and acronyms and their full names in this manual.

Index lists the indexes in this manual.

Intended Audience

The manual is intended for the following readers:

Telecom Network technicians Telecom management personnel Network system engineers

Conventions

The manual uses the following conventions:

I. General Conventions

Convention Description

Arial Normal paragraphs are in Arial.

Boldface Headings are in Boldface.

Courier New Terminal Display is in Courier New.

II. GUI Conventions

Convention Description

< > Button names are inside angle brackets. For example, click the <OK> button.

[ ] Window names, menu items, data table and field names are inside square brackets. For example, pop up the [New User] window.

/ Multi-level menus are separated by forward slashes. For example, [File/Create/Folder].

Page 13: UMG8900 Installation Manual-Hardware Installation

Huawei Technologies Proprietary

III. Keyboard Operation

Format Description

<Key> Press the key with the key name inside angle brackets. For example, <Enter>, <Tab>, <Backspace>, or <A>.

<Key1+Key2> Press the keys concurrently. For example, <Ctrl+Alt+A> means the three keys should be pressed concurrently.

<Key1, Key2> Press the keys in turn. For example, <Alt, A> means the two keys should be pressed in turn.

IV. Mouse Operation

Action Description

Click Press the left button or right button quickly (left button by default).

Double Click Press the left button twice continuously and quickly.

Drag Press and hold the left button and drag it to a certain position.

V. Symbols

Eye-catching symbols are also used in the manual to highlight the points worthy of special attention during the operation. They are defined as follows:

Caution, Warning, Danger: Means reader be extremely careful during the

operation.

Note, Comment, Tip, Knowhow, Thought: Means a complementary description.

Environmental Protection

This product has been designed to comply with the requirements on environmental protection. For the proper storage, use and disposal of this product, national laws and regulations must be observed.

Page 14: UMG8900 Installation Manual-Hardware Installation

Installation Manual - Hardware Installation U-SYS UMG8900 Universal Media Gateway Table of Contents

Huawei Technologies Proprietary

i

Table of Contents

Chapter 1 Overview of Hardware Installation............................................................................. 1-1 1.1 About This Chapter ............................................................................................................ 1-1 1.2 Hardware Installation Procedure ....................................................................................... 1-1 1.3 Overview of Hardware Installation Steps........................................................................... 1-3

1.3.1 Installation Preparations.......................................................................................... 1-3 1.3.2 Installing Cabling Rack or Cabling Trough.............................................................. 1-3 1.3.3 Installing Supports and Slide Rails.......................................................................... 1-3 1.3.4 Installing Cabinets................................................................................................... 1-3 1.3.5 Installing Internal Components................................................................................ 1-3 1.3.6 Installing Power Cables and Protection Grounding Cables .................................... 1-3 1.3.7 Installing Signal Cables........................................................................................... 1-4 1.3.8 Installing Cabinet Fittings ........................................................................................ 1-4 1.3.9 Installing Peripherals............................................................................................... 1-4 1.3.10 Hardware Installation Check ................................................................................. 1-4

1.4 Hardware Installation Notices ............................................................................................ 1-4

Chapter 2 Installation Preparations............................................................................................. 2-1 2.1 About This Chapter ............................................................................................................ 2-1 2.2 Preparation of Technical Documents................................................................................. 2-1 2.3 Personnel Preparation ....................................................................................................... 2-2 2.4 Preparation of Mounting Tools and Instruments................................................................ 2-2 2.5 Installation Environment Check ......................................................................................... 2-3

2.5.1 Checking Building Conditions of Equipment Room ................................................ 2-3 2.5.2 Checking Environment Conditions.......................................................................... 2-3 2.5.3 Checking Power Supply Conditions........................................................................ 2-4 2.5.4 Checking Grounding Conditions ............................................................................. 2-4 2.5.5 Checking Auxiliary Devices..................................................................................... 2-4 2.5.6 Checking Other Facilities ........................................................................................ 2-5

2.6 Unpacking and Inspection ................................................................................................. 2-5 2.6.1 Unpacking Wooden Crate ....................................................................................... 2-6 2.6.2 Unpacking Carton ................................................................................................... 2-7 2.6.3 Acceptance and Handover...................................................................................... 2-8

Chapter 3 Installing Cabinets....................................................................................................... 3-1 3.1 About This Chapter ............................................................................................................ 3-1 3.2 Introduction to Cabinet....................................................................................................... 3-1 3.3 Installing Cabinets on ESD-Preventive Floor .................................................................... 3-1

3.3.1 Introduction to Supports and Floor Holder-Slide Rail Assemblies .......................... 3-1

Page 15: UMG8900 Installation Manual-Hardware Installation

Installation Manual - Hardware Installation U-SYS UMG8900 Universal Media Gateway Table of Contents

Huawei Technologies Proprietary

ii

3.3.2 Amount of Supports, Floor Holders, and Slide Rails............................................... 3-3 3.3.3 Installation Procedure on ESD-Preventive Floor .................................................... 3-4 3.3.4 Planning Support Positions ..................................................................................... 3-5 3.3.5 Installing Supports and Slide Rails.......................................................................... 3-9 3.3.6 Installing Floor Holder Fixing Components ........................................................... 3-13 3.3.7 Leveling Cabinets.................................................................................................. 3-14 3.3.8 Fixing Cabinets...................................................................................................... 3-15 3.3.9 Performing Insulation Test .................................................................................... 3-16

3.4 Installing Cabinets on Cement Floor................................................................................ 3-17 3.4.1 Installation Procedure on Cement Floor ............................................................... 3-17 3.4.2 Planning Cabinet Positions ................................................................................... 3-18 3.4.3 Leveling Cabinets.................................................................................................. 3-22 3.4.4 Fixing Cabinets...................................................................................................... 3-23 3.4.5 Performing Insulation Test .................................................................................... 3-25

Chapter 4 Installing Internal Components.................................................................................. 4-1 4.1 About This Chapter ............................................................................................................ 4-1 4.2 Introduction to Internal Components and Installation ........................................................ 4-1

4.2.1 Introduction to Internal Components....................................................................... 4-1 4.2.2 Introduction to Internal Component Installation ...................................................... 4-2

4.3 Installing Internal Components .......................................................................................... 4-3 4.3.1 Installing MGW Frames........................................................................................... 4-3 4.3.2 Installing Boards...................................................................................................... 4-3

Chapter 5 Installing Power Cables and Protection Grounding Cables.................................... 5-1 5.1 About This Chapter ............................................................................................................ 5-1 5.2 Installation Procedure ........................................................................................................ 5-1 5.3 Installation Notices............................................................................................................. 5-3 5.4 Installing Power Cables for Internal Components ............................................................. 5-3

5.4.1 Introduction to Power Cables for Internal Components .......................................... 5-3 5.4.2 Installing Power Cables from Power Distribution Frame to MGW Frame............... 5-5 5.4.3 Installing Power Cables for Fan Boxes in MGW Frames........................................ 5-6

5.5 Installing Protection Grounding Cables for Cabinets......................................................... 5-7 5.5.1 Introduction to Protection Grounding System ......................................................... 5-7 5.5.2 Installing Protection Grounding Cables for Cabinet Body....................................... 5-7 5.5.3 Installing Protection Grounding Cables for MGW Frames...................................... 5-9 5.5.4 Installing Protection Grounding Cables between Adjacent Cabinets.................... 5-10

5.6 Installing Power Cables and Protection Grounding Cables between DC Power Distribution Cabinet to N68-22 Cabinet .................................................................................................... 5-11

5.6.1 Introduction to Installing Power Cables and Protection Grounding Cables for Cabinets ......................................................................................................................... 5-11 5.6.2 Core Areas of Power Cables and Protection Grounding Cables .......................... 5-12 5.6.3 Installing Power Cables and Protection Grounding Cables .................................. 5-13

Page 16: UMG8900 Installation Manual-Hardware Installation

Installation Manual - Hardware Installation U-SYS UMG8900 Universal Media Gateway Table of Contents

Huawei Technologies Proprietary

iii

5.6.4 Requirements for Installing Power Cables and Protection Grounding Cables ..... 5-15 5.7 Installing Power Bus Cables between DC Power Distribution Cabinet and DC Switchboard5-16

5.7.1 Introduction to Power Bus Cables......................................................................... 5-16 5.7.2 Connecting Power Bus Cables ............................................................................. 5-16 5.7.3 Requirements for Installing Power Bus Cables..................................................... 5-18 5.7.4 Requirements for Laying Cables Inside DC Power Distribution Cabinet .............. 5-20

5.8 Engineering Labels for Cables......................................................................................... 5-21

Chapter 6 Installing Signal Cables .............................................................................................. 6-1 6.1 About This Chapter ............................................................................................................ 6-1 6.2 Introduction to Signal Cables............................................................................................. 6-1

6.2.1 Category of Signal Cables ...................................................................................... 6-1 6.2.2 Introduction to Internal Signal Cables ..................................................................... 6-1 6.2.3 Introduction to External Signal Cables.................................................................... 6-2

6.3 Introduction to Installation Procedure ................................................................................ 6-2 6.3.1 Procedure of Installing Internal Signal Cables ........................................................ 6-2 6.3.2 Procedure of Installing External Signal Cables....................................................... 6-3

6.4 Requirements for Installing Signal Cables......................................................................... 6-3 6.4.1 General Requirements ............................................................................................ 6-3 6.4.2 Method of Using Fiber Coiler .................................................................................. 6-4 6.4.3 Method of Installing Cables In and Out of Cabinets................................................ 6-5

6.5 Installing Internal Signal Cables ........................................................................................ 6-6 6.5.1 Installing Internal Clock Cables............................................................................... 6-6 6.5.2 Installing Monitoring Cables .................................................................................. 6-10 6.5.3 Installing Cascading Cables.................................................................................. 6-13 6.5.4 Installing Internal E1/T1 Cables ............................................................................ 6-18

6.6 Installing External Signal Cables ..................................................................................... 6-21 6.6.1 Installing Trunk Cables.......................................................................................... 6-21 6.6.2 Installing External Clock Cables............................................................................ 6-22 6.6.3 Installing External Network Cables ....................................................................... 6-23 6.6.4 Installing External Optical Fibers........................................................................... 6-24

Chapter 7 Installing Cabinet Fittings........................................................................................... 7-1 7.1 About This Chapter ............................................................................................................ 7-1 7.2 Installing ESD-Preventive Floor Holders and Recovering Floor........................................ 7-1

7.2.1 Installing ESD-Preventive Floor Holders................................................................. 7-1 7.2.2 Adjusting Holder Height .......................................................................................... 7-2 7.2.3 Cutting and Recovering ESD-Preventive Floor....................................................... 7-2

7.3 Installing Door Lintels ........................................................................................................ 7-2 7.4 Installing Cabinet Side Panels ........................................................................................... 7-4 7.5 Installing Front and Back Doors......................................................................................... 7-5

Chapter 8 Installing Peripherals .................................................................................................. 8-1 8.1 About This Chapter ............................................................................................................ 8-1

Page 17: UMG8900 Installation Manual-Hardware Installation

Installation Manual - Hardware Installation U-SYS UMG8900 Universal Media Gateway Table of Contents

Huawei Technologies Proprietary

iv

8.2 Introduction to UMG8900 Peripherals ............................................................................... 8-1 8.3 Connecting to the LMT ...................................................................................................... 8-1

8.3.1 Connecting Network Cables between the LMT and UMG8900 .............................. 8-1 8.3.2 Installing Protection Grounding Cables for the LMT ............................................... 8-2 8.3.3 Connecting Protection Grounding Cables between the LMT and UMG8900 ......... 8-2

8.4 Connecting to the Alarm System ....................................................................................... 8-2 8.4.1 Introduction to the Alarm Box.................................................................................. 8-2 8.4.2 Connecting to the Alarm Box .................................................................................. 8-3

8.5 Laying Cables for Peripherals............................................................................................ 8-4

Chapter 9 Hardware Installation Check....................................................................................... 9-1 9.1 About This Chapter ............................................................................................................ 9-1 9.2 Checking Appearance of Hardware Components ............................................................. 9-1

9.2.1 Checking Cabinets .................................................................................................. 9-1 9.2.2 Checking Cable Distribution.................................................................................... 9-1 9.2.3 Checking Connectors and Sockets ......................................................................... 9-2 9.2.4 Other Checks .......................................................................................................... 9-3

9.3 Checking Power Supplies for Cabinets and Frames......................................................... 9-3 9.4 Performing Board Power-On Test ..................................................................................... 9-4

Appendix A Installing Cabling Rack............................................................................................A-1 A.1 About This Appendix .........................................................................................................A-1 A.2 Introduction to the Cabling Rack .......................................................................................A-1

A.2.1 Functions of the Cabling Rack................................................................................A-1 A.2.2 Components of Cabling Rack .................................................................................A-1 A.2.3 Installation Modes...................................................................................................A-7 A.2.4 Cabling Rack Specifications ...................................................................................A-7

A.3 Installing Cabling Rack......................................................................................................A-7 A.3.1 Installation Procedure .............................................................................................A-7 A.3.2 Assembling Cabling Ladder....................................................................................A-8 A.3.3 Connecting and Installing Cabling Troughs..........................................................A-10 A.3.4 Installing Turning Cabling Rack ............................................................................A-11 A.3.5 Installing Cabling Rack in Suspension Mounting Mode or Ground Supporting ModeA-13 A.3.6 Installing Triangular Support.................................................................................A-14 A.3.7 Installing Cabling Rack over Cabinet....................................................................A-16 A.3.8 Installing Accessories ...........................................................................................A-17

Appendix B Engineering Labels for Cables ...............................................................................B-1 B.1 Introduction to the Appendix..............................................................................................B-1 B.2 Introduction to Labels ........................................................................................................B-1

B.2.1 Functions of Engineering Labels ............................................................................B-1 B.2.2 Label Material Specifications ..................................................................................B-1 B.2.3 Type and Shape of Labels......................................................................................B-2 B.2.4 Printing Labels ........................................................................................................B-3

Page 18: UMG8900 Installation Manual-Hardware Installation

Installation Manual - Hardware Installation U-SYS UMG8900 Universal Media Gateway Table of Contents

Huawei Technologies Proprietary

v

B.2.5 Writing Labels .........................................................................................................B-5 B.2.6 Affixing Labels.........................................................................................................B-6 B.2.7 Information Carried on Labels ................................................................................B-9 B.2.8 Remarks..................................................................................................................B-9

B.3 Engineering Labels for External Cables of Alarm Box ....................................................B-10 B.4 Engineering Labels for Ethernet Cables .........................................................................B-11

B.4.1 Introduction to the Labels .....................................................................................B-11 B.4.2 Label Information Meanings .................................................................................B-11 B.4.3 Label Example ......................................................................................................B-12

B.5 Engineering Labels for Optical Fibers .............................................................................B-13 B.5.1 Introduction to the Labels .....................................................................................B-13 B.5.2 Labels for Fiber that Connects Two Devices........................................................B-13 B.5.3 Labels for Fiber that Connects the Device and the ODF......................................B-15

B.6 Engineering Labels for Trunk Cables..............................................................................B-16 B.6.1 Introduction to the Labels .....................................................................................B-16 B.6.2 Labels for Trunk Cable that Connects Two Devices ............................................B-16 B.6.3 Labels for Trunk Cable that Connects the Device and the DDF ..........................B-17

B.7 Engineering Labels for Subscriber Cables......................................................................B-19 B.7.1 Introduction to the Labels .....................................................................................B-19 B.7.2 Label Information Meanings .................................................................................B-19 B.7.3 Label Example ......................................................................................................B-19

B.8 Engineering Labels for Power Cables.............................................................................B-20 B.8.1 Labels for DC Power Cables ................................................................................B-20 B.8.2 Labels for AC Power Cables.................................................................................B-22

Appendix C Installing Antenna System ......................................................................................C-1 C.1 Introduction to the Appendix .............................................................................................C-1 C.2 Introduction to Antenna System........................................................................................C-1 C.3 Installation Preparations....................................................................................................C-2

C.3.1 Planning Grounding Points.....................................................................................C-2 C.3.2 Planning Antenna Installation Positions .................................................................C-3

C.4 Installing Antenna System.................................................................................................C-3 C.4.1 Installation Procedure.............................................................................................C-3 C.4.2 Fixing Antenna Support ..........................................................................................C-4 C.4.3 Installing Antenna ...................................................................................................C-7 C.4.4 Installing Lightning Arrester ....................................................................................C-9 C.4.5 Making N Connector of 1/2" Super Flexible Feeder Cable ..................................C-10 C.4.6 Connecting Cables ...............................................................................................C-12 C.4.7 Grounding Feeder with Grounding Clip................................................................C-16 C.4.8 Requirements for Installing Antenna Feeder System...........................................C-17

Appendix D Connecting the UAM................................................................................................D-1 D.1 Connecting the SSM with the Main Frame .......................................................................D-1

Page 19: UMG8900 Installation Manual-Hardware Installation

Installation Manual - Hardware Installation U-SYS UMG8900 Universal Media Gateway Table of Contents

Huawei Technologies Proprietary

vi

D.1.1 Connecting the SSM with the Rear Access PV8 Main Frame ...............................D-1 D.1.2 Connecting the SSM with the Front Access UAFM Frame ....................................D-2

D.2 Connecting the Main Frame and Sub Frame....................................................................D-4 D.3 Connecting the SSM with the Direct Frame......................................................................D-5

D.3.1 Connecting the RSP Frame....................................................................................D-5 D.3.2 Connecting the RSB Frame....................................................................................D-6

D.4 Connecting the SSM with the RSA Frame........................................................................D-7 D.5 Connecting the RSA Frame with the RSA Sub Frame .....................................................D-8

Appendix E Requirements for Equipment Operating Environment.........................................E-1 E.1 Introduction to the Chapter................................................................................................E-1 E.2 Site Requirements.............................................................................................................E-1 E.3 Building Requirements ......................................................................................................E-2 E.4 Humidity and Temperature Requirements ........................................................................E-4 E.5 Air Cleanness Requirements.............................................................................................E-4 E.6 Erosive Gas Condition Requirements ...............................................................................E-5 E.7 Electromagnetic Requirements .........................................................................................E-6 E.8 ESD-Preventive Requirements .........................................................................................E-6 E.9 Lightning Protection Requirements ...................................................................................E-7 E.10 Requirements for Power Supply......................................................................................E-9

E.10.1 Requirements for AC Power Supply.....................................................................E-9 E.10.2 Requirements for DC Power Supply...................................................................E-10

Appendix F List of Abbreviations and Acronyms...................................................................... F-1

Index ................................................................................................................................................ i-1

Page 20: UMG8900 Installation Manual-Hardware Installation

Installation Manual - Hardware Installation U-SYS UMG8900 Universal Media Gateway Chapter 1 Overview of Hardware Installation

Huawei Technologies Proprietary

1-1

Chapter 1 Overview of Hardware Installation

1.1 About This Chapter

According to normal installation sequence, equipment installation procedure includes two major stages: hardware installation and software installation. This manual introduces the hardware installation for the UMG8900.

For detailed information on software installation and related contents, refer to U-SYS UMG8900 Universal Media Gateway Installation Manual Software Installation.

This chapter contains the following sections:

Hardware Installation Procedure Overview of Hardware Installation Steps Hardware Installation Notices

1.2 Hardware Installation Procedure

The normal operation of the UMG8900 is closely concerned with the quality of installation. In this case, it is required to do systematic and standard installation to reduce the unfavorable factors to the equipment operations caused by installation, and to improve the reliability of equipment operation over network.

Figure 1-1 shows the procedures for installing the UMG8900 equipment.

Page 21: UMG8900 Installation Manual-Hardware Installation

Installation Manual - Hardware Installation U-SYS UMG8900 Universal Media Gateway Chapter 1 Overview of Hardware Installation

Huawei Technologies Proprietary

1-2

Start

Install cabinets

Install internal componets

Install signal cables

Install cabinet fittings

Install peripherals

Hardware installation check

End

Installation preparations

Install power cables and protection

grounding cables

Figure 1-1 Procedures for installing the UMG8900 equipment

Note:

In the UMG8900, the internal components, including service frames and air deflectors, are configured from bottom upward. Except the boards in service frame, the internal components are installed before delivery. To install upgrade/expansion devices, refer to the procedure as shown in Figure 1-1 and procedure for installing internal components described in Section 4.3 in Chapter 4 "Installing Internal Components".

Page 22: UMG8900 Installation Manual-Hardware Installation

Installation Manual - Hardware Installation U-SYS UMG8900 Universal Media Gateway Chapter 1 Overview of Hardware Installation

Huawei Technologies Proprietary

1-3

1.3 Overview of Hardware Installation Steps

1.3.1 Installation Preparations

Before installation, you need carefully read the related contents in U-SYS UMG8900 Universal Media Gateway Hardware Description Manual and this manual to get familiar with the overall hardware structure of the equipment to be installed and the technical specifications, as well as the prerequisites for the equipment installation. Then, you must prepare installation tools and meters.

1.3.2 Installing Cabling Rack or Cabling Trough

According to the project design documents and specific conditions in the equipment room, you need to install auxiliary cabling rack or cabling trough for the equipment. If there is DC power distribution cabinet provided together with the equipment, you have to install the DC power distribution cabinet before installing power cables and protection grounding cables.

1.3.3 Installing Supports and Slide Rails

If the equipment room is covered with ESD-preventive floor, you have to draw lines and drill holes on the ground, and then install supports and slide rails before installing cabinets. Otherwise, you have to draw lines and drill holes on the ground, and then install the cabinets on the cement floor directly.

1.3.4 Installing Cabinets

In this step, you will install the cabinets and combine the adjacent cabinets according to the project design document.

1.3.5 Installing Internal Components

According to the actual configuration, you will install fiber coilers, service frame, air deflector and blank filler panel, and insert boards into the service frames.

1.3.6 Installing Power Cables and Protection Grounding Cables

After installing the cabinets, you must install the protection grounding cables to ensure that the equipment is correctly grounded and to prevent the equipment from electrostatic discharge (ESD) damage during the subsequent work. After the power cables are installed, it is not allowed to use them directly to supply power to the

Page 23: UMG8900 Installation Manual-Hardware Installation

Installation Manual - Hardware Installation U-SYS UMG8900 Universal Media Gateway Chapter 1 Overview of Hardware Installation

Huawei Technologies Proprietary

1-4

system before hardware installation check and system power-on test. After the installation check and power-on test, you have to power on the system according to the power-on steps.

1.3.7 Installing Signal Cables

The signal cables used in the UMG8900 include clock cable, monitoring cable, subtending cable, trunk cable, external optical fiber and external network cable.

1.3.8 Installing Cabinet Fittings

The cabinet fittings include door lintel, front and back doors and side panels.

1.3.9 Installing Peripherals

The peripherals include maintenance terminal system, alarm box and other network devices.

1.3.10 Hardware Installation Check

Before starting software installation, it is required to check the hardware installation. For the checklist and criterions, refer to Chapter 9 "Hardware Installation Check" in this manual, and rectify the unqualified installation items until they totally comply with the criterions.

1.4 Hardware Installation Notices

This manual helps you install the hardware components and cables of the UMG8900 equipment. However, the provided information might not cover all possible site conditions and optional devices in the actual installation procedure. For this reason, you need use specific methods based on the actual site conditions.

Before installation, you need to pay attention to the following points:

Carefully read the Site Survey Report to understand the position and state of the equipment in the network.

Get clear of the interface types of line transmission device, the length of cables, and the accounting modes of access devices.

Confirm whether the customer’s order for the equipment is changed greatly.

Page 24: UMG8900 Installation Manual-Hardware Installation

Installation Manual - Hardware Installation U-SYS UMG8900 Universal Media Gateway Chapter 2 Installation Preparations

Huawei Technologies Proprietary

2-1

Chapter 2 Installation Preparations

2.1 About This Chapter

This chapter contains the following sections:

Preparation of Technical Documents Personnel Preparation Preparation of Mounting Tools and Instruments Installation Environment Check Unpacking and Inspection

2.2 Preparation of Technical Documents

The documents for the UMG8900 hardware installation are listed in Table 2-1.

Table 2-1 Documents for the UMG8900 hardware installation

Documents Classification Name Description

Network Plan, Equipment Room Design, Construction Diagram, Cable Routing Diagram

Prepared by the design company consigned by you. The copies shall be provided the equipment suppliers with before delivery.

Site Survey Report Filled out on site by the Huawei engineering personnel.

Instruction documents for installation

Engineering Design Document

Delivered with the equipment. It is made by Huawei on the basis of the equipment configuration of each site.

U-SYS UMG8900 Universal Media Gateway Hardware Description Manual Product

manual U-SYS UMG8900 Universal Media Gateway Installation Manual - Hardware Installation

Delivered with the equipment.

contracts and agreements

configuration table Others

package list

Provided by Huawei.

Page 25: UMG8900 Installation Manual-Hardware Installation

Installation Manual - Hardware Installation U-SYS UMG8900 Universal Media Gateway Chapter 2 Installation Preparations

Huawei Technologies Proprietary

2-2

2.3 Personnel Preparation

In the cooperative installation project, the technicians of the cooperator install the equipment with the assistance of the technical personnel of the customer.

In the non-cooperative installation project, the technical personnel of Huawei install the equipment with the assistance of the technical personnel of the customer.

The technical personnel from the cooperator should receive systematic training given by Huawei so as to master the procedures of system installation and commissioning. Only after they have obtained the related operation certificates can they implement the installation and commissioning.

The technical personnel of the customer should also be trained beforehand by Huawei to master the installation and construction methods.

Number of people required in the installation depends on the specific arrangement on project progress and the installation condition. Normally 3 ~ 5 engineers is required.

2.4 Preparation of Mounting Tools and Instruments

All the tools and instruments listed in Table 2-2 should be available for the installation.

Page 26: UMG8900 Installation Manual-Hardware Installation

Installation Manual - Hardware Installation U-SYS UMG8900 Universal Media Gateway Chapter 2 Installation Preparations

Huawei Technologies Proprietary

2-3

Table 2-2 List of tools and meters

Measuring and marking-off tools

Angle square, long tape, ruler(1 m), powder marker and pencil

Drilling tools

Percussion drill (one), drill bits (φ6, φ8, φ10, φ12, φ14, φ16), vacuum cleaner (one)

Firming tools

Straight screwdriver M3 – M6

Cross screwdriver M3 – M6

Monkey wrench, torque wrench

Socket wrench M10, M13, M16, M18

Double offset ring spanner M10, M13, M16, M18

Locksmith tools

Sharp-nose pliers, diagonal pliers, vice, hand-held electric drill, file, Handsaw, ripping bar, rubber hammer, nail hammer

General-purpose tools

Auxiliary tools

Brush, nippers, paper knife, bellows, plumb, electric iron, soldering tin wire, forklift, ladder, panel lifter, hot-air blower, power connector board (including three two phase sockets and three three phase sockets with more than 15A current)

Special tools

Industrial horizontal ruler, ground resistance tester (optional), ESD-preventive wrist strap, cable winding gun, cable peeler (optional), pressing pincers (optional), pressing pincers with crystal head, wire punchdown tool (optional), SMB coaxial trunk self-ring cable

Meters Multimeter, 500 V megohm meter (used to measure the insulation impedance)

2.5 Installation Environment Check

2.5.1 Checking Building Conditions of Equipment Room

Check the area, height, load bearing capacity, and groove distribution of the equipment room. If any item does not meet the requirements, suggest the customer to reconstruct.

2.5.2 Checking Environment Conditions

The check items include:

Page 27: UMG8900 Installation Manual-Hardware Installation

Installation Manual - Hardware Installation U-SYS UMG8900 Universal Media Gateway Chapter 2 Installation Preparations

Huawei Technologies Proprietary

2-4

The illumination conditions must satisfy the requirements for equipment maintenance. There must be normal illumination, standby illumination, and emergency illumination systems.

The air-conditioning and ventilation systems can ensure the temperature and humidity requirements.

Effective ESD-preventive measures are taken. The equipment room is equipped with sufficient fire-fighting facilities. The equipment room meets the quake-proof requirements. The floor in the

equipment room is solid enough to install and fasten the equipment. Safe lightning-proof measures are taken for the equipment room.

2.5.3 Checking Power Supply Conditions

The check items include:

The AC power supply facilities are complete, and the power meets the requirement. Besides the mains power supply, there must be standby power supply by diesel generator.

The DC power distribution devices can provide stable power supply, and the output voltage is within the specified range.

Enough available storage batteries ensure the equipment is able to run in case of power supply accident.

The AC power distribution system has independent AC protection ground.

2.5.4 Checking Grounding Conditions

Good grounding ensures the stable running of the equipment, and prevents the equipment from lightning and interference. In this case, it is required to carefully check the grounding conditions of the site, and take correct grounding measures.

Usually, the grounding impedance of the telecommunication site where the base station equipment is located is recommended to be less than 10 ohm. It also should conform to the relevant stipulation of the country.

2.5.5 Checking Auxiliary Devices

I. Digital Distribution Frame

If E1 trunk cables are led out of the UMG8900 in the networking scheme, the qualified digital distribution frame (DDF) must be configured according to the international requirements. Before the installation, you must complete the installation or expansion for the DDF. According to the capacity of the project and future expansion, the capacity of the DDF must be figured out. For the convenience of soldering the connectors of trunk cables at the DDF side, refer to the contract

Page 28: UMG8900 Installation Manual-Hardware Installation

Installation Manual - Hardware Installation U-SYS UMG8900 Universal Media Gateway Chapter 2 Installation Preparations

Huawei Technologies Proprietary

2-5

checklist for the model of the trunk cables used in the UMG8900 equipment, or consult the engineering designer at local office.

II. Optical Transmission Equipment

If there is auxiliary transmission equipment, check the following items before the UMG8900 hardware installation:

The optical transmission equipment has been installed. The optical transmitter and receiver have been installed and debugged. Optical fibers have been laid. The fiber tails from connection box are marked, The connectivity of the optical fibers has been checked. The cabling rack and distribution frame have been installed.

III. Interface to IP Network

The UMG8900 is connected to IP network through 100 Mbit/s standard Ethernet port, and then connected to the devices over the network. In this case, you must install routers and LAN Switches, and lay the network cables to prepare the interfaces to the IP network before installation, thus ensuring that the UMG8900 can access the IP network normally.

IV. Building Integrated Timing Supply System

The UMG8900 provides embedded signaling gateway. When it also serves as the signaling gateway to get interconnected with SS7 links, it must synchronize the clock of the links at the opposite end. If the building integrated timing supply system (BITS) is provided by you, you must complete installing the BITS and make access preparation before the UMG8900 hardware installation.

2.5.6 Checking Other Facilities

There must be a workbench in compliance with ESD-preventive requirements in the control room. It is used to install maintenance terminal, network management workstation and printer.

Desk, chair, power socket for computer, and phone set are necessary during installation. It is required to prepare for any possibilities according to the site conditions.

2.6 Unpacking and Inspection

In the non-turn-key project, both the customer and the project supervisor (engineer from Huawei or cooperator) are required to be present at the unpacking site. If either

Page 29: UMG8900 Installation Manual-Hardware Installation

Installation Manual - Hardware Installation U-SYS UMG8900 Universal Media Gateway Chapter 2 Installation Preparations

Huawei Technologies Proprietary

2-6

is absent at the unpacking site, the party who unpacks shall take the responsibility for any errors occurring to the articles.

In the turn-key project, it is the project supervisor and the order management engineer who unpack, check and accept, hand over the articles, and make a confirmation with signatures.

Before unpacking, both parties should check if the packing cases are damaged. If so, stop unpacking and contact the order management engineer at the local office of Huawei, waiting for the handling. Meanwhile, check if the quantity of cases on the site agrees with the packing list, if the place of delivery agrees with the actual installation place, and if the articles have been inversed during the transportation. If there is any disagreement, the project supervisor should feed back the Article Problem Feedback Form confirmed by the customer with a signature to the order management engineer at the local office within 3 days.

After all the above inspections are ok, unpack the cases to check and accept the articles.

There are two kinds of packages: wooden crate and cartons. The unpacking tools should be used accordingly.

2.6.1 Unpacking Wooden Crate

I. Overview of Unpacking Wooden Crate

Caution:

The wooden case is direction-oriented and should not be placed upside down. Otherwise, fatal damages would be caused to the product.

Wooden crate is used to package cabinets and batteries. A packaged cabinet is composed of wooden board, angle steel, tongue, and foam corner protector. Before unpacking the wooden crate, move the packing crate to the equipment room or nearby (if there is sufficient space), to avoid damage to the cabinet when moving the cabinet.

II. Operation Procedures of Unpacking Wooden Crate

The unpacking steps are as shown in Figure 2-1.

Page 30: UMG8900 Installation Manual-Hardware Installation

Installation Manual - Hardware Installation U-SYS UMG8900 Universal Media Gateway Chapter 2 Installation Preparations

Huawei Technologies Proprietary

2-7

(1) Angel steel (2) Tongue (3) Wooden board (4) Spanner

Figure 2-1 Unpacking the wooden crate

The unpacking steps are as follows.

1) Insert the spanner into the tongue holes in the cover, and turn the spanner to straighten the tongues, as shown in Figure 2-1 (a).

2) Lift and remove the covers, as shown in Figure 2-1 (b). 3) Straighten the tongues in the surrounded wooden board, and then remove the

surrounded wooden board, as shown in Figure 2-1 (c). 4) When moving or lifting the cabinet, use both hands to hold the firm parts of the

cabinet, such as brackets or major frames, instead of other parts, such as cable brackets and cable fixing beam, to avoid damage to the cabinet or personal injury. Remove the lining boards of the cabinet on the installation site to avoid damage to signal cables and boards when moving or lifting the cabinet.

2.6.2 Unpacking Carton

The unpacking steps are as shown in Figure 2-2

Page 31: UMG8900 Installation Manual-Hardware Installation

Installation Manual - Hardware Installation U-SYS UMG8900 Universal Media Gateway Chapter 2 Installation Preparations

Huawei Technologies Proprietary

2-8

Figure 2-2 Unpacking the wooden cartons

Generally, the carton is used to pack various boards, fibers, network cables, terminal equipments and other accessories. The board is placed in an antistatic bag for transportation. Inside the bag, there is a desiccant to keep it dry. The tool to open the carton is generally a paper knife.

Unpack the carton as follows:

1) Rip the adhesive tape along the joint seams using a paper knife. Be careful not to insert the knife too deep, avoiding damage to the boards.

2) Unpack the carton and take out the inner goods.

Caution:

If the equipment is moved from an environment with relatively low temperature and humidity to one with relatively high temperature and humidity, do not unpack it until at least 30 minutes later. Otherwise, the moisture may condense on the equipment surface and thus cause damage to the equipment.

Antistatic measures should be taken for unpacking boards so that boards will not be damaged.

2.6.3 Acceptance and Handover

I. Acceptance

The inspector should carefully check and accept the articles piece by piece with reference to the name, type and quantity of the articles stated on the packing list.

The acceptance of articles mainly includes the following aspects:

Appearance inspection: check if there are any defects on the appearance of the rack, if the rack is secure and fast, if there is any looseness or damage, if the

Page 32: UMG8900 Installation Manual-Hardware Installation

Installation Manual - Hardware Installation U-SYS UMG8900 Universal Media Gateway Chapter 2 Installation Preparations

Huawei Technologies Proprietary

2-9

identification is legible, and if the nameplate and decorating plates are completely installed and if they meet the use requirements.

Integrity inspection: check if all the parts and accessories necessary for the installation of racks are matching and complete.

Inspection of computer terminal: check if the display, keyboard and mouse are all ready and if there is any damage on them.

Board inspection: check if the board type agrees with the description in packing list, and if there is any broken printed circuit boards or any components detached from the board.

Note:

The project supervisor should take a major role in the inspection of equipment and components whose electric characteristics are apt to be affected.

The inspected articles should be placed by types. The packing cases after opened should be saved until the customer signs on the packing list.

II. Handover

After the acceptance, both parties must sign on the “Packing List” to confirm that there is no problem with the articles. After that, the articles are handed over to the customer.

During the inspection, if “outstanding articles” is stated in the packing list, it is necessary for the project supervisor to feed it back to the order management engineer at the local office. The order management engineer will urge the relevant department of Huawei to deliver the outstanding articles as soon as possible. Then both parties sign on the packing list. For any short, wrong, or extra shipment, or for any damage of articles, both parties should sign the “Unpacking Inspection Memo” and “Packing List”. Moreover, the project supervisor should fill in the “Article Problem Feedback Form” and feed it back to the order management engineer at the local office within 3 days. The project supervisor should also be responsible for well keeping the original condition of articles with problems as well as the inner and outer packing, for future investigation and verification.

If the articles are damaged or lost due to the improper keeping of the customer party after the customer accepts them, the customer party shall bear all the responsibility.

During the implementation, if there are any damaged parts or any other parts need to be replaced or re-issued, the project personnel should carefully fill in the “Article Problem Feedback Form” and feed it back in time to the article manager at the local office to put it on records.

Page 33: UMG8900 Installation Manual-Hardware Installation

Installation Manual - Hardware Installation U-SYS UMG8900 Universal Media Gateway Chapter 3 Installing Cabinets

Huawei Technologies Proprietary

3-1

Chapter 3 Installing Cabinets

3.1 About This Chapter

This chapter contains the following sections:

Introduction to Cabinet Installing Cabinets on ESD-Preventive Floor Installing Cabinets on Cement Floor

3.2 Introduction to Cabinet

The UMG8900 adopts standard 19-inch N68-22 cabinet, with flexible and simple structure, and powerful versatility. The dimensions are 2200 mm (height with door lintel) x 600 mm (width) x 800 mm (depth). Five cabinets can satisfy the requirements for full configuration of the UMG8900.

According to different equipment rooms, a cabinet can be installed on the cement floor or ESD-preventive floor. When two or more cabinets are installed in the same row, they must be combined and fixed.

Note:

Wear clean gloves when touching the surfaces of cabinets or frames.

3.3 Installing Cabinets on ESD-Preventive Floor

3.3.1 Introduction to Supports and Floor Holder-Slide Rail Assemblies

I. Introduction to Supports

If N68-22 cabinets are installed in equipment room with ESD-preventive floor, N800 series supports are used.

Supports, made of welded steel plates, are used to block the cabinets up, thus facilitating floor paving and cabling. Before the whole set of equipment is grounded,

Page 34: UMG8900 Installation Manual-Hardware Installation

Installation Manual - Hardware Installation U-SYS UMG8900 Universal Media Gateway Chapter 3 Installing Cabinets

Huawei Technologies Proprietary

3-2

insulation plates must be installed under the supports, and insulating coverings must be added to the expansion bolts to satisfy the insulation requirements.

N800 series supports have four kinds of components, of which three kinds are height adjustable and one kind is of fixed height.

The appearance of the N800 supports is shown in Figure 3-1. The height adjustment range of each kind of component is shown in Table 3-1.

(7)

(8)

(1)

(2)

(3)

(4)

(5)

(6)

(6)

(1) Upper beam of support

(2) Height mark of ESD-preventive floor (3) Lower beam of support

(4) Standby installation hole (5) Installation hole (6) Connection hole for slide rail (7) Height-locking bolt(in the middle) (8) Height locking bolts(at both sides)

Figure 3-1 Appearance of N800 support

Table 3-1 Height range of N800 support components

Component Applicable ESD-preventive floor height (mm)

I 210 – 255

II 256 – 345

III 346 – 525

IV Customized for the floor height (minimum height: 100 mm)

Note: The height of floor refers to the distance between the upper surface of ESD-preventive floor and the cement floor.

The height of N800 series I, II and III components can be adjusted within their adjustable ranges, which is realized by means of the relative move of upper beam and lower beam.

Page 35: UMG8900 Installation Manual-Hardware Installation

Installation Manual - Hardware Installation U-SYS UMG8900 Universal Media Gateway Chapter 3 Installing Cabinets

Huawei Technologies Proprietary

3-3

N800 IV component is the support of fixed height, which is applicable to ultra-high and ultra-low floors. The lowest applicable floor height of this component is 100 mm.

II. Introduction to Floor Holder-Slide Rail Assemblies

Floor holder-slide rail assemblies include floor holder, holder fixing component, and slide rail. Floor holders are used to support the floor around cabinet, and can be divided into front and back floor holders, and side floor holder. Holder fixing components are installed under slide rails, and they are used to connect slide rails and front and back floor holders.

Slide rails are used to connect cabinet and supports, and to move the equipment and adjust the equipment positions. They can join two supports and a cabinet together to keep the cabinet in a horizontal line and the connection stable. Due to their elasticity, the slide rails can absorb the vibrations.

The appearance of a slide rail is shown in Figure 3-2.

(2)

(1)

(1) Connection hole for support (2) Connection hole for cabinet

Figure 3-2 Appearance and dimensions of slide rail

3.3.2 Amount of Supports, Floor Holders, and Slide Rails

I. Amount of Supports

To connect cabinets, 2N mode is used to determine the number of supports to be used. That is, each N68-22 cabinet uses two supports, and N cabinets in a row need 2N supports, as shown in Figure 3-3.

Page 36: UMG8900 Installation Manual-Hardware Installation

Installation Manual - Hardware Installation U-SYS UMG8900 Universal Media Gateway Chapter 3 Installing Cabinets

Huawei Technologies Proprietary

3-4

Figure 3-3 Installing N800 support

II. Amount of Floor Holders and Slide Rails

Each cabinet has one set of floor holder-slide rail assemblies, which is delivered together with the supports. Each set of floor holder-slide rail assemblies include two slide rails, two side holders, one front floor holder and one back floor holder.

Each cabinet needs two holder fixing components, one front floor holder, and one back floor holder, and each cabinet row needs two side floor holders, even if there is only one cabinet in a row.

3.3.3 Installation Procedure on ESD-Preventive Floor

The procedure for installing cabinets on ESD-preventive floor is shown in Figure 3-4.

Page 37: UMG8900 Installation Manual-Hardware Installation

Installation Manual - Hardware Installation U-SYS UMG8900 Universal Media Gateway Chapter 3 Installing Cabinets

Huawei Technologies Proprietary

3-5

Plan support positions

Install supportsand slide rails

Install ESD-preventivefloor holder fixing

components

Position cabinets

Level cabinets

Pass theinsulation

test?

Combine cabinets

Fix cabinets

N

Y

Start

End

Figure 3-4 Procedure of installing cabinets on ESD-preventive floor

When two or more cabinets are placed in the same row, they must be combined and fixed. Generally, internal components and cables are installed before the floor holder installation, floor recovering, door lintel installation and door installation are implemented. For detailed information, see Chapter 7 "Installing Cabinet Fittings" of this manual.

3.3.4 Planning Support Positions

I. Determining Cabinet Positions

Before installing cabinets, plan available space of the equipment room. Keep sufficient space around cabinets for maintenance and operation purposes, as shown in Figure 3-5 and Figure 3-6.

II. Marking Installation Hole Positions

To mark the positions of installation holes, do as follows:

Page 38: UMG8900 Installation Manual-Hardware Installation

Installation Manual - Hardware Installation U-SYS UMG8900 Universal Media Gateway Chapter 3 Installing Cabinets

Huawei Technologies Proprietary

3-6

1) Specify installation positions for the supports with reference to the benchmark dimensions and the support dimensions specified in the construction plan.

2) Mark a few points for line drawing with a long tape and draw two straight lines parallel to the benchmark with a distance of 690 mm between them.

3) According to the design requirements, specify the installation holes for the first support on the two lines.

4) With these holes as reference, mark the installation holes for other supports one by one.

5) To avoid faults, measure all location lines again after marking the holes to ensure correct dimensions.

The holes for installing supports for a single cabinet are shown in Figure 3-5.

The holes for installing supports for multiple cabinets in a row are shown in Figure 3-6.

=800

690 800

=800

=800

=800

354

600

4- Ø 16

Figure 3-5 Hole positions for installing supports for a single cabinet

Page 39: UMG8900 Installation Manual-Hardware Installation

Installation Manual - Hardware Installation U-SYS UMG8900 Universal Media Gateway Chapter 3 Installing Cabinets

Huawei Technologies Proprietary

3-7

=800

=800

=800

600

800

=800

4- Ø 16

600 600

354

690

354 354

Figure 3-6 Hole positions for installing supports for multiple cabinets in a row

It is also available to use line drawing template to mark the positions of the expansion bolt holes. Based on the cabinet layout, place the line drawing template on the floor, as shown in Figure 3-7. To mark the hole positions for expansion bolts on the floor, use the template (each cabinet has four expansion bolts). The half-circle gap on the template indicates the front direction of the cabinet.

Page 40: UMG8900 Installation Manual-Hardware Installation

Installation Manual - Hardware Installation U-SYS UMG8900 Universal Media Gateway Chapter 3 Installing Cabinets

Huawei Technologies Proprietary

3-8

Front

Back

RightLeft

800

354

600

690

Figure 3-7 Line drawing template (used for installation on ESD-preventive floor)

Note:

Be sure to use the template in correct direction.

III. Drilling Holes

To fix supports onto the ground with the M12 expansion bolts, it is required to drill holes for the expansion bolts using a percussion drill with bit φ16.

To drill a hole, do as follows:

To drill a hole, do as follows:

1) Keep the drilling bit vertical to the ground and hold tight the drillstock to make holes 52 mm to 60 mm deep. The depth of the holes must be within 52 mm to 60 mm. Otherwise the expansion bolts cannot be fastened. Make sure that the depths of all holes are the same.

2) Clean the dust inside the holes with a vacuum cleaner. 3) Measure the depth to make sure that the depths of all holes are the same.

Page 41: UMG8900 Installation Manual-Hardware Installation

Installation Manual - Hardware Installation U-SYS UMG8900 Universal Media Gateway Chapter 3 Installing Cabinets

Huawei Technologies Proprietary

3-9

If the ground is too hard or smooth to settle the drill bit, punch a sample pit first for easy drilling.

Drawing lines and drilling holes are the fundamental work for hardware installation. Good quality is the prerequisite to guarantee the quality of the overall installation. If the accuracy is not high enough, the future work will be greatly affected.

Note:

The depth of drilled hole must be 52 mm to 60 mm. A depth less than 52 mm or more than 60 mm will cause the expansion bolt unable for normal installation and fastening.

3.3.5 Installing Supports and Slide Rails

I. Installing Expansion Bolts

Before fixing expansion bolts, clean up the dust inside and around the holes with a vacuum cleaner. Measure the distance between the holes and place the supports to check whether the supports and holes match exactly. For the holes with big deviation, plan and drill new holes before installing expansion bolts in them.

To install an expansion bolt, do as follows:

1) Take expansion tube and nut off the expansion bolt, and put them vertically into a hole after the guiding rib on the expansion nut has been inserted in to the guiding slot.

2) Strike directly on the expansion tube with a rubber hammer until it is completely driven into the ground.

The installation of expansion tube and expansion nut is shown in Figure 3-8.

Page 42: UMG8900 Installation Manual-Hardware Installation

Installation Manual - Hardware Installation U-SYS UMG8900 Universal Media Gateway Chapter 3 Installing Cabinets

Huawei Technologies Proprietary

3-10

(1)

(2)

(3)

(4)

(1) Expansion tube

(2) Guiding slot on expansion tube

(3) Expansion nut

(4) Guiding rib on expansion nut

Figure 3-8 Installation of expansion tube and expansion nut

Note:

The guiding rib on expansion nut must be inserted into the guiding slot on expansion tube before the tube is driven into the ground. Otherwise, the expansion bolt could not be installed and fastened normally.

II. Adjusting Support Height

To ensure that the upper surface of slide rails and the upper surface of the ESD-preventive floor are on the same level after the supports and slide rails are assembled, it is required to adjust all the supports to the preset height before installation.

To adjust the support height, do as follows:

1) Measure the height of the upper surface of the ESD-preventive floor. 2) Make the value minus the height of the slide rail (50 mm) to get the preset height

of the supports. 3) According to the ESD-preventive floor height mark on the supports, adjust all the

supports to the preset height and tighten the height-locking bolts to 45 Nm with a torque spanner.

4) Tighten the bolts in the middle and then those at both sides, as shown in Figure 3-9.

Page 43: UMG8900 Installation Manual-Hardware Installation

Installation Manual - Hardware Installation U-SYS UMG8900 Universal Media Gateway Chapter 3 Installing Cabinets

Huawei Technologies Proprietary

3-11

(1)

(2)

(1) Height-locking bolts (In the middle) (2) Height-locking bolt (at both sides)

Figure 3-9 Connection of support and floor

III. Assembling Supports and Slide Rails

To assemble the supports and slide rails, do as follows:

1) Assemble the supports and slide rails together with M12x30 bolts, spring washer and flat washer, as shown in Figure 3-10.

2) Correct the support positions before fastening all bolts to make the diagonal lines (A and B shown in Figure 3-10) of the two slide rails are equal in length.

3) Fasten all bolts.

B

A

Figure 3-10 Assembly of support and slide rails

Page 44: UMG8900 Installation Manual-Hardware Installation

Installation Manual - Hardware Installation U-SYS UMG8900 Universal Media Gateway Chapter 3 Installing Cabinets

Huawei Technologies Proprietary

3-12

IV. Fixing Supports

To fix the supports, do as follows:

1) Align the support installation holes with the corresponding expansion bolt holes. 2) Fit the spring and flat washers on M12x60 bolts, and insert the bolts vertically into

the expansion bolt holes through the support installation holes. 3) Correct the support positions and screw M12x60 bolts to 45 Nm, as shown in

Figure 3-11.

(1)(2)(3)

(1) Bolt M12x60 (2) Spring washer 12 (3) Flat washer 12

Figure 3-11 Assembly of supports and slide rails

When installing supports for a row of cabinets, align all supports by front side and keep the spacing adjacent supports as 128 mm for convenience of connecting cabinets, as shown in Figure 3-12.

Page 45: UMG8900 Installation Manual-Hardware Installation

Installation Manual - Hardware Installation U-SYS UMG8900 Universal Media Gateway Chapter 3 Installing Cabinets

Huawei Technologies Proprietary

3-13

128

Figure 3-12 Relative positions of supports

3.3.6 Installing Floor Holder Fixing Components

Floor holder fixing components are used to fix front floor holder and back floor holder. Before the cabinets are positioned, the floor holder fixing components must be fixed under the slide rails, as shown in Figure 3-13.

(1)

(1) Holder fixing components

Figure 3-13 Installation of holder fixing components

Page 46: UMG8900 Installation Manual-Hardware Installation

Installation Manual - Hardware Installation U-SYS UMG8900 Universal Media Gateway Chapter 3 Installing Cabinets

Huawei Technologies Proprietary

3-14

3.3.7 Leveling Cabinets

I. Positioning Cabinets

To position a cabinet, do as follows:

1) Determine the front view of a cabinet. 2) Lift it onto the slide rails. 3) Align the four fixing holes in the cabinet with the four holes in the slide rails.

II. Installing Insulation plates

Put the insulation plates on the slide rails under the cabinet, as shown in Figure 3-14. Each cabinet requires two insulation plates.

(1)(2)

(4)(3)

(5)

(6)

(1) Bolt M12x45 (2) Spring washer 12 (3) Insulation plate (4) Washer (5) Flat washer 12, Nut 12 (6) Slide rail

Figure 3-14 Fixing a cabinet

III. Leveling Cabinets

To level the cabinets, do as follows:

1) Place horizontal rulers in both longitudinal and latitudinal directions on the top surface of the cabinet to check the levelness.

2) Use washers to adjust the cabinet height to keep the cabinet horizontal, as shown in Figure 3-14.

Page 47: UMG8900 Installation Manual-Hardware Installation

Installation Manual - Hardware Installation U-SYS UMG8900 Universal Media Gateway Chapter 3 Installing Cabinets

Huawei Technologies Proprietary

3-15

Note:

The washers for leveling should be installed between the insulation plates and slide rails. Otherwise, insulation will not work.

3.3.8 Fixing Cabinets

I. Fixing Bottom of Cabinet

To fix the cabinet bottom, do as follows:

1) Fit the spring washers on M12x45 bolts (the big flat washers and insulation coverings have been installed in the cabinet).

2) Insert the bolts vertically into the connection holes in the slide rails through the lower enclosure frame of the cabinet.

3) Fit the flat washers and nuts and screw M12x45 bolts to 45 Nm, as shown in Figure 3-14. Be sure to fasten the bolts in cross way to reduce the stress between bolts and cabinet.

II. Fixing Top of Combined Cabinets

When two or more cabinets are installed, they must be combined and fixed by connecting plates.

The connecting plates for combining cabinets are installed on the top of the cabinets and they are delivered with cabinets, as shown in Figure 3-15.

To connect two adjacent cabinets, do as follows:

1) Disassemble the connecting plates of the two adjacent cabinets. 2) Reassemble them according to Figure 3-15.

Page 48: UMG8900 Installation Manual-Hardware Installation

Installation Manual - Hardware Installation U-SYS UMG8900 Universal Media Gateway Chapter 3 Installing Cabinets

Huawei Technologies Proprietary

3-16

1 2 3

4 5 6 7

Figure 3-15 Installation of connecting plate for combining cabinets

3.3.9 Performing Insulation Test

To test the insulation effect of the cabinets, do as follows:

1) Set the multimeter to Megohm range. 2) Measure the impedance between the supports and cabinets.

If the impedance measured is more than 5 MΩ, it indicates that the cabinets are insulated from the supports. In this case, you can end the installation.

Otherwise, do as follows:

1) Disassemble all installed components. 3) Check whether the insulation parts have been installed or whether the insulation

parts have been damaged. 4) Re-fix the cabinets. 5) Implement insulation test again.

Page 49: UMG8900 Installation Manual-Hardware Installation

Installation Manual - Hardware Installation U-SYS UMG8900 Universal Media Gateway Chapter 3 Installing Cabinets

Huawei Technologies Proprietary

3-17

3.4 Installing Cabinets on Cement Floor

3.4.1 Installation Procedure on Cement Floor

If N68-22 cabinets are installed on cement floor, they can be fixed by expansion bolts directly.

Caution:

During installation, the insulation pads between each cabinet and floor, as well as the insulation coverings for expansion bolts must be correctly installed, to make the whole set of equipment insulated from the ground before protection grounding cables are connected, and to meet the insulation requirements.

The procedure for installing cabinets on cement floor is shown in Figure 3-16.

Combine cabinets

Fix cabinets

Plan cabinet positions

Install expansion bolts

Position cabinets

Level cabinets

Pass theinsulation

test?

N

YEnd

Start

Figure 3-16 Procedure of installing cabinets on cement floor

When two or more cabinets are placed in the same row, they must be firmly combined and fixed.

Page 50: UMG8900 Installation Manual-Hardware Installation

Installation Manual - Hardware Installation U-SYS UMG8900 Universal Media Gateway Chapter 3 Installing Cabinets

Huawei Technologies Proprietary

3-18

3.4.2 Planning Cabinet Positions

I. Determining Cabinet Positions

Before installing the cabinets, it is required to plan the available space of the equipment room. Sufficient space around the cabinets should be reserved for maintenance and operation, as shown in Figure 3-17 and Figure 3-18.

II. Marking Installation Hole Positions

To mark installation hole positions, do as follows:

1) Specify the positions for the expansion bolts with reference to the dimensions of planned positions and the dimensions of the holes for installing cabinet specified in the construction plan.

2) Mark a few points for line drawing with a long tape and draw two straight lines parallel to the benchmark with a distance of 687 mm between them.

3) According to the design requirements, specify the expansion bolt holes for the first cabinet.

4) With these holes as reference, mark the expansion bolt holes for other cabinets one by one.

5) To avoid faults, measure all location lines again after marking the holes to ensure correct dimensions.

The layout of expansion bolt holes for a single cabinet is shown in Figure 3-17.

The layout of expansion bolt holes for multiple cabinets in a row is shown in Figure 3-18.

Page 51: UMG8900 Installation Manual-Hardware Installation

Installation Manual - Hardware Installation U-SYS UMG8900 Universal Media Gateway Chapter 3 Installing Cabinets

Huawei Technologies Proprietary

3-19

800

687 800

800

800

800

413

600

4- 16∅

Figure 3-17 Hole positions for expansion bolts used for a single cabinet

Page 52: UMG8900 Installation Manual-Hardware Installation

Installation Manual - Hardware Installation U-SYS UMG8900 Universal Media Gateway Chapter 3 Installing Cabinets

Huawei Technologies Proprietary

3-20

800

800

800

600

800

800

4- 16

600 600

413

687

413 413

Figure 3-18 Hole positions for expansion bolts used for multiple cabinets in a row

It is also available to use line drawing template to mark the positions of the expansion bolt holes. Based on the cabinet layout, place the line drawing template on the floor, as shown in Figure 3-19. To mark the hole positions for all expansion bolts on the floor, use the template (each cabinet has four expansion bolts). The half-circle gap on the template indicates the front direction of the cabinet.

Page 53: UMG8900 Installation Manual-Hardware Installation

Installation Manual - Hardware Installation U-SYS UMG8900 Universal Media Gateway Chapter 3 Installing Cabinets

Huawei Technologies Proprietary

3-21

Front

Back

RightLeft

800

600

687

413

Figure 3-19 Line drawing template (used for installation on cement floor)

Note:

Be sure to use the template in correct direction.

III. Drilling Holes

To fix cabinets onto ground with the M12 expansion bolts, it is required to drill holes for expansion bolts using a percussion drill with bit φ16.

To drill a hole, do as follows:

1) Keep the drilling bit vertical to the ground and hold tight the drillstock to make holes 52 mm to 60 mm deep. The depth of the holes must be within 52 mm to 60 mm. Otherwise the expansion bolts cannot be fastened. Make sure that the depths of all holes are the same.

2) Clean the dust inside the holes with a vacuum cleaner. 3) Measure the depth to make sure that the depths of all holes are the same.

Page 54: UMG8900 Installation Manual-Hardware Installation

Installation Manual - Hardware Installation U-SYS UMG8900 Universal Media Gateway Chapter 3 Installing Cabinets

Huawei Technologies Proprietary

3-22

If the ground is too hard or smooth to settle the drill bit, punch a sample pit first for easy drilling.

Drawing lines and drilling holes are the fundamental work for hardware installation. Good quality is the prerequisite to guarantee the quality of the overall installation. If the accuracy is not high enough, the future work will be greatly affected.

Note:

The depth of the drilled hole should be 52 mm to 60 mm. A depth less than 52 mm or more than 60 mm will cause the expansion bolt unable for normal installation and fastening.

IV. Installing Expansion Bolts

Before fixing expansion bolts, clean up the dust inside and around the holes using a vacuum cleaner. Measure the distance between the holes. For the holes with big deviation, plan and drill new holes before installing expansion bolts in them.

To install an expansion bolt into a hole, do as follows:

1) Take the expansion tube and nut off the expansion bolt. 2) Put them vertically into the hole after the guiding rib on the expansion nut has

been inserted into the guiding slot of the expansion tube. 3) Strike directly on the expansion tube with a rubber hammer until it is completely

driven into the ground.

Figure 3-8 shows the installation of expansion tube and expansion nut.

3.4.3 Leveling Cabinets

I. Positioning Cabinets

To position a cabinet as shown in Figure 3-20, do as follows:

1) Lay insulation plates on the floor (two plates for each cabinet). 2) Place a cabinet at the planned position. 3) Align the installation holes in the cabinets with corresponding expansion bolt

holes.

II. Leveling Cabinets

To level the cabinets, do as follows:

Page 55: UMG8900 Installation Manual-Hardware Installation

Installation Manual - Hardware Installation U-SYS UMG8900 Universal Media Gateway Chapter 3 Installing Cabinets

Huawei Technologies Proprietary

3-23

1) Place horizontal rulers in both longitudinal and latitudinal directions on the top surface of cabinets to check the levelness of the cabinets.

2) Use washers under the insulation plates to adjust the cabinet height to keep the cabinets horizontal, as shown in Figure 3-20.

3) Align all cabinets.

(1)

(2)

(3)

(4)

(1) Bolt M12x70 (2) Spring washer 12 (3) Insulation plate (4) Washer

Figure 3-20 Leveling and fixing a cabinet

Note:

The washers for leveling should be installed between the insulation plates and floor. Otherwise, insulation will not work.

3.4.4 Fixing Cabinets

I. Fixing Bottom of Cabinet

To fix the cabinet bottom, do as follows:

Page 56: UMG8900 Installation Manual-Hardware Installation

Installation Manual - Hardware Installation U-SYS UMG8900 Universal Media Gateway Chapter 3 Installing Cabinets

Huawei Technologies Proprietary

3-24

1) Fit the spring washers on M12x70 bolts (the big flat washers and insulation coverings have been installed in the cabinet).

2) Insert the bolts vertically into the expansion bolt holes in the slide rails through the lower enclosure frame of the cabinet.

3) Screw M12x70 bolts to 45 Nm, as shown in Figure 3-20.

II. Fixing Top of Combined Cabinets

When two or more cabinets are installed, they must be combined and fixed by connecting plates.

The connecting plates for combining cabinets are installed on the top of cabinets and they are delivered with cabinets, as shown in Figure 3-21.

To combine two adjacent cabinets, do as follows:

1) Disassemble the connecting plates of the two adjacent cabinets. 2) Reassemble them according to Figure 3-21.

1 2 3

4 5 6 7

Figure 3-21 Installation of connecting plate for combining cabinets

Page 57: UMG8900 Installation Manual-Hardware Installation

Installation Manual - Hardware Installation U-SYS UMG8900 Universal Media Gateway Chapter 3 Installing Cabinets

Huawei Technologies Proprietary

3-25

3.4.5 Performing Insulation Test

To test the insulation effect of the cabinets, do as follows:

1) Set the multimeter to Megohm range. 2) Measure the impedance between expansion bolts M12x70 and cabinets.

If the impedance measured is more than 5 MΩ, it indicates that the cabinets are insulated from the expansion bolts. In this case, you can end the installation.

Otherwise, do as follows:

1) Disassemble all installed components. 3) Check whether the insulation parts have been installed or whether the insulation

parts have been damaged. 4) Re-fix the cabinets. 5) Implement insulation test again.

Page 58: UMG8900 Installation Manual-Hardware Installation

Installation Manual - Hardware Installation U-SYS UMG8900 Universal Media Gateway Chapter 4 Installing Internal Components

Huawei Technologies Proprietary

4-1

Chapter 4 Installing Internal Components

4.1 About This Chapter

This chapter contains the following sections:

Introduction to Internal Components and Installation Installing Internal Components

4.2 Introduction to Internal Components and Installation

4.2.1 Introduction to Internal Components

The internal components of N68-22 cabinet include power distribution frame, air deflector, media gateway (MGW) frame, fiber coiler, wiring bar, and cabling trough. The N68-22 cabinet adopts standard 19-inch frame, each of which has an air deflector.

The power distribution frame is installed in the top of the cabinet, and the fiber coiler is installed in the bottom. The fiber coiler is inserted or pulled out from the rear side of the cabinet, and 1U high blank filler panels are installed on the corresponding empty front panel positions. For the back cabling mode, wiring bars and cabling troughs are installed at the rear side of the cabinet.

Two fully configured cabinets are shown in Figure 4-1.

Page 59: UMG8900 Installation Manual-Hardware Installation

Installation Manual - Hardware Installation U-SYS UMG8900 Universal Media Gateway Chapter 4 Installing Internal Components

Huawei Technologies Proprietary

4-2

(1) Front view (2) Back view (3) Power distribution frame

(4) MGW frame (5) Air deflector

(6) Blank filler panel (7)Wiring bars (8) Back cabling trough (9) Fiber coiler

Figure 4-1 Internal components in fully configured cabinets

For the appearance, structure and performance of the internal components, refer to Chapter 2 in HUAWEI UMG8900 Universal Media Gateway Hardware Description Manual.

4.2.2 Introduction to Internal Component Installation

When a single MGW frame is configured in an N68-22 cabinet, it is used as the main control frame and must be installed in the middle of the cabinet. In other cases, to keep the balance of the cabinet and avoid effect to installation, it is recommended to configure and install the MGW frames from bottom upward.

Before delivery, the fiber coiler, wiring bars, cabling troughs and air deflectors have been assembled, so only such internal components as MGW frames and boards have to be installed on site.

Page 60: UMG8900 Installation Manual-Hardware Installation

Installation Manual - Hardware Installation U-SYS UMG8900 Universal Media Gateway Chapter 4 Installing Internal Components

Huawei Technologies Proprietary

4-3

4.3 Installing Internal Components

4.3.1 Installing MGW Frames

To install an MGW frame, do as follows:

1) Lift the MGW frame on corresponding guide rails and slowly push it into the cabinet.

2) Put four panel fasteners through the installation holes of the mount angles of the frame and of the mount angles at the left and right sides of the cabinet.

3) Screw them with screwdriver slightly. Fasten the four fasteners in diagonal order, and then the other fasteners in turn.

During the installation, arrange the mount angles of components correctly and keep even space between components, between component and blank filler panel, as well as between blank filler panels to avoid too large space.

4.3.2 Installing Boards

Warning:

Before installing a board, wear ESD-preventive wrist strap and ensure that the cabinets are grounded correctly. The ESD-preventive wrist strap can be connected to any grounding point in the cabinets or internal components, usually with a clip or connector. For the methods about installing and connecting protection grounding cables for the cabinets, refer to Chapter 5 "Installing Power Cables and Protection Grounding Cables" in this manual.

The steps for installing a board are as follows:

1) Loosen the fastening screws counter-clockwise on the blank filler panel with a screwdriver, and then take out the panel.

2) Put on an ESD-preventive wrist strap. Remove the antistatic bag of the board to be installed.

3) Hold tight the ejector levers of the board with both hands, pull them backward, and insert the board into the slot along the guide rail smoothly and slowly until the positioning pins on the front panel contact the positioning holes on the frame.

4) Pull the ejector levers toward each other to let the positioning pins on the front panel go smoothly into the positioning holes on the frame. Do not insert the board forcedly when the ejector levers are not in correct contact with the frame

Page 61: UMG8900 Installation Manual-Hardware Installation

Installation Manual - Hardware Installation U-SYS UMG8900 Universal Media Gateway Chapter 4 Installing Internal Components

Huawei Technologies Proprietary

4-4

beam; otherwise, you might damage the ejector levers on the board and even the slot pins on the backplane.

5) Fasten the screws clockwise to fix the board.

The installation procedure is shown in Figure 4-2.

Figure 4-2 Board installation

Warning:

When a board is power on, pull out the board after the blue hot-plugging indicator OFFLINE turns on to avoid possible damage to the equipment. After the OFFLINE indicator turns on, the board must be pulled out and then inserted again before you can power on the equipment.

Page 62: UMG8900 Installation Manual-Hardware Installation

Installation Manual - Hardware Installation U-SYS UMG8900 Universal Media Gateway

Chapter 5 Installing Power Cables and Protection Grounding Cables

Huawei Technologies Proprietary

5-1

Chapter 5 Installing Power Cables and Protection Grounding Cables

Note:

Only craftspersons who have been trained to work with powered communication circuits can do the operations specified in this chapter.

5.1 About This Chapter

This chapter contains the following sections:

Installation Procedure Installation Notices Installing Power Cables for Internal Components Installing Protection Grounding Cables for Cabinets Installing Power Cables and Protection Grounding Cables between DC Power

Distribution Cabinet to N68-22 Cabinet Installing Power Bus Cables between DC Power Distribution Cabinet and DC

Switchboard Engineering Labels for Cables

5.2 Installation Procedure

The procedure for installing power cables and protection grounding cables is shown in Figure 5-1.

Page 63: UMG8900 Installation Manual-Hardware Installation

Installation Manual - Hardware Installation U-SYS UMG8900 Universal Media Gateway

Chapter 5 Installing Power Cables and Protection Grounding Cables

Huawei Technologies Proprietary

5-2

Installing cabinets andinternal components

complete

Install protection grounding cables forconnecting grounding bars of adjacent

cabinets

Is DC power distributioncabinet provided together

with UMG8900cabinets?

Install power cables for internalcomponents

Install DC power distribution cabinet

Install protection grounding cables fromDC power distribution cabinet to

protection grounding bus in equipmentroom

Install power and protectiongrounding cables from DC

distribution cabinet provided by thecustomer to UMG8900 cabinets

Installing power cables andprotection grounding cables

complete

Yes No

Install power and protection groundingcables from DC distribution cabinet to

UMG8900 cabinets

Install power bus cables from DC powerdistribution cabinet to power room (DC

switchboard)

Figure 5-1 Procedure of installing power cables and protection grounding cables

Page 64: UMG8900 Installation Manual-Hardware Installation

Installation Manual - Hardware Installation U-SYS UMG8900 Universal Media Gateway

Chapter 5 Installing Power Cables and Protection Grounding Cables

Huawei Technologies Proprietary

5-3

5.3 Installation Notices

Whether the DC power distribution cabinet is provided together with the UMG8900 equipment depends on the contract. Generally, DC power distribution cabinet is provided by the customer.

The PGND grounding bar of DC power distribution cabinet must be correctly connected with the nearest protection grounding bar offered by the customer through protection grounding bus cable. The protection grounding cable uses green and yellow plastic insulation copper core wires whose core area is the same as that of power cable.

Before installation, mark or stick labels on both ends of each power cable and protection grounding cable to identify the device that the cable is connected to, and to ensure correct connection. For information about filling in and sticking engineering labels, refer to Appendix B "Engineering Labels for Cables" in this manual.

5.4 Installing Power Cables for Internal Components

5.4.1 Introduction to Power Cables for Internal Components

Note:

Before delivery, the power cables in the N68-22 cabinet have been connected to the connecting terminals in the power distribution frame of the cabinet. After the internal components are installed, it is only required to connect the other ends of the power cables to the components.

The power cables for internal components include power cables from power distribution frame to MGW frames and power cables for fan boxes in MGW frames.

The connection of power cables for the internal components in a cabinet is shown in Figure 5-2.

The six power switches (SW1 to SW6) on the front panel of the power distribution frame control corresponding MGW frames, as shown in Table 5-1.

Page 65: UMG8900 Installation Manual-Hardware Installation

Installation Manual - Hardware Installation U-SYS UMG8900 Universal Media Gateway

Chapter 5 Installing Power Cables and Protection Grounding Cables

Huawei Technologies Proprietary

5-4

1 3 5 6

SW1 SW3 SW4 SW6

Powerdistribution

subrack 2 4

Air deflector

Fan box

MGW subrack 3

MGW subrack 2

MGW subrack 1

SW2 SW5

1 4

52

3 6

Fan box

Fan box

Air deflector

Air deflector

Figure 5-2 –48 VDC cables from power distribution frame to various components

Table 5-1 Relationship between MGW frames and power control switches

Frame name Corresponding power control switch

SW3 MGW frame 1

SW6

SW2 MGW frame 2

SW5

SW1 MGW frame 3

SW4

Page 66: UMG8900 Installation Manual-Hardware Installation

Installation Manual - Hardware Installation U-SYS UMG8900 Universal Media Gateway

Chapter 5 Installing Power Cables and Protection Grounding Cables

Huawei Technologies Proprietary

5-5

5.4.2 Installing Power Cables from Power Distribution Frame to MGW Frame

A fully configured cabinet has three MGW frames and every MGW frame has two input power supplies. The power cables of MGW frames in different positions are only different in length.

The appearance of this power cable is shown in Figure 5-3.

Figure 5-3 Appearance of power cable for MGW frame

The power cable is made of UL1015 8AWG wire materials (core area about 8.6 mm2). One end of the power cable has two cord end terminals, which are connected to corresponding output connection holes in the power distribution frame. The other end has two OT terminals, which are connected to MGW frame. The blue cable is the –48 VDC cable and the black one is the RTN cable. Each MGW frame needs two power cables, one left and one right, and they are connected to corresponding wire posts at both ends of the filter box at the lower back of an MGW frame.

Caution:

Before powering on the equipment, confirm that the all cables are connected correctly according to the connection diagram. Wrong connection might result in severe accidents. All captive screws and nuts must be fastened, or it might result in severe accidents. The OT terminals of unused power cables must be covered with insulation coverings and then bound to cabinet. Otherwise, it might cause severe short-circuit accidents.

The procedure for installing power cables for an MGW frame goes as follows:

1) Shut off the power distribution frame in the top of the cabinet. 2) Connect the power cable from the power distribution frame to the MGW frame

strictly according to the cable connection diagram in Figure 5-2. Connect the blue cable to –48V wire post at the back of the MGW frame and the black one to the RTN wire post at the back of the MGW frame.

Page 67: UMG8900 Installation Manual-Hardware Installation

Installation Manual - Hardware Installation U-SYS UMG8900 Universal Media Gateway

Chapter 5 Installing Power Cables and Protection Grounding Cables

Huawei Technologies Proprietary

5-6

3) Confirm that the connection positions are correct, captive screws and nuts are fixed, and all power cables are fastened securely.

4) Bind the power cables to correct positions.

5.4.3 Installing Power Cables for Fan Boxes in MGW Frames

The power cable for fan box is used to supply power to the fan box in each MGW frame.

The appearance of this power cable is shown in Figure 5-4.

B direction A direction

Type 2-female-1-male

Type 2-female-1-male

Figure 5-4 Appearance of power cable for fan box

The power cable for fan box is made of UL2562 18AWG wire materials (blue-black wire with core area about 0.82 mm2), and its both ends are 3V3 connectors.

Caution:

To insert a connector into a socket, do it slowly and straightly. Do not insert by force if you feel difficult. In so doing, pull the connector out and check whether it is inserted in wrong direction or its pins are distorted.

The procedure for installing power cable for a fan box goes as follows

1) Confirm that the type-D 3V3 connector matches the 3V3 socket before inserting the connector.

2) Insert one end of the cable into the 3V3 socket at the back of an MGW frame and insert the end into the 3V3 socket at the back of the fan box under the MGW frame.

3) After the connector is inserted, tighten the two captive screws and confirm that the connector is fastened.

Page 68: UMG8900 Installation Manual-Hardware Installation

Installation Manual - Hardware Installation U-SYS UMG8900 Universal Media Gateway

Chapter 5 Installing Power Cables and Protection Grounding Cables

Huawei Technologies Proprietary

5-7

5.5 Installing Protection Grounding Cables for Cabinets

5.5.1 Introduction to Protection Grounding System

The UMG8900 equipment adopts joint grounding mode. The input terminals of GND and protection ground (PGND) of cabinets have been connected before delivery to ensure they are equipotential. In actual installation, the grounding points of MGW frames and internal components of cabinets are interconnected through protection grounding cables and all cabinets are interconnected too through protection grounding cables as an equipotential system.

5.5.2 Installing Protection Grounding Cables for Cabinet Body

Note:

The grounding of a cabinet body is done after front and back doors and side panels are installed.

In actual installation, protection grounding cables can be installed in either upward cabling mode or downward cabling mode.

If upward cable mode is adopted, do as follows to install protection grounding cables for the cabinet body:

1) Lead protection grounding cables from the copper grounding bar on DC power distribution cabinet to the grounding bolts on the top of a cabinet.

2) Use UL1015 8AWG green-yellow cables (core area about 8.6 mm2) to connect the grounding bar that connects to the grounding bolts on top of the cabinet and grounding bars on the side columns of the cabinet, as shown in Figure 5-5.

Page 69: UMG8900 Installation Manual-Hardware Installation

Installation Manual - Hardware Installation U-SYS UMG8900 Universal Media Gateway

Chapter 5 Installing Power Cables and Protection Grounding Cables

Huawei Technologies Proprietary

5-8

(4) (3)

(1)

(2)

(1) Grounding bolt on cabinet top

(2) Grounding bar on side column

(3) To cabling rack

(4) Cabinet side

Figure 5-5 Upward cabling of protection grounding cable

If the downward cabling mode is adopted, do as follows to install protection grounding cables for the cabinet body:

3) Lead the protection grounding cables from the copper grounding bar on DC power distribution cabinet through the cabling hole at the bottom of the cabinet, and lay the cable along the cabling trough on the side columns of the cabinet, finally to the top of the cabinet.

4) Use UL1015 8AWG green-yellow cables to connect the grounding bolts and the grounding bars on the side columns of the cabinet, as shown in Figure 5-6.

Page 70: UMG8900 Installation Manual-Hardware Installation

Installation Manual - Hardware Installation U-SYS UMG8900 Universal Media Gateway

Chapter 5 Installing Power Cables and Protection Grounding Cables

Huawei Technologies Proprietary

5-9

(2)

(1)

(3)

(5)

(4)(6)

(7)

(8)

(1) Back door (2) Side panel (3) Cabinet base (4) Grounding point of base

(5) Grounding bar on side column

(6) Grounding cable for cabinet door

(7) Grounding point of cabinet door

(8) To cabling trough

Figure 5-6 Downward cabling of protection grounding cable of cabinet

The grounding points of the cabinet door and the cabinet base are shown in Figure 5-6.

There are two grounding points on front door, and two on back door. After cabinet doors are installed, it is required connect four grounding cables from the four grounding points on the cabinet doors to the grounding points on the cabinet base. The protection grounding cables from the grounding points on the top of cabinet to the grounding bars are configured in pair, the same as those from the grounding points on the cabinet base to the grounding bars. In addition, the core area of the protection grounding cable from the protection grounding bar of DC power distribution cabinet is required to be not less than 25 mm2, and the grounding impedance in the equipment room is required to be less than 1 ohm.

5.5.3 Installing Protection Grounding Cables for MGW Frames

The grounding points of an MGW frame are located on the back of the frame. There are holes for installing screws Ф4 and Ф6 on the grounding bars of each cabinet.

Page 71: UMG8900 Installation Manual-Hardware Installation

Installation Manual - Hardware Installation U-SYS UMG8900 Universal Media Gateway

Chapter 5 Installing Power Cables and Protection Grounding Cables

Huawei Technologies Proprietary

5-10

To install protection grounding cables for MGW frames, use UL1015 10AWG green-yellow protection grounding cables to connect the grounding points of MGW frames and grounding bars of the cabinet, as shown in Figure 5-7.

ALARM FAN_48V

Service subrackgrounding point

MONITOR

Cabinet grounding barCabinet grounding bar

MGW subrack

RTN-48VRTN-48V

Figure 5-7 Installing protection grounding cables for MGW frame

5.5.4 Installing Protection Grounding Cables between Adjacent Cabinets

To connect grounding bars of adjacent cabinets, use UL1015 10AWG cables (300 mm long) to connect upper, middle and lower parts of the grounding bars of adjacent cabinets, as shown in Figure 5-8.

Note:

For the convenience of installing and binding other cables, connect grounding bars of adjacent cabinets after all cables have been installed.

Page 72: UMG8900 Installation Manual-Hardware Installation

Installation Manual - Hardware Installation U-SYS UMG8900 Universal Media Gateway

Chapter 5 Installing Power Cables and Protection Grounding Cables

Huawei Technologies Proprietary

5-11

Grounding bar

Service subrack

Service subrack

Service subrack

Service subrack

Service subrack

Service subrack

Figure 5-8 Connecting grounding bars of adjacent cabinets

5.6 Installing Power Cables and Protection Grounding Cables between DC Power Distribution Cabinet to N68-22 Cabinet

5.6.1 Introduction to Installing Power Cables and Protection Grounding Cables for Cabinets

If DC power distribution cabinet is provided together with the UMG8900 equipment, you need to install the DC power distribution cabinet first and use the PGND cables to connect DC power distribution cabinet and protection grounding bar of the equipment room before installing power cables and protection grounding cables between DC power distribution cabinet and N68-22 cabinet.

Page 73: UMG8900 Installation Manual-Hardware Installation

Installation Manual - Hardware Installation U-SYS UMG8900 Universal Media Gateway

Chapter 5 Installing Power Cables and Protection Grounding Cables

Huawei Technologies Proprietary

5-12

Caution:

If there is no DC power distribution cabinet in the equipment room, connect the power cables from the -48V1 and -48V2 connecting terminals of the N68-22 cabinet directly to the -48 V DC negative line bank of the DC switchboard or DC power, and connect the power cables from the GND connecting terminals of the N68-22 cabinet directly to the -48 V DC positive link bank of the DC switchboard of DC power. The PGND connecting terminals must be connected directly to the nearest protection grounding bar in the equipment room. The protection grounding cable uses green and yellow plastic insulation copper core wires whose core area is the same as that of power cable.

5.6.2 Core Areas of Power Cables and Protection Grounding Cables

The power cable from the DC power distribution cabinet to a N68-22 cabinet includes –48 VDC cables (blue) and RTN cables (black), which, together with protection grounding cable (green-yellow), are delivered with the equipment.

Their core areas are shown in Table 5-2.

Table 5-2 Core areas of cables from DC power distribution cabinet to UMG8900 cabinet

Name Specification

–48 VDC cable (blue) 25 mm2 copper core — dual

RTN cable (black) 25 mm2 copper core — dual

Protection grounding cable (green-yellow) 25 mm2 copper core

Note:

The cross area of power bus cable from DC switchboard to DC power distribution cabinet is designed according to the parameters such as loop length of the power bus cable, terminal load payload capacity for the engineering and design voltage drop. If the core area of all available power cables cannot meet the design requirements, it would be considered to connect two or more power cables in parallel. For example, if there is only 120 mm2 power cable, but a 240 mm2 power cable is required, you can use two 120 mm2 power cables in parallel connection as one power bus cable.

Page 74: UMG8900 Installation Manual-Hardware Installation

Installation Manual - Hardware Installation U-SYS UMG8900 Universal Media Gateway

Chapter 5 Installing Power Cables and Protection Grounding Cables

Huawei Technologies Proprietary

5-13

5.6.3 Installing Power Cables and Protection Grounding Cables

If DC power distribution cabinet is provided together with the UMG8900 equipment, it is required to install and connect it to the nearby protection grounding bar offered by the customer through protection grounding bus cable before installing power cables and protection grounding cables from DC power distribution cabinet to the UMG8900 cabinets.

Note:

Before connecting power cables and protection grounding cable, measure the distance between protection grounding bar and power distribution cabinet, and that between DC power distribution cabinet and connecting terminals of the power distribution frame in the cabinet. Use cables that are long enough to avoid shortage during actual wiring. If a cable is not long enough, stop your work and replace it with a new one. Do not splice cables by connectors or soldering.

It is required to stick labels on both ends of power cables, and a label must be stuck at the place where it is 30 mm apart from the root of the cable.

The connection of power cables and protection grounding cables from the DC power distribution cabinet to the N68-22 cabinets is shown in Figure 5-9.

-48V2

GND

PGND

-48V1

PGN

D

-48V

1-4

8V2

BGN

D

(1)

(2)

(3)

(4)

GND

PGN

D

-48V

1-4

8V2

BGN

D

PGN

D

-48V

1-4

8V2

BGN

D

(3) (3)

(1) To DC switchboard (2) DC power distribution cabinet (3) N68-22 cabinet (4) Protection grounding bar in equipment room

Figure 5-9 Power distribution cable connections of N68-22 cabinets

The following describes how to connect power cable and protection grounding cable from DC power distribution cabinet to a UMG8900 cabinet:

Page 75: UMG8900 Installation Manual-Hardware Installation

Installation Manual - Hardware Installation U-SYS UMG8900 Universal Media Gateway

Chapter 5 Installing Power Cables and Protection Grounding Cables

Huawei Technologies Proprietary

5-14

1) Insert the cord end terminals (as shown in Figure 5-10) of the two –48 VDC cables into the connecting terminals marked “–48V1” and “–48V2” on the power distribution frame in the cabinet. Connect the other ends of the two cables to the output connectors marked “–48V1” and “–48V2” in the DC power distribution cabinet, for example, the “–48V1” and “–48V2” power cables in the third cabinet must be connected to the third output connector of “–48V1” and third output connector of “–48V2” in the DC power distribution cabinet.

Figure 5-10 Power cable cold end terminal

2) Connect the black RTN cables to the connecting terminals marked “RTN” on the power distribution frame of the cabinet, and then connect the other ends of the black grounding cables to GND grounding bar in the DC power distribution cabinet.

Note:

The connecting terminals of DC power distribution cabinet are assigned in terms of the principles “first up, last down” and “first left, last right”. That is, for –48V1 and –48V2 connecting terminals, use the upper group first, then the lower group; for the upper group, use the connecting terminals from left to right (from the front view) one by one. The connecting terminals of positive line bank and lightning protection ground are used from left to right in sequence. In other cases when power cables are led from DC power distribution cabinet (for example, to connect protection grounding cables for a terminal), reverse principle is applied, that is, connecting terminals are used from down to top and from right to left, to facilitate future expansion and connection.

If only DC switchboard is configured in the equipment room, do as follows:

Page 76: UMG8900 Installation Manual-Hardware Installation

Installation Manual - Hardware Installation U-SYS UMG8900 Universal Media Gateway

Chapter 5 Installing Power Cables and Protection Grounding Cables

Huawei Technologies Proprietary

5-15

3) Connect the power cables led from –48V1 and –48V2 connecting terminals of the UMG8900 cabinet to –48 VDC negative line bank of DC switchboard (or DC power supply);

4) Connect the power cable led from GND connecting terminal of the UMG8900 cabinet to –48 VDC positive line bank of DC switchboard (or DC power supply);

5) Connect the protection grounding cable led from the PGND connecting terminal of the UMG8900 cabinet to the protection grounding bar nearby provided by the customer. The cable material must be the green and yellow plastic insulation copper core wire whose core area is the same as that of power cable.

5.6.4 Requirements for Installing Power Cables and Protection Grounding Cables

I. Laying Power Cables and Protection Grounding Cables at N68-22 Cabinet Side

1) When downward cabling is used, lead the power and protection grounding cables into the cabinet through the cabling holes at the bottom of the cabinet. Lay the cables along the cabling troughs on the side columns of the cabinet until they reach the top of the cabinet through the cabling holes in the top. The subsequent layout and connection are the same as those mentioned in upward cabling below.

2) When upward cabling is used, lay the power and protection grounding cables on the top of the cabinet. Connect the protection grounding cables to the grounding bolts, and then lead them out from the grounding bar that connects to the grounding bolts. Lead the power cables through the cabling holes at the top of the cabinet, and connect them to the corresponding connecting terminals in the power distribution frame.

3) To lay the power and protection grounding cables, straight and even appearance is required, and different colors must be separated, and the cables must be bound every 200 mm.

4) After the power and protection grounding cables are laid out, cut the rubber cover to match the size of the left space of the cabling hole.

II. Laying Power Cables and Protection Grounding Cables in DC Power Distribution Cabinet

To lay the power cables and protection grounding cable in the DC power distribution cabinet, do as follows:

1) Lead the power cables (settled according to colors) into DC power distribution cabinet through cabling holes in the top of the cabinet.

2) Bind them along the side columns.

Page 77: UMG8900 Installation Manual-Hardware Installation

Installation Manual - Hardware Installation U-SYS UMG8900 Universal Media Gateway

Chapter 5 Installing Power Cables and Protection Grounding Cables

Huawei Technologies Proprietary

5-16

3) After the cables reach corresponding connecting bars, bind them along the beam of the cabinet. Ensure that the cables are laid inside the cabinet with smooth and uncrossed appearance.

4) Keep proper redundancy for the cables, and cut out the surplus parts.

When you make an OT terminal for a cable, be sure to cover it with heat-shrinkable tube, solder it (soldering is not allowed when your make a cable with large core area), and shrink the heat-shrinkable tube.

When OT terminals are connected to GND copper bar and –48V wire post, add flat washers and spring washers, and arrange them in correct positions.

Note:

When power cables and protection grounding cable are laid outside cabinet, they must be bound separately. When cables are laid inside cabinet, power cables and protection grounding cable are bound separate from signal cables.

5.7 Installing Power Bus Cables between DC Power Distribution Cabinet and DC Switchboard

5.7.1 Introduction to Power Bus Cables

Power bus cables are used to connect DC power distribution cabinet and DC switchboard.

Generally provided by the customer, a power bus cable in the power room includes –48 VDC cable (blue) and grounding cable (black). The specifications of the power bus cables are determined according to the result of site survey.

5.7.2 Connecting Power Bus Cables

The connection of power cables for the auxiliary DC power distribution cabinet of the UMG8900 is shown in Figure 5-11.

For detailed information on connecting power cables, refer to User Manual delivered with the power distribution cabinet.

Page 78: UMG8900 Installation Manual-Hardware Installation

Installation Manual - Hardware Installation U-SYS UMG8900 Universal Media Gateway

Chapter 5 Installing Power Cables and Protection Grounding Cables

Huawei Technologies Proprietary

5-17

(1) GND lead-in connecting terminal

(2) –48V1 power lead-in connecting terminal

(3) –48V2 power lead-in connecting terminal

(4) PGND lead-in connecting terminal

(5) –48V1 output connecting terminal

(6) –48V2 output connecting terminal

(7) GND output connecting terminal

(8) PGND output connecting terminal

(9) GND lead-in connecting terminal for downward cabling of the system

Figure 5-11 Connecting terminals in DC power distribution cabinet

Two groups of primary power supply are used for a DC power distribution cabinet, and there are five power bus cables: one –48V1 bus cable, one –48V2 bus cable, two GND bus cables and one PGND bus cable.

The following describes how to connect the power bus cables between the DC power distribution cabinet and the DC switchboard:

1) Connect –48V1 bus bar in the DC power distribution cabinet to –48 VDC negative line bank in the active DC switchboard (or active DC power supply),

2) Connect –48V2 bus bar in the DC power distribution cabinet to –48 VDC negative line bank in the standby DC switchboard (or standby DC power supply).

3) Connect the GND bus bars in the DC power distribution cabinet to the –48 VDC positive line banks in the active and standby DC switchboards (or active and standby DC power supply).

If there is only one power supply device, connect both of the –48V1 and –48V2 bus bars of the DC power distribution cabinet to the –48 VDC output terminals of the DC switchboard (or DC power supply).

Page 79: UMG8900 Installation Manual-Hardware Installation

Installation Manual - Hardware Installation U-SYS UMG8900 Universal Media Gateway

Chapter 5 Installing Power Cables and Protection Grounding Cables

Huawei Technologies Proprietary

5-18

Note:

The PGND grounding bar of the DC power distribution cabinet must be reliably connected to the protection grounding bar in the equipment room through grounding bus cable.

5.7.3 Requirements for Installing Power Bus Cables

I. Requirements for Making and Installing Power Bus Cables

To make an OT terminal for a power cable or protection grounding cable at DC power distribution cabinet side, do as follows:

1) Cover the cable with a heat-shrinkable tube. 2) Solder (soldering is not allowed when you make a cable with large core area) or

press the OT terminal tightly. 3) Shrink the heat-shrinkable tube, and ensure that no bare wires or OT terminal

handle exist.

To fix an OT terminal at DC distribution cabinet side, add flat washers and spring washers to make the terminal fixed firmly, and to ensure secure contact, as shown in Figure 5-12.

Note:

Proper redundancy for power cables can be kept at bending angles, but other surplus parts must be cut out. If the surplus parts are cut out, OT terminal must be remade.

Page 80: UMG8900 Installation Manual-Hardware Installation

Installation Manual - Hardware Installation U-SYS UMG8900 Universal Media Gateway

Chapter 5 Installing Power Cables and Protection Grounding Cables

Huawei Technologies Proprietary

5-19

(2)

(5)(6) (4)

(3)

(1)

(1) Cable (2) Heat-shrinkable tube (3) Nut (4) Spring washer (5) Flat washer (6) Connection bolt

Figure 5-12 Connecting OT terminal

II. Requirements for Installing OT Terminals

If it is required to install two or more cables on a wire post, install the OT terminals crosswise or back-to-back without being overlapped. If the OT terminals have to be overlapped, bend the terminals by 45 degree or 90 degree, and install the biggest OT terminal at lower position. This rule is adaptable to all situations where OT terminals are installed.

The overlapped OT terminals are shown in Figure 5-13.

Page 81: UMG8900 Installation Manual-Hardware Installation

Installation Manual - Hardware Installation U-SYS UMG8900 Universal Media Gateway

Chapter 5 Installing Power Cables and Protection Grounding Cables

Huawei Technologies Proprietary

5-20

(4)

(6)

45°90°

(2)(3)

(1)

(2)(3)

(1)

(2)(3)

(1)

(5)

(1) Flat washer (2) Nut (3) Spring washer (4) 45 degree or 90 degree of bending (5) Back-to-back installation (6) Cross installation

Figure 5-13 Installing two OT terminals

5.7.4 Requirements for Laying Cables Inside DC Power Distribution Cabinet

The requirements for laying cables inside DC power distribution cabinet are as follows:

The cables laid inside DC power distribution cabinet are smooth and not crossed, and the cables in different colors are bound separately.

Proper redundancy for cables is kept and the surplus parts are cut out. Both ends of a cable have labels made by Huawei Technologies and marked

corresponding serial number. The labels are stuck 30 mm away from the cable root.

The cables are bundled by different cable ties according to the actual conditions. The cable ties face the same direction after the cables are bundled, and the burrs of the cable ties must be sheared.

When the cables are laid in the upward cabling mode, the DC power distribution cabinet is shown in Figure 5-14.

Page 82: UMG8900 Installation Manual-Hardware Installation

Installation Manual - Hardware Installation U-SYS UMG8900 Universal Media Gateway

Chapter 5 Installing Power Cables and Protection Grounding Cables

Huawei Technologies Proprietary

5-21

Figure 5-14 Upward cabling in the DC power distribution cabinet

5.8 Engineering Labels for Cables

The engineering labels are made by Huawei Technologies. For detailed information on the labels, refer to Appendix B "Engineering Labels for Cables" in this manual.

Page 83: UMG8900 Installation Manual-Hardware Installation

Installation Manual - Hardware Installation U-SYS UMG8900 Universal Media Gateway Chapter 6 Installing Signal Cables

Huawei Technologies Proprietary

6-1

Chapter 6 Installing Signal Cables

6.1 About This Chapter

This chapter contains the following sections:

Introduction to Signal Cables Introduction to Installation Procedure Requirements for Installing Signal Cables Installing Internal Signal Cables Installing External Signal Cables

6.2 Introduction to Signal Cables

6.2.1 Category of Signal Cables

The signal cables of the UMG8900 include internal signal cables and external signal cables. Among the external signal cables, global positioning system (GPS) clock cable and 2 Mbit/s clock cable are optional according to the actual configuration of the equipment.

6.2.2 Introduction to Internal Signal Cables

The internal signal cables are the connection cables necessary for the equipment to provide functions and services. They are:

Internal clock cables, including clock distribution cable and 8 kHz clock cable Monitoring cables, including monitoring cables for power distribution frame and

fan box Cascading cables, including fast Ethernet (FE) cascading cable, gigabit Ethernet

(GE) cascading cable, and time division multiplexing (TDM) cascading cable Internal E1/T1 cables to connect the UAM

Note:

The monitoring cables for power distribution frame and fan box have been installed before delivery. If it is required to expand or upgrade the equipment, refer to the method for installing monitoring cables described in Section 6.5.2 in this chapter.

Page 84: UMG8900 Installation Manual-Hardware Installation

Installation Manual - Hardware Installation U-SYS UMG8900 Universal Media Gateway Chapter 6 Installing Signal Cables

Huawei Technologies Proprietary

6-2

6.2.3 Introduction to External Signal Cables

The external signal cables are used to connect external equipment to the UMG8900. They are:

Trunk cables External optical fibers External clock cables (optional), including GPS clock cable and 2 Mbit/s clock

cable. External network cables, including straight through network cable and crossover

network cable.

6.3 Introduction to Installation Procedure

6.3.1 Procedure of Installing Internal Signal Cables

Figure 6-1 shows the procedure for installing the internal signal cables.

Installing power cables andgrounding cables completed

Install internal signalcables completed

Install internal clock cable

Install monitoring cable

Install internal E1/T1 cable

Install subtending cable

Figure 6-1 Installing internal signal cables

Page 85: UMG8900 Installation Manual-Hardware Installation

Installation Manual - Hardware Installation U-SYS UMG8900 Universal Media Gateway Chapter 6 Installing Signal Cables

Huawei Technologies Proprietary

6-3

6.3.2 Procedure of Installing External Signal Cables

The procedure for installing the external signal cables is shown in Figure 6-2.

Install trunk cable

Installing external signalcables completed

Installing internal signalcables completed

Install external network cable

Install external clock cable (optional)

Install external fiber

Figure 6-2 Installing external signal cables

Note:

Generally, trunk cables and external clock cables have same cabling route and are bound together for cabling, therefore, it is unimportant whether the trunk cables or the external clock cables are installed first.

6.4 Requirements for Installing Signal Cables

6.4.1 General Requirements

The general requirements for installing signal cables are as follows:

Before being installed, each cable must be marked or have engineering labels at both ends to identify the cable. For detailed information, refer to Appendix B "Engineering Labels for Cables" of this manual.

Page 86: UMG8900 Installation Manual-Hardware Installation

Installation Manual - Hardware Installation U-SYS UMG8900 Universal Media Gateway Chapter 6 Installing Signal Cables

Huawei Technologies Proprietary

6-4

Different types of cables, such as power cable, signal cable and protection grounding cable, must be separately bundled. When cables are laid inside cabinet, power cables and protection grounding cables must be bundled and placed along the inside cabling trough, while signal cables along the outside cabling trough.

When cables are laid in vertical directions, they must be bundled and placed along the side columns of the cabinet. When cables are laid in horizontal direction, they must be bundled and placed along cabling trough.

When power cables and signal cables are laid in groove, it is prohibited to bind them together, instead, a distance of at least 30 mm between them must be ensured.

Connectors must be secure and in good contact. Cables must be bundled to correct positions with proper tightness.

6.4.2 Method of Using Fiber Coiler

A fiber coiler is installed at the bottom of cabinet to coil the superfluous fibers.

The appearance of a fiber coiler is shown in Figure 6-3.

Figure 6-3 Appearance of a fiber coiler

A fiber coiler is a drawer-like component having guide rails at both ends. It can be pulled out of the cabinet from the back. To pull the fiber coiler out, loosen the two captive screws at both sides and then pull the fiber coiler out to a proper position along the guide rails.

When coiling optical fibers, be careful and do not force to do that to prevent fibers from being damaged. There must be proper redundancy to ensure that the optical fibers will not be stretched when the fiber coiler is inserted into the original position.

Page 87: UMG8900 Installation Manual-Hardware Installation

Installation Manual - Hardware Installation U-SYS UMG8900 Universal Media Gateway Chapter 6 Installing Signal Cables

Huawei Technologies Proprietary

6-5

After coiling the optical fibers, insert the fiber coiler into the cabinet and tighten the captive screws. Finally, arrange the optical fibers outside the fiber coiler in correct positions and bundle them firmly.

6.4.3 Method of Installing Cables In and Out of Cabinets

There is one rectangle cabling hole at each of the four corners on the top of cabinet and of the four corners at the bottom of cabinet. All the cabling holes have rodent-proof nets.

The cabling holes on the top and bottom of a cabinet are indicated by rings in Figure 6-4.

Figure 6-4 Cabling holes on the top and bottom of a cabinet

According to the actual conditions of the equipment room, the cables led in and out of cabinet can be laid through the cabling holes on the top or bottom of a cabinet.

Page 88: UMG8900 Installation Manual-Hardware Installation

Installation Manual - Hardware Installation U-SYS UMG8900 Universal Media Gateway Chapter 6 Installing Signal Cables

Huawei Technologies Proprietary

6-6

To lay the cables, do as follows:

1) Lead the cables into the cabinet through the two back cabling holes on the top or bottom of the cabinet.

2) Lay them along the side columns of the cabinet into corresponding cabling frame under each MGW frame.

3) Lay the cables through the cabling frames and insert them into corresponding sockets on the front panels of MGW frames. Be sure to get the cables in correct positions.

4) Fix them in the wire bushing.

At the cabling holes, there are rodent-proof nets, through which the cables shall pass. After cabling is completed, it is required to tie the rodent-proof nets to ensure no space left around the cables.

The external cables are laid through cabling trough or cabling rack. For the methods of installing cabling rack, refer to Appendix A "Installing Cabling Rack" of this manual.

6.5 Installing Internal Signal Cables

6.5.1 Installing Internal Clock Cables

Caution:

When installing the internal clock cable, do not insert the RJ45 connector of the clock cable into the debugging serial port of a board. Otherwise, the board may fail to start normally.

I. Type and Appearance of Internal Clock Cables

Internal clock cables include clock distribution cable and 8 kHz clock cable. Clock distribution cable connects the fixed network clock unit (FCLK) and fixed network gigabit Ethernet net unit (FNET) to provide clock signals to MGW frames. The 8 kHz clock cable is used to provide 8 kHz clock signals to the FCLKs in the main control frame. The 8 kHz line clock signals are provided by the fixed network 32 port E1 interface board (FE32), fixed network 32 port T1 interface board (FT32), fixed network ATM 4-port STM-1 fiber interface board (FA4L), fix network POS 4-port STM-1 fiber interface board (FP4L), fix network 2 x 155M SDH fiber interface board (FS2L), or fix network 2 x 155M SDH Electrical interface board (FS2E).

The appearance of the clock distribution cable is shown in Figure 6-5.

Page 89: UMG8900 Installation Manual-Hardware Installation

Installation Manual - Hardware Installation U-SYS UMG8900 Universal Media Gateway Chapter 6 Installing Signal Cables

Huawei Technologies Proprietary

6-7

One end of the cable has a DB26PIN plastic connector and the other end has six UL2464-28AWG-100Ω cables with RJ45 connectors, which correspond to three MGW frames. The cables are different in length.

B

BX2

X3

X4

X5

X6

X7

1 8

1

13

14

26

A

A

X1

Figure 6-5 Appearance of clock distribution cable

One end of 8 kHz clock cable has an RJ45 connector and the other end has two RJ45 connectors. The cable is made of two UL2464-28AWG-100Ω cables.

The appearance of this cable is shown in Figure 6-6.

A

AX1 X2

X31 8

Figure 6-6 Appearance of 8 kHz clock cable

II. Installation Requirements

Clock cables are laid separately from power cables, and bundled along the horizontal cabling trough at the back of cabinet and along the vertical cabling troughs on side columns of cabinet.

III. Installing Internal Clock Cables

The UMG8900 has three master clock distribution cables and three slave clock distribution cables to provide clock signals from the FCLKs in the main control frame to other MGW frames.

When the UMG8900 is fully configured, the connection relationships of clock distribution cables are shown in Figure 6-7.

Page 90: UMG8900 Installation Manual-Hardware Installation

Installation Manual - Hardware Installation U-SYS UMG8900 Universal Media Gateway Chapter 6 Installing Signal Cables

Huawei Technologies Proprietary

6-8

Serv icef rame

Maincontrolf rame

Centralswitching

f rame

Expensioncontrolf rame

FNET

FNET

FNET

FNET

FNET

FNET

FNET

FNET

FNET

FNET

FNET

FNET

FNET

FNET

FNET

FNET

FNET

FNET

FCLK

FCLK

Connect to the FCLKinserted in the slot 0

Serv icef rame

Serv icef rame

Serv icef rame

Serv icef rame

Serv icef rame

Connect to the FCLKinserted in the slot 1

Figure 6-7 Connecting clock distribution cables

Note:

It is not required to connect the FCLKs and FNETs in the main control frame through clock distribution cables because the clock signals are connected through the backplane.

To install the master clock distribution cables, do as follows:

1) Connect the DB26PIN connectors of the three clock distribution cables respectively to the interfaces CLK_OUT0, CLK_OUT1 and CLK_OUT2 on the front panel of the FCLK in slot 0.

2) Connect the RJ45 connectors of the cables respectively to the interfaces CLK0_IN of the FNETs in MGW frames.

To install the slave clock distribution cables, do as follows:

Page 91: UMG8900 Installation Manual-Hardware Installation

Installation Manual - Hardware Installation U-SYS UMG8900 Universal Media Gateway Chapter 6 Installing Signal Cables

Huawei Technologies Proprietary

6-9

1) Connect the DB26PIN connectors of another three clock distribution cables respectively to the interfaces CLK_OUT0, CLK_OUT1 and CLK_OUT2 on the front panel of the FCLK in slot 1.

2) Connect the RJ45 connectors of them to the interfaces CLK1_IN on the six FNETs.

Note:

The clock distribution cables must be labeled before installing. Make sure the first cable has been installed correctly before installing the second cable.

The connection relationships of clock distribution cables are shown in Figure 6-8.

CLK

_OU

T0

CLK

_OU

T0

FCLK FCLKFNET FNET

FNET FNET

FNET FNET

CLK

1_IN

CLK

0_IN

CLK

1_IN

CLK

0_IN

CLK

1_IN

CLK

0_IN

CLK

1_IN

CLK

0_IN

CLK

1_IN

CLK

0_IN

CLK

1_IN

CLK

0_IN

(1)(2)

(1) The FCLK in slot 0 (2) The FCLK in slot 1

Figure 6-8 Connection relationships of clock distribution cables

The UMG8900 has one master line clock cable and one slave line clock cable.

To install the master line clock cable, do as follows:

1) Connect its one end to interface 8k_OUT (RJ48 interface) of the active FE32, FT32, FA4L, FP4L, FS2L or FS2E.

Page 92: UMG8900 Installation Manual-Hardware Installation

Installation Manual - Hardware Installation U-SYS UMG8900 Universal Media Gateway Chapter 6 Installing Signal Cables

Huawei Technologies Proprietary

6-10

2) Connect the other end respectively to interfaces 8k_IN1 (RJ45 interfaces) on the front panels of the active and standby FCLKs.

To install the slave line clock cable, do as follows:

1) Connect its one end to interface 8k_OUT (RJ48 interface) on the standby FE32, FT32, FA4L, FP4L, FS2L, or FS2E.

2) Connect the other end respectively to interfaces 8k_IN2 (RJ45 interfaces) on the front panels of the active and standby FCLKs.

Figure 6-9 shows the connection relationships of 8 kHz line clock cables, taking FE32 board as an example.

E1/

T1_0

~15

8K_O

UT

E1/

T1_1

6~31

E1/

T1_0

~15

E1/

T1_1

6~31

8K_O

UT

8K_I

N2

8K_I

N2

8K_I

N1

8K_I

N1

FE32 FE32 FCLK FCLK

Figure 6-9 Connection relationships of 8 kHz line clock cable

6.5.2 Installing Monitoring Cables

I. Type and Appearance of Monitoring Cables

Monitoring cables include monitoring cable for power distribution frame and monitoring cable for fan box. The former is used to monitor power distribution frame and the latter is used to monitor fan box in each MGW frame.

In each cabinet, one MGW frame is required to provide monitoring cable interface to the power distribution frame of the cabinet. In the main control cabinet, main control frame provides the monitoring cable interface. In service cabinet, the middle service frame provides the monitoring cable interface. For such MGW frame, to monitor

Page 93: UMG8900 Installation Manual-Hardware Installation

Installation Manual - Hardware Installation U-SYS UMG8900 Universal Media Gateway Chapter 6 Installing Signal Cables

Huawei Technologies Proprietary

6-11

power distribution frame and auxiliary fan box at the same time, a monitoring cable with two branches is required, as shown in Figure 6-10.

A

APOS.1

POS.9 X1

(1)

X2

X3

(2)

(3)POS.1

POS.15

POS.15

POS.1

C

B

B

Figure 6-10 Appearance of monitoring cable with two branches

For other MGW frames, only monitoring cable for fan box is required, as shown in Figure 6-11.

(1) (2)

A

A

POS.9

POS.1

X1 X2

B

BPOS.15

POS.1

Figure 6-11 Appearance of monitoring cable for fan box

II. Installation Requirements

The installation requirements are as follows:

The label print on cable connector must be consistent with the silk-screen on corresponding socket.

Confirm that the type-D connector matches the type-D socket before inserting the connector. Incorrect insertion may bend the pins.

Insert connector slowly and straightly into socket. If you feel difficult to insert it, do not insert by force. Pull it out and check whether it is inserted in reverse direction or the connector is deformed.

After the connector is inserted, tighten the two captive screws and confirm that the connector is fastened.

Page 94: UMG8900 Installation Manual-Hardware Installation

Installation Manual - Hardware Installation U-SYS UMG8900 Universal Media Gateway Chapter 6 Installing Signal Cables

Huawei Technologies Proprietary

6-12

III. Installing Monitoring Cables

To install a monitoring cable, do as follows:

1) Insert the DB9 male connector into the socket marked “Monitor” at the back of MGW frame.

2) Insert the DB15 male connector into the monitoring cable interface of the fan box under the MGW frame.

3) Insert the DB15 female connector into the monitoring cable interface at the back of power distribution frame in the top of the cabinet.

From the rear view of cabinets, the connection relationships of the monitoring cables are shown in Figure 6-12.

DB15

DB15

DB15

DB9

DB9

DB9

Power distribution frame

Service frame

Central switching frame

Main control frame

Dummy panel

Fan box

Dummy panel

Fan box

Fan box

DB15

DB15

DB15

DB15

DB9

DB9

DB9

Dummy panel

Fan box

Dummy panel

Fan box

Fan box

DB15

Service frame

Service frame

Service frame

Main control cabinet Service cabinet

Power distribution frame

Figure 6-12 Connection relationships of monitoring cables

Page 95: UMG8900 Installation Manual-Hardware Installation

Installation Manual - Hardware Installation U-SYS UMG8900 Universal Media Gateway Chapter 6 Installing Signal Cables

Huawei Technologies Proprietary

6-13

6.5.3 Installing Cascading Cables

I. Type and Appearance of Cascading Cables

Cascading cables include FE cascading cable, GE cascading cable and TDM cascading cable. FE cascading cable is crossover network cable, and GE and TDM cascading cables are optical fibers.

The appearance of a crossover network cable is shown in Figure 6-13.

Figure 6-13 Appearance of crossover network cable

The connection relationships of the crossover network cable are shown in Table 6-1.

Table 6-1 Connection relationships of the crossover network cable

X1 Cable No. X2 Cable No. Remark

1 3

2 6 One twisted pair

3 1

4 4 One twisted pair

5 5

6 2 One twisted pair

7 7

8 8 One twisted pair

Cascading optical fiber is LC fiber, as shown in Figure 6-14.

Page 96: UMG8900 Installation Manual-Hardware Installation

Installation Manual - Hardware Installation U-SYS UMG8900 Universal Media Gateway Chapter 6 Installing Signal Cables

Huawei Technologies Proprietary

6-14

Figure 6-14 LC optical fiber

Note:

When two or more frames are configured, cascading cables are required. When two frames are configured, direct connection mode is adopted. If three or more frames are configured, a central switching frame is required to provide cascading boards to connect with the frames.

II. Installation Requirements

To prevent optical fibers from being damaged, cables and optical fibers must be laid separately. Colligate optical fibers with nylon straps. The curvature radius of the bending part of optical fibers must not be less than 35 mm and the surplus fibers must be rolled on fiber coiler.

III. Installing Cascading Cables

When two frames are cascaded, connect the main control frame and service frames directly with cascading cables. Between the NETs of the main control frame and of a service frame, use one pair of FE cascading cables and two pairs of GE cascading cables. Between TDM central switching network units (TNUs) of the main control frame and TDM convergence & link units (TCLUs) of a service frame, use three pairs of TDM cascading cables. The NETs, TCLUs and TNUs are configured in active/standby mode and the connection relationships are the same.

When three or more frames are cascaded, one of them functions as the central switching frame that has back link units (BLUs) used to implement cascading. The

Page 97: UMG8900 Installation Manual-Hardware Installation

Installation Manual - Hardware Installation U-SYS UMG8900 Universal Media Gateway Chapter 6 Installing Signal Cables

Huawei Technologies Proprietary

6-15

connection method between the main control frame and the central switching frame is the same as that when two frames are cascaded, that is:

Use one pair of FE cascading cables and two pairs of GE cascading cables between the NETs of the main control frame and of a service frame

Use three pairs of TDM cascading cables between the TCLUs of the main control frame and the TNUs of the central switching frame.

The BLUs in the central switching frame provide cascading cable interfaces for cascading cables to connect to service frames. Every pair of BLUs can be cascaded with one service frame. Each BLU can be connected to the NETs of a service frame with one pair of FE cascading cables and two pairs of GE cascading cables, and to the TCLUs of a service frame with three pairs of TDM cascading cables. The extended control frame and the central switching frame are connected through FE cascading cable.

When the frames are fully configured, the connection relationships of cascading cables are shown in Figure 6-15..

When two frames are cascaded, the connection relationships are shown in Figure 6-16.

When three frames are cascaded, the connection relationships are shown in Figure 6-17.

NET

TNU

NET

BLU

(1#)

(0#)

2#(2# to 7#)

3# 4# 5# 6# 7#

NET

TNU

BLU

BLU

BLU

BLU

BLU

BLU

BLU

BLU

BLU

BLU

BLU

NET

TNU

NET

TNU

NET

NET

TNU

NET

BLU

Centralswitchingsubrack

NET

TNU

BLU

BLU

BLU

BLU

BLU

BLU

BLU

BLU

BLU

BLU

BLU

NET

TNU

NET

TNU

NET

NET

TNU

NET

BLU

GE

NET

TNU

BLU

BLU

BLU

BLU

BLU

BLU

BLU

BLU

BLU

BLU

BLU

NET

TNU

NET

TNU

NET

NET

TNU

NET

BLU

(8#)

NET

TNU

BLU

BLU

BLU

BLU

BLU

BLU

BLU

BLU

BLU

BLU

BLU

NET

TNU

NET

TNU

NET

NET

TNU

NET

BLU

Main controlsubrack

Control subrack

Service subrack

NET

TNU

BLU

BLU

BLU

BLU

BLU

BLU

BLU

BLU

BLU

BLU

BLU

NET

TNU

NET

TNU

NET

FETDM

Figure 6-15 Connection relationships of cascading cables

Page 98: UMG8900 Installation Manual-Hardware Installation

Installation Manual - Hardware Installation U-SYS UMG8900 Universal Media Gateway Chapter 6 Installing Signal Cables

Huawei Technologies Proprietary

6-16

(1)

(2)

(4) (4)

(3) (3)

(5) (5)

FNET

RUNALMACT

ACT

LINK

TX0

RX0

ACT

LINK

TX1

RX1

CO

M0

CLK

1_IN

CLK

0_IN

FE1

FE0

MIR

OM

C

OFFLINE

FNET

RUNALMACT

ACTLIN

K

TX0

RX0

ACTLIN

K

TX1

RX1

CO

M0

CLK

1_IN

CLK

0_IN

FE1

FE0

MIR

OM

C

OFFLINE

TCLU

RUNALMACT

ACTLIN

K

TX0

RX0

ACT

LINK

TX1

RX1

ACT

LINK

TX2

RX2

CO

M0

OFFLINE

TCLU

RUNALMACT

ACT

LINK

TX0

RX0

ACTLIN

K

TX1

RX1

ACTLIN

K

TX2

RX2

CO

M0

OFFLINE

FNET

RUNALMACT

ACT

LINK

TX0

RX0

ACT

LINK

TX1

RX1

CO

M0

CLK

1_IN

CLK

0_IN

FE1

FE0

MIR

OM

C

OFFLINE

FNET

RUNALMACT

ACTLIN

K

TX0

RX0

ACTLIN

K

TX1

RX1

CO

M0

CLK

1_IN

CLK

0_IN

FE1

FE0

MIR

OM

C

OFFLINE

FTNU

RUNALMACT

ACT

LINK

TX0

RX0

ACT

LINK

TX1

RX1

ACT

LINK

TX2

RX2

CO

M0

OFFLINE

FTNU

RUNALMACT

ACT

LINK

TX0

RX0

ACTLIN

K

TX1

RX1

ACTLIN

K

TX2

RX2

CO

M0

OFFLINE

(1) Service frame

(2) Main control frame

(3) FE cascading cable

(4) TDM cascading cable (fiber)

(5) GE cascading cable (fiber)

Figure 6-16 Connection relationships when two frames are cascaded

Page 99: UMG8900 Installation Manual-Hardware Installation

Installation Manual - Hardware Installation U-SYS UMG8900 Universal Media Gateway Chapter 6 Installing Signal Cables

Huawei Technologies Proprietary

6-17

(2)

(3)

(4) (4)

(5) (5)

(6)

(6)

FNET FNET TCLU

FTNU

RUNALMACT

ACTLIN

K

TX0

RX0

ACTLIN

K

TX1

RX1

ACTLIN

K

TX2

RX2

CO

M0

OFFLINE

FTNU

RUNALMACT

ACTLIN

K

TX0

RX0

ACTLIN

K

TX1

RX1

ACTLIN

K

TX2

RX2

CO

M0

OFFLINE

FNET

TX1

RX1

FNET

TX0

RX0

TX1

RX1

FBLU

RUNALMACT

RX1

CO

M0

FE0

OFFLINE

FBLU

RUNALMACT

CO

M0

FE0

OFFLINE

RUNALMACT

ACTLIN

K

TX0

RX0

ACTLIN

K

CO

M0

CLK

1_IN

CLK

0_IN

FE1

FE0

MIR

OM

C

OFFLINE

RUNALMACT

ACTLIN

K

ACTLIN

K

CO

M0

CLK

1_IN

CLK

0_IN

FE1

FE0

MIR

OM

C

OFFLINE

RUNALMACT

ACTLIN

K

TX0

RX0

ACTLIN

K

CO

M0

CLK

1_IN

CLK

0_IN

FE1

FE0

MIR

OM

C

OFFLINE

RUNALMACT

ACTLIN

K

ACTLIN

K

CO

M0

CLK

1_IN

CLK

0_IN

FE1

FE0

MIR

OM

C

OFFLINE

TCLU

RUNALMACT

ACTLIN

K

TX0

RX0

ACTLIN

K

TX1

RX1

ACTLIN

K

TX2

RX2

CO

M0

OFFLINE

RUNALMACT

ACTLIN

K

TX0

RX0

ACTLIN

K

TX1

RX1

ACTLIN

K

TX2

RX2

CO

M0

OFFLINE

(1)

(4) (4)

(5) (5)

FNET FNET TCLU

RUNALMACT

ACTLIN

K

TX0

RX0

ACTLIN

K

CO

M0

CLK

1_IN

CLK

0_IN

FE1

FE0

MIR

OM

C

OFFLINE

RUNALMACT

ACTLIN

K

ACTLIN

K

CO

M0

CLK

1_IN

CLK

0_IN

FE1

FE0

MIR

OM

C

OFFLINE

TCLU

RUNALMACT

ACTLIN

K

TX0

RX0

ACTLIN

K

TX1

RX1

ACTLIN

K

TX2

RX2

CO

M0

OFFLINE

RUNALMACT

ACTLIN

K

TX0

RX0

ACTLIN

K

TX1

RX1

ACTLIN

K

TX2

RX2

CO

M0

OFFLINE

ACTLIN

K

TX0

RX0

ACTLIN

K

TX1

ACTLIN

K

TX0

RX0

ACTLIN

K

TX1

RX1

ACTLIN

K

TX0

RX0

ACTLIN

K

TX1

ACTLIN

K

TX0

RX0

ACTLIN

K

TX1

RX1RX1

RX2ACT

LINK

TX2 ACTLIN

K

TX2

RX2

TDM TDM

GE GE

(6)

(6)

(1) Service frame (2) Main control frame (3) Central switching frame (4) TDM cascading cable (fiber) (5) FE cascading cable (6) GE cascading cable (fiber)

Figure 6-17 Connection relationships when three frames are cascaded

Page 100: UMG8900 Installation Manual-Hardware Installation

Installation Manual - Hardware Installation U-SYS UMG8900 Universal Media Gateway Chapter 6 Installing Signal Cables

Huawei Technologies Proprietary

6-18

6.5.4 Installing Internal E1/T1 Cables

I. Type and Appearance of Internal E1/T1 Cables

The internal E1/T1 cable is used to connect the user access module. There are two types of internal trunk cables, 75/120 ohm E1 trunk cable and 100 ohm T1 trunk cable.

The 75 ohm E1 trunk cable is 32-core coaxial cable with the impedance of 75 ohm, and the 120 ohm E1/T1 trunk cable uses 32 pairs of twisted pairs with the characteristic impedance of 120 ohm.

The appearance of a trunk cable is shown in Figure 6-18.

Figure 6-18 Appearance of a trunk cable

II. Installation Requirements

The UMG8900 can be used as a local exchange in the traditional PSTN upgrading and expansion or as a large capacity AG in the NGN. In such cases, the UMG8900 consists of two modules, Service Switching Module (SSM) and User Access Module (UAM), as shown in Figure 6-19.

Page 101: UMG8900 Installation Manual-Hardware Installation

Installation Manual - Hardware Installation U-SYS UMG8900 Universal Media Gateway Chapter 6 Installing Signal Cables

Huawei Technologies Proprietary

6-19

SSM

Mainframe

Directframe

RSAframe......

TDMConnection

Softx3000

UMG8900

Sub frame RSA subframe

UAM

POTS/ISDN/XDSL User

Figure 6-19 UMG8900 architecture

The frame modes of the UAM are shown in Table 6-1.

Table 6-1 UAM frame modes

Mode Description

Main frame A main frame is the frame that has the PV8 or PV4 main control board. It connects with the SSM by the internal E1 cable. It connects with and manages the sub board through the HW cable.

Sub Frame A sub frame is the frame that has the RSP main control board. It connects with the main frame by the HW cable and receives the management of the main control board of the main frame.

Direct frame A direct frame is the frame that has the RSP or RSA main control board. It connects with the SSM by the E1/T1 cable but cannot attach other types of sub frames.

RSA frame A RSA frame is the frame that has the RSA main control board. It connects with the SSM by the E1/T1 cable. It connects with and manages the RSA sub frame by the HW cable and the NOD cable.

RSA sub frame

A RSA sub frame is the subscriber frame that has the DRV main control board. It connects with the RSA main frame by the HW cable and the NOD cable. It receives the management from the main control board of the RSA main frame.

Page 102: UMG8900 Installation Manual-Hardware Installation

Installation Manual - Hardware Installation U-SYS UMG8900 Universal Media Gateway Chapter 6 Installing Signal Cables

Huawei Technologies Proprietary

6-20

III. Installing Internal E1/T1 Cables

The three main ways to connect the SSM with the UAM are shown as follows:

The SSM and the USM connect with each other directly by cables.

If there is no DDF rack in the machine room, the E1/T1 cable of the SSM can be connected with the corresponding E1/T1cable of the UAM by using coaxial cable conversion connectors.

The SSM and the UAM connect with each other by the DDF rack.

If there is a DDF rack in the machine room, the E1/T1 cables of the SSM and the UAM can be connected to the DDF rack by the jumper provided by the DDF rack.

The SSM and the UAM connect with each other through the SDH transmission equipment.

If the UAM is located at the remote end, the SSM and the UAM are connected to their respective transmission equipment by the E1/T1 cable. The transmission equipment at both ends are connected through the transmission network.

For details about the connection modes between the SSM and the UAM, refer to Appendix D “Connecting the UAM”.

For the detailed installation description of the UAM, refer to the series of UAM user manuals listed below:

U-SYS UMG8900 Universal Media Gateway UAM-F01&02A User Manual

U-SYS UMG8900 Universal Media Gateway UAM-F01&02AF User Manual

U-SYS UMG8900 Universal Media Gateway UAM-F01D200 User Manual

U-SYS UMG8900 Universal Media Gateway UAM-F01D500 User Manual

U-SYS UMG8900 Universal Media Gateway UAM-F01D1000 User Manual

U-SYS UMG8900 Universal Media Gateway UAM-160B User Manual

U-SYS UMG8900 Universal Media Gateway UAM-60A User Manual

U-SYS UMG8900 Universal Media Gateway UAM-N68 User Manual

Page 103: UMG8900 Installation Manual-Hardware Installation

Installation Manual - Hardware Installation U-SYS UMG8900 Universal Media Gateway Chapter 6 Installing Signal Cables

Huawei Technologies Proprietary

6-21

6.6 Installing External Signal Cables

6.6.1 Installing Trunk Cables

I. Type and Appearance of Trunk Cables

There are two types of trunk cables used in the UMG8900, 75/120 ohm E1 trunk cable and 100 ohm T1 trunk cable. Both types adopt HD100PIN connectors with pin spacing of 1.27 mm, and each cable includes 16 channels of E1 or T1 signals.

The 75 ohm E1 trunk cable is 32-core coaxial cable with the impedance of 75 ohm, and the 120 ohm E1/T1 trunk cable uses 32 pairs of twisted pairs with the characteristic impedance of 120 ohm.

The appearance of a trunk cable is shown in Figure 6-20.

II. Installation Requirements

The length of the trunk cables and the type of the DDF are confirmed during the site survey. Because the external diameter of a single wire jacket is 1.95 mm and the external diameter of the insulation jacket is 1.05 mm, it is required to use corresponding connectors when the DDF is installed on site.

The length of the cables to be laid is determined during the site survey, and proper redundancy is required. If a cable is not long enough, you must replace it with other proper cable. In some special cases, you can use dedicated coaxial cable connector to splice cables, but soldering is prohibited.

Note:

It is not recommended to bundle trunk cables in cabling trough behind frame to facilitate board insertion.

III. Installing Trunk Cables

To install a trunk cable, do as follows:

1) Connect one end to the FE32 or FT32. 2) Connect the other end to the DDF.

Figure 6-20 shows the connection relationships of trunk cables, taking E1 cable (connected to FE32 board) as example.

Page 104: UMG8900 Installation Manual-Hardware Installation

Installation Manual - Hardware Installation U-SYS UMG8900 Universal Media Gateway Chapter 6 Installing Signal Cables

Huawei Technologies Proprietary

6-22

FE32

16E1

16E1

E1/T

1_16

~31

E1/T

1_0~

15

(1)

(1) To DDF

Figure 6-20 Connection relationships of trunk cables

6.6.2 Installing External Clock Cables

I. Type and Appearance of Externla Clock Cables

External clock cables include 2 Mbit/s external clock cable and GPS clock cable. The 2Mbit/s clock cable is BITS clock cable, which has SMB female connectors. It is used to access the synchronous clock signals provided by external BITS. The GPS clock cable has SMA male connectors and it is used to connect FCLK board and GPS clock device. For connection of GPS clock cables, refer to Appendix C “Installing Antenna System”.

The appearance of a clock cable is shown in Figure 6-21.

Page 105: UMG8900 Installation Manual-Hardware Installation

Installation Manual - Hardware Installation U-SYS UMG8900 Universal Media Gateway Chapter 6 Installing Signal Cables

Huawei Technologies Proprietary

6-23

II. Installation Requirements

The clock signals between external clock device and the UMG8900 have to be transferred by DDF. For this, one end of external clock cable has no connector, and it will be crimped with connector according to the type of the DDF on site.

III. Installing External Clock Cables

To install an external clock cable, do as follows:

1) Connect one end to FCLK. 2) Connect the other end to DDF.

The connection relationships of external clock cables are shown in Figure 6-21.

ANT

(1)

(2)

(3)

(4)

FCLK

CLK_OUT2

CLK_OUT1

CLK_OUT0

8K_IN1

8K_IN2

2M_OUT

2M_IN

RUNALMACT

(1)GPS clock cable (2) 2 Mbit/s clock cable (output) (3) 2 Mbit/s clock cable (input) (4) To DDF

Figure 6-21 Connection relationships of external clock cables

6.6.3 Installing External Network Cables

I. Type and Appearance of External Network Cables

External network cables are used to connect the UMG8900 and local maintenance terminal (LMT), the SOFTX3000 device or another Media Gateway (MGW) device.

Page 106: UMG8900 Installation Manual-Hardware Installation

Installation Manual - Hardware Installation U-SYS UMG8900 Universal Media Gateway Chapter 6 Installing Signal Cables

Huawei Technologies Proprietary

6-24

External network cables include straight through network cable and crossover network cable. Crossover network cable is used when a PC or MGC is connected to the UMG8900 directly. Straight through network cable is used when they are connected through HUB or Ethernet switch.

Straight through network cable looks the same as crossover network cable. They have shielded plastic crystal connectors at both ends and their cable materials are category-5 shielded twisted pair. They are only different in line assignment.

The appearance of the network cable is shown in Figure 6-13.

II. Installation Requirements

Network cable is laid through DDF and the length is determined according to the site survey. The installation and layout requirements are similar to those for trunk cable and clock cable.

III. Installing External Network Cables

For specific installation method, refer to construction documentation.

6.6.4 Installing External Optical Fibers

I. Type and Appearance of External Optical Fibers

You need to select a fiber connector according to the optical interface type of the opposite device that is connected to the network interface module of the UMG8900. Single-mode optical interface can only use single-mode fiber and multi-mode optical interface can only use multi-mode fiber.

The optical modules in fixed network gigabit 1-port optical fiber interface board (FG1O), fixed network 1-port 622M POS fiber interface board (FP1H), FS2L, FA4L and FP4L boards all adopt LC connectors and LC optical fibers are used correspondingly.

The appearance of the external optical fiber is shown in Figure 6-14.

II. Installation Requirements

Before connecting optical fibers, it is required to ensure the connector type and fiber type are applicable to the type of the adopted optical interface.

To lay the external fibers, it is required to use corrugated plastic tubes or other protection tubes to protect the optical fibers.

Page 107: UMG8900 Installation Manual-Hardware Installation

Installation Manual - Hardware Installation U-SYS UMG8900 Universal Media Gateway Chapter 6 Installing Signal Cables

Huawei Technologies Proprietary

6-25

III. Installing External Optical Fibers

To install an external optical fiber, do as follows:

1) Lead the optical fiber out of the optical module interface on the front panel of FG1O, FP1H, FS2L, FA4L or FP4L.

2) Connect it to the external optical distribution frame (ODF) or external optical interface/transmission device.

For specific connection relationships, refer to the construction documentation.

Page 108: UMG8900 Installation Manual-Hardware Installation

Installation Manual - Hardware Installation U-SYS UMG8900 Universal Media Gateway Chapter 7 Installing Cabinet Fittings

Huawei Technologies Proprietary

7-1

Chapter 7 Installing Cabinet Fittings

7.1 About This Chapter

This chapter contains the following sections:

Installing ESD-Preventive Floor Holders and Recovering Floor Installing Door Lintels Installing Cabinet Side Panels Installing Front and Back Doors

7.2 Installing ESD-Preventive Floor Holders and Recovering Floor

7.2.1 Installing ESD-Preventive Floor Holders

The floor holder-slide rail assemblies are used to support ESD-preventive floor around the cabinet. The assemblies include front floor holder, back floor holder, and side floor holder. Front and back floor holders are fixed on the holder fixing components, and side floor holders are fixed on the supports at both ends of a cabinet row.

To install the floor holders, do as follows:

1) Use M12 bolts, spring washers, and flat washers to fix the front and back floor holders of each cabinet onto the holder fixing components.

2) Insert M12x30 bolts through the bolt holes of side floor folders and front and back floor folders to fix the side floor holders onto the supports at both ends of a cabinet row, as shown in Figure 7-1.

Page 109: UMG8900 Installation Manual-Hardware Installation

Installation Manual - Hardware Installation U-SYS UMG8900 Universal Media Gateway Chapter 7 Installing Cabinet Fittings

Huawei Technologies Proprietary

7-2

(1) Cabinet (2) Slide rail (3) Support (4) Bolt M12x30 (5) Spring washer 12(6) Flat washer 12 (7) Front floor holder (8) Holder fixing component (9) Side floor holder

Figure 7-1 Fixing floor holders and slide rails

7.2.2 Adjusting Holder Height

To adjust the height a floor holder, do as follows:

1) Loosen the bolt M12 in the floor holder. 2) Adjust the height of the floor holder to make its upper plane on the same height

as the lower plane of the ESD-preventive floor. 3) Secure the bolts M12.

7.2.3 Cutting and Recovering ESD-Preventive Floor

In this step, cut the ESD-preventive floor around the cabinet to match the border of the cabinet according to actual conditions on site and then recover the floor.

7.3 Installing Door Lintels

Each cabinet has four door lintels, which are installed on the upper/lower enclosure frames at the front and back of the cabinet.

Page 110: UMG8900 Installation Manual-Hardware Installation

Installation Manual - Hardware Installation U-SYS UMG8900 Universal Media Gateway Chapter 7 Installing Cabinet Fittings

Huawei Technologies Proprietary

7-3

To install door lintels, do as follows:

1) Align the door lintels with the mount brackets on the upper and lower enclosure frames.

2) Put the hooks of the door lintels into the slots of the mount brackets. 3) Use four M3 countersunk screws to fasten the door lintels, as shown in Figure

7-2.

Figure 7-3 shows the cabinet with door lintels.

(4)

(3)

(2)

(1)

(5)

(1) Mount bracket slot

(2) Door lintel hook

(3) Door lintel (4) M3 countersunk screw

(5) Cabinet

Figure 7-2 Installation of door lintel

Page 111: UMG8900 Installation Manual-Hardware Installation

Installation Manual - Hardware Installation U-SYS UMG8900 Universal Media Gateway Chapter 7 Installing Cabinet Fittings

Huawei Technologies Proprietary

7-4

Figure 7-3 Cabinet with door lintels

7.4 Installing Cabinet Side Panels

A cabinet row requires four side panels at both ends. Each ends has two side panels installed on the flat column of the cabinet.

To install the side panels, do as follows:

1) Loosen the clamping pole on the flat column. 2) Make the slot of a side panel onto the clamping pole downward, and buckle the

side panel into the open slot of the mount bracket. 3) Align the installation holes and secure the two M6 countersunk screws, as shown

in Figure 7-4.

Page 112: UMG8900 Installation Manual-Hardware Installation

Installation Manual - Hardware Installation U-SYS UMG8900 Universal Media Gateway Chapter 7 Installing Cabinet Fittings

Huawei Technologies Proprietary

7-5

(1)

(2)

(3)

(1) Clamping pole (2) Side panel slot (3) M6 countersunk screw

Figure 7-4 Installation of side panel

7.5 Installing Front and Back Doors

A front door is composed of left door panel and right door panel, the same as the back door. Before installing the front and back doors, it is required to complete the installation of all kinds of frames, internal components, and circuit boards, as well as the connection of cables. The front and back doors must not be installed until all other hardware devices are installed completely.

The installation of the front and back doors is shown in Figure 7-5.

The installation procedure is as follows:

1) Align the lower pin of a door panel with the pin hole on the lower enclosure frame of the cabinet to install the lower border of the door panel.

2) Pull down the shuffle pin at the upside of the door panel, and align the hole for the pin on the door panel with the pin hole on the upper enclosure frame.

3) Release the shuffle pin. The shuffle pin is pulled by the spring to return to the original position. The door panel is installed on the cabinet.

4) After the front doors are installed, stick the product brand in the concave on the upper part of front door.

Page 113: UMG8900 Installation Manual-Hardware Installation

Installation Manual - Hardware Installation U-SYS UMG8900 Universal Media Gateway Chapter 7 Installing Cabinet Fittings

Huawei Technologies Proprietary

7-6

A

A

(1)

(2)

(1) Direction A: Align the lower pin of the door with the pin hole on the lower enclosure frame of the cabinet to install the lower border of the door. (2) Pull down the shuffle pin, align hole for the shuffle pin on the door panel with the pin hole on the upper enclosure frame. Then loosen the shuffle pine, and the shuffle pin returns to the original position, thus the door panel is installed on the cabinet.

Figure 7-5 Installing front and back doors

Page 114: UMG8900 Installation Manual-Hardware Installation

Installation Manual - Hardware Installation U-SYS UMG8900 Universal Media Gateway Chapter 7 Installing Cabinet Fittings

Huawei Technologies Proprietary

7-7

Note:

The shuffle pins have been installed on the door panels before delivery. After the front and back doors and side panels are installed, it is required to install protection grounding cables at the positions of lower pins to ensure reliable grounding for the cabinet. For specific installation method, see Section 5.5.2 in Chapter 5 "Installing Power Cables and Protection Grounding Cables" in this manual.

Page 115: UMG8900 Installation Manual-Hardware Installation

Installation Manual - Hardware Installation U-SYS UMG8900 Universal Media Gateway Chapter 8 Installing Peripherals

Huawei Technologies Proprietary

8-1

Chapter 8 Installing Peripherals

8.1 About This Chapter

This chapter contains the following sections:

Introduction to UMG8900 Peripherals Connecting to the LMT Connecting to the Alarm System Laying Cables for Peripherals

8.2 Introduction to UMG8900 Peripherals

The UMG8900 manages and maintains the equipment through LMT, which adopts universal PC as its hardware system. In addition, the equipment adopts universal alarm box provided by Huawei Technologies to implement alarm prompt function during the operations and service maintenance.

8.3 Connecting to the LMT

8.3.1 Connecting Network Cables between the LMT and UMG8900

Generally, the UMG8900 is connected with multiple LMTs, through which the UMG8900 manages and maintains the equipment. LMTs can be connected to the UMG8900 locally or remotely.

To connect an LMT to the UMG8900 locally, do as follows:

1) Use straight through network cable to connect the PC which the LMT software is installed in to LAN Switch or HUB.

2) Use straight through network cable to connect the LAN Switch or HUB to the OMC interface on the front panel of the NET.

If an LMT and the UMG8900 are not in the same network segment, use remote connection mode. That is, connect the LMT to the OMC interface provided on the NET of the UMG8900 through routers.

Page 116: UMG8900 Installation Manual-Hardware Installation

Installation Manual - Hardware Installation U-SYS UMG8900 Universal Media Gateway Chapter 8 Installing Peripherals

Huawei Technologies Proprietary

8-2

IP NetworkR

R

UMG8900

UMG8900LANSwitch

LANSwitch1 LANSwitch2Router1 Router2LMT

LMT

Local connection mode

Remote connection mode

Figure 8-1 Connection modes for LMT

8.3.2 Installing Protection Grounding Cables for the LMT

Disconnect the protection grounding cable between the protection grounding terminals of the LMT and protection grounding cable of public 220 V AC power cables and connect the shell of the LMT to the protection grounding bar in the equipment room through protection grounding cables.

8.3.3 Connecting Protection Grounding Cables between the LMT and UMG8900

The communication cables between an LMT and the UMG8900 include network cable (with RJ45 connectors), RS232 serial port cable and RS422 serial port cable. No matter which cable is used, it is required to interconnect the protection grounding cables of the LMT and UMG8900 with cables whose cross section must not be less than 4 mm2. That is, it is required to connect both the protection grounding cables of the LMT and UMG8900 to the same protection grounding bar.

8.4 Connecting to the Alarm System

8.4.1 Introduction to the Alarm Box

The universal alarm box adopts box structure.

The appearance of the alarm box is shown in Figure 8-2.

Page 117: UMG8900 Installation Manual-Hardware Installation

Installation Manual - Hardware Installation U-SYS UMG8900 Universal Media Gateway Chapter 8 Installing Peripherals

Huawei Technologies Proprietary

8-3

Figure 8-2 Appearance of a universal alarm box

8.4.2 Connecting to the Alarm Box

I. Alarm Box Connection Description

The alarm box can be connected to the LMT alarm console or directly to the UMG8900.

Connecting to the LMT alarm console

When the alarm box is connected to the LMT alarm console, the UMG8900 reports alarm information to the LMT, which then forwards the information to the alarm box. The LMT alarm console and the alarm box communicate with each other through the RS232 serial ports.

Connecting to the UMG8900

When the alarm box is directly connected to the UMG8900, the UMG8900 is connected to the serial port of the alarm box through the interface ALARM provided on the back filter box of the main control frame. The interface complies with the RS422 standard. Through the interface ALARM, alarm information can be reported to the alarm box directly.

II. Grounding for the Alarm Box

If single-phase AC power supply is used for the alarm box, it is required to conduct lightning protection measures for the AC power sockets, that is, you must use yellow-green protection grounding cable whose cross section is not less than 4 mm2

Page 118: UMG8900 Installation Manual-Hardware Installation

Installation Manual - Hardware Installation U-SYS UMG8900 Universal Media Gateway Chapter 8 Installing Peripherals

Huawei Technologies Proprietary

8-4

to connect the metal shell of the alarm box to the protection grounding bar in the equipment room.

For detailed methods for installing the alarm box and connecting related cables, refer to Universal Alarm Box User Manual delivered with the alarm box.

8.5 Laying Cables for Peripherals

The alarm box, Hub, Modem and various clients (workstations) are generally installed in the maintenance room. The modes and requirements for cabling and connecting serial port cable for the alarm box and network cable for HUB are similar to those for cabling and connecting external clock cables or trunk cables. It is required to lead the signal cables to the maintenance room through cabling trough or cabling rack. The power cables of the LMTs, signal cables of monitors, and network cables of Hub must be laid orderly and bundled separately. To ensure the safety of personnel and devices, the power system must be reliably grounded.

Page 119: UMG8900 Installation Manual-Hardware Installation

Installation Manual - Hardware Installation U-SYS UMG8900 Universal Media Gateway Chapter 9 Hardware Installation Check

Huawei Technologies Proprietary

9-1

Chapter 9 Hardware Installation Check

9.1 About This Chapter

After hardware installation, it is required to check the hardware installation quality before subsequent software installation and system commissioning. This chapter contains the following sections:

Checking Appearance of Hardware Components Checking Power Supplies for Cabinets and Frames Performing Board Power-On Test

For detailed check items, refer to UMG8900 Hardware Self-Check Table.

9.2 Checking Appearance of Hardware Components

9.2.1 Checking Cabinets

Following are the cabinet check items:

The cabinets in a row are correctly positioned, and both the front and back planes of the cabinets are aligned.

All bolts are screwed tightly. All bolts have flat washers and spring washers, and they are fixed in correct direction.

The components and cables of the cabinets are complete and in good condition. All labels are correct, clear and complete.

There are no surplus cable ties, stubs or other sundries in the cabinets. The front and back doors and side panels are clean without defilement or handprint.

After all cables are laid, the small cover plates on both the top and bottom of cabinets cover corresponding cabling holes, thus preventing animals or dust from entry.

9.2.2 Checking Cable Distribution

I. Checking Power Cables and Protection Grounding Cables

The check items include:

The power cables and protection grounding cables from DC power distribution cabinet to power distribution frames in the top of cabinets are connected securely.

Page 120: UMG8900 Installation Manual-Hardware Installation

Installation Manual - Hardware Installation U-SYS UMG8900 Universal Media Gateway Chapter 9 Hardware Installation Check

Huawei Technologies Proprietary

9-2

The power cables and protection grounding cables from power distribution frames to service frames are connected securely.

Grounding polarities are correct and the contacts are good. The power cables and protection grounding cables are not laid together with

signal cables.

II. Checking Internal Cables

The check items include:

The cable connections are correct and firm. The cable ties are in correct positions and spaced properly. The cable ties are not overlapped and there are no sharp ends.

III. Checking Trunk Cables, Optical Fibers and Network Cables

The check items include:

The cables are not stretched at turnings. The cabling paths are consistent with the requirements and the cable ties are

spaced properly. The cables are straight and smooth. There is no cable crossover in the cabinet

and the cables outside cabinet are bundled according to the cabinets they are connected to.

The cables in the cabling troughs and on the cabling ladders are orderly arranged and all the cables are bundled with no damage on the coating.

The cables have proper redundancy and the cable ties have no sharp ends or overlaps.

9.2.3 Checking Connectors and Sockets

I. Checking Connectors

The latches of cable connectors must be tightly locked and the coaxial cable connectors be fastened tightly.

II. Checking Sockets

The sockets include trunk cable sockets, network cable sockets and HEADER sockets for all backplanes. There must be neither lack of pins nor short-circuit resulting from bent pins.

Page 121: UMG8900 Installation Manual-Hardware Installation

Installation Manual - Hardware Installation U-SYS UMG8900 Universal Media Gateway Chapter 9 Hardware Installation Check

Huawei Technologies Proprietary

9-3

9.2.4 Other Checks

I. Labels

All labels must be clean, tidy and in correct positions.

II. Cabling Trough and Cabling Rack

There must be no such sundries as cable ties, stubs, or dryer bags left in the cabling troughs and cabinets, on the cabling rack and top of the cabinets, or under the movable floor around the cabinets.

III. Environment of the Equipment Room

There must be no useless objects in the equipment room and all the necessities must be neatly arranged in the room. The workbench and movable floor must be clean and tidy.

9.3 Checking Power Supplies for Cabinets and Frames

The check on power supply for the cabinets and frames is to see whether there is short circuit in all output power lines from the DC power distribution frame, whether the input DC voltage to the UMG8900 cabinets is normal, whether the visual and audio alarm function of the frames in all cabinets is normal, and whether the input DC voltage to all internal components of the cabinets is normal. The check steps are described as follows.

1) Shut down the power supply of DC power distribution cabinet, and set all AC power sockets and switches to OFF. Set the multimeter to ohm range and check whether there is short circuit between power supplies (–48V1 and –48V2) of the DC power distribution frame and between grounds (BGND and PGND), and whether the power supply is disconnected from the ground. The hot wire, ground wire and neutral wire of every socket must not be shorted.

2) Set all the switches of the power distribution frame in the top of the cabinet to OFF, and then power on the DC power distribution cabinet. In the case of no load, use the multimeter to check whether the output of power supply is within the allowed voltage range (–57 V to –40 V). At this time, red “ALM” indicator on the power distribution frame should flash and the buzzer will give off audible alarm upon setting the ALARM switch to “ON”.

3) Set all the switches of the power distribution frame in the top of the cabinet to “ON” after making sure that there is no board inserted into the corresponding slot on the backplane. At this time, there should be no power alarm or audible alarm and the red WARN indicator should not light up. The fan frame should operate normally and there is no abnormal noise.

Page 122: UMG8900 Installation Manual-Hardware Installation

Installation Manual - Hardware Installation U-SYS UMG8900 Universal Media Gateway Chapter 9 Hardware Installation Check

Huawei Technologies Proprietary

9-4

4) Check whether other devices in the cabinets are with power supply input of –48 V and their voltage is within the proper range (–57 V to –40 V). If everything is normal, the power supply is in good condition.

If any of the above items does not meet the requirement, find out the reason and perform troubleshooting before the power-on check.

The alarm indicators on the power distribution frame can indicate analog value alarm information and Boolean value alarm information. To analyze analog value alarm information, follow the method below.

1) Check whether there is alarm for analog values through the background, including voltage of the two power supplies, humidity sensor, and temperature sensor. Check whether the reported values are normal.

Item Default normal value

Voltage –42V to –58V

Humidity 5% to 90%

Temperature 5°C to 70°C

2) If the above values are normal, check whether the values are beyond the upper limit or lower limit configured in the background.

To analyze Boolean value alarm information, follow the method below.

1) Check whether there is Boolean value related alarm, including: Lightning protection fault of dual channel Power distribution output switch fault of four to eight channels Inverter fault of three channels Preserved Boolean value fault of three channels

2) Check whether the corresponding Boolean value detection is configured. If yes, check whether there is alarm for Boolean value and check whether the alarm is normal.

If Boolean value detection is not configured, execute alarm disabling/enabling command through the background to mask those Boolean values not configured

9.4 Performing Board Power-On Test

The working status of a board powered on can be known according to indicators on the board front panel. For the meanings of board indicators, refer to HUAWEI UMG8900 Universal Media Gateway Hardware Description Manual.

The steps to conduct the trial power-on check are as follows.

1) Check whether the input and output cables of –48 VDC power supply are correctly connected and whether the connection cables are firm.

Page 123: UMG8900 Installation Manual-Hardware Installation

Installation Manual - Hardware Installation U-SYS UMG8900 Universal Media Gateway Chapter 9 Hardware Installation Check

Huawei Technologies Proprietary

9-5

2) Set all the switches on DC power distribution frame for the boards to “OFF”, and then insert the boards into the slots on the backplanes and fasten the front planes of the boards.

3) Set the power switches controlling the frames to “ON”. At this time, all board indicators should be normal. If the indicators of all boards do not light up after the power switches are turned on, it indicates no –48 VDC input or error of the input terminal connection. If the power switch jumps upon being closed, it means there would be short-circuit of payload or connection error on the output terminal (short circuit).

Page 124: UMG8900 Installation Manual-Hardware Installation

Installation Manual - Hardware Installation U-SYS UMG8900 Universal Media Gateway Appendix A Installing Cabling Rack

Huawei Technologies Proprietary

A-1

Appendix A Installing Cabling Rack

A.1 About This Appendix

This appendix contains the following sections:

Introduction to the Cabling Rack Installing Cabling Rack

A.2 Introduction to the Cabling Rack

A.2.1 Functions of the Cabling Rack

When upward cabling mode is used, it is required to install cabling rack in equipment room to lay cables, to reinforce cabinet connections and to enhance shockproof performance.

A.2.2 Components of Cabling Rack

The channel-section steel is shown in Figure A-1.

Figure A-1 Channel-section steel

The channel-section connecting piece is shown in Figure A-2.

Page 125: UMG8900 Installation Manual-Hardware Installation

Installation Manual - Hardware Installation U-SYS UMG8900 Universal Media Gateway Appendix A Installing Cabling Rack

Huawei Technologies Proprietary

A-2

Figure A-2 Channel-section connecting piece

The 200 mm long cross stay is shown in Figure A-3.

Figure A-3 Cross stay (200 mm)

The 400 mm long cross stay is shown in Figure A-4.

Figure A-4 Cross stay (400 mm)

The 600 mm long cross stay is shown in Figure A-5.

Figure A-5 Cross stay (600 mm)

The angel connecting piece is shown in Figure A-6.

Page 126: UMG8900 Installation Manual-Hardware Installation

Installation Manual - Hardware Installation U-SYS UMG8900 Universal Media Gateway Appendix A Installing Cabling Rack

Huawei Technologies Proprietary

A-3

Figure A-6 Angle connecting piece

The cable-through clip is shown in Figure A-7.

Figure A-7 Cable-through clip

The triangular support for the 200 mm-wide cabling ladder is shown in Figure A-8.

Figure A-8 Triangular support (for 200 mm-wide cabling ladder)

The triangular support for the 400 mm-wide cabling ladder is shown in Figure A-9.

Page 127: UMG8900 Installation Manual-Hardware Installation

Installation Manual - Hardware Installation U-SYS UMG8900 Universal Media Gateway Appendix A Installing Cabling Rack

Huawei Technologies Proprietary

A-4

Figure A-9 Triangular support (for 400 mm-wide cabling ladder)

The triangular support for the 600 mm-wide cabling ladder is shown in Figure A-10.

Figure A-10 Triangular support (for 600 mm-wide cabling ladder)

The connecting clip for cabling trough is shown in Figure A-11.

Figure A-11 Connecting clip for cabling trough

The fixing clip for cabling trough is shown in Figure A-12.

Page 128: UMG8900 Installation Manual-Hardware Installation

Installation Manual - Hardware Installation U-SYS UMG8900 Universal Media Gateway Appendix A Installing Cabling Rack

Huawei Technologies Proprietary

A-5

Figure A-12 Fixing clip for cabling trough

The 200 mm long cabling trough is shown in Figure A-13.

Figure A-13 Cabling trough (200 mm)

The 400 mm long cabling trough is shown in Figure A-14.

Figure A-14 Cabling trough (400 mm)

The insulating washer is shown in Figure A-15.

Figure A-15 Insulating washer

Page 129: UMG8900 Installation Manual-Hardware Installation

Installation Manual - Hardware Installation U-SYS UMG8900 Universal Media Gateway Appendix A Installing Cabling Rack

Huawei Technologies Proprietary

A-6

The insulating plate is shown in Figure A-16.

Figure A-16 Insulating plate

The end cover is shown in Figure A-17.

Figure A-17 End cover

Bolt B (M8 x 20) is shown in Figure A-18.

Figure A-18 Bolt B (M8 x 20)

The movable cable bushing is shown in Figure A-19.

Figure A-19 Movable cable bushing

Page 130: UMG8900 Installation Manual-Hardware Installation

Installation Manual - Hardware Installation U-SYS UMG8900 Universal Media Gateway Appendix A Installing Cabling Rack

Huawei Technologies Proprietary

A-7

A.2.3 Installation Modes

The cabling rack can be installed in four different modes:

Install a suspender on the ceiling to hang the cabling rack (hereinafter referred to as the “suspension mounting mode”).

Install a bracket on the ground to support the cabling rack (hereinafter, referred to as the “ground supporting mode”).

When the cabling rack is placed against the wall, install a triangular support on the wall to support the cabling rack.

When the cabling rack passes over the cabinet, install a shockproof support or a ladder on the cabinet to support the cabling rack.

A.2.4 Cabling Rack Specifications

Cabling rack is made of cabling ladder, and cabling trough which is optional component.

The cabling ladder and the cabling trough have the following specifications:

200mm-wide cabling ladder matches the 200mm-wide cabling trough; 400mm-wide cabling ladder matches the 400mm-wide cabling trough; 600mm-wide cabling ladder matches the 200mm +400mm-wide cabling trough.

It is recommended to use 400mm-wide cabling ladder over the cabinet, and not to use cabling trough, to facilitate cabling and to improve the heat dissipation of the system.

A.3 Installing Cabling Rack

A.3.1 Installation Procedure

Caution:

The cabling rack must be insulated from the floor, ceiling and walls.

The procedure for installing the cabling rack is shown in Figure A-20.

Page 131: UMG8900 Installation Manual-Hardware Installation

Installation Manual - Hardware Installation U-SYS UMG8900 Universal Media Gateway Appendix A Installing Cabling Rack

Huawei Technologies Proprietary

A-8

Start

Mark the drilling position

Drill the hole (φ 8, 60mm deep)

Install thecabling trough?

N

Install such accessories ascable-through rack, cablebaffle ring, end cover andprotective cable sheathing

Y

End

Assemble the cabling ladder

Check the drilling position

Secure the cabling ladder onto theground, the rooftop or the wall

Install and securethe cabling trough

Figure A-20 Procedure of installing cabling rack

A.3.2 Assembling Cabling Ladder

The cabling ladder uses channel-section steel and cross stays for form its framework. The channel-section steel functions as the vertical beams of the cabling ladder and the cross stays function as the horizontal beams. To assemble a cabling ladder, use fastener to connect the cross stays with the channel-section steel. The spacing

Page 132: UMG8900 Installation Manual-Hardware Installation

Installation Manual - Hardware Installation U-SYS UMG8900 Universal Media Gateway Appendix A Installing Cabling Rack

Huawei Technologies Proprietary

A-9

between two cross stays is 250 mm. Because the spacing between holes in the channel-section steel is 50 mm, install one cross stay every five trough holes. When the assembled cabling ladder is used for horizontal installation, the bolt head of the cabling ladder should face downward to ensure that there is no protrusion on the ladder surface and to facilitate the installation of cabling trough.

The basic structure of a cabling ladder is shown in Figure A-21.

(1) Fastener (2) Cross stay (3) Channel-section steel

Figure A-21 Basic structure of a cabling ladder

If a longer cabling ladder is required, you can join several cabling ladders in an “end to end” fashion. The channel-section connecting piece is used to connect ladders, as shown in Figure A-22. If the length of a cabling ladder is not an integral multiple of 2.5 m, cut off the remaining part. Use brush the paint the cross section to ensure protection against corrosion and to provide aesthetic look for the ladder.

Channel-section steel

Channel-sectionconnecting piece

Figure A-22 Connections between two cabling ladders

Page 133: UMG8900 Installation Manual-Hardware Installation

Installation Manual - Hardware Installation U-SYS UMG8900 Universal Media Gateway Appendix A Installing Cabling Rack

Huawei Technologies Proprietary

A-10

A.3.3 Connecting and Installing Cabling Troughs

Because cabling trough is cone-shaped, you can insert the smaller end of a cabling trough to the bigger end of another. The depth of inserted part is 250 mm. When 200mm-wide or 400mm-wide cabling trough is used, directly place the cabling trough on cabling ladder, and secure the cabling trough on the cabling ladder with fixing clips. For each segment of the cabling trough, four such clips are used and they should be symmetrical at both sides.

The connection of cabling troughs is shown in Figure A-23.

Cabling trough

Cabling troughfixing clip

Cabling ladder Protective ring

Figure A-23 Connection of cabling troughs (200 mm or 400 mm wide)

If a cabling trough is installed on 600mm-wide cabling ladder, it can be formed by means of joining a 200mm-wide trough and a 400mm-wide trough together with connecting clips. For each segment of cabling trough, three connecting clips are required. To install a cabling trough, secure it on cabling ladder with fixing clips. If a longer cabling trough is required, the connecting method is same as that mentioned earlier. Here, follow the principle “extended first and fixed next”.

The structure of 600 mm-wide trough is shown in Figure A-24.

(1)

(2)

(3)

(4)

(5)

(1) Cabling trough (400 mm) (2) Cabling ladder (600 mm wide) (3) Cabling trough (200mm)(4) Cabling trough connecting clip (5) Cabling trough fixing clip

Figure A-24 Structure of 600 mm-wide cabling trough

Page 134: UMG8900 Installation Manual-Hardware Installation

Installation Manual - Hardware Installation U-SYS UMG8900 Universal Media Gateway Appendix A Installing Cabling Rack

Huawei Technologies Proprietary

A-11

A.3.4 Installing Turning Cabling Rack

I. Connecting Cabling Racks on a Horizontal Surface

When a cabling rack has to turn perpendicularly on a horizontal surface, there are two different installation ways with regard to whether the cabling trough is adopted or not.

Cabling trough is not adopted

If the crossed cabling racks consist of only cabling ladders, use angle connecting pieces and fasteners to joint the two cabling ladders. Make sure that the two cabling ladders are on the same horizontal surface as shown in Figure A-25.

(1) Angle connecting piece

Figure A-25 Cabling ladders turning on a horizontal surface

Cabling trough is adopted

When either or both of the crossed cabling racks have cabling troughs, there must be a height difference between the two cabling racks, that is, the height of the cabling ladder of one cabling rack must be the same as the height of the cabling trough of another cabling rack, to ensure that the cables shall not encounter any trouble while turning on the cabling rack. The installation is shown in Figure A-26. In the installation, angle connecting pieces and fasteners are also used, whereas the installation method of the angle connecting pieces is different from that in as shown in Figure A-25.

(1) Angle connecting piece

Figure A-26 Cabling rack with cabling trough turning on a horizontal surface

Page 135: UMG8900 Installation Manual-Hardware Installation

Installation Manual - Hardware Installation U-SYS UMG8900 Universal Media Gateway Appendix A Installing Cabling Rack

Huawei Technologies Proprietary

A-12

II. Connecting Cabling Racks not in Horizontal Surface

When you want to connect cabling ladders not in a horizontal surface, use a segment of cabling ladder to make a climbing ladder. Use angle connecting pieces and fasteners to connect the cabling ladder and climbing ladder.

Figure A-27 shows the vertical connection of cabling ladders, in which the left figure shows front view of the connection, and the right figure shows the side view of the connection. Pay attention to the installation of the angle connecting pieces shown in the figure.

The sloping connection of cabling ladders is shown in Figure A-28.

(1)

(2)(3)

(4)

(5) (5)

(1) End cap (2) Bushing (3) Cabling trough (4) Cabling ladder (5) Angle connecting piece

Figure A-27 Vertical connection of cabling ladders

(1)

(1)

(1) End cap

Figure A-28 Sloping connection of cabling ladders

III. Connecting Cabling Ladder onto Wall

When the cabling rack has to be connected to the wall, use the installation method as shown in Figure A-29. The connecting components include angle connecting piece,

Page 136: UMG8900 Installation Manual-Hardware Installation

Installation Manual - Hardware Installation U-SYS UMG8900 Universal Media Gateway Appendix A Installing Cabling Rack

Huawei Technologies Proprietary

A-13

insulating plate, insulating washer, fastener and expansion bolt. Insulating plate and insulating washer are used to ensure insulation between the cabling rack and the wall. Meanwhile, big flat washer (φ8 of GB96-85) is used to replace the washer for the expansion bolt to increase the contact area between the washer and the insulating washer

(1)

(3)(2) (4) (5)

(6)

(7)

(8)

(1) Expansion bolt

(2) Insulation plate (3) Insulation washer (4) Big flat washer

(5) Spring washer (6) Nut (7) Channel-section

steel (8) Angle connecting piece

Figure A-29 Connecting the cabling rack into the wall

A.3.5 Installing Cabling Rack in Suspension Mounting Mode or Ground Supporting Mode

You can use suspension mounting mode or ground supporting mode when cabling rack is not placed against the wall. The suspension mounting mode is similar to the ground supporting mode, except that in the former installation mode, the cabling rack is connected to the ceiling, while in the latter the cabling rack is connected to the ground. The connecting components include channel-section steels, angle connecting pieces, fasteners and expansion bolts. To install a cabling rack in suspension mounting mode or ground supporting mode, use two pieces of channel-section steels to connect the cabling ladder to the ceiling or the ground. The installation method is the same as that of connecting cabling rack to the wall.

Page 137: UMG8900 Installation Manual-Hardware Installation

Installation Manual - Hardware Installation U-SYS UMG8900 Universal Media Gateway Appendix A Installing Cabling Rack

Huawei Technologies Proprietary

A-14

Each piece of channel-section steel is 2.5 m long. You can cut proper length according to the heights of the cabling rack and of the equipment room. If the required length is longer than 2.5 m, connect two pieces of channel-section steel by channel-section connecting piece with the same method as connecting cabling ladders. Meanwhile, paint the cut cross sections.

Because the spacing between the holes in the channel-section steel is 50 mm, the spacing between the suspenders or between the supporting levers must be an integral multiple of 50 mm. Otherwise, it is impossible to proceed with the installation. It is recommended that each segment of the cabling ladder is hung or supported by two sets of suspenders or supporting levers, and the spacing between two suspenders or between two supporting levers is 1250 mm .

When the suspension mounting mode or ground supporting mode is adopted, the suspenders or the supporting levers have to be installed at the outer side of the cabling ladder to facilitate the placement of cabling trough. Meanwhile, insulating plate and insulating washer must be used to ensure the insulation between the suspension components and the ceiling, or between the ground supporting components and the ground, as shown in Figure A-30.

(1)

(2)

(3)

(4)

(5)

(6)

(1) Expansion bolt (2) Angle connecting piece (3) Channel-section steel (4) Washer 8(GB96-85) (5) Insulation washer (6) Insulation plate

Figure A-30 Suspension mounting mode or ground supporting mode

A.3.6 Installing Triangular Support

Page 138: UMG8900 Installation Manual-Hardware Installation

Installation Manual - Hardware Installation U-SYS UMG8900 Universal Media Gateway Appendix A Installing Cabling Rack

Huawei Technologies Proprietary

A-15

Note:

The spacing between two triangular supports must be an integral multiple of 50 mm; otherwise, cabling ladders cannot be connected and fixed to triangular supports. A spacing of 1250 mm is recommended between two triangular supports, that is, each segment of cable ladder is supported by two triangular supports.

When cabling rack is placed against the wall, a triangular support is used to support the cabling rack. The triangular support adopts a welded structure, and it is fixed onto the wall by expansion bolts. It provides holes in its horizontal beam for installing cabling ladder. The triangular support has three specifications corresponding to the 200mm-wide, 400mm-wide, and 600mm-wide cabling ladders respectively. A larger triangular support can be used to support smaller cabling ladder, but it is not recommended here. The sizes of their installation holes in the wall are the same.

To install a triangular support, use expansion bolts to fix the support onto the wall. Use big flat washers (φ8 of GB96-85) to replace the flat washers of the expansion bolts. Meanwhile, install two insulating plates between the vertical beam of the triangular support and the wall, and install an insulating washer between the nut and the vertical beam.

To install cabling ladder onto the triangular support, place it directly on the horizontal beam of the triangular support. Align the holes on the lower side of the channel-section steel with the holes in the horizontal beam of the triangular support, and then fix them with fasteners, as shown in Figure A-31.

(1)

(2)

(3)

(4)

(5)

(6)

(1) Expansion bolt (2) Insulation plate (3) Cabling ladder (4) Beam of the triangular support

(5) Triangular support

(6) Vertical beam of the triangular support

Figure A-31 Installation of triangular support

Page 139: UMG8900 Installation Manual-Hardware Installation

Installation Manual - Hardware Installation U-SYS UMG8900 Universal Media Gateway Appendix A Installing Cabling Rack

Huawei Technologies Proprietary

A-16

A.3.7 Installing Cabling Rack over Cabinet

I. Introduction to Installation Ways

Cabling rack can be installed over the cabinet in the following two ways (Generally, cable distribution trough is not configured on the top of cabinet for the purpose of improving system heat dissipation).

If shockproof support is installed on the cabinet, connect the cabling rack with the quake-proof support.

If no shockproof support is installed on the cabinet, connect the cabling rack with the cabinet by climbing ladder.

II. Connecting Cabling Rack with Shockproof Support

Shockproof support on the top of cabinet is welded with channel steel, and it can meet the strength requirements. It can be fixed to the two bolt holes on top of cabinet. There are bolt holes on the top plate of the shockproof support, used for fixing and bearing the cabling rack (cabling ladder).

The connection method is shown in Figure A-32 and Figure A-33.

(1) Cabinet (2) Shockproof support (3) Flat washer 8 (4) Spring washer (5) Blot M8x20

Figure A-32 Connection of cabinet and shockproof support

Page 140: UMG8900 Installation Manual-Hardware Installation

Installation Manual - Hardware Installation U-SYS UMG8900 Universal Media Gateway Appendix A Installing Cabling Rack

Huawei Technologies Proprietary

A-17

(1) Cabinet (2) Shockproof support (3) Cabling rack (4) Flange bolt M8x20 (5) Flange nut M8

Figure A-33 Connection of cabling rack and shockproof support

III. Connecting Cabling Rack with Climbing Ladder

If there is no support installed on the top of cabinet, use climbing ladder based on the size of the connecting holes provided on the top of cabinet. For specific connecting method for climbing ladder, refer to the right figure in Figure A-27 or Figure A-28.

A.3.8 Installing Accessories

I. Installing Cable-Through Clip

Cable-through clip can be divided into two types according to whether cabling rack has cabling trough or not. Figure A-34 illustrates the case when cabling trough is not configured on cabling rack, in which, upward cable-through clip is used. When cabling trough is configured on cabling rack, downward cable-through clip is used to ensure that the upper plane of cable-through clip stays on the same level with the uppermost plane of cabling rack, and to facilitate cabling. Generally, cable-through clip is installed on the cabling ladder on the top of cabinet, and the required quantity and location depend on actual conditions of the installation site.

Page 141: UMG8900 Installation Manual-Hardware Installation

Installation Manual - Hardware Installation U-SYS UMG8900 Universal Media Gateway Appendix A Installing Cabling Rack

Huawei Technologies Proprietary

A-18

(1) (2)

(3)

(1) Holes in the upper row of the cable-through rack (2) Holes in the lower row of the cable-through rack (3) Cable-through rack

Figure A-34 Installation of cable-through clip when cabling trough is not configured on cabling rack

II. Installing Baffle Rings

Baffle rings are directly snapped at both sides of a cabling trough. Configuring baffle rings can increase the height of a cabling trough to prevent cables from going beyond the cabling trough. Each segment of cabling trough uses four such rings and they are distributed evenly at both sides, as shown in Figure A-23.

III. Installing End Covers

End covers are installed at the ends of a cabling ladder. Wherever possible, end covers must be installed to provide better appearance and prevents unintended damage to cables.

IV. Installing Cable Bushings

Cable bushings are installed at the bottom edge of a cabling trough, used to prevent cables from any possible damage. Any uncovered bottom edge of cabling troughs must be installed with cable bushing.

The installation of end cover and cable bushing is shown in the left part of Figure A-27.

Page 142: UMG8900 Installation Manual-Hardware Installation

Installation Manual - Hardware Installation U-SYS UMG8900 Universal Media Gateway Appendix B Engineering Labels for Cables

Huawei Technologies Proprietary

B-1

Appendix B Engineering Labels for Cables

B.1 Introduction to the Appendix

This appendix contains the following sections:

Introduction to Labels Engineering Labels for External Cables of Alarm Box Engineering Labels for Ethernet Cables Engineering Labels for Optical Fibers Engineering Labels for Trunk Cables Engineering Labels for Subscriber Cables Engineering Labels for Power Cables

B.2 Introduction to Labels

B.2.1 Functions of Engineering Labels

Engineering labels are affixed to both ends of various cables to identify the physical positions of cables on different devices. Labels facilitate correct and orderly connection of cables, and easy maintenance after the installation.

Note:

If there is special requirement from the customer for the description method of the labels, the labels shall be printed accordingly. However, this must be stated in the self-check report.

B.2.2 Label Material Specifications

The label material is polyester (PET) with UL and CSA certifications. The material specifications are shown as follows:

Color Thickness Applicable ambient temperature Printing method

Chalk white 0.09 mm -29 °C – 149 °C Laser

Page 143: UMG8900 Installation Manual-Hardware Installation

Installation Manual - Hardware Installation U-SYS UMG8900 Universal Media Gateway Appendix B Engineering Labels for Cables

Huawei Technologies Proprietary

B-2

B.2.3 Type and Shape of Labels

I. Introduction to Label Types

There are two types of engineering labels, specialized for signal cables and power cables respectively. Power cables include AC power cables and DC power cables (excluding the power cable that connects the distribution cabinet and the cabinet). Signal cables include external cables of alarm box, Ethernet cables, optical fibers, trunk cables and subscriber cables (excluding the antenna feeders).

II. Labels for Signal Cables

The label for signal cables is L-shaped with fixed dimensions, as shown in Figure B-1 (expressed in mm).

(2)

10.0

84.0

1.5

0.6

2.0

1.0

(1)

11.0

11.0

7.5 7.05.5

5.5

5.5

5.57.0

7.537.0

TO:

(2)

(1)

(1) Dividing line (2) Cut dotted line

Figure B-1 Label for signal cables

The dividing lines on the label help to specify more clearly the position of a cable. For example, there is one between the cabinet number and the frame number and another one between the frame number and the slot number. The dividing line is 1.5 mm ×0.6 mm in size with the color of PONTONE 656c (light blue).

The cut dotted line helps to fold the label when affixing it to the cable, and its size is 1.0 mm ×2.0 mm.

There is a mark “TO:” (upside down in the figure) at the lower right corner of the label. The mark is used to identify the opposite end of the cable on which the label is affixed.

Page 144: UMG8900 Installation Manual-Hardware Installation

Installation Manual - Hardware Installation U-SYS UMG8900 Universal Media Gateway Appendix B Engineering Labels for Cables

Huawei Technologies Proprietary

B-3

III. Labels for Power Cables

The labels for power cables must be attached to the identification plate on the cable ties that are bundled to the cable. The identification plate has an embossment of 0.2 mm ×0.6 mm around (symmetric on both sides), and the area in the middle is for affixing the label, as shown in Figure B-2 (expressed in mm):

(1)

(2)

(3)

26.2

12.2

0.6

11

10

100

R1.0

25

1.5

0.6

TO:

(1) Cable tie (2) Label (3) Dividing line on the label

Figure B-2 Label for power cables

B.2.4 Printing Labels

I. Introduction to Label Printing

The contents can be printed or written on the labels. Printing is recommended for the sake of high efficiency and eye-pleasant layout.

II. Template for Printing

The Word-format template is available for label printout. You can download the template from http://tech-support.huawei.com/asp/comm/index.asp (path: //support/technical document/project management/installation and maintenance/document/others), or get the template from Huawei local office.

When using the template, you can directly modify the contents on the template, and the following must be observed:

The settings of centered characters, direction, and fonts must not be changed. When there are too many characters to be filled in, zoom out the characters, but

make sure the printouts are clear and legible.

Page 145: UMG8900 Installation Manual-Hardware Installation

Installation Manual - Hardware Installation U-SYS UMG8900 Universal Media Gateway Appendix B Engineering Labels for Cables

Huawei Technologies Proprietary

B-4

III. Cells Merging on the template

To merge the cells, you need first recover the table structure (if gridlines are displayed, you can start from Step 3 directly).

1) Select the menu item [Edit/Select All]. 2) Select the menu item [Format/Borders and Shading/Borders]. Select Box and

click <OK>. 3) Drag the mouse to select the cells to be merged and select the menu item

[Table/Merge Cells].

If two merged cells are still not enough to accommodate the characters, use multiple lines.

IV. Requirements For the Printer

To print the labels, laser jet printer must be used, although there is no restriction on the model of the printer. Before printing the label, set up the page and try the printing on ordinary blank paper (both sides are blank):

1) Cover the blank paper onto the whole page of label paper, and check whether the page setup conforms to the requirement.

2) Make sure the printer properties, such as "paper size" and “direction”, have been set correctly.

3) If the warning prompt as shown in Figure B-3 appears before printing, click <Ignore> to continue the printing.

Figure B-3 Warning prompt before printing

If the printout confoms to the requiremnt, print it to label paper. If the printout does not conform, adjust the page setup and try the printing again, until the correct printout is produced. The method of adjusting the page setup is as follows:

1) Select the menu item [File/Page Setup]. 2) Select the Margins tab page. 3) Select Left for Gutter Position. 4) Set Header and Footer as 0, and adjust the values of Top, Bottom, Left, and

Right.

After the page setup has been made correct, save it for future use. This page setup is only necessary in the first time you use the template to print the labels.

Page 146: UMG8900 Installation Manual-Hardware Installation

Installation Manual - Hardware Installation U-SYS UMG8900 Universal Media Gateway Appendix B Engineering Labels for Cables

Huawei Technologies Proprietary

B-5

V. Requirements for Feeding the Printer

Different from the ordinary paper, the label paper is composed of two pages. No matter what model of printer you are using, feed in the labels one after another by hand. Never use the auto-feed mode in order to avoid jamming the labels. Different models of printers may have different feeding modes, make sure to feed in the labels correctly.

VI. Requirements for Printed Labels

Make sure the printed labels satisfy the following requirements:

All the printouts must be on the label, and nothing must be printed on the bottom page of the label.

Contents in the cells must be aligned in the center. In a single-line printout, the dividing lines and the mark “TO” must not be covered by the printed characters.

When the cells are merged and the printouts are made in multiple lines, avoid covering the mark “TO” when printing the texts by using the space bar to move the printing contents to the next line.

B.2.5 Writing Labels

Use the black oiliness markers delivered together with the device to write the labels.

In special cases, black ball-pens are allowed, although not recommended. When writing with the ball-pen, take care not to leave the oil on the label, which may contaminate the label and blur the words..

Note:

The delivered marker has two nibs. Make sure to use the smaller nib to write on the labels.

For the sake of easy recognition and good looking, the font in handwriting must be close to the standard typeface as much as possible. Table B-1 shows the standard typeface.

Page 147: UMG8900 Installation Manual-Hardware Installation

Installation Manual - Hardware Installation U-SYS UMG8900 Universal Media Gateway Appendix B Engineering Labels for Cables

Huawei Technologies Proprietary

B-6

Table B-1 Standard typeface for handwriting

0 1 2 3 4 5 6 7 8

9 A B C D E F G H

I J K L M N O P Q

R S T U V W X Y Z

Write the characters in proper size, and the direction is as shown in Figure B-4:

TO:

1-A01-2-A-06

0-B02-1-5-05

Figure B-4 Writing direction of the label

B.2.6 Affixing Labels

I. Affixing Label to Signal Cable

After printing or writing the label, remove the label from the bottom page and affix it to the signal cable, or the identification plate of the power cable.

The steps to affix a label to a signal cable are shown in Figure B-5, Figure B-6 and Figure B-7. The finished labels must be on the right or top of the cables, according to different cabling methods. The left part of the figures shows the method to affix the label when the cable is laid vertically, while the right part of the figures shows the method to affix the label when the cable is laid horizontally.

The label is affixed 2 cm from the connector on the signal cable. In special cases, for example, to avoid cable bent or affecting other cables, other positions are allowed to affix the labels.

The steps to affix a label to a signal cable are as follows:

1) Stick the label to the proper position on the cable, fold the narrow part of the label according to the directions shown in Figure B-5.

Page 148: UMG8900 Installation Manual-Hardware Installation

Installation Manual - Hardware Installation U-SYS UMG8900 Universal Media Gateway Appendix B Engineering Labels for Cables

Huawei Technologies Proprietary

B-7

Stick side

Fold to right

Cable

Stick side

Fold down

Cable

Figure B-5 Sticking the label onto proper position of the signal cable

The lengh of the narrow part is based on an external cable diameter of 2.6mm, after this part has been stuck to the back of the label, it may not overlap the entire printed part.

2) Fold the printed part along the dotted line according to the directions shown in Figure B-6.

Cable

Stick side

Fold up

Cable

Stick side

Fold to right

Figure B-6 Folding up the label

3) After the printed part of the label has been folded up, the narrow part of the label must be covered completely, as shown in Figure B-7.

Page 149: UMG8900 Installation Manual-Hardware Installation

Installation Manual - Hardware Installation U-SYS UMG8900 Universal Media Gateway Appendix B Engineering Labels for Cables

Huawei Technologies Proprietary

B-8

TO:A03 33 33 33 33

Cable

TO :A03 33 33 33 33

Cable

Figure B-7 Appearance of affixed labels on signal cables

II. Affixing Label to Power Cable

Remove the label from the bottom page, then affix it to the identification plate on the cable tie. The label must be stuck to the rectangular flute, and must be stuck to only one side of the identification plate. Make sure to affix the labels on the same side of the identification plates. The cable ties are bundled at 2cm from the connectors, and other positions are allowed in special circumstances.

Cable ties must be bundled on both ends of a cable. After the bundling, the finished identification plate must be on top of the cable in horizontal cabling, or on the right side of the cable in vertical cabling. Make sure the label is facing out, as shown in Figure B-8.

Cable

TO:B03 -48V2

Cable

TO:

B03 -48V2

Figure B-8 Appearance of affixed labels on power cables

Page 150: UMG8900 Installation Manual-Hardware Installation

Installation Manual - Hardware Installation U-SYS UMG8900 Universal Media Gateway Appendix B Engineering Labels for Cables

Huawei Technologies Proprietary

B-9

B.2.7 Information Carried on Labels

I. Information for Power Cables

Labels for power cables are only affixed on one side of the identification plates. On the labels, there is information (the part after the mark “TO:”) about the location of the device on the other end of the cable, like the location of control cabinet, distribution cabinet or power socket.

II. Information for Signal Cables

The two sides of the label affixed on the signal cable carry information about the location of the ports connected to both ends of the cable, as shown in Figure B-9.

The information is given like this:

Area 1 contains the location information of local end of the cable. Area 2 (with the mark "TO:") contains the location information of the opposite end

of the cable. Area 3 has been folded up inside the label.

Area 3Area 1Area 2 TO:

Figure B-9 Printed parts on the label for signal cables

Seen from the cabling end of the equipment, the text part of the label is on the right side of the cable. The side with “TO:” that is facing outside carries the location information of the opposite end; and the other side carries the location information of the local end. Therefore, the information in Area 1 at one end is the same as the information in Area 2 at the other end of the cable, and vice versa. In other words, the local information at one end is called the opposite information at the other end.

B.2.8 Remarks

The following remarks are made for attentions.

When printing/writing and affixing labels, pay attention to keep the labels clean. Because the label paper is made of moistureproof and waterproof material,

ink-jet printers and ink pens are forbidden for printing and writing labels. Labels must be affixed with good order in alignment.

Page 151: UMG8900 Installation Manual-Hardware Installation

Installation Manual - Hardware Installation U-SYS UMG8900 Universal Media Gateway Appendix B Engineering Labels for Cables

Huawei Technologies Proprietary

B-10

Cable ties must be bundled in the same position of power cables, with identification plates on the same side.

The positions of “up”, “down”, “right” or “left” are all based on the viewpoint of the engineering person who is working on the label.

B.3 Engineering Labels for External Cables of Alarm Box

The external cables of alarm box are connected with the first subscriber cabinet of each row (used for power distribution). Labels pasted on the first cabinet of each row indicate which equipment is using the access terminal. Labels are not needed on the equipment side unless there is special requirement. In this case, only Area 2 of the label is filled in.

Table B-2 shows the information on the labels of alarm box external cables.

Table B-2 Information on labels affixed to the external cables of alarm box

Content Meaning Example

MN

MN: serial number of the cabinet in the equipment room

M: The cabinet rows from front to back are numbered from A to Z.

N: The cabinet columns from left to right are numbered from 01 to 99.

For example, A01 indicates a cabinet at Row A, Column 01.

Note:

Generally, the above numbering method is enough to identify the position of a specific cabinet. If cabinets are installed in a back-to-back manner, the facing direction of the cabinet must be specified, the numbering method like MNO is used. Here, “O” means the direction of the cabinet, which can be “A” or “B”. On the cable labels described below, this numbering method is used, unless otherwise stated.

The label on the alarm cable carries simple information, and only part of the text area needs to be filled in. It is recommended to keep the whole length of the label instead of cutting out the blank area.

Figure B-10 shows a label on the alarm cable, on which “A01” indicates that the alarm cable is connected from the first cabinet to the cabinet at Row A, Column 01 in the equipment room.

Page 152: UMG8900 Installation Manual-Hardware Installation

Installation Manual - Hardware Installation U-SYS UMG8900 Universal Media Gateway Appendix B Engineering Labels for Cables

Huawei Technologies Proprietary

B-11

Figure B-10 Example of the label on the alarm cable

B.4 Engineering Labels for Ethernet Cables

B.4.1 Introduction to the Labels

These labels are affixed to the Ethernet cables that connect the boards in the frames, or on the cables that connect HUBs and servers or agents of the value-added service (VAS) products.

B.4.2 Label Information Meanings

I. Introduction to Information on Labels

Table B-3 shows the information on both sides of the labels affixed to the Ethernet cables that connect the boards in the frames.

Table B-3 Information on labels affixed to the Ethernet cables

Content Meaning Example

MN: Cabinet number For example, A01

B: Frame number

Numbered in top-down order with two digits, for example, 01

C: Physical slot number

Numbered in top-down and left-right order with two digits, for example, 01

MN-B-C-D

D: Ethernet port number

Numbered in top-down and left-right order with two digits, for example, 01

Page 153: UMG8900 Installation Manual-Hardware Installation

Installation Manual - Hardware Installation U-SYS UMG8900 Universal Media Gateway Appendix B Engineering Labels for Cables

Huawei Technologies Proprietary

B-12

Content Meaning Example

MN: Cabinet number For example, B02

MN-Z Z: Location number

Valid location number of the terminal device onsite. If the cable is connected to a router in a cabinet, the serial numbers of the cabinet, the frame and the Ethernet interface of the router must be specified, for example, B02-03-12. If the cable is connected to the Network Management Station (NMS), specific location of the NMS must be given.

In VAS products, the information provided on the labels is different, subject to different devices that the Ethernet cables are connecting.

II. Labels for Ethernet Cable that Connects HUB and Server

The information provided on the labels includes:

The label at the HUB end indicates the number of the frame and cabinet where the HUB locates, and the serial number on the HUB.

The label at the server end indicates the number of the frame and cabinet where the server locates. In case it is a stand-alone server, specific position of the server should be provided.

III. Labels for Ethernet Cable that Connects HUB and Agent

The information provided on the labels includes:

The label at the agent end contains the serial number of the Ethernet port. The definitions of the cabinet number and frame number are the same as those described in Table B-3 above.

If it is a stand-alone HUB without any cabinet or frame, the label contains specific location information that identifies the HUB.

The label contains the serial number of the HUB, the network port number of the agent and the location of the stand-alone server according to actual connection.

B.4.3 Label Example

Figure B-11 shows the label on the Etherent cable:

Page 154: UMG8900 Installation Manual-Hardware Installation

Installation Manual - Hardware Installation U-SYS UMG8900 Universal Media Gateway Appendix B Engineering Labels for Cables

Huawei Technologies Proprietary

B-13

Figure B-11 Example of the label on the Ethernet cable

“A01-03-10-05” indicates that on the local end of the Ethernet cable is connected with Ethernet Port 05, Slot 10, Frame 03 of the cabinet at Row A, Column 01 in the equipment room.

“B02-03-12” indicates that the opposite end of the Ethernet cable is connected with Ethernet Port 12, Frame 03 of the cabinet at Row B, Column 02 in the equipment room.

B.5 Engineering Labels for Optical Fibers

B.5.1 Introduction to the Labels

These labels are affixed to the optical fibers that connect the optical interfaces on the boards in a frame, or on the device boxes. There are two types of labels for optical fibers: one is for the fiber that connects the optical interfaces on two devices, the other is for the fiber that connects the device and the optical distribution frame (ODF).

B.5.2 Labels for Fiber that Connects Two Devices

I. Label Information Meanings

Table B-4 shows the information on both sides of the labels affixed to the optical fiber that connects two devices.

Page 155: UMG8900 Installation Manual-Hardware Installation

Installation Manual - Hardware Installation U-SYS UMG8900 Universal Media Gateway Appendix B Engineering Labels for Cables

Huawei Technologies Proprietary

B-14

Table B-4 Information on labels affixed to the fiber between two devices

Content Meaning Example

MN: cabinet number For example, A01

B: frame number Numbered in top-down order with two digits, for example, 01

C: physical slot number Numbered in top-down and left-right order with two digits, for example, 01

D: optical interface number

Numbered in top-down and left-right order with two digits, for example, 05

MN-B-C-D-R/T

R: optical receiving interface

T: optical transmitting interface

MN: cabinet number

B: frame number

C: physical slot number

D: optical interface number

The meanings are the same as above. When the local device and the opposite end device are not in the same equipment room, MN can be the name of the equipment room.

MN-B-C-D-R/T

R: optical receiving interface

T: optical transmitting interface

II. Label Example

Figure B-12 shows the label on the optical fiber between two devices:

Figure B-12 Example of the label on the optical fiber between two devices

“A01-01-05-05-R” indicates that the local end of the optical fiber is connected with Optical Receiving Interface 05 on Slot 5, Frame 01 in the cabinet at Row A, Column 01 in the equipment room.

Page 156: UMG8900 Installation Manual-Hardware Installation

Installation Manual - Hardware Installation U-SYS UMG8900 Universal Media Gateway Appendix B Engineering Labels for Cables

Huawei Technologies Proprietary

B-15

“G01-01-01-01-T” indicates that the opposite end of the optical fiber is connected with Optical Transmitting Interface 01 on Slot 01, Frame 01 in the cabinet at Row G, Column 01 in the equipment room

B.5.3 Labels for Fiber that Connects the Device and the ODF

I. Label Information Meanings

Table B-5 shows the information on both sides of the labels affixed to the optical fiber that connects the device and the ODF.

Table B-5 Information on labels affixed to the fiber between the device and the ODF

Content Meaning Example

MN: cabinet number For example, A01

B: frame number Numbered in bottom-up order with two digits, for example, 01

C: physical slot number

Numbered in top-down and left-right order with two digits, for example, 01.

D: optical interface number

Numbered in top-down and left-right order with two digits, for example, 05

MN-B-C-D-R/T

R: optical receiving interface

T: optical transmitting interface

MN: row number and column number of ODF

Numbered in the same rule as that of the cabinets, for example, G01 indicates an ODF at Row G, Column 01

B: row number of the terminal device

C: column number of the terminal device

Range from 01 to 99, for example, 01-01 ODF-MN-B-C-R/T

R: optical receiving interface

T: optical transmitting interface

II. Label Example

Figure B-13 shows the label on the optical fiber between the device and the ODF.

Page 157: UMG8900 Installation Manual-Hardware Installation

Installation Manual - Hardware Installation U-SYS UMG8900 Universal Media Gateway Appendix B Engineering Labels for Cables

Huawei Technologies Proprietary

B-16

Figure B-13 Example of the label on the optical fiber between the device and the ODF

“ODF-G01-01-01-R” indicates that the local end of the optical fiber is connected with the optical receiving terminal at Row 01, Column 01 of the ODF at Row G, Column 01 in the equipment room.

“A01-01-05-05-R” indicates that the opposite end of the optical fiber is connected with Optical Receiving Interface 5 on Slot 05, frame 01 in the cabinet at Row A, Column 01 in the equipment room.

B.6 Engineering Labels for Trunk Cables

B.6.1 Introduction to the Labels

There are two types of labels for trunk cables. One type is used for the trunk cable connecting two devices, such as the trunk board and built-in transmission unit, or two trunk boards. The other type is used for connecting the device and the digital distribution frame (DDF).

The trunk cables include 75Ω/120Ω E1 cables, 120Ω T1 cables, 34M, 45M, 140M, 155M cables and 120-to-75Ω trunk cables, as well as clock cables.

B.6.2 Labels for Trunk Cable that Connects Two Devices

I. Label Information Meanings

Table B-6 shows the information on both sides of the labels affixed to the trunk cable that connects two devices.

Page 158: UMG8900 Installation Manual-Hardware Installation

Installation Manual - Hardware Installation U-SYS UMG8900 Universal Media Gateway Appendix B Engineering Labels for Cables

Huawei Technologies Proprietary

B-17

Table B-6 Information on labels affixed to the trunk cable between two devices

Content Meaning Example

MN: cabinet number For example, A01

B: frame number Numbered in bottom-up order with two digits, for example, 01

C: physical slot number

Numbered in top-down and left-right order with two digits, for example, 01

D: cable number Numbered in top-down and left-right order with two digits, for example, 12

MN-B-C-D-R/T

R: optical receiving interface

T: optical transmitting interface

MN-B-C-D-R/T Same as above Same as above

II. Label Example

Figure B-14 shows the label on the trunk cable between two devices:

Figure B-14 Example of the label on the trunk cable between two devices

“G01-01-05-12-T” indicates that the local end of the trunk cable is connected with the transmitting terminal of Trunk Cable 12 on Slot 05, Frame 01 in the cabinet at Row G, Column 01 in the equipment room.

“D02-01-01-10-R” indicates that the opposite end of the trunk cable is connected with the receiving terminal of Trunk Cable 10 on Slot 01, Frame 01 in cabinet at Row D, Column 02 in the equipment room

B.6.3 Labels for Trunk Cable that Connects the Device and the DDF

I. Label Information Meanings

Table B-7 shows the information on both sides of the labels affixed to the trunk cable that connects the device and the DDF.

Page 159: UMG8900 Installation Manual-Hardware Installation

Installation Manual - Hardware Installation U-SYS UMG8900 Universal Media Gateway Appendix B Engineering Labels for Cables

Huawei Technologies Proprietary

B-18

Table B-7 Information on labels affixed to the trunk cable between the device and the DDF

Content Meaning Example

MN: cabinet number For example, A01

B: frame number Numbered in bottom-up order with two digits, for example, 01

C: physical slot number

Numbered in top-down and left-right order with two digits, for example, 01

D: cable number Numbered in top-down and left-right order with two digits, for example, 05

MN-B-C-D-R/T

R: optical receiving interface

T: optical transmitting interface

MN: row number and column number of the DDF

Numbered in the same rule as that of the cabinets, for example, G01 indicates a DDF at Row G, Column 01.

B: row number of the terminal

C: column number of the terminal

Range from 01 to 99, foe example: 01-01.

DDF-MN-B-C-D/R/T

D: direction A or B

R: optical receiving interface

T: optical transmitting interface

There is such a mark in DDF:

A: indicating the DDF terminals are connected to the optical network equipment

B: indicating the DDF terminals are connected to the switching equipment

II. Label Example

Figure B-15 shows the label on the trunk cable between the device and the DDF:

Figure B-15 Example of the label on the trunk cable between the device and the DDF

Page 160: UMG8900 Installation Manual-Hardware Installation

Installation Manual - Hardware Installation U-SYS UMG8900 Universal Media Gateway Appendix B Engineering Labels for Cables

Huawei Technologies Proprietary

B-19

“A01-03-01-01-R” indicates that local end of the trunk cable is connected with the receiving terminal of Trunk Cable 01 in Slot 01, Frame 03 of the cabinet at Row A, Column 01 in the equipment room.

“DDF-G01-01-01-AR” indicates that the opposite end of the trunk cable is connected with the receiving terminal of Direction A (connected to optical network equipment) at Row 01, Column 01 of the DDF at Row G and Column 01 in the equipment room.

B.7 Engineering Labels for Subscriber Cables

B.7.1 Introduction to the Labels

The labels are affixed to both ends of the subscriber cables to identify the position of the cables on the device side and the main distribution frame (MDF) side.

B.7.2 Label Information Meanings

Table B-8 shows the information on both sides of the labels affixed to the subscriber cables.

Table B-8 Information on labels affixed to the subscriber cables

Content Meaning Example

MN: cabinet number For example, A01

B: frame number Numbered in bottom-up order with two digits, for example, 03

C: physical slot number Numbered in top-bottom and left-right order in two digits, for example, 01

MN-B-C-D

D: cable number Numbered in top-bottom and left-right order with two digits, for example, 01

MN: row number and column number of MDF

Numbered in the same rule as that of the cabinets, for example, G01 means the MDF of Row G and Column 01

B: row number of the terminal

MDF-MN-B-C

C: column number of the terminal

Range from 01 to 99, for example: 01-01

B.7.3 Label Example

Figure B-16 shows the label on the subscriber cable.

Page 161: UMG8900 Installation Manual-Hardware Installation

Installation Manual - Hardware Installation U-SYS UMG8900 Universal Media Gateway Appendix B Engineering Labels for Cables

Huawei Technologies Proprietary

B-20

TO:

Figure B-16 Example of the label on the subscriber cable

“A01-03-01-01” indicates that local end of the subscriber cable is connected with Terminal 01 on Slot 1, Frame 03 of the cabinet at Row A, Column 01 in the equipment room.

“MDF-G01-01-01” indicates that the opposite end of the label is connected with the terminal at Row 01, Column 01 of the MDF at Row G, Column 01 in the equipment room.

B.8 Engineering Labels for Power Cables

B.8.1 Labels for DC Power Cables

I. Introduction to the Labels

The labels are affixed to the DC cables that provide power for the cabinets, and the protection grounding cables, including the -48V, PGND, and BGND cables. The labels for DC power cables are affixed to one side of the identification plates on cable ties.

II. Label Information Meanings

Table B-9 shows the information carried on the labels for the DC power cables:

Table B-9 Information on labels affixed to the DC power cables

Content Meaning

MN(BC)--48V1

MN(BC)--48V2

MN(BC)-BGND

MN(BC)-PGND

MN(BC): BC is written right under MN.

On the equipment cabinet side, only MN is used to identify the cabinet.

On the power cabinet side, MN identifies the row and column number of the power distribution equipment like the control cabinet and distribution cabinet, BC identifies the row and column number of the -48V connecter (if there is no row number or column number, or the connecter can be identified without them, BC can be omitted). BGND and PGND have no row and column number for identification.

Page 162: UMG8900 Installation Manual-Hardware Installation

Installation Manual - Hardware Installation U-SYS UMG8900 Universal Media Gateway Appendix B Engineering Labels for Cables

Huawei Technologies Proprietary

B-21

The label only carries location information about the opposite equipment, the control cabinet or the distribution cabinet, while information of the local end is not necessary. Table B-9 lists the information of two -48V power supplies on the label. The information for other DC voltages (such as 24V, 60V) should be given in similar methods.

III. Label Example

Make sure that labels are affixed in correction direction. That is, after the cable ties are bundled onto the cable, the identification plates with the labels should face up, and the text on the labels in the same cabinet should be in the same direction, as shown in Figure B-17.

(1) (2)

TO: A01 -48V2 B08

TO: B03 -48V2

Figure B-17 Example of the labels on the DC power cable

In Figure B-17, (1) indicates the label on the equipment cabinet side, which carries the information about the position of the cable on the power distribution cabinet. (2) indicates the label on the distribution cabinet side, which carries the information about the position of the cable on the equipment cabinet side.

On the equipment cabinet side, the label marked “A01/B08--48V2” on the cable indicates that the cable is -48V2 DC supply, which is from the 8th connecter on the second row of -48V bus bar in the cabinet at Row A, and Column 1 in the equipment room.

On the distribution cabinet side, the label marked “B03--48V2” indicates that the cable is -48V2 DC supply, which is from the equipment cabinet at Row B, Column 03 in the equipment room.

Page 163: UMG8900 Installation Manual-Hardware Installation

Installation Manual - Hardware Installation U-SYS UMG8900 Universal Media Gateway Appendix B Engineering Labels for Cables

Huawei Technologies Proprietary

B-22

Note:

In the power distribution cabinet (or the first power cabinet of a row in the transmission equipment room), every terminal on the -48V terminal block has a numeric identification, like “08” in “A01/B08--48V2” in the above example. PGND and BGND are copper bars, on which all the terminals are connected. In this case, it is only necessary to specify the row and column of the power distribution cabinet. For example, “A01-BGND” means that the power cable is a BGND cable that connects to the BGND copper bar of the power distribution cabinet at Row A, Column 01 in the equipment room.

B.8.2 Labels for AC Power Cables

I. Introduction to the Labels

The labels are affixed to the AC cables that provide power for the cabinets, and the protection grounding cables, including the POWER, PGND, and BGND cables. The 220V AC cables and related PGND and BGND cables are covered with insulating sheath, so the labels only need to contain the words of “AC" and the cabinet number. The labels for AC power cables are affixed to one side of the identification plates on cable ties.

II. Label Information Meanings

Table B-10 shows the information carried on the labels for the AC power cables.

Table B-10 Information on labels affixed to the AC power cables

Content Meaning

MN-AC

MN: serial number of the cabinet or the socket where the power is led in

The location of the socket is marked out according to onsite situation. If the sockets can be identified by row number and column number, they can be numbered following the same rule for the cabinets. If the sockets cannot be identified by rows and columns, specify the detailed locations to avoid confusing with other sockets.

The label only carries location information about the opposite equipment and the power socket, while information of the local end is not necessary.

Page 164: UMG8900 Installation Manual-Hardware Installation

Installation Manual - Hardware Installation U-SYS UMG8900 Universal Media Gateway Appendix B Engineering Labels for Cables

Huawei Technologies Proprietary

B-23

III. Label Example

Make sure that labels are affixed in correction direction. That is, after the cable ties are bundled onto the cable, the identification plates with the labels should face up, and the text on the labels in the same cabinet should be in the same direction, as shown in Figure B-18:

TO: A01 AC

TO: B01 AC

(1) (2)

Figure B-18 Example of the labels on the AC power cable

In Figure B-18, (1) indicates the label on the equipment cabinet side, which carries the information about the position of the cable on the power socket. (2) indicates the label on the power socket side, which carries the information about the position of the cable on the equipment cabinet side.

On the equipment cabinet side, the label marked “A01-AC” indicates that the power cable is connected to the socket of Row A Column 01 in the equipment room.

On the power socket side, the label marked “B01-AC” indicates that the power cable is connected to the equipment cabinet at Row B, Column 01 in the equipment room.

Page 165: UMG8900 Installation Manual-Hardware Installation

Installation Manual - Hardware Installation U-SYS UMG8900 Universal Media Gateway Appendix C Installing Antenna System

Huawei Technologies Proprietary

C-1

Appendix C Installing Antenna System

C.1 Introduction to the Appendix

This appendix contains the following sections:

Introduction to Antenna System Installation Preparations Installing Antenna System

C.2 Introduction to Antenna System

Table C-1 lists the BOM and model of the components contained in the antenna system.

Table C-1 BOM and model of the component

Component BOM Model Structure

GPS antenna (40 dB) 27010176 -

GPS antenna (50 dB) 27010175 -

GPS/GLONASS antenna (36 dB) 27010177 -

GPS antenna lightning arrester 19020011 -

Antenna support 21150243 40700174MX -

1.5m jumper 04025334 W4186 (FSJ4-50B)-N-Male/N-Male-1.5m

TNC/N conversion connector 14040130 N/TNC

converter-50 -

70m feeder cable 04024385 W3518 N-J-10D/10D-FB/N-J-10D

100m feeder cable 04040046 None N-J10 Straight Male/10D-FB/N-J10 Straight Male

150m feeder cable 04024142 W3307 N-J-1/2"/SYWY-50-1/2"/N-J-1/2"

FSJ4-50B 1/2” super flexible feeder cable 25070025 Cable material

Page 166: UMG8900 Installation Manual-Hardware Installation

Installation Manual - Hardware Installation U-SYS UMG8900 Universal Media Gateway Appendix C Installing Antenna System

Huawei Technologies Proprietary

C-2

Component BOM Model Structure

N connector (applicable to 1/2” super flexible feeder cable)

14040150

Feeder conversion cable 04042556 N connector+ 3.5m coaxial cable +SMA connector

Grounding clip of feeder cable 27150007 None

Grounding copper+1m grounding cable 10mm^2

Extended cable of grounding clip 04020210 W0961

PGND power cable 6m-2*OT10-8/BVR10mm^2 Yellow

Waterproof silica gel 28010167 703 silica gel -

Double faced Adhesive Tape 30070016 Semiconductor

adhesive tape -

Insulation adhesive tape 30070008

Adhesive Tape, All-Weather Adhesive Tape (38 mm x 13.4 m)

-

C.3 Installation Preparations

C.3.1 Planning Grounding Points

To achieve lightning protection, the antenna system must be correctly grounded. Generally, there are two grounding points, namely outdoor grounding point and indoor grounding point.

The satellite signal receiving antenna is usually installed on the top of a building. The outdoor grounding point should be set near the entrance from which the feeder cable is led in, and you must ensure that the grounding point is reliable. For example, if there is a mobile base station antenna or other antenna installed on the roof of the building, the feeder cable of the antenna is grounded reliably near the entrance. If you are not sure whether the grounding point is reliable, or there is no grounding point outdoors, it is allowed that the cable is not grounded outdoors. Because the grounding cable of grounding clip is 1m long, the distance between the grounding point and the feeder cable should be as near as possible, and is no more than 1 m generally. For the ease of fixation, the grounding body should be a piece of metal in the shape of board or strip.

Page 167: UMG8900 Installation Manual-Hardware Installation

Installation Manual - Hardware Installation U-SYS UMG8900 Universal Media Gateway Appendix C Installing Antenna System

Huawei Technologies Proprietary

C-3

The indoor grounding point is the protection grounding bar, which may not be near with the UMG8900 cabinet, for the feeder cable can go to the protection grounding bar.

C.3.2 Planning Antenna Installation Positions

I. Antenna Visible Range

To ensure the amount of satellites that the antenna can receive, the antenna must be installed in a position with enough visible range, that is, the visible range must be over 50% of the whole sky.

II. Radio Frequency (RF) Interference

Because the GPS satellite signal is weak and vulnerable to the interference of other RF signals, the GPS antenna should be installed in a position where there is no high-power transmitter antenna. If there is no other choice, the antenna should be kept as far from the transmitter antenna as possible. In general, it should be kept 20 m away from the mobile base station antenna. If there is a microwave transmitter antenna, the GPS antenna should be installed at the back of it, with a distance of more than 5 m.

III. Lightning Protection

To achieve lightning protection, the antenna cannot be installed at the corner of the roof. There should be lightning arrester, icon tower or other building higher than the antenna nearby, and in addition, the visual range and RF interference should be also taken into account.

C.4 Installing Antenna System

C.4.1 Installation Procedure

Figure C-1 shows the procedure for installing an antenna system.

Page 168: UMG8900 Installation Manual-Hardware Installation

Installation Manual - Hardware Installation U-SYS UMG8900 Universal Media Gateway Appendix C Installing Antenna System

Huawei Technologies Proprietary

C-4

Start

Fix antenna support

Install antenna

Install lightning arrester

End

Check

Build cement pedestal

Connect and lay out feeder cable

Make N connector

Ground feeder with grounding clip

Determine installation position

Figure C-1 Antenna installation procedures

C.4.2 Fixing Antenna Support

I. Fixing Support Onto Low Wall

If there is low wall of more than 40 cm around the roof, the antenna support can be fixed onto the wall. However, the pedestal of the support should be removed first. Follow the steps below to fix the support onto the wall:

Page 169: UMG8900 Installation Manual-Hardware Installation

Installation Manual - Hardware Installation U-SYS UMG8900 Universal Media Gateway Appendix C Installing Antenna System

Huawei Technologies Proprietary

C-5

1) Lift the antenna pole and put it again the wall. Two U clips are needed for fixing the antenna pole onto the wall. Draw the positions for installing U clips. To ensure reliability and stability, two U-shape clips should keep a distance of no less than 40 cm, and their positions on the wall should be symmetrical.

2) Drill holes according to the marks on the wall. The expansion bolt M10 is used. 3) Fix the antenna pole with U-shape clips. To ensure stability, the washer is

needed. After the fixation, pull and spin the pole to check whether it is fixed tightly.

If there are two sets of antenna systems, they should be kept more than 2m away from each other. The antenna support fixed on the wall is as shown in Figure C-2.

1. Antenna pole 2. Lightning protection box 3. Low wall 4. Expansion bolt

Figure C-2 Schematic diagram of antenna support fixed onto the low wall

II. Fixing Support onto Cement Pedestal

If the antenna support is required to be fixed in the middle of the roof, a cement pedestal need be built first, which should be 500 mm long, 500 mm wide and 200 mm high. The cement pedestal should be strong enough and its surface should be level.

Page 170: UMG8900 Installation Manual-Hardware Installation

Installation Manual - Hardware Installation U-SYS UMG8900 Universal Media Gateway Appendix C Installing Antenna System

Huawei Technologies Proprietary

C-6

In addition, the impact of outdoor temperature should be taken into account when building the pedestal. Especially in cold area, the cement pedestal should be built in advance, for if the temperature is too low, the construction cannot be carried out on site. Generally, it is required that the cement pedestal is built in advance before installing the equipment. If there are two sets of antenna systems, their pedestals should be kept 2m away from each other.

Caution:

It is prohibited to directly drill holes on the roof to fix the support.

Follow the steps below to fix the support onto the cement pedestal:

1) Put the metal underpan of the antenna support onto the middle position of the pedestal, and then mark the positions of the installation holes.

2) Drill holes according to the marks with the D-12 mm drill. 3) Fasten the expansion bolts to fix the underpan. To ensure good receiving

capability of the antenna, keep the underpan as horizontal as possible. If not, add washers.

4) Insert the antenna pole into the underpan and ensure the pole is vertical, with the deviation less than 5 degree. Fasten the screws on the underpan to fix the antenna pole.

The antenna support fixed on the cement pedestal is as shown in Figure C-3.

Page 171: UMG8900 Installation Manual-Hardware Installation

Installation Manual - Hardware Installation U-SYS UMG8900 Universal Media Gateway Appendix C Installing Antenna System

Huawei Technologies Proprietary

C-7

1. Metal underpan 2. Cement pedestal 3. Expansion bolt

Figure C-3 Schematic diagram of antenna support fixed onto the cement pedestal

C.4.3 Installing Antenna

The holder on the top of the support is used to fix the antenna. Place the antenna on the holder and insert the signal interface at the bottom of the antenna into the hole of the holder, then fix the antenna with four screws on the antenna support, as shown in Figure C-4 and Figure C-5.

Page 172: UMG8900 Installation Manual-Hardware Installation

Installation Manual - Hardware Installation U-SYS UMG8900 Universal Media Gateway Appendix C Installing Antenna System

Huawei Technologies Proprietary

C-8

1. GPC antenna 2. Holder 3. Screw

Figure C-4 Schematic diagram of installing GPS Antenna

1. Screw 2. GPS/GLONASS antenna3. Holder 4. Washer 5. Nut

Figure C-5 Schematic diagram of installing GPS/GLONASS antenna

Page 173: UMG8900 Installation Manual-Hardware Installation

Installation Manual - Hardware Installation U-SYS UMG8900 Universal Media Gateway Appendix C Installing Antenna System

Huawei Technologies Proprietary

C-9

C.4.4 Installing Lightning Arrester

I. Installing Outdoor Lightning Arrester

The outdoor lightning arrester leads the Inducting lightning current inducted on the feeder core to the cover of lightning arrester, which is connected to the shielding layer of feeder. Because the shielding layer is grounded through grounding clip before the feeder enters the building, it is not necessary to ground the outdoor lightning arrester separately. To install the outdoor lightening arrester in the lightening protection box on the antenna support, follow the procedure below:

1) Unscrew the screws on the lightning protection box and take off the cover. You can see the lightning arrester bracket.

2) There are two holes in the bracket, a bigger one and a smaller one. Insert the N connector at the “SURGE” end of the lightning arrester into the bigger hole, and insert the small screw of the N connector into the smaller hole. Then fix the N connector and the small screw with the accessory nuts and washers of the lightning arrester. See Figure C-6.

1. Lightning arrester 2. Lightning arrester bracket

Figure C-6 Schematic diagram of installing outdoor lightning arrester

II. Installing Indoor Lightning Arrester

The indoor lightning arrester leads the over-voltage that may inducted on the feeder core to the cover of lightning arrester. The indoor lightning arrester is not installed in the cabinet or other dedicated equipment, instead, it is usually placed on the cabling rack or under the ESD-preventive floor. The output end (that is, "PROTECTED" end) of the lightning arrester is connected to FCLK board by 3.5m feeder conversion cable. The small screw on the lightning arrester cover is the grounding end, which is

Page 174: UMG8900 Installation Manual-Hardware Installation

Installation Manual - Hardware Installation U-SYS UMG8900 Universal Media Gateway Appendix C Installing Antenna System

Huawei Technologies Proprietary

C-10

connected to the PGND of the cabinet or the grounding bar in equipment room by the grounding cable of the lightning arrester.

C.4.5 Making N Connector of 1/2" Super Flexible Feeder Cable

If the FSJ4-50B 1/2" super flexible feeder cable is used, the N connector will be made on site. In this case, the surplus feeder cable can be cut off. Refer to the instruction book delivered with the N connector to make it.

The required tools include hacksaw, knife, small file, brush, 19 mm spanner, 22 mm spanner, and electric dryer.

To make an N connector, follow the steps below:

1) To ensure quality, the cable for connecting the connector must be straight. 2) Cut the cable with a hacksaw to ensure the evenness of the cable section, as

shown in Figure C-7.

Figure C-7 Cable section

3) Strip the sheath of the cable for 28 mm long with a knife to expose the corrugated cooper tube. The sheath should be cut neatly, and be careful not to damage the copper pipe, as shown in Figure C-8.

Figure C-8 28 mm sheath stripped

4) Cut a 7 mm long corrugated cooper tube at the front end with the hacksaw, and then clear the foam with the knife to expose the core. Clean up the cut of the corrugated cooper tube with a file and brush. Be careful not to damage the core. See Figure C-9.

Page 175: UMG8900 Installation Manual-Hardware Installation

Installation Manual - Hardware Installation U-SYS UMG8900 Universal Media Gateway Appendix C Installing Antenna System

Huawei Technologies Proprietary

C-11

Figure C-9 Cutting 7 mm-long corrugated cooper tube to expose the core

5) Put the small rubber band around the corrugated cooper tube until it encloses the cable sheath, as shown in Figure C-10.

Figure C-10 Adding rubber band

6) Use the small file to rasp the section of the core into a slant face with width of 1mm, to facilitate connecting the N connector.

7) Smear a little lubricant on the small rubber band, and install the latter part of the N connector and then fasten it, as shown in Figure C-11.

Figure C-11 Lower part of N connector

8) Smear a little lubricant on the rubber band to install the front part of the N connector, and then fasten it by cooperation of two spanners. See Figure C-12.

Page 176: UMG8900 Installation Manual-Hardware Installation

Installation Manual - Hardware Installation U-SYS UMG8900 Universal Media Gateway Appendix C Installing Antenna System

Huawei Technologies Proprietary

C-12

Figure C-12 Upper part of N connector

9) Cover the connector with a heat-shrinkable tube and then blow it with an electric dryer. See Figure C-13.

Figure C-13 Finished N connector

C.4.6 Connecting Cables

I. Illustration of Cable Connection

The cable connection of antenna system is shown in Figure C-14.

Page 177: UMG8900 Installation Manual-Hardware Installation

Installation Manual - Hardware Installation U-SYS UMG8900 Universal Media Gateway Appendix C Installing Antenna System

Huawei Technologies Proprietary

C-13

UMG8900cabinet

Equipment room

ANT interfaceon MCLK

PGND

Lightning-proof net

Antenna

1.5m jumper

outdoor lightning arrester

Antenna support

Feeder

Grounding cable

PGND

Grounding clip

Grounding point

Feeder conversion

cable

Wall

Protection grounding bar

Grounding clipIndoor lightning arrester

Grounding cable

Figure C-14 Diagram of cable connection in antenna system

II. Connecting and Laying Jumper

The 1.5 m jumper is used to connect the antenna and outdoor lightning arrester through N connector. To connect and lay jumper, follows the steps below:

1) For GPS antenna, N connector is used. Smear the front part of the N connector with a little silica gel, but keep the latter part clean, and then connect it with 1.5 m jumper.

2) For GPS/GLONASS antenna, TNC/N conversion connector should be used. Smear a little silica gel on the TNC/N conversion connector first, add the TNC/N conversion connector, then smear some silica gel on the TNC/N conversion connector, and then connect it with 1.5 m jumper.

Page 178: UMG8900 Installation Manual-Hardware Installation

Installation Manual - Hardware Installation U-SYS UMG8900 Universal Media Gateway Appendix C Installing Antenna System

Huawei Technologies Proprietary

C-14

3) After connecting the jumper, paste semiconductor adhesive tape on the connecting point for at least 8 cm long and 3 layers thick. Then use insulating tape to cover the semiconductor adhesive tape.

4) Connect the other end of the jumper to the "SURGE" end of the outdoor lightning arrester. The jumper out of the lightning protection box should be bent downwards, to prevent rain water from entering the box.

5) Use cable ties to bind the jumper onto the antenna support, but the first binding point should keep a distance of 20 cm from the antenna head, avoiding the antenna head from bearing weight. Bind the cable tightly and leave the cable ties towards the same direction. All the cable ties should be cut smoothly. The antenna support connected with the feeder cable is as shown in Figure C-15.

Figure C-15 Antenna support connected with feeder cable

III. Connecting and Laying Feeder Cable

The feeder is used to connect the “PROTECTED” end of outdoor lightning arrester and the “SURGE” end of indoor lightning arrester through N connector.

To connect and lay feeder cable, follow the steps below:

Page 179: UMG8900 Installation Manual-Hardware Installation

Installation Manual - Hardware Installation U-SYS UMG8900 Universal Media Gateway Appendix C Installing Antenna System

Huawei Technologies Proprietary

C-15

1) Connect the "PROTECTED" end of the outdoor lightning arrester to the feeder cable. At the connecting points, first use the semiconductor adhesive tape, then use the insulating tape to seal them.

2) Lay the feeder cable along the roof and wall/outdoor cabling ladder to the entrance of the building. When cabling by cabling ladder, the feeder cables should be bound with cable ties; when cabling by wall, the feeder cable clips should be used.

3) The feeder cable clip is as shown in Figure C-16. First, fix the L-shape bracket onto the wall with two M8 expansion bolts. Then clip the feeder cables with the U clip. Note to add rubber pads at the top and the bottom. Fasten the M5 screws.

1. L bracket 2. M5 screw 3. U-shape clip 4. Rubber pad

Figure C-16 Schematic diagram of feeder cable bracket

4) The feeder cables are bound with a feeder cable clip about every two meters. In case of cabling across the wall, to avoid damaging the feeder cables, use three clips respectively before crossing the wall, on the wall and after crossing the wall to prevent feeder cables from contacting the wall.

5) Before the feeder cable enters the building, if there is a reliable grounding point on the roof (for example, the grounding point used by the base station antenna), you need ground the shielding layer of the feeder cable with grounding clip as near as possible. Refer to Section C.4.7 Grounding Feeder with Grounding Clip for specific information about grounding procedure and attentions.

Page 180: UMG8900 Installation Manual-Hardware Installation

Installation Manual - Hardware Installation U-SYS UMG8900 Universal Media Gateway Appendix C Installing Antenna System

Huawei Technologies Proprietary

C-16

6) After the feeder cable is led indoors, it is led along the cabling ladder to the protection grounding bar in equipment room, keeping a distance of less than 1m from the protection grounding bar since the grounding cable of grounding clip is 1m long. Connect the shielding layer of the feeder cable to the PGND with the grounding clip. Refer to Section C.4.7 Grounding Feeder with Grounding Clip for specific information about grounding procedure and attentions.

7) In case of cabling indoors, the feeder cable is led along the cabling ladder or through the ESD-preventive floor. If the cabling ladder is adopted, the cables should be bound with cable ties.

8) Connect the feeder cable near the equipment side to the "SURGE" end of indoor lightning arrester.

9) Paste the labels as shown in Figure C-17 at both ends of the feeder cable. In the blank square, you need mark the feeder cable number, and then fold it oppositely. Make the side with words easy to see.

75mm

12mm

30mm

ANT

Figure C-17 Feeder cable label

IV. Connecting and Laying Feeder Conversion Cable

The feeder conversion cable is used to connect the “PROTECTED” end of indoor lightning arrester and the ANT interface on FCLK board. Refer to Section 6.6.2 “Installing External Clock Cables” in Chapter 6 "Installing Signal Cables" of this manual for the specific connecting and cabling procedures.

C.4.7 Grounding Feeder with Grounding Clip

The grounding clip is used to ground the shield layer of feeder. The grounding cable of the grounding clip is 1m long, so ensure that the distance between the grounding point and the feeder cable is within 1m. If the grounding cable of the grounding clip is not long enough, extended cable of grounding clip can be used. However, it is not suggested to do so. By default, the yellow grounding cable with the length of 6m and the size area of 10 mm2 is delivered as the extended cable of grounding clip.

To ground feeder with grounding clip, follow the steps below:

1) Strip the sheath of the feeder cable for about 10 cm long. Be careful not to damage the shielding layer.

2) Roll the copper sheet of the grounding clip around the shielding layer for one circle, and then pull it out of the breach at the root. Clip the copper sheet with the

Page 181: UMG8900 Installation Manual-Hardware Installation

Installation Manual - Hardware Installation U-SYS UMG8900 Universal Media Gateway Appendix C Installing Antenna System

Huawei Technologies Proprietary

C-17

copper bar of the grounding clip, and spin the copper bar with straight screwdriver to tighten the cooper sheet, to make it well contacted with the shielding layer. However, do not tighten it too much, which may damage the feeder cable. At this time, the copper bar is wrapped inside the copper sheet. Do not take it out.

3) Use semiconductor adhesive tape to seal the connecting point for at least 20 cm long. It should be noted that no gap is allowed between grounding cable and the feeder cable. Then use insulating tap to cover the semiconductor adhesive tape completely. No part of the semiconductor adhesive tape should be exposed.

4) Fix the other end of the grounding cable onto the grounding body with bolt M8. Seal the connecting point with the semiconductor adhesive tape first and then the insulating tape. If the grounding cable of the grounding clip is not long enough, extension cable can be used. However, it is better not to use the extension cable. Seal the connecting point with the semiconductor adhesive tape first and then the insulating tape.

C.4.8 Requirements for Installing Antenna Feeder System

The requirements for installing antenna feeder system are as follows:

The connectors of the feeder cables must be tightened, to ensure its performance.

The connecting points should be sealed well with silica gel, semiconductor adhesive tape and insulating tape, especially at the connecting point between the antenna and the 1.5 m jumper.

Be careful when laying the feeder cable. Be sure to unroll the cable before laying it, avoiding damaging the cable due to inter-twist. The bending semi-diameter of the cable should be more than 15 cm.

If the connectors at both ends of the feeder cable have been made before the delivery, it is recommended not to cut the feeder cable on site, for the quality of the connectors cannot be ensured if they are re-made on site.

After the cables are connected to indoor lightning arrester, use the semiconductor adhesive tape and the insulating tape respectively to wrap the indoor lightning arrester and its connectors wholly. No metal should be exposed.

After the equipment is powered on, you can check the satellites that can be tracked. If more than four satellites can be tracked, it indicates that the antenna system functions normally.

Page 182: UMG8900 Installation Manual-Hardware Installation

Installation Manual - Hardware Installation U-SYS UMG8900 Universal Media Gateway Appendix D Connecting the UAM

Huawei Technologies Proprietary

D-1

Appendix D Connecting the UAM

D.1 Connecting the SSM with the Main Frame A main frame is the frame that has the PV8 or PV4 main control board. It connects with the SSM by the E1 cable. The main frame can be classified into front access frame and rear access frame based on the different maintenance modes.

D.1.1 Connecting the SSM with the Rear Access PV8 Main Frame

The SSM can connect with the UAM through the TDM interface board such as the E32, S1L and S2L, as shown in Figure D-1.

PV8frame

PV8 PV8

RUNALM

8K_O

UT

FE32

E1/

T1_0

-15E1

/T1

_16

-31

OFFLINE

RUNALM

8K_O

UT

E1/

T1_0

-15E1

/T1

_16

-31

OFFLINE

FE32

RUNALM

8K_O

UT

FE32

E1/

T1_0

-15E1

/T1

_16

-31

OFFLINE

RUNALM

8K_O

UT

E1/

T1_0

-15E1

/T1

_16

-31

OFFLINE

FE32

SSM

X8X32

X9X16

X2 X1X8X32

X9X16

X2 X1

Figure D-1 SSM connecting with the main frame

Page 183: UMG8900 Installation Manual-Hardware Installation

Installation Manual - Hardware Installation U-SYS UMG8900 Universal Media Gateway Appendix D Connecting the UAM

Huawei Technologies Proprietary

D-2

The connection between the SSM and the UAM is shown in Figure D-1.

This figure illustrates the connection mode between the SSM and the rear access UAM through the example of the SSM connecting with the PV8 main frame by the E32 board. The PV8 board connects with the E32 board through eight E1 cables. The dashed line in the diagram above represents a logical line. A logical line means the two ends connect with each other through the transmission equipment or the DDF instead of connecting directly.

The two E1 cables of the PV8 main frame must be configured to different E32 boards in order to avoid the loss of communication between the UAM and the SSM due to the E32 board default.

D.1.2 Connecting the SSM with the Front Access UAFM Frame

The cables of the front access UAM are connected to the corresponding interfaces of the cabling area. The interfaces are marked with distinctive silk printing.

The connection between the SSM and the front access UAFM is shown in Figure D-2.

Page 184: UMG8900 Installation Manual-Hardware Installation

Installation Manual - Hardware Installation U-SYS UMG8900 Universal Media Gateway Appendix D Connecting the UAM

Huawei Technologies Proprietary

D-3

RUNALM

8K_O

UT

FE32

E1/

T1_0

-15E1

/T1

_16

-31

OFFLINE

RUNALM

8K_O

UT

E1/

T1_0

-15E1

/T1

_16

-31

OFFLINE

FE32

SSMRUNALM

8K_O

UT

FE32

E1/

T1_0

-15E1

/T1

_16

-31

OFFLINE

RUNALM

8K_O

UT

E1/

T1_0

-15E1

/T1

_16

-31

OFFLINE

FE32

X8X32

X9X16

X2 X1

X8X32

X9X16

X2 X1

UAFM

(1) (2)

(1) W1-Left PV8/PV4 (5 - 8)E1 W2-Right PV8/PV4(5 - 8)E1

(2) W1-Left PV8/PV4 (1 – 4)E1 W2-Right PV8/PV4 (1 - 4)E1

Figure D-2 SSM connecting with the UAFM

As shown in Figure D-2, the UAFM frame connects with the E32 board of the SSM through the two interfaces PV4 E1 and PV8 E1.

If the PV4 main control board is adopted, the UAFM frame provides 8 E1 interfaces through the PV4 E1. In such networking, the PV8 E1 interface is not used.

If the PV8 main control board is adopted, the UAFM frame provides the first 4 E1 interfaces for the two PV8 boards through the PV4 E1, the number of which are from 0 to 3 and 8 to 11. The PV8 E1 provides the last 4 E1 interfaces for the two PV8 boards, the number of which are from 4 to 7 and 12 to 15.

The data configuration between the SSM and the UAM must be the same as that in the physical connection. It is strongly recommended to follow the networking configuration requirements for the actual connection.

Page 185: UMG8900 Installation Manual-Hardware Installation

Installation Manual - Hardware Installation U-SYS UMG8900 Universal Media Gateway Appendix D Connecting the UAM

Huawei Technologies Proprietary

D-4

D.2 Connecting the Main Frame and Sub Frame A main frame is the frame that uses the PV8 or PV4 main control board. It can also be called a PV8 frame. A sub frame is the frame that uses the RSP main control board and can also be called an RSP sub frame.

The connection between a main frame and a sub frame is shown in Figure D-3.

RSPframe

RSP RSP

HWC

PV8

frame

Figure D-3 Connection between a main frame and a sub frame

The connection between a rear access main frame and a rear access sub frame is shown in Figure D-3.

Each HW cable in the diagram contains four HW connections. The PV8 frame altogether provides 32 HW connections. The PV8 frame cascades with the RSP frame through the HW cables. The number of the HW cables determines the convergence ratio of the RSP frame.

The correctness of the HW cable connection decides whether the sub frame can work properly. It is strongly recommended to follow the networking configuration requirements for actual connection.

The HW cable of the front access frame is connected to the corresponding interfaces of the cabling area. There is distinctive silk printing on the interfaces. For details, refer to U-SYS UMG8900 Universal Media Gateway UAM Hardware Description.

Page 186: UMG8900 Installation Manual-Hardware Installation

Installation Manual - Hardware Installation U-SYS UMG8900 Universal Media Gateway Appendix D Connecting the UAM

Huawei Technologies Proprietary

D-5

D.3 Connecting the SSM with the Direct Frame A direct frame includes an RSP frame with the RSP main control board and an RSB frame with the RSA main control board.

D.3.1 Connecting the RSP Frame

Presently a RSP frame includes RSP_10, RSP_12, RSP_14, RSP_19 and other frames.

The connection between a SSM frame and a RSP frame is shown in Figure D-4.

RUNALM

8K_O

UT

FE32E1

/T1

_0-15

E1/

T1_1

6-31

OFFLINE

RUNALM

8K_O

UT

E1/

T1_0

-15E1

/T1

_16

-31

OFFLINE

FE32

RUNALM

8K_O

UT

FE32

E1/

T1_0

-15E1

/T1

_16

-31

OFFLINE

RUNALM

8K_O

UT

E1/

T1_0

-15E1

/T1

_16

-31

OFFLINE

FE32

SSMX32

X5X8 X4 X1X32

X5X8 X4 X1

RSPframe

RSP RSP

X1X2X3X4 X1X2X3X4X1X2X3X4X1X2X3X4

Figure D-4 A SSM frame connecting with a RSP frame

Page 187: UMG8900 Installation Manual-Hardware Installation

Installation Manual - Hardware Installation U-SYS UMG8900 Universal Media Gateway Appendix D Connecting the UAM

Huawei Technologies Proprietary

D-6

D.3.2 Connecting the RSB Frame

The RSB frame is classified into two types: RSB and RSB-HK.

The connection between the RSB and the SSM is shown in Figure D-5.

RUNALM

8K_O

UT

FE32

E1/

T1_0

-15E1

/T1

_16

-31

OFFLINE

RUNALM

8K_O

UT

E1/

T1_0

-15E1

/T1

_16

-31

OFFLINE

FE32

SSM

T1R15

R1T15

R0 T0JN4RX

JN3TX

JN1RX

JN2TX

RSB Frame

Figure D-5 The SSM connecting with the RSB

As shown in Figure D-5, the RSB frame connects with the SSM through the E1 interface of the backplane.

The connection between the SSM and the RSB-HK is shown in Figure D-6.

Page 188: UMG8900 Installation Manual-Hardware Installation

Installation Manual - Hardware Installation U-SYS UMG8900 Universal Media Gateway Appendix D Connecting the UAM

Huawei Technologies Proprietary

D-7

RUNALM

8K_O

UT

FE32

E1/

T1_0

-15E1

/T1

_16

-31

OFFLINE

RUNALM

8K_O

UT

E1/

T1_0

-15E1

/T1

_16

-31

OFFLINE

FE32

SSM

T1R15

R1T15

R0 T0

RXTX RXTX

RSA RSAPIN 17 PIN 17

PIN 24 PIN 24

RSB_HK

Figure D-6 The SSM connecting with the RSB_HK

As shown in Figure D-6, the RSB_HK connects with the SSM through the E1 interfaces provided by No. 17 – 24 pins of the RSA board on the backplane of the RSB_HK frame.

D.4 Connecting the SSM with the RSA Frame The RSA frame is in a 19-inch cabinet and provides 11 usable slots. The boards include the power board, TSS testing board and four pairs of RSA boards. Each pair of RSA boards can provide 2 HW cables to interconnect with the RSA sub frames. The RSA sub frame provides subscriber interfaces and the backplane provides eight E1 interfaces.

The SSM connects with the RSA frame through the E1 interface, as shown in Figure D-7.

Page 189: UMG8900 Installation Manual-Hardware Installation

Installation Manual - Hardware Installation U-SYS UMG8900 Universal Media Gateway Appendix D Connecting the UAM

Huawei Technologies Proprietary

D-8

RUNALM

8K_O

UT

FE32

E1/

T1_0

-15

E1/

T1_1

6-31

OFFLINE

RUNALM

8K_O

UT

E1/

T1_0

-15

E1/

T1_1

6-31

OFFLINE

FE32

SSM

T1R15

R1T15

R0 T0

J1RX

J11RX

J15RX

J12TX

J2TX

J3RXJ4TXJ5RXJ67X

J13RXJ14TX

J7RXJ8TXJ9RXJ10TX

J16TX

RSA Frame

Figure D-7 The SSM connecting with the RSA

The J1-J16 in the diagram represents 75 ohm E1 coaxial cable interfaces and there are altogether eight E1 interfaces.

D.5 Connecting the RSA Frame with the RSA Sub Frame The RSA frame is a remote access frame and can support four pairs of RSA boards at most. Each pair of RSA boards can provide two HW interfaces to connect with RSA sub frames. Currently there are two types of RSA main frames, which are RSA_22 and RSA_26. The difference between the two types is in the number of their slots.

The RSA sub frame communicates with the RSA main frame through the DRV board. There are now two kinds of RSA sub frames, which are USR_16 and USR_19. The difference in the two types is in the number of their subscriber boards.

The connection between the RSA main frame and the RSA sub frame is shown in Figure D-8.

Page 190: UMG8900 Installation Manual-Hardware Installation

Installation Manual - Hardware Installation U-SYS UMG8900 Universal Media Gateway Appendix D Connecting the UAM

Huawei Technologies Proprietary

D-9

USRframe

DRV DRV

RSAframe

RSA RSA

(2)

(1)

(1) HW cable (2) NOD cable

Figure D-8 The RSA main frame connecting with the RSA sub frame

As shown in Figure D-8, the RSA main frame connects with the RSA sub frame through the HW cable and the NOD cable.

Page 191: UMG8900 Installation Manual-Hardware Installation

Installation Manual - Hardware Installation U-SYS UMG8900 Universal Media Gateway

Appendix E Requirements for Equipment Operating Environment

Huawei Technologies Proprietary

E-1

Appendix E Requirements for Equipment Operating Environment

E.1 Introduction to the Chapter

This chapter contains the following sections:

E.2 Site Requirements

The communication equipment should run in a favorable environment. Its equipment room should be located at a place free from high temperature, dust, toxic gases, explosive materials or instable voltage, and away from great vibrations, strong noise or power transformer stations. During project designing, such factors as hydrographic, geological, seismic, power supply and transportation factors should be taken into consideration to select the site in line with the engineering and environmental requirements for the communication equipment.

The construction, structure, heating and ventilation, power supply, lighting, and firefighting designs of the communications equipment room are done by specialized construction designers and the environment design requirements of the switch should be strictly followed. The communication equipment room shall be designed in accordance with the industrial, environmental protection, fire-fighting and civil defense requirements, as well as the current standards/regulations of the local country or region and the requirements of special technical process for building construction design.

Site requirements are as follows:

The site should be kept away from pollution sources. For sources of heavy pollution such as the smeltery and coal mine, keep a distance of 5 km. For sources of medium pollution such as the chemical, rubber and galvanization industries, keep a distance of 3.7 km. For sources of light pollution such as food and tanner industries, keep a distance of 2 km. If these sources of pollution cannot be avoided, the equipment room must be in the perennial upwind direction of the pollution sources. In addition, quality equipment room or protection product must be adopted.

The ventilation port for air exchange of the equipment room must be kept away from the exhaust of city waste pipes, big cesspools and sewage treatment tanks. The equipment room should be kept in the positive pressure state lest

Page 192: UMG8900 Installation Manual-Hardware Installation

Installation Manual - Hardware Installation U-SYS UMG8900 Universal Media Gateway

Appendix E Requirements for Equipment Operating Environment

Huawei Technologies Proprietary

E-2

the corrosive gases enter the equipment room and erode components and circuit boards.

The equipment room should be kept away from the industrial and heating boilers.

It is best to locate the equipment room in or above the second floor. If this requirement cannot be satisfied, the ground for equipment installation in the equipment room shall be at least 600 mm above the maximum flood level in the local record.

The equipment room should be kept away from livestock farms. If this requirement cannot be satisfied, it should be located in the perennial upwind direction of the livestock farms.

The equipment room should be kept 3.7 km away from the seaside or salt lake. If this requirement cannot be satisfied, the equipment room should be airtight with cooling facilities. In addition, the alkalized soil cannot be used as the construction material. Otherwise, the equipment applicable in atrocious environment must be adopted.

The old livestock room or the chemical fertilizer warehouse cannot be used as the equipment room.

The equipment room should be solid enough to withstand wind and downpour. The equipment room should be kept away from the road or sand field with

dusts flying around. If this requirement cannot be satisfied, the windows and doors of the equipment room should be kept away from the sources of pollution

E.3 Building Requirements

Table E-1 shows the requirements for the building specifications of the equipment room.

Table E-1 Requirements for building specifications of the equipment room

Item Specification

Area The equipment room can hold the whole equipment.

Net height The indoor minimum height is the net height under beam or air pipe. The net heath must not be less than 3 meters.

Indoor floor It is required that the floor is semi-conducting and dust-free. Generally, it is required to pave ESD-preventive floor. The floor blocks must be paved securely, and the error per square meter must not be more than 2 mm. If there is not raised floor, it is required to use static-conducing material (size to impedance ratio is 1.0 x 107 – 1.0 x 1010Ω). The static-conducting material or raised floor must be well connected to grounding device through current-limited resistance and connection cable. The impedance of current limit resistance is 1 MΩ.

Page 193: UMG8900 Installation Manual-Hardware Installation

Installation Manual - Hardware Installation U-SYS UMG8900 Universal Media Gateway

Appendix E Requirements for Equipment Operating Environment

Huawei Technologies Proprietary

E-3

Item Specification

Floor load bearing capacity

More than 400 kg/m2

Door and window The door is 2 meters high and 1 meter wide. It is OK to use one door panel. It is required to seal the door and window by dust-proof rubber tape, and use double-layer windows and seal them.

Wall surface It is possible to paste wall paper or paint lusterless paint on the wall, but chalked paint is not recommended.

Indoor groove Groove is used to lay cables. It must be clean inside. The reserved length, width, the number of holes, the hole positions and hole size must comply with the requirements for the layout of optical synchronous transmission devices.

Water supply and drainage

The power supply pipe, drainage pipe and rain pipe must not pass through the equipment room, and fire extinguisher should be equipped where it is easy to find and access, such as corridor or staircase, instead of in the equipment room.

Partition in equipment room

The installation place must be separated from the door of the equipment room. The partition panel will be helpful to prevent some dust. The partition is shown in Figure E-1.

Air conditioner position

The outlet air of the air conditioner must not directly point to the equipment.

Other requirements In the equipment room, specific measures must be taken to prevent epiphyte and mildew, as well as rodent animals, such as mouse.

Equipment

Airconditioner

Partition panel

Figure E-1 Partition in equipment room

Page 194: UMG8900 Installation Manual-Hardware Installation

Installation Manual - Hardware Installation U-SYS UMG8900 Universal Media Gateway

Appendix E Requirements for Equipment Operating Environment

Huawei Technologies Proprietary

E-4

E.4 Humidity and Temperature Requirements

To ensure that the equipment operates in good condition, the humidity and temperature must be kept within a certain range in the equipment room. Table E-2 shows the specific requirements.

Table E-2 Humidity and temperature requirements

Temperature Relative humidity

Long term Short term Long term Short term

+5 °C – +40 °C -5°C – +55°C 5% – 85% 5% – 95%

Note:

The measurement points of temperature and humidity refer to the values measured 1.5 m above the floor and 0.4 m away from the front side of the cabinet when there are no protection panels in the front and back of the cabinet.

Short term means that the consecutive working duration is not more than 48 hours and that the accumulated working duration of a year is not more than 15 days.

To meet the above requirements, the following measures must be taken in the equipment room:

The temperature control facility is equipped in the equipment room. Humidifier can be used in dry areas. It is also possible to use wet mop to mop

the floor to keep the humidity. In areas with high humidity, desiccating machine can be used.

E.5 Air Cleanness Requirements

The dust accumulated on the equipment might cause static attached, which might cause metal connectors or metal contacts in bad contact. This will affect the life of the equipment, and bring the equipment with faults.

In the equipment room, there must not exist explosive, conducing, magnetic-conductive, or erosive dust. Table E-3 shows the requirements on dust density.

Page 195: UMG8900 Installation Manual-Hardware Installation

Installation Manual - Hardware Installation U-SYS UMG8900 Universal Media Gateway

Appendix E Requirements for Equipment Operating Environment

Huawei Technologies Proprietary

E-5

Table E-3 Dust particle limit in the equipment room

Mechanically active material Unit Content

Dust particle particle/m³ ≤3×104

(There is no visible dust on desk within 3 days)

Note: Dust particle: diameter ≥5 µm

To meet the above requirements, the following measures must be taken in the equipment room:

Dust-free materials must be used on the floor, walls, and ceiling. Door screen and window screen must be used for the doors and windows

toward outdoors. The windows must have dust-proof function. The equipment room and dust filter of the equipment must be cleaned

periodically (every 3 months). People entering the equipment room must wear ESD-preventive shoes,

ESD-preventive suits, and ESD-preventive wrist straps.

E.6 Erosive Gas Condition Requirements

Besides dust-proof measures, erosive gas proof measures must be taken in the equipment room to prevent such gases as SO2, H2S, and NH3. Table E-4 shows the requirements on the density of erosive gases.

Table E-4 Erosive gas density limit

Chemically active material Unit Content

SO2 mg/m³ ≤0.20

H2S mg/m³ ≤0.006

NH3 mg/m³ ≤0.05

Cl2 mg/m³ ≤0.01

To meet the above requirements, the following measures must be taken in the equipment room:

The equipment room must be far away from the areas with high density of erosive gases, such as chemical plants.

The air inlet must be against the pollution sources. The storage batteries must be placed separately in an independent room. It is required to ask professional company to inspect the environment

periodically.

Page 196: UMG8900 Installation Manual-Hardware Installation

Installation Manual - Hardware Installation U-SYS UMG8900 Universal Media Gateway

Appendix E Requirements for Equipment Operating Environment

Huawei Technologies Proprietary

E-6

E.7 Electromagnetic Requirements

Table E-5 shows the electromagnetic requirements.

Table E-5 Electromagnetic range

Environment electromagnetic Parameter

Frequency (Hz) 50 to 20 000 Low-frequency magnetic field

Ampl. A/m (rms) 10 to 0.025

Frequency (MHz) 0.009 – 1000 Amplitude-modulation radio-frequency electric field

Ampl. V/m (rms) 3

Frequency (GHz) 1–20 Pulse-modulation radio-frequency electric field

Ampl. (V/m (peak)) 3

The following measures can be taken to suppress the interference signals:

The equipment must be far away from transformer, high-voltage electricity transmission lines, and high-current devices. For example, there is no AC transformer within 20 square meters, or high-voltage electricity transmission lines within 50 square meters.

The equipment must be far away from high-power broadcast transmitter, for example, there is no high-power broadcast transmitter within 500 square meters.

If there is mobile communication transmitter in the equipment building, the interference must comply with related requirements, and shielding measures must be taken to prevent the interference.

In the equipment room, it is prohibited to use wireless handy set near the equipment.

E.8 ESD-Preventive Requirements

The absolute voltage of electrostatic must be less than 1000 V.

To meet the above requirement, the following measures must be taken in the equipment room:

All operators must be trained in ESD-preventive knowledge. The humidity must be kept within a certain range, for example, above 60%RH,

to reduce the effect by electrostatic. The equipment room must have ESD-preventive floor, and people entering the

equipment room must wear ESD-preventive shoes, ESD-preventive suits, and ESD-preventive wrist straps.

Page 197: UMG8900 Installation Manual-Hardware Installation

Installation Manual - Hardware Installation U-SYS UMG8900 Universal Media Gateway

Appendix E Requirements for Equipment Operating Environment

Huawei Technologies Proprietary

E-7

E.9 Lightning Protection Requirements

Table E-6 shows the lightning protection requirements.

Table E-6 Lightning protection requirements

Item Description

Building requirements

It is better that the equipment building is of reinforced concrete structure.

The equipment building must have lightning arrester.

The ground for lightning arrester of the equipment building and the protection ground of the equipment room share the same group of grounding bodies.

AC power supply system adopts TN-S power supply

The communication office has dedicated power transformer. The power cables must have metal bushing or insulation bushing, and are led in to the office through metal pipe under ground. The metal bushing or metal pipe must be grounded at both ends. The length under group must be not less than 15 meters.

The three phase lines at the low-voltage side of the AC transformer in the communication office must have separate gapless zinc oxide lightning protector. The shell of the transformer, the AC neutral line at the low-voltage side, and the metal bushing of the power cable connected to transformer shell must be grounded nearby.

Lightning protector for incoming power cable

It is not allowed to lead in or out the AC or DC power cables to/from communication office in overhead way.

After low-voltage power cables are led into the equipment room, lightning protector must be installed for the power cables in the AC voltage regulator and AC switchboard, and the lightning protector must be grounded nearby.

In the city, it is recommended to use power lightning protector with nominal discharge current of more than 20 kA. In the suburbs with more lightning dangers, it is recommended to use power lightning protector with strike through-flow of more than 60 kA. In mountains or higher buildings in the city, it is recommended to use power lightning protector with strike through-flow of more than 100 kA.

The length of grounding cable for power lightning protector must be less than 1 meter.

DC power distribution grounding

The DC working ground of the communication office (positive of –48V or negative of 24V) must be connected to the indoor grounding bus nearby, and the grounding cable must satisfy the requirements for the maximum load of the equipment.

The power supply devices for the communication office must have DC working grounding cable connected to the grounding bus in the communication building or the protection grounding bar in the equipment room.

Page 198: UMG8900 Installation Manual-Hardware Installation

Installation Manual - Hardware Installation U-SYS UMG8900 Universal Media Gateway

Appendix E Requirements for Equipment Operating Environment

Huawei Technologies Proprietary

E-8

Item Description

Equipotential connection

The communication equipment and auxiliary devices, such as mobile base station, transmission device, switching device, power supply device, and cable distribution rack, must be well grounded. Their protection grounds must be connected to the grounding bar in the equipment room.

The working ground and protection ground of the communication equipment in the equipment room share the same ground net.

The cabling rack, suspension metal bracket, cabinet or shell, metal air vent and metal doors and windows must be well grounded.

Grounding requirements

It is prohibited to connect the neutral line of AC power cable to protection ground of the communication equipment.

It is prohibited to use fuse or switch on the grounding cables.

All grounding cables must be as short and straight as possible.

Grounding impedance requirements

The grounding impedance is less than 1 ohm.

The upper part of the grounding body must be more than 0.7 m from the ground. In cold areas, the grounding body must be buried under frozen soil layer.

It is required to measure the grounding impedance periodically, to ensure the validity of grounding.

Signal cable layout requirements

In the communication office, signal cables must be laid underground.

The communication cables must have metal bushing or be laid in metal pipe when they are led in or out of the communication office.

The grounding cable for lightning protector must be as short as possible, and unused wires in the cables must be well grounded in the equipment room.

Grounding bus requirement

The grounding bus can be realized in grounding ring mode or grounding bar mode.

The grounding cable must not be aluminum. When different kinds of metals are connected, correct measures must be taken to prevent couple corrosion.

The grounding bus cable is made of copper bar with sectional area of not less than 120 mm2 or zinc-coated steel with the same impedance. The grounding bus cable must be insulated from the steel of the building.

Grounding lead-in cable requirement

The grounding lead-in cable must not be longer than 30 meters, and it is recommended to use zinc-coated steel with sectional area of 40mm x 4mm or 50mm x 5mm as the material.

Page 199: UMG8900 Installation Manual-Hardware Installation

Installation Manual - Hardware Installation U-SYS UMG8900 Universal Media Gateway

Appendix E Requirements for Equipment Operating Environment

Huawei Technologies Proprietary

E-9

E.10 Requirements for Power Supply

E.10.1 Requirements for AC Power Supply

I. Generic requirements on AC power supply

Adopt the centralized AC power supply model of mains, uninterrupted power supply (UPS), and a reserved diesel generator.

Ensure simplicity in cable connection, security in operation, flexibility in scheduling, and convenience in maintenance.

Adopt three-phase and five-wire, or monophase three-wire AC power for low-voltage power supply system.

Table E-7 lists the nominal voltage and rated frequency of low-voltage power supply system.

Table E-7 Specifications of AC voltage and frequency

Nominal voltage Rate frequency

110/127//220/380 V 50 Hz

Adopt UPS for the backup AC power supply. Keep it the same phase with mains. Set the switching time between mains and UPS less than 10 ms; otherwise, the product will reboot or reset itself.

Ensure that the equipment runs well below nominal current; never in the threshold of failure.

Use a separate AC power supply protection unit for a piece of separate equipment. The current to trigger the protection should be greater than the

When designing the DC power supply system, consider the maximum static and dynamic load of the system. Always keep sufficient room for the two thresholds.

Choose the model of the power cables by the maximum load of power supply.

The diesel generator set of the office automatically functions in case of power failure, automatically supply when the mains is insufficient, and automatically stops functioning when power restores. It can be tested and controlled remotely in standard interface and communication protocols.

II. Power supply specifications of AC-powered equipment

Here are the power supply specifications of AC-powered equipment:

Page 200: UMG8900 Installation Manual-Hardware Installation

Installation Manual - Hardware Installation U-SYS UMG8900 Universal Media Gateway

Appendix E Requirements for Equipment Operating Environment

Huawei Technologies Proprietary

E-10

Voltage fluctuation of communications equipment: –10% – +5% of rated voltage.

Voltage fluctuation of power supply equipment and important buildings:–15% – +10% of rated voltage.

Frequency fluctuation:–4% – +4%. Aberration rate of voltage sine wave: ≤5%.

III. Specifications of power cables

Here are the specifications of the power cables:

Use the neutral line of the same cross-sectional area as the live line. Select the DC power feeder on long-term load. Use fire-resistant AC cables.

Suggestions on AC power supply are as fllows:

When the voltage of mains power supply is not stable, use the voltage regulator in any of the following conditions:

Powered by mains, the voltage fluctuation of communications equipment exceeds the rated threshold (–10% – +5% of rated voltage).

Powered by mains, the voltage exceeds the rated voltage fluctuation of communications equipment.

Not directly powered by mains, the voltage fluctuation exceeds the rated threshold (–15% – +10% of rated voltage).

The voltage exceeds the rated AC voltage fluctuation of DC power supply equipment.

Use UPS or inverter to prevent interruption or surge of power supply. Use a diesel generator set when the mains is faulty. The capacity of the

generator set should 1.5 to 2 times of the capacity of UPS. Use two groups of storage batteries in parallel. Use one group of UPS storage batteries. The batteries can be working in

parallel or serial connection. Use main inverter based on the maximum power. Keep a backup one.

E.10.2 Requirements for DC Power Supply

Ensure stable power supply. Close the power supply equipment to the communications equipment to minimize the feeder line. The voltage level between battery and the equipment should be less than 3.2 V.

When there are more than two switching systems, use two or multiple independent power supply systems.

Set up multiple independent power supply systems for important communication centers, each of which powers a separate equipment room. For ordinary offices,

Page 201: UMG8900 Installation Manual-Hardware Installation

Installation Manual - Hardware Installation U-SYS UMG8900 Universal Media Gateway

Appendix E Requirements for Equipment Operating Environment

Huawei Technologies Proprietary

E-11

adopt the model of a centralized power supply room plus a battery room. For small-capacity offices, adopt the centralized power supply model. Always prevent the boards from the erosive chemicals given out from batteries.

Table E-8 specifies the requirements on DC power supply.

Table E-8 DC power supply specifications

Item Specifications

Voltage fluctuation of –48-V input end

–40V–57V

Anti-surge current capability

Should be 1.5 times greater than the rated load current capability.

Voltage stability When the AC input voltage range is from 85% to 110% of the rated value, and the load current is from 5% to 100% of the rated value, the output voltage of the current stabilizer is an integral value between –56.4 and –46.0V. The variance is less than equal to 1%.

Voltage surge at power-on and power-off

Less than equal to the integral value of DC output value ±5%

Peek-to-peek noise voltage

≤200mV

Dynamic response The recovery time is less than 200 ms. The exceeding amount should not be more or less than 5% of the rated DC output voltage.

Suggestions on DC power supply are as follows:

Use the distributed power supply model. Scatter the power supply systems to multiple sites.

Adopt standard DC power supply system. The output voltage of the power supply equipment should meet the requirement of the communications equipment.

Enhance the reliability of the power supply system. Optimize the capacity of the storage batteries. In small-capacity offices, when it is difficult to maintain the reliability of the power supply system, expand the capacity of the storage batteries.

The total configuration of high-frequency switch rectifier should meet the load power of communication and the recharging power of the storage batteries. Adopt the redundant configuration model for the rectifier module. Use a standby rectifier for less than ten active ones; and add one rectifier for every additional ten active ones.

Page 202: UMG8900 Installation Manual-Hardware Installation

Installation Manual - Hardware Installation U-SYS UMG8900 Universal Media Gateway

Appendix E Requirements for Equipment Operating Environment

Huawei Technologies Proprietary

E-12

Equip the storage batteries in two or multiple groups. The total capacity is determined by the power feeding duration. Ensure at least one hour of power supply capability for the storage battery group.

Page 203: UMG8900 Installation Manual-Hardware Installation

Installation Manual - Hardware Installation U-SYS UMG8900 Universal Media Gateway

Appendix F List of Abbreviations and Acronyms

Huawei Technologies Proprietary

F-1

Appendix F List of Abbreviations and Acronyms

A

A4L 4 Port STM-1 ATM Fiber Interface Board

AC Alternating Current

B

BGND Backloop GND

BITS Building Integrated Timing Supply

BLU Back Link Unit

C

CSA Canadian Standards Association

D

DDF Digital Distribution Frame

DRV Dual Tone Number Receiving & Drive Board

F

FA4L Fixed Network 4 Ports STM-1 ATM Optical Interface Board

FCLK Fixed Network Clock Unit

FE Fast Ethernet

FE32 Fixed network 32E1 ports TDM interface board

FG1O Fixed Network one-port GE Optical interface board

FNET Fixed Network Packet Switch Unit

FP1H Fixed Network 1 Port STM-4 POS Optical Interface Board

FP4L Fixed Network 4 Port STM-1 POS Optical Interface Board

FS2L Fixed Network 2*155M SDH/SONET optical interface board

FT32 Fixed network 32T1 ports TDM interface board

FTNB Fixed Network TDM switching Net Unit B

G

GE Gigabit Ethernet

GLONASS GLObal NAvigation Satellite System

GND Ground

Page 204: UMG8900 Installation Manual-Hardware Installation

Installation Manual - Hardware Installation U-SYS UMG8900 Universal Media Gateway

Appendix F List of Abbreviations and Acronyms

Huawei Technologies Proprietary

F-2

GPS Global Position System

H

HW Highway

I

IP Internet Protocol

L

LAN Local Area Network

LMT Local Maintenance Terminal

M

MGW Media Gateway

N

NGN Next Generation Network

NOD Node Communication Board

O

ODF Optical Distribution Frame

OMC Operation & Maintenance Center

P

P4L 4 Ports STM-1 POS Interface Board

PC Personal Computer

PGND Protection Ground

PSTN Public Switched Telephone Network

R

RSA Remote RSA Interface Board

RSP Remote Subscriber Processor

S

S1L 1*155M SDH/SONET interface board

S2L 2*155M SDH/SONET interface board

SDH Synchronous Digital Hierarchy

SSM Service Switching Module

T

TCLU TDM Convergence & Link Unit

TDM Time Division Mulitiplex(ing)

TNU TDM central switching Net Unit

TSS Test Board

Page 205: UMG8900 Installation Manual-Hardware Installation

Installation Manual - Hardware Installation U-SYS UMG8900 Universal Media Gateway

Appendix F List of Abbreviations and Acronyms

Huawei Technologies Proprietary

F-3

U

UL Underwriters Laboratories

UPS Uninterrupted Power Supply

W

Page 206: UMG8900 Installation Manual-Hardware Installation

Installation Manual - Hardware Installation U-SYS UMG8900 Universal Media Gateway Index

Huawei Technologies Proprietary

i-1

Index

A affixing label

to power cable, B-8

to signal cable, B-6

C connecting the UAM

connecting main and sub frame, D-4

connecting RSA and RSA sub, D-8

front access main frame, D-2

rear access main frame, D-1

RSA frame, D-7

RSB frame, D-6

RSP frame, D-5

connecting to alarm system

alarm box, 8-2

connection description, 8-3

grounding, 8-3

connecting to LMT

connecting, 8-1

connecting grounding cable, 8-2

grounding, 8-2

E engineering label

affixing label, B-6

for AC power cable, B-22

for DC power cable, B-20

for ethernet cable, B-11

for of alarm box, B-10

for optical fiber, B-13

for subscriber cable, B-19

for trunk cable, B-16

function, B-1

information carried on label, B-9

label for power cable, B-3

label for signal cable, B-2

label type, B-2

material specification, B-1

printing label, B-3

remark, B-9

writing label, B-5

engineering label for cable, 5-21

F fixing antenna support

onto cement pedestal, C-5

onto low wall, C-4

H hardware installation check

checking cabinet, 9-1

checking cabling trough and rack, 9-3

checking connector, 9-2

checking environment, 9-3

checking internal cable, 9-2

checking label, 9-3

checking network cable, 9-2

checking optical fiber, 9-2

checking power cable, 9-1

checking power supply, 9-3

checking protection grounding cable, 9-1

checking socket, 9-2

checking trunk cable, 9-2

performing board power-on test, 9-4

I information carried on label

for power cable, B-9

for signal cable, B-9

installation preparation

BITS, 2-5

digital distribution frame, 2-4

interface to IP network, 2-5

Page 207: UMG8900 Installation Manual-Hardware Installation

Installation Manual - Hardware Installation U-SYS UMG8900 Universal Media Gateway Index

Huawei Technologies Proprietary

i-2

optical transmission equipment, 2-5

installing antenna system

antenna system, C-1

connecting and laying feeder cable, C-14

connecting and laying jumper, C-13

connecting feeder conversion cable, C-16

fixing antenna support, C-4

grounding feeder, C-16

installing antenna, C-7

installing lightning arrester, C-9

making N connector, C-10

planning antenna position, C-3

planning grounding point, C-2

procedure, C-3

requirement, C-17

installing cabinet fitting

adjusting holder height, 7-2

installing cabinet side panel, 7-4

installing door lintel, 7-2

installing floor holder, 7-1

installing front and back door, 7-5

recovering ESD-preventive floor, 7-2

installing cabinet on cement floor

determining cabinet position, 3-18

drilling hole, 3-21

fixing bottom of cabinet, 3-24

fixing top of combined cabinet, 3-24

installing expansion bolt, 3-22

leveling cabinet, 3-23

marking installation hole position, 3-18

N68-22 cabinet, 3-1

performing insulation test, 3-25

positioning cabinet, 3-22

procedure, 3-17

installing cabinet on ESD-preventive floor

adjusting support height, 3-10

amount of holder and rail, 3-4

amount of support, 3-3

assembling support and slide rail, 3-11

determing cabinet position, 3-5

drilling hole, 3-8

fixing bottom of cabinet, 3-15

fixing support, 3-12

fixing top of combined cabinet, 3-15

floor holder-slide rail assembly, 3-3

installing expansion bolt, 3-9

installing holder fixing component, 3-13

installing insulation plate, 3-14

leveling cabinet, 3-14

marking installation hole position, 3-6

N68-22 cabinet, 3-1

N800 series support, 3-1

performing insulation test, 3-16

positioning cabinet, 3-14

procedure, 3-4

installing cabling rack

assembling cabling ladder, A-8

component, A-1

function, A-1

installation mode, A-7

installing baffle ring, A-18

installing cable bushing, A-18

installing cable-through clip, A-17

installing cabling rack, A-13

installing cabling trough, A-10

installing end cover, A-18

installing rack over cabinet, A-16

installing triangular support, A-15

installing turning cabling rack, A-11

procedure, A-7

specification, A-7

installing cabling rack over cabinet

connecting cabling rack, A-16

installation way, A-16

installing cascading cable

cascading cable connection, 6-15

crossover cable relationship, 6-13

installing, 6-14

requirement, 6-14

type and appearance, 6-13

installing external clock cable

connection relationship, 6-23

installing, 6-23

requirement, 6-23

Page 208: UMG8900 Installation Manual-Hardware Installation

Installation Manual - Hardware Installation U-SYS UMG8900 Universal Media Gateway Index

Huawei Technologies Proprietary

i-3

type and appearance, 6-22

installing external grounding cable

core areas of cable, 5-12

installing, 5-13

requirement, 5-15

installing external network cable

installing, 6-24

requirement, 6-24

type and appearance, 6-23

installing external optical fiber

installing, 6-25

requirement, 6-24

type and appearance, 6-24

installing external power cable

core areas of cable, 5-12

installing, 5-13

requirement, 5-15

installing external signal cable

installing external clock cable, 6-22

installing external network cable, 6-23

installing external optical fiber, 6-24

installing trunk cable, 6-21

installing internal clock cable

clock distribution cable connection, 6-9

installing master clock distribution, 6-8

installing master line clock cable, 6-9

installing slave clock distribution, 6-8

installing slave line clock cable, 6-9

line clock cable connection, 6-10

requirement, 6-7

type and appearance, 6-6

installing internal component

installing board, 4-3

installing MGW frame, 4-3

introduction to internal component, 4-1

installing internal E1/T1 cable

frame modes of the UAM, 6-19

installing, 6-20

requirement, 6-18

type and appearance, 6-18

installing internal grounding cable

between adjacent cabinet, 5-10

cabinet body, 5-7

MGW frame, 5-9

protection grounding system, 5-7

installing internal power cable

fan box, 5-6

from PDF to MGW Frame, 5-5

internal component, 5-3

installing lightning arrester

installing indoor lightning arrester, C-9

installing outdoor lightning arrester, C-9

installing monitoring cable

connection relationship, 6-12

installing, 6-12

requirement, 6-11

type and appearance, 6-10

installing power bus cable

connecting, 5-16

power bus cable, 5-16

requirement for installing, 5-18

requirement for installing OT, 5-19

requirement for laying cable, 5-20

installing power cable

procedure, 5-1

installing protection grounding cable

procedure, 5-1

installing signal cable

general requirement, 6-3

installing cable into cabinet, 6-5

installing cascading cable, 6-13

installing internal clock cable, 6-6

installing internal E1/T1 cable, 6-18

installing monitoring cable, 6-10

method of using fiber coiler, 6-4

procedure of external signal cable, 6-3

procedure of internal signal cable, 6-2

installing trunk cable

connection relationship, 6-21

installing, 6-21

requirement, 6-21

type and appearance, 6-21

installing turning cabling rack

connecting ladder onto wall, A-12

Page 209: UMG8900 Installation Manual-Hardware Installation

Installation Manual - Hardware Installation U-SYS UMG8900 Universal Media Gateway Index

Huawei Technologies Proprietary

i-4

rack not in horizontal surface, A-12

rack on horizontal surface, A-11

L label for AC power cable

example, B-23

information on label, B-22

label for DC power cable

example, B-21

information on label, B-20

label for ethernet cable

connect HUB and agent, B-12

connect HUB and server, B-12

example, B-12

information on label, B-11

label for subscriber cable

example, B-19

information on label, B-19

laying cable for peripheral, 8-4

N N800 series support

appearance, 3-2

height range, 3-2

P planning antenna position

antenna visible range, C-3

lightning protection, C-3

RF interference, C-3

printing label

cell merging on template, B-4

requirement for feeding printer, B-5

requirement for printed label, B-5

requirement for the printer, B-4

template, B-3

S signal cable

category, 6-1

external signal cable, 6-2

internal signal cable, 6-1

i.