Urban Transportation planning A study for: (Public transport demand and requirement in 2020 for Kajang- Bangi-Putrajaya-Bandar Seri Putra-Nilai3) PROF. IR. DR. RIZA ATIQ ABDULLAH OK RAHMAT Done by: Hassn ahmed h hassn ID P64139 Malek m a algadi ID P64143 Sarah Hazim ID P65407 ~ 1 ~

ukm - publick transport proposal

Embed Size (px)

DESCRIPTION

nilai- kajang- putrajaya-bangi

Citation preview

Page 1: ukm - publick transport proposal

Urban Transportation planning

A study for:

(Public transport demand and requirement in 2020 for Kajang-Bangi-Putrajaya-Bandar Seri Putra-Nilai3)

PROF. IR. DR. RIZA ATIQ ABDULLAH OK RAHMAT

Done by:

Hassn ahmed h hassn ID P64139

Malek m a algadi ID P64143

Sarah Hazim ID P65407

~ 1 ~

Page 2: ukm - publick transport proposal

INTRODUCTION:

General lines:

1. Kajang

2. Bangi-

3. Putrajaya

4. Bandar Seri Putra

5. Nilai3

are cities which have been defined to develop and upgrade their public transportation to become

sustainable environment so we will go through is to study the urban transportation facilities like :

1. project review

2. Urban transportation study

3. Urban Public transportation

4. Solutions of urban transportation problems

5. ITS

6. Financial analysis

The strategy for the City is focused on the creation of a transport network that enables these

objectives to be realized; this means that the network must be efficient, reliable, affordable,

accessible and safe. Above all, it must provide a quality of experience that enhances everyday life

and adds a significant dimension to the City’s local and national profile

For design of above items , a lot of performences should be applied ,

Here in below you can see in brief , the procedure which is going to be used in this project :

1. extrct all useful information from the given map

2. Indicate the derived information and tabulate them

3. With attention to the urban notes allocate appropriate coefficints for each especific area determined

above

~ 2 ~

Page 3: ukm - publick transport proposal

(1-1) The Location of Study Area

~ 3 ~

Page 4: ukm - publick transport proposal

DEVELOPMENT CONTEXT

The area of the specific region which is going to be constructed has been defined and physical

development is to proceed at a rate in line with the aspirations of Vision 2020.

Land use projections at future time horizons will be the basis of future public transport pattern in term of

origin and destination of movement. The corridor currently forms a zone of mixed density and different form

of land usage. These corridors have developed zone of residential, commercial, industrial, institutional and

others. However for this study only residential and commercial will be consider for calculate the demand.

We will introduce each zone briefly…..

~ 4 ~

Page 5: ukm - publick transport proposal

Nilai 3 wholesale centre, Malaysia

Nilai 3 wholesale centre is undoubtedly a

one-stop destination of wholesale, tourist and

shopping paradise that offers a wide variety of

goods and items at very attractive and

competitive prices.

Especially its located in Negeri Sembilan,

Malaysia where very rare having this kind of

concept.

In judging from its sheer size — 165ha — It is currently still holds the record as the country’s largest

wholesale centre even though there are some areas try to establish same concept. It is not easy to emerge

as such and success like Nilai-3, Malaysia. Apparently, hard work from the management and state

government linkage is crucial. They have done a great job on this. 

When we visited this place last

year, 2007 it still have some free

lands to be developed in future .

Recently, the developer just

completed some rows of shop

named Istanabul near the first

entrance junction. Roughly about

40 newly built shops there.

~ 5 ~

nilia 3

1 nilai 3 roads

Page 6: ukm - publick transport proposal

This is an additional good news for tourist.

After completed these shops, size of the unoccupied land is reduced by some portion. We do believe in

the near future there will be some more shops to be build by developer. This is to cope with the people

coming to this place especially weekends and public holidays.

2 Nilai-3-pasar-borong

~ 6 ~

street view “ free barking “

Page 7: ukm - publick transport proposal

Normal restaurant most of popular shops.

~ 7 ~

3 nilai 3 location

Page 8: ukm - publick transport proposal

Bangi, Malaysia

Bangi is a small town situated on the south of the district of Hulu Langat, in Selangor, Malaysia. It is

roughly situated between the towns of Kajang (9 kilometres away) and Putrajaya (formerly Prang Besar)

(also 9 kilometres away), and is linked to KTM Komuter commuter train services via the Bangi Komuter

station. The town is surrounded by palm oil estates; a Malaysian Palm Oil Board/UKM research station is

also based close to the town.

Bangi is not to be confused with Bandar Baru Bangi, a newer and larger township several kilometres north,

similar to the town only by name and located closer to Kajang.

~ 8 ~

Bangi,selangor

Page 9: ukm - publick transport proposal

Currently, public transportation in Bandar Baru Bangi still not satisfied. It is because there is no bus or taxi

terminal in that town which on the other words, there is no centralized for public transportation. For the time

being, bus terminal in Bandar Baru Bangi sharing with Kajang town which the location is at Hentian Kajang.

There are a lot of bus stop have been provided in Bandar Baru Bangi for public facilities. The

distance between each bus stop is around 300 meter. Bus cater in Bandar Baru Bangi are Rapid KL, Mini

bus and Universiti Kebangsaan Malaysia (UKM) bus.

Because there is no centralized for buses and taxis, many of the taxi drivers concentrated to get

their passengers at shopping complex likes Warta and around the bus stop near Seksyen 1. It happened

because of the places attraction where near the residential area and pasar malam.

UKM Commuter Station

UKM commuter train halt situated close to and named after the National University of Malaysia. The

station strictly serves as a small two platform train halt for Rawang-to-Seremban KTM Komuter train

services, with an operational ticket counter and two ticket vending machines. The station has seen the

addition of a new extension.

The station halt is located on the northeast tip of the university's grounds, 1.5 km from the university's

academics compound. The university's club house and driving range are located immediately close to the

station. Bus services are provided to carry passengers between the station and the university. Because of

its location close to the National University, the station typically receives a large number of passengers,

~ 9 ~4 KTM Commuter Route Map

Page 10: ukm - publick transport proposal

MAIN PROBLEMS in bangi

No Bus and Taxi Terminal

Residents in Bandar Baru Bangi were difficult to go to another destination

No centralize in public transportation

Mini bus and Taxi Terminal at Section 1

Bus stop Condition

The facilities were damages for example the seats, lamps and bus stop roof. Some of the source

are because of the vandalisme.

No lighting at night. This condition encourages crime to be happened.

~ 10 ~

Page 11: ukm - publick transport proposal

Bus Stop Condition at Section 1, Bandar Baru Bangi

~ 11 ~

Page 12: ukm - publick transport proposal

UKM Commuter

Signboard of UKM commuter

Parking spaces is too limited for public. It is because some of the parking area has been used by

taxi drivers to wait for their passengers.

Taxis used car parking spaces

Very near to the residential area. This situation makes noise pollution to environment.

~ 12 ~

Page 13: ukm - publick transport proposal

The facilities at the UKM station were hopeless. There were no directions on where are the buses

or any alternative transportation.

kajang, MalaysiaKajang, is a city in the eastern part of Selangor, Malaysia. Kajang is the district capital of Hulu Langat. It is

located 21 kilometers (13 mi) from of Malaysia's capital, Kuala Lumpur.[1]

The current locational gravity of growth in

Kajang would be Sungai Chua. The total

population of Kajang has grown rapidly

in the past few years, with estimated

population growth of 9% per annum.

As of 2004, a few townships have been

developed in Kajang, such as

Taman Prima Saujana

(straight from Jalan Cheras),

Taman Kajang Perdana

(Kajang Highlands) and Taman Sepakat Indah I & II (Sungai Chua). Lately, many high-end developments

has mushroomed in Kajang such as Twin Palms, Sri Banyan, Country Heights, Jade Hills and Prima

Paramount.Areas surrounding these new townships are easily accessible via the SILK Expressway.

Existing Situation in Kajang

All local government’s planning aimed to get the sustainable urban transport of the city. Transport is

exists to support the achievement of other, wider, policy objectives, such as economic development, urban

regeneration, and social inclusion and reduced levels of crime and disorder. It can also contribute towards

improvements to health and fitness, and to raising educational standards. These factors all, ultimately, lead

~ 13 ~

Page 14: ukm - publick transport proposal

to improved quality of life for the people of Kajang and they are reflected in the objectives of this Local

Transport Planning.

The strategy for the City is focused on the creation of a transport network

that enables these objectives to be realized; this means that thenetwork must be efficient, reliable,

affordable, accessible and safe.

Above all, it must provide a quality of experience that enhances everyday life and adds a significant

dimension to the City’s local and national profile.

In Kajang, there are two stations.

Kajang train station or KTM Kajang which is located in jalan Bukit and bus station in Pusat Hentian Kajang.

Both of them have

a special function as its name.

Bus station in Pusat Hentian

Kajang is provided only for one

modal transport. There are many

kinds of buses will transit here,

such as RAPID KL bus mini

(traveling inside the city),

buses for the workers,

buses for the long time journey

(traveling intra the city) and so on.

Separation of the station of modals transport will cause some problems in transportation. It will

increase the level of air pollution and makes the people prefer to private vehicles than public transport.

~ 14 ~

5 mosque in kajang

Page 15: ukm - publick transport proposal

KTM Kajang

No more space for parking area in Kajang rail station.

Location of Kajang rail station is far from the highway and taxi station. So, it will cause the people

prefer to private vehicles than public transport.

Surrounding area of Kajang Rail Station is nearby the residential area. The noise pollution can

disturb the residents who are living there.

Bus Station in Pusat Hentian Kajang

Actually no significant problems about the location of bus station

It is not easy for the passenger if they want to continue their travel by using the train. It will take

more time to change from one modal transport to the others one. And of course, it will increase the

travel cost. So, there is no choice for the passenger to choose more than one modals transport.

Taxi Terminal in Kajang Town

~ 15 ~

6 Kajang Rail Station

Page 16: ukm - publick transport proposal

The location of taxi terminal is not strategic because it is located in the middle of town and makes

traffic congested.

Signboard of Taxi Terminal in Kajang town

The location of taxi terminal is not strategic

Bus Stop Condition

There is one bus stop point located in the centre of Kajang Town. This bus stop situated in front of

the shops and very near to the main road. This situation makes the road become crowded with the

buses and also the taxis. At the same time, this bus stop point is the major source of traffic

congested in Kajang town.

~ 16 ~

Page 17: ukm - publick transport proposal

The condition is very poor because there are no seats for passengers used to wait for buses. The

facilities are not provided well.

No seats for waiting the buses Bus stop is too close with shops

Narrow road and variable width from the main intersection

~ 17 ~

Page 18: ukm - publick transport proposal

Bandar Seri Putra, MalaysiaBandar Seri Putra (formerly Bandar Putra Mahkota) is a new township in Bangi, Selangor, Malaysia. This

township is developed by UM Land Berhad. Located about --km from Kuala Lumpur and --km from Kuala

Lumpur International Airport (KLIA). It is accessible via a Putra Mahkota Interchange EXIT 213 of the

North-South Expressway Southern Route .

Near the townships is Bukit Mahkota and Nilai Industrial Park at Negeri Sembilan side

~ 18 ~

MASJID AL -AZHAR

Jalan seri

putra

Page 19: ukm - publick transport proposal

Existence situation:

1-Limit in transport facilities

2- Wide range of area without any service

3- Limitation in public transportation

~ 19 ~

7 main location

Page 20: ukm - publick transport proposal

Putrajaya, Malaysia

is a planned city, located south of Kuala Lumpur, that serves as the federal administrative centre of Malaysia. The seat of government was shifted in 1999 from Kuala Lumpur due to the overcrowding and congestion there.

1. What is the size of Putrajaya?A. The size of Putrajaya is 4,931 hectares (one third the size of Kuala Lumpur)

2. How many precincts are there in Putrajaya? A. The entire of Putrajaya is divided into 20 precincts.

3. Who is the developer of Putrajaya?A. Putrajaya Holdings Sdn Bhd is the company entrusted to develop the Putrajaya project. The company was incorporated on October 19, 1995.

4. Who are Putrajaya Holdings' shareholders?A.Petroliam Nasional Berhad (PETRONAS) is the majority shareholder with 64.4%, Khazanah Nasional Berhad has a 15.6% and Kumpulan Wang Amanah Negara, the national trust fund (registered as Sharikat Nominee Bumiputera Sdn Bhd) with 20%.

5. Who manages the city of Putrajaya?A.Perbadanan Putrajaya is the local authority which administers and manages Putrajaya. As local planning authority, Perbadanan Putrajaya is responsible for formulating and implementing planning and development control policies and urban design guidelines to fulfill the vision and objectives of Putrajaya.

6. What is the population of Putrajaya?A. The current population (working and living) is about 75,000.

Nevertheless, Kuala Lumpur remains as Malaysia's national capital and also as the commercial and

financial centre. Putrajaya was the brainchild of a former Prime Minister Tun Dr Mahathir Mohammad who

was in power then. In 2001, Putrajaya was made a Federal Territory, increasing the number of federal

territories to three. Kuala Lumpur and Labuan are the other two.

~ 20 ~

Page 21: ukm - publick transport proposal

Named after the first Malaysian Prime Minister, Tunku Abdul Rahman Putra the city is situated within the

Multimedia Super Corridor, beside the also newly developed Cyberjaya. The development started in 1995

and today major landmarks are completed and the population is expected to grow in the relatively new city

~ 21 ~

Perbadanan Putrajaya

Page 22: ukm - publick transport proposal

Planned as the garden and intelligent city, 38% of the area is reserved for green areas by emphasizing the

enhancement of natural landscape. A network of open spaces and wide boulevards were incorporated to

the plan. Construction began in August 1995 and it was Malaysia's biggest project and one of Southeast

Asia's largest with estimated final cost of US$ 8.1 billion. The entire project was designed and constructed

by Malaysian companies with only 10% of the materials imported

A total of 7 park and ride facilities in the peripheral precincts has been identified at the planning stage.

These facilities will act as integrated transportation nodes for different mode of transportation and will be

linked with a network of pedestrian and cycle ways. In general these provisions will have a long term

impact on the sustainability of the city

At the present time, Putrajaya Corporation has taken an active role in implementing the policy by

supporting it with the provision of an efficient public bus service throughout the city. As part of the

conscious effort in ensuring environmental sustainability in transportation planning, the entire fleet of buses

are run on natural gas.

~ 22 ~

Putrajaya mosque at dusk

Page 23: ukm - publick transport proposal

Various modes of public transport are available

in Putrajaya such as bus, taxi and ERL.

Depot Bus or Terminal Bas and Teksi is

located in Precinct 1, Putrajaya.

It is design to serve as a transportation

hub for busses and taxi. Feeding to the hub, there are taxi services and Putrajaya Bus services

called Nadi Putra.

Putrajaya project now an eyesore(Monorail Suspension Bridge)

Monorail Suspension Bridge is one of the many bridges in Putrajaya, Malaysia. It was built to link several

important landmarks in the Putrajaya area like the Putrajaya Convention Centre, Putra Mosque and the

Government Administrative Complex in Parcel E. The bridge's main span has a length of approximately

240m and width of 10m. It is owned by Putrajaya Holding Sdn. Bhd. and was designed by PJS

International Sdn. Bhd.

~ 23 ~

Precincts of Putrajay

Page 24: ukm - publick transport proposal

By GEETHA KRISHNAN

Going nowhere: The structure referred to cynically as the “suspended suspension bridge.”

IT'S BEEN four years since the Putrajaya Monorail project ground to a halt and there may be some light at the end of the tunnel yet.

The Federal Territories Ministry has instructed the Putrajaya Corpo-ration to appoint an independent consultant to conduct a study on the project’s viability.

Sources say if the advantages outweigh the disadvantages, then it should be all systems go. Otherwise, the RM400mil project would be scrapped.

“Whatever the outcome, authorities should acknowledge that the basic framework is now an eyesore. Something needs to be done about the rusting steel fittings and ugly concrete pillars with wire protrusions,” one observer said.

Tourists, too, often ask if Putra-jaya has another bridge under construction in reference to the elevated track built across the Putrajaya Lake. One dignitary cynically re-ferred to the structure as the “suspended suspension bridge” and as a new tourist attraction.

The elevated track was 90% complete when the project stalled in 2004 because the Government had not approved further funding.

~ 24 ~

Page 25: ukm - publick transport proposal

In the balance: The bridge spanning the Putrajaya Lake is almost complete.

MTrans Monorail Sdn Bhd (MTrans) was appointed to finish the project within 30 months. The plan was to have two monorail lines with a total length of 20km, divided into 13.2km for Line 1 and 6.8km for Line 2.

A total of 26 stations were planned, including stops at the Putra Mosque, Education Ministry, Putrajaya Hospital, the Putrajaya International Convention Centre, Alamanda, Precinct 9 and Precinct 14.

Phase 1 of the project with 9km of track line is ready with a 4km underground tunnel originally designed to have seven stations. The Putra Bridge is a three-tiered bridge with a monorail and service tunnel on the lower deck and a pedestrian walkway on the upper deck.

The stalled project has often been described as the missing link of the public transport system designed for the federal administrative capital.

Seven park-and-ride facilities were designed to complement the monorail service to allow public servants and visitors to travel freely within Putrajaya.

~ 25 ~

Page 26: ukm - publick transport proposal

Still in place: Wire protrusions and scaffolding can still be seen adorning the ugly concrete pillars.

The monorail was also designed to integrate with the ERL service.

The Core Island, where the main government offices are located, can only offer parking for 30% of the vehicles travelling to the ministries and lack of space is now a common problem. An efficient internal bus service should be able to address this.

When the monorail idea was mooted, critics said Putrajaya did not require the system as much as Subang, Puchong and other densely populated or fast-growing areas. The population of Putrajaya, at 55,000, did not warrant the service, they argued.

Even if the authorities are adopting a wait-and-see attitude, the public want justification to be made for the spending of public funds

The project halted in 2004 because the government had not approved further funding. The stalled project

has often been described as the missing link of the public transport system designed for the federal

administrative capital. The Ministry of the Federal Territories instructed the Putrajaya Corporation to

appoint an independent consultant to conduct a study on the project’s viability

Western Transport Terminal or Putrajaya Central in Presint 7

Western Transport Terminal (WTT) is located on the west part of Putrajaya in Precinct 7. From WTT

public can easily reach the Putrajaya Hospital, Putrajaya Police Headquarters and the Precinct 9

Affordable Homes (Pangsapuri Putra Harmoni).

Western Transport Terminal

~ 26 ~

Page 27: ukm - publick transport proposal

WTT is design to serve as a transportation Hub for Putrajaya and is currently serving Express Rail

Link (ERL) to KL International Airport (KLIA) in the south and Kuala Lumpur in the North. Feeding to the

Hub, there are taxi services and Putrajaya Bus services called Nadi Putra. Nadi Putra reaches WTT every

15 minutes during the peak hours and every 30 minutes during off peak hours starting from 6.52 am and

the last bus is at 10.50 pm.

Bus Services Condition

The intracity bus company operates only 14 buses to transport passengers from residential areas in

the periphery to offices and commercial centers in the core area. Generally, these buses have poor

service frequency with an average of 2 per hour, even during the morning and afternoon peak

periods. The buses are of standard high-floor design with no provision for the disabled and elderly.

With limited rolling stock, bus service has also been unreliable.

Putrajaya Central

Intercity rail services are provided by the Express Rail System (ERL) and the Keretapi Tanah

Melayu Berhad (KTMB) rail commuter system. However, both systems can at best be described as

inadequate. For example, the KLIA Transit service provided by the ERL stops at a station quite far

from the city center, forcing passengers to take transfer bus rides.

There are not many facilities provided yet such as restaurants and shops.

~ 27 ~

Page 28: ukm - publick transport proposal

Present transportation facilities

Existing Situatian in Bandar Baru Bangi

One of the most important part of urban transportation division is Public transportation .

Public transportation divide into 2 main parts :

1. Bus 2. train

BUS

There are a lot of bus stop have been provided in Bandar Baru Bangi for public facilities. The

distance between each bus stop is around 300 meter. Bus cater in Bandar Baru Bangi are Rapid KL, Mini

bus and Universiti Kebangsaan Malaysia (UKM) bus.

1. Busmini

The Kuala Lumpur Mini-Bus Service or Bas Mini was one of the oldest and popular Malaysian

public bus service, having served in Kuala Lumpur and the Klang Valley region. The buses were

primarily painted pink with a white stripe on the sides, and had a capacity of 20-30 passengers, due

~ 28 ~

Page 29: ukm - publick transport proposal

to its smaller size. The bus operated on a commission basis, with service operators being paid

according to the fare they collected.

The mini-bus service was discontinued from 1 July 1998 onwards, to be replaced by the Intrakota bus service and, later, Rapid KL buses in 2005.

Brief History

The mini bus started operating on 23 September 1975 under the Ministry of Transportation. At that

time, the mini bus operated on various routes according to their individual colours (blue- white,

yellow-white, red-white, purple-white and dark green-white). The mini bus was responsible for

servicing nearly sixty different routes. Three major companies (Syarikat Kerjasama Pengaman (M)

Bhd, Bas Mini Wilayah and Konsortium Pengusaha Bas Mini Sdn Bhd) monopolized the various

bus routes while smaller operators were allowed to service certain areas only.

In 1975, when the mini bus was introduced as a service, the bus-fare was just 40 sen. Later in

1991, the fare was increased to 50 sen while two years after, the fare was again adjusted to 60 sen.

The mini bus did not have any fixed time-table. Instead, the service operated on a commission

basis whereby the operators were paid according to the number of trips and fare collection they

could raise in one day. Sometimes, in order to outdo a competitor, a driver would detour from the

designated route much to the annoyance of the passengers.

In 1990, the then Deputy Minister of Transport, Datuk Paduka Rahmah Osman, standardized the

colour of the mini bus to “Pink” and white. On the 1st July 1998, the services of the mini bus was

terminated in the city of Kuala Lumpur . Once a notorious mode of transport for the many

commuters in Kuala Lumpur, the “Pink Lady” will always be remembered for its death-defying

activities on public roads.

2. Rapid KL

Rangkaian Pengangkutan Integrasi Deras Sdn Bhd (RapidKL) is the company tasked with providing

an integrated public transport system in the Klang Valley incorporating rail and bus services. Today,

RapidKL operates 165 bus routes within the Klang Valley which consist of 10 City Bus routes, 87 Local Bus

routes, 65 Trunk Bus routes and 3 Express Bus routes. We currently have 11 bus depots spreading across

the Klang Valley and over one thousand buses in operation. Everyday RapidKL transport over 192,000

passengers. To continuously encourage the use of public transport and to provide services to the general

public, RapidKL is also continuously studying new bus routes with the arrival of more new buses.

~ 29 ~

Page 30: ukm - publick transport proposal

8 2. Rapid KL

Because there is no centralized for buses and taxis, many of the taxi drivers concentrated to get their

passengers at shopping complex likes Warta and around the bus stop near Seksyen 1. It happened

because of the places attraction where near the residential area and pasar malam.

the RAPIDKL bus network which is divided into 6 main areas, namely :

• Area 1 : Kuala Lumpur City Centre

• Area 2 : Kepong, Selayang, Batu Caves , Gombak, Sentul

• Area 3 : Wangsa Maju, Hulu Klang, Keramat, Ampang, Pandan

• Area 4 : Cheras, Hulu Langat, Kajang, Putrajaya, Serdang

~ 30 ~

Page 31: ukm - publick transport proposal

• Area 5 : Klang, Shah Alam Selatan, Subang Jaya, Jln Klang Lama, Puchong

• Area 6 : Shah Alam Utara, Subang, Damansara, PJ Utara, Bangsar

Service pattern Service major activity centers such as office buildings, school and hospital.

Population density > 30. Serve at least 90% of the residents.

Space routes at about 0.75 km in urban area

and 1.5 in sub-urban area.

Service Level Service period : 6 am-12 pm

Headway: Peak: 5 minutes

Bus Stop CBD: 5 -7 stops / km, sub-urban: 1 - 3 stops /km

Passenger comfort Passenger shelter

Route and destination sign

Driver courtesy

Bus Operation Design

n = Demand for service (passengers / hr) N = Maximum number of passengers per bus Usually the minimum headway is set in multiples of 7.5 or 10 minutes for the shake of

coordination.

~ 31 ~

Frequency, f = n / N

Page 32: ukm - publick transport proposal

~ 32 ~

Page 33: ukm - publick transport proposal

TRAINS

It is obvious by which reason this part of transportation id the most important one ,

It can inferred that because of below results :

High percentage of users

Fuel consumption

Low effect on environment contamination

Low cost

Better traffic condition

This part of transportation commonly has been paid more attention in compare to others

Introduce of two train types used in urban transportation

MRT

LRT

Ktm komuter

1. MRT

Speed up to 100 km/hr

~ 33 ~

Page 34: ukm - publick transport proposal

Couches 4 – 12 couches per trainCouches 22m x 3.1 mCapacity up to 80,000 passengers /hr / directionAcceleration deceleration _ 1.2 m/s 2Rail 1435mm gauge Headway _ 120 sSuitable Suitable for radial movement For high density and high

plot ratioSub-station: 3 – 5 km spacing

2 LRT

Speed up to 40 km/hr2 – 6 couches per train

Capacity up to 40,000 passengers /hr / direction

Acceleration / deceleration _ 1.2 m/s 2Rail 1000 or 1435mm gaugeHeadway 120 sSuitable Suitable for radial movement For high density and high plot ratio areaSub-station

Sub-station: 3 – 5 km spacing

~ 34 ~

Page 35: ukm - publick transport proposal

3- ktm komuter

KTM Komuter is an electrified commuter train service operated by Keretapi Tanah Melayu Berhad. It was

first introduced in 1995 to cater especially to commuters in Kuala Lumpur and the surrounding suburban

areas and is a popular mode of transport for commuters working in Kuala Lumpur, as they can travel to the

city without being caught in traffic congestion. Coaches are modern and air-conditioned. For those who

drive to the stations/halts, 'Park & Ride' facilities are provided at a nominal charge.

KTM Komuter is currently the most profitable passenger service offered by KTMB, contributing RM84.63

million to group revenue in 2006, higher than KTM Intercity's profit of 70.94 million in the same year.[1]

According to the Ministry of Transport Malaysia 2008 Statistics, the annual ridership for KTM Komuter was

36,557 millions of passenger

No. of stations 46

Type Regional rail

Line length 173 km

Service Area Klang-Kuala Lumpur-Sentul/Tanjung Malim-Rawang-Kuala Lumpur-Seremban

Ticketing TnG, Store Value Ticket & Monthly Pass

Operational Mode With driver

~ 35 ~

Page 36: ukm - publick transport proposal

Route expansion in progress

The new Tanjung Malim railway station will become the new terminus of the KTM Komuter network

Besides new stations, additional plans were made to extend the Komuter network outwards from it original

route

The 179 km (111 mi) Rawang-Ipoh electrification and double-tracking project will ultimately allow

the KTM Komuter service to be extended to Tanjung Malim on the Selangor-Perak border, nearly

100 kilometers (62 mi) from Kuala Lumpur. The project has suffered several delays due several

reasons, but has seen limited revitalisation. The first phase of the extension, which includes

22 kilometers (14 mi) of rebuilt railway lines and three new stations became operational when a

shuttle service from the Rawang stations was launched on April 21, 2007.[6].The service was

extended to Kuala Kubu Bharu on January 5, 2008.[7]. Shuttle service to Tanjung Malim and Ipoh

will begin by December 2008.[8]

A 7.2 km (4 mi), four-station extension from the Sentul station to Batu Caves has been approved.

The project - which will cost RM515 million - will include electrification, double-tracking and refitting

the existing old track, signalling, communications, as well as construction of new stations at Sentul,

Batu Cantonment, Batu Village, Taman Wahyu and Batu Caves. Site possession was given to

contractor YTL Corporation Berhad on November 17, 2006, and the project is to be completed by

April 2010. The Sentul station is part of the Sentul Raya masterplan development under YTL.[9]

KTMB also plans to extend 8.5 km (5 mi) Komuter services to Senawang and Sungai Gadut, Negeri

Sembilan. Construction is expected to complete by 2011. This will be part of the Seremban-Gemas

line

~ 36 ~

Page 37: ukm - publick transport proposal

TRAFFIC CALCULATIONS FORMULAS

GeneralThe methodology employed in the execution of the model development portion of this study has closely followed the guideline contained in the Manual for the Preparation of Urban Transport Plans in Malaysia (HPU-1995). The computer traffic model was developed using the EMME/2 software. The model was initially developed was for private vehicles and also to allow for movements of passengers by public transport modes. The project is a green field site and currently has very low levels of public transport service. Neverthe-less overall policy for the MSC plans a high usage of public transport and an efficient network is envisaged.

In order to develop the traffic model, a number of data items were required.

These included data on the highway inventory and vehicle movement flows and patterns. The following data was input to the EMME/2 traffic model.

Network inventory;

Junction layouts;

Link capacities;

Volume delay functions;

Vehicle volume counts.(for comparison of model assigned traffic) The model developed will enable testing for the impact of changes in the highway configuration and forecast future year flows on all new and existing links.

Network and Model DetailsThe network structure is node and link based. The nodes were established as junctions, merging and

diverging intersections, key traffic loading points on to the highway network and points of delay. A link is

defined as the connection between two nodes to represent a road or highway, input with all its features,

including, volume delay function, capacity and free flow speed. All nodes were allocated a unique number.

Numbering was consecutive starting at 1 to 199 for zones and their centroid connectors. In total the model

comprises 193 zones, covering the entire secondary and primary zones of study as shown in Figure 6.0 All

other nodes on the link-node model were numbered 200 and above.

The consultants regard the development of the MSC and its link with Kuala Lumpur, in particular, of major

significance. The Land Use study indicates that the final population of the project zone may reach 2.5

million.

~ 37 ~

Page 38: ukm - publick transport proposal

As a means of comparison this reflects the population size of the Klang Valley in 1994.

The quantum of travel between the MSC and all zones close to the area, including Shah Alam, Serdang,

Kajang, Bangi, Nilai and Labu can be expected to be high. The presence of the airport in KLIA needs also

to be taken into consideration as a major cause of change in the overall regional travel pattern.The

approach used has taken full cognizance of the above matters by including these zones as part of the

overall model, rather than providing amodel truncated at the entry points to the MSC. The value of the

model will come into play in forecasting future year traffic pattern and providing for the

future traffic demand.

Establishing OD Traffic Model Calibration & Validation

In this study, the double constrained gravity model (Danial, et al, 1997) was

employed to distribute the generated trips using a range of the model

parameter values, with the model in the form as follows :-

~ 38 ~

Page 39: ukm - publick transport proposal

The synthesised O-D trip matrices from the gravity model were then assigned to the existing road network

using equilibrium traffic assignment program (Danial, et al, 1997). The equilibrium traffic assignment was

adopted due to its superiority over the all-or-nothing assignment which was used in Maximisation of

Entropy adopted by Irving, et al, especially when there are parallel routes between an O-D pair.

A simple iterative search procedure was employed with the numerical value of the gravity model parameter

() being changed comparisons between the assigned traffic link volumes with actual site data were then

undertaken. The () value corresponding to the minimum value of the objective function considered was

taken as the appropriate solution. The objective function considered in this study was the sum of square

differences between observed and assigned traffic link volumes. This function is frequently identified as

‘the sum of squares of errors’ (SSE) and it

is written as :

~ 39 ~

Page 40: ukm - publick transport proposal

THE STUDY METHODOLOGY

The overall procedure adopted is shown in Figure 15 and the initial step involves evaluation of

existing data and plans

1 TRIP GENERATION

Land use projections at future time horizons will be the basis of future public transport pattern in

term of origin and destination (O-D) of movement. The corridor currently forms a zone of mixed

density and different form of land usage. These corridors have developed zone of residential,

commercial, industrial, institutional and others. Estimation of total production and attraction from

one zone to onother zones in this study area based on land use and sosio-economic.

~ 40 ~

Modal Split Trip Assignment

Trip Generation Trip Distribution

Page 41: ukm - publick transport proposal

Population table

ZONE POPULATIONPUTRAJAYA 240000KAJANG 300000BANGI 100000NILAI 3 2300BANDRE SERI PUTRA 35000

Total

TRIP DISTRIBUTION

The trip distribution is an estimation of trip distribution from the origin to others destination.

This model will create a matrix origin-destination trips which is included in this study area.

The production and attraction between each zone are calculated by multiply the current population with

rate of expected growth. Besides, there are a few characteristic had been consider in calculating an

expected production and attraction for these zones Double constrained gravity model was used to

distribute the trips generated by each zone. The form of the gravity model used was as

follows :

~ 41 ~

Page 42: ukm - publick transport proposal

A

zone population production attractionputrajaya 240000 59559.2 86169.9

kajang 300000 53603 38776

Bangi 100000 11078 10909

nilai 3 2300 470 770

bandre seri putra

350005539 3818

total 21708.2 23407.15

B

Balance the production and the attraction

ZONE PRODUCTION ATTRACTIONBALANCE PRO

BALANCE ATTRA.  

1 59559.2 86169.9 61890 83043

2 53603 38776 55701 37369

3 11078 10909 11511 10513

4 470 770 488 742

5 5539 3818 5756 3679

  0 0 0 0

SUM 21708.2 23407.15 22558 22558

AVERAGE 22558    

~ 42 ~

Page 43: ukm - publick transport proposal

attraction1 2 3 4 5 6

83043 37369 10513 742 3679 0 1353461 61890 37973 17088 4807 339 1683 0 618902 55701 34176 15379 4327 305 1514 0 557013 11511 7063 3178 894 63 313 0 115114 488 300 135 38 3 13 0 4885 5756 3531 1589 447 32 156 0 57566 0 0 0 0 0 0 0 0

135346 83043 37369 10513 742 3679 0

Compute O-D trip matrix for the area

~ 43 ~

Prod

uctio

n

Page 44: ukm - publick transport proposal

Modal ChoiceThe total travel demand from one zone to another modal split for trips to an office building in the city centre

will be very different to that in a sub urban area. Likewise the modal split of building in the vicinity of public

transport network will not to be similar to a building far from the network. Provision of parking space can

also alter the modal split.

The current modal split can be determined by observing equivalent land use in the area based on

observation and data collection by City Hall of Kuala Lumpur average modal split in Klang Valley

Item Land Use Bus user %

car/van/jeep user

%

m/cycle user %

1. Government Office 27.6% 57.4% 15.0%

2. Non-Government Office 48.0% 45.6% 6.4%

3. Bank 49.9% 45.0% 5.1%

4. Hotel 35.9% 60.1% 4.0%

5. Shopping Centre 54.3% 40.7% 5.0%

6. Bungalow House 12.1% 84.0% 3.9%

7. Semi-Detached House 16.2% 79.4% 4.4%

~ 44 ~

Page 45: ukm - publick transport proposal

8. Link House 42.1% 48.5% 9.4%

9. Condominium 13.7% 85.1% 1.2%

10. Apartment 39.9% 45.0% 15.1%

11. Flat 49.5% 28.3% 21.7%

Matrix DevelopmentThe future year trip matrices were developed using population and employment growth factors for each zone derived from data on land use changes. Such data was taken from Structure Plan and Local Plan information supplied by the local planning authorities. The data related to changes in population, employment and commercial activity, together with the likely change in car ownership levels.

~ 45 ~

Page 46: ukm - publick transport proposal

MODAL COICE MODEL

Introduction

Transport networks are Kajang, Bangi, Bandar Seri Putra, putrajaya, Nilai3, , of the utmost importance in

facilities is the movement of people within the city, provided that this means the capacity and efficiency of

high-quality acceptable.

To lead this city’s position as an international commercial and financial centre in Malaysia after Kuala

Lumpur must be able to provide an efficient and equitable city structure, that is as far as possible, allows all

members of the community equal accessibility to all areas and facilities so that everyone may enjoy the

maximum benefits of city living.

Although these cities have many means of public transport like buses, trains and taxis but there are some

problems and deficiencies in the quality of services we offer, which will report in detail.

Recently, increased reliance on private transport by 17% from the use of public transport. The shortfall is

due to the use of public transport instead of private transport to the following reasons :-

1-Increasing personal wealth and material improvement in the situation of citizen.

2-Inefficient public transport.

3-Comfort and luxury, which find use in private cars is better than public transport.

4-Lack of discipline time of arrival and departure of public transport.

5-Lack of public transportation in some regions, such as nilai3.

EXISTING SITUATIONS AND PROBLEMS

GENERAL

A) Transport Modal Share

I. Existing Situation

The institutional structure responsible for urban transportation within Malaysia and more specifically,

KAJANG, BANGI, BANDAR SERI PUTRA, PUTRAJAYA, NILAI3 and are divided between federal

departments and City Hall Kajang, Bangi, Bandar Seri Putra, PUTRAJAYA, Nilai3,.

The Transport Department is entrusted with wide ranging coordination and administrative functions for the

planning of urban transport in an effective manner. The Federal Government deals more with nationwide

transportation plans, policy guidelines and matters concerning overall transport administration and

~ 46 ~

Page 47: ukm - publick transport proposal

planning. Private sector involvement in the provision of transport infrastructure has expanded from the

original role of bus and taxi transport operations to toll road construction and the implementation, operation

and maintenance of the commuter, light rapid transit (LRT) and people mover rapid transit (PRT) systems.

PROBLEM

Lack of high-efficiency of transport in the year that found citizens of transport in private, leading to an

increase in traffic congestion .

B) Travel Demand

I. Existing Situation

Because of luxury and the high personal income there was increasing in number of private transport

vehicles of cars and motorcycles, which led to a traffic jam, especially in intersections at peak hours at after

noon time. In addition to increasing in number of visitors to the centers of, Kajang, Bangi, Bandar Seri

Putra, to eliminate their daily needs of purchase, working and the educational purposes of teaching and

studying in schools and universities. So these streets could not accommodate this traffic density and

increasing in the number of daily trips.

Increasing in numbers of daily trips from and to these cities led to a traffic jam especially in the center, and

driving in speed resulted traffic accidents in streets and intersections especially at the traffic peak in crowds

and the maximum capacity.

II. PROBLEM

Crowding in city streets during the peak hours .

C) Traffic Management

I. Existing Situation

This smart traffic controlling system is able to effectively reduce traffic congestion. This system has been

employed at main intersections around Bandar Baru Bangi and Kajang Town for the past few years.

The smart traffic light uses a camera as a sensor that really ”sees” the real traffic situation. Video images are captured by the cameras placed on high positions and the images are processed in order to gauge the the number of incoming vehicles, the length of the queue as well as to detect accidents.

~ 47 ~

Page 48: ukm - publick transport proposal

This means that the smart traffic system responds almost immediately every time there occurs a slight

change in the traffic patterns. It is done by using the total-disperse system and all the traffic lights at every

intersection are all smart traffic lights. Thus, a fast response is achieved according to the traffic situation at

a particular intersection.

During peak periods, it distributes the green time according to the ratio length of the respective queue. It

also priorities traffic flows accordingly. Test on site shows that the system is able to respond correctly

within 120 seconds.Physically, the system consists of four basic components, namely the Smart Camera

sensor for collecting traffic data, the Intelligent Controller for controlling traffic flows at an individual

intersection, the Intelligent Coordinator for coordinating the timing of an individual controller with it's

neighbors and the Smart Traffic Advisor. Communication is based on wireless Local Area Network that

links all local controllers.

II. PROBLEM

In spite of the traffic management measures to ease the traffic flows especially in city centre, that can not

continue to do if the traffic demands still growing, because traffic management measures alone can not

effectively increase existing road capacity levels.

D) Transportation Institutional Framework

I. Existing Situation

Public institutions and the role of the private sector

group of organizations and departments of transportation in Malaysia, specifically in Kajang, Bangi, Bandar

Seri Putra, Bukit Mahkota, Nilai3 and Nilai, these departments directly interesting for the urban transport

planning in these cities to improve and develop more efficient and effective for the present and future and

improve the existing deal and the Federal Government policies and issues concerning the management of

public transport, planning and introduction of private sector to build roads that implementation of fees,

operation and maintenance and increasing the use of bus transport and taxis.

II. PROBLEM

In some instances there were overlaps and duplication in functions of the responsible agencies of the transportation networks in KAJANG, BANGI, BANDAR SERI PUTRA, PUTRAJAYA NILAI3 , which has led to conflicting policies and programmers. And that has made it more difficult to determine policies for public and private transportation which are consistent.

~ 48 ~

Page 49: ukm - publick transport proposal

PUBLIC TRANSPORT

A) Rail - Based Public Transport

I. Existing Situation

Last years train transportation become a significant way of public transport between Kajang, Bangi, Bandar

Seri Putra, Bukit Mahkota, Nilai3 and Nilai,in addition to KL Sentral station in the capital Kuala Lumpur and

the international airport (KLIA), to save money and time and to short the long distance in a short time

comparing with other transportation ways .

II.PROBLEM

Rail station has been encouraged form the government, but the optimal usage had not be achieved due to:

~ 49 ~

Page 50: ukm - publick transport proposal

1-Inefficient facilities at stations including car and motor cycle parking.

2- Poor support services and service coverage.

B) Bus Services

I. Existing Situation

Many of companies operating in the area like ((Rapid KL ,Bus Mini ,Road Liner)) to support the public

transport by buses between each of (OUR AREAS) and connect them with capital Kuala Lumpur. These

companies do operating daily flights contribute to these trips to provide transport for the citizens of the

areas mention most of these trips launched from the town of Kajang.

II. PROBLEMThat there are improvements in the existing bus system and infrastructure is still lacking a lot :

1- The existence of these types of buses to lack the basic means of comfort and safety, such as the Mini

Bus.

2- Lack of key stations model .... For example, the absence of a bus station in Kajang and model Bangi

such as the plant Kajang.

3- The stations of stops somewhat acceptable, but must be doing maintenance because of the impact of

negative climate and the need to provide protection for people from the rain stations.

C) Taxis

I. Existing Situation

Taxi is an important way of transportation because not all of people have private cars, so they need taxis

to carry them from place to other in a private way without crowding in buses , and to save time if you see

the time is more important than money.

II. PROBLEM

There is no shortage of taxis, but the problem is at peak periods and during bad weather, and because of

the variety of drivers nationalities and origins taxis became unreliable.

~ 50 ~

Page 51: ukm - publick transport proposal

4.2.3. PRIVATE TRANSPORTATION

A) Cars and Car Parking

II. Existing Situation

The growth of both urban for (OUR AREAS), and the number of population who own and use motor

vehicles in their daily activities has increased the demand for vehicle parking spaces for all categories of

land uses. This growth together with the increase in density and intensity of developments such, as

residential, industrial and commercial land uses, make the existing parking guidelines and parking

standards for all Malaysian cities obsolete. As parking demand and parking requirements change very fast,

this study looks into the approaches and methods which have been used in other cities in their works in

revising their parking guidelines and standards to suit the current situation within their context.

II. PROBLEM

Parking charges in the city centre favor regular long-term parking with many car park operators offering

cheap seasonal parking tickets. This, together with the flexibility afforded by private transport, encourages

commuters to continue to use private transport into the city centre.

~ 51 ~

Page 52: ukm - publick transport proposal

The low cost of long-term parking in the city centre together with the abundance of parking spaces and the

flexibility of movement associated with car transport, has made car transport the preferred means of travel

in the city.

B) Motorcycles

I. Existing Situation

Motorcycle is the cheapest way of transportation, that is why it is used by the young and lower income

groups, and it is has economical usage of fuel around the city, but it is not safe for those who don't have

driving license, and that caused making road accidents.

II. PROBLEM

There is 52% of accidents involve motorcycles, which is higher than all other ways of transport.

The motorcycles contribute significantly to noise and air pollution, and that is harmful for air and climate

and the human health.

~ 52 ~

Page 53: ukm - publick transport proposal

ROAD INFRASTRUCTURE

I. Existing Situation

In today's world of globalization, the provision of infrastructures, of which road network plays an important

and integral role, is essential to enhance the nation's competitiveness and maintain an edge over its

competitions. In Malaysia, the road network forms the bloodline of the country’s economic activities

carrying about 96% of transported goods and passengers.

Based on the Ministry of Transport’s statistics, the share of road transport of passengers comprises 64.8%

by private car and 30.0% by bus, as compared to 4.7% by rail transport and 0.5% by air transport. The

road transport also moved 303 million tons of goods or an overwhelming 96.4% of total trips.

Development of the transportation infrastructure during the Seventh Plan period focused on capacity

expansion to ensure the availability of facilities to meet demand. For the Eighth Plan period, emphasis was

given to increasing the capacity and accessibility in less developed areas while in urban areas, the focus

was to enhance efficiency and improve public transport services. In the Ninth Malaysia Plan, PWD has so

far been allocated RM9.6 billion for the construction of new roads as well as upgrading of existing ones

~ 53 ~

Page 54: ukm - publick transport proposal

II. PROBLEM

The development of major roads in (OUR AREAS), has not always fully observed road classification

requirements. In addition, some roads have assumed functions for which they were not originally designed

such as residential roads that have become trunk roads due to ill-considered road connections. These

anomalies have presented difficulties in the design and management of the overall road network.

Plot ratios for commercial spaces within the City Centre have progressively increased over the years and

created increased pressure on the road network.

4.2.5. NON-MOTORISED TRANSPORT

A) Pedestrian

I. Existing Situation

A pedestrian network is progressively being implemented in the City Centre. This will facilitate pedestrian

and non-motorised vehicle movement at the activity of centers, connect transit stations and terminals for

convenient inter-modal transfer, provide pedestrian malls and act as traffic restraint measures. The network

will also help increase the utilisation of public transportation and reduce short vehicle trips.

~ 54 ~

Page 55: ukm - publick transport proposal

II. PROBLEM

Areas in this study lacks alleyways and walk ways and the lack of awnings for infantry, such as protection

from rain. Because of the tropical climate.

B) Bicycles

Existing Situation

The bicycle, cycle, or bike is a pedal-driven, human-powered vehicle with two wheels attached to a frame,

one behind the other.

Cycle ways have, for some time, been incorporated into new housing estates and Recreational areas.

Despite the relatively flat terrain (OUR AREAS), cycling as a convenient means of transport is under

utilised partly due to local climatic conditions. There are also, however, some shortcomings in the existing

cycle way network which contribute to the under utilisation of bicycles.

II. PROBLEM Opportunities exist for bicycle transport in providing connections to public transport services and short

distance local travel. Other cities have utilised their roads, rail and open space corridors to create a

comprehensive local area cycle way network.

Bicycles ways in housing estates suffer from under usage, misuse (illegal parking) and poor maintenance.

~ 55 ~

Page 56: ukm - publick transport proposal

FORECASTING FUTURE DEMAND OF PUBLIC TRANSPORT

INTEGRATED PUBLIC TRANSPORTATION SYSTEM

The complete vehicles network of the years ( 2008-2014 ) including integrated park-and-ride stations and multimodal interchanges are indicated in Figure (5.1).

Figure 5.1

. ROAD NETWORK

This section contains reference points and information regarding the development, maintenance and

operation of both the local and national road network.

~ 56 ~

Page 57: ukm - publick transport proposal

The road network is often defined as a mix of Strategic roads - the main national network of motorways and

major roads much of which is managed by the Highways Authority; and Local roads - those managed by

local or regional highway authorities. This section is categorized accordingly, with each section containing

appropriate sub-divisions such as maintenance and street works. Best Value Performance.

Indicators are available in the Service levels sub-directory of Local Roads for example. The Road Policy

sub-division contains general documents of relevance to all road management, including ’Managing our

Roads’, The Department for Transport’s key discussion document road network .

. ROAD POLICY

Overarching policy and strategy documents related to the management of the road network . Includes

’Managing our Roads’, the Department’s main road strategy publication, and guidance on the procedures

for inquiries held into road proposals.

~ 57 ~

Page 58: ukm - publick transport proposal

PROPOSAL FOR PHYSICAL DEVELOPMENT ANDPOLICY CHANGES

To create an efficient and equitable city structure for Kajang, Bangi, Bandar Seri Putra, PUTRAJAYA , Nilai 3 and, The government should aim to:

Study the light rail subway system in japan

Tokyo Subways

The Tokyo subway is an integral part of the world's most extensive rapid transit system in a single

metropolitan area, Greater Tokyo. While the subway system itself is largely within the city center, the lines

extend far out via extensive through services onto suburban railway lines.

Tokyo's subway network is operated by two companies, the Toei Subways with four lines, and Tokyo Metro

(formerly known as Eidan Subways) with nine lines. Together, they densely cover central Tokyo, especially

the area inside the Yamanote circle and the areas around Ginza and Shitamachi.

Note, that at their terminal stations, the trains of some subway lines continue to operate on the tracks of

different companies on suburban train lines. For example, the Chiyoda Subway Line is directly connected

with the suburban Odakyu Line at Yoyogi-Uehara Station, and some trains on the Hibiya Subway Line

continue to run on the tracks of the Tokyu Toyoko Line at Nakameguro Station. The subways are the only

way to travel. It's a fantastic way to see people and cross the city rapidly at a relatively low cost. Of course

as you're riding the subway here, it's important to keep in mind the New York subway,

~ 58 ~

Page 59: ukm - publick transport proposal

Subway informations

Transit type Rapid transit

Number of lines 13

Number of stations 282

Daily ridership 8.7 million

Operator(s) Tokyo Metro Co., Ltd., Tokyo Metropolitan Bureau of Transportation (Toei), Tokyo Waterfront Area Rapid Transit

Track gauge 1,067 mm

Fares For single ride. It costs 70 yen (2.7 RM)

• 1 R.M = 26 JPY

~ 59 ~

Page 60: ukm - publick transport proposal

System administrationBoth Tokyo Metro and Toei Subway systems are closely integrated with a unified system of line colors,

line codes and station numbers. However, the separate administration of metro systems has these

ramifications:

calculated based on the possible shortest route of the ride between the origin and destination

stations.[3] However, the Passnet system got around the issue of ticketing, by allowing one stored-

fare card to be used on most of the rail operators

~ 60 ~

Page 61: ukm - publick transport proposal

~ 61 ~

Page 62: ukm - publick transport proposal

Main PURPOSES TO FORECAST THIS PROJECT

II. ISSUES

1- , (OUR AREAS) have experienced rapid and intensive urbanization. As a

result of in-migration from rural areas and provincial centers, the population of (OUR AREAS), has

doubled. Today,, which is facing serious urban development challenges, including insufficient transport

infrastructure and poor quality of public transport services. Investments in urban transport, traffic

management, and road safety have significantly lagged behind the pace of urbanization.

Coordination among relevant agencies is lacking, and the institutions responsible for regulating

public transport service provision are weak.

2- Transport infrastructure and services in (OUR AREAS), are suffering from increasing road

congestion, insufficient traffic management, poor safety conditions, and a weak public transport

system.

3 These factors contribute to economic inefficiency due to increased trip times,excessive fuel use, and poor air quality, which all serve to reduce residents’ quality of life and

act as a bottleneck to growth. According to estimates of the city’s traffic police, about 50,000

~ 62 ~

Page 63: ukm - publick transport proposal

vehicles, most of which are secondhand and of poor quality, are added to the city’s roads

annually, representing an increase of about 25% per year—one of the highest urban private

vehicle growth rates in the world. While technical and environmental standards for vehicle safety

and emissions have been put in place, they are not sufficiently enforced.

3. The public transport system is struggling with technical, financial, and institutional

challenges. Bus tariffs have not been increased since 1999, while fuel costs have increased

more than 5 times in the same period. The municipal budget subsidizes about 42% of the bus

companies’ annual costs, but the mechanism for allocating subsidies lacks transparency and is

perceived as inequitable. Bus operators lack financial resources to renew and expand their bus

fleet and provide adequate transportation services. Interaction among the different modes of

public transport is far from optimal. Instead of feeding higher-capacity bus routes, minibuses

tend to compete with the higher-capacity buses, thereby adding to road congestion. Bus and

minibus routes are not designed as part of a feeder-and-main-line system, and the system for

allocating routes needs updating

.

4. The road network is well developed in the central area of Ulaanbaatar, but in outlying

residential areas, where many low income families live, ill-maintained primary feeder roads and

un-surfaced connector roads are the norm. Budgetary allocations for new roads have increased

significantly with help from the Mongolian Development Fund, and investment levels in roads far

5 . Traffic congestion is aggravated by insufficient enforcement of parking control,

designated parking spaces, pedestrians, lack of driver discipline, inadequate signaling, and

insufficient traffic control. Traffic accidents are common due to poor traffic management and the

uncontrolled interaction of pedestrians and vehicles.5 Encroachment on roads and sidewalks by

parked vehicles worsens the traffic situation. Planning and budgeting for pedestrian and parking

infrastructure are lacking.

6. Given the rapid growth in private vehicles, road improvements will only make limited and

temporary improvements. Strong institutions with clear mandates are required to implement

investments, attract financing, coordinate among stakeholders, and regulate service providers.

Multiple institutions at the central and local levels are involved in urban transport services and

clarifying their roles and enhancing coordination among them should be prioritized. Without a

viable system of public transport, Ulaanbaatar will soon experience serious traffic congestion

with negative impacts on economic vitality and quality of life. Improvements in traffic and parking

control, driving behavior, and enforcement are also critical for addressing the city’s transport

needs.

~ 63 ~

Page 64: ukm - publick transport proposal

7 - The urban poor suffer disproportionately from an inadequate transport system.

Under investment in public transportation raises the cost of commuting and restricts access to

jobs and services. The poor tend to be more exposed to risks associated with externalities in

transport. For example, they lack adequate means to avoid exposure to polluted air, face higher

commuting distances and costs, and are particularly affected when there is a lack of provisions

for pedestrians. The poor stand to benefit significantly from improved transportation services.

~ 64 ~

Page 65: ukm - publick transport proposal

~ 65 ~

2

5

1

4

3

Page 66: ukm - publick transport proposal

DEVELOPMENT AREAS1 NILAI 32 Bandar Seri Putra3 Putrajaya4 BangI5 Kajang

DEVELOPMENT AREA

We Can Open Main Stations At These Areas Or Make Links With Komuter Stations Company.

So Under Ground Subway And Upper ground Can Make A great Solutions For Traffic Jam And Consider As A spark Of Development For Those Areas

Riding the Subway is Great because you can:

1- Transportation by rail has decreased with the invention of cars and airplanes, thus a change to long-distance intercity transportation and commuter lines.  Commuter lines are rails that take people to and from work in the suburbs.  Since the cost of living is tremendous in the city, people are moving to the suburbs in order to find acceptable housing that is a reasonable cost.  The price they pay is more time spent waiting while commuting to work and back.

~ 66 ~

Page 67: ukm - publick transport proposal

2- In Japan, there are nine cities that have subway systems with the first one starting in 1927.  Many subways also link with commuter lines to reach out to the suburbs as well. Japan is also looking into linking the publi and private transportation systems.  Further rail developments include a light rail transit (LRT) which was initiated in Kumamoto in 1997, this is the first one operated in Japan.

Stand very close to very many people

See the latest technology Since you're so close to someone anyhow, it's not totally unexpected for you to lean in close to watch them play Galaga on their iMode phone.

Enjoy the handles The Tokyo subways had quite an ample number of handles for crowded cars - I enjoyed looking at them and hanging on them some..:

Study crowd dynamics People all around the world rush out of subways, but I suspect there's something uniquely singleminded about the headlong rush that most Tokyo folks make out of the trains and through the stations. I was working on a theory of self-determined traffic systems - since Japanese cars drive on the left side of the road (like Britian; the opposite of America and mainland Europe), I wondered if they would stay on the left side in most self-determining crowd situations. It seemed to go about fifty-fifty, surprising if they are mostly trained by their roads to lean leftward. My American mind was inspired to think that our right-travelling system is more natural and human and these folks are taking it up on their own. Poppycock

.

.~ 67 ~

Page 68: ukm - publick transport proposal

Witness advanced Subway development

Being from the Bay Area near San Francisco, I can only lust after a useful subway system. Tokyo is laced with subway stops, and the trains run very often - every few minutes. One train line running through Ginza had an electronic readout that showed you which stop you were at, and where you were headed. The subway cars are saturated with handles for stability in crowd situations.

Store your luggage If you're a busy vagabond on the go, you've got to have somewhere to store your stuff - the subway stations in Tokyo all have lockers that will store small roll-on baggage.

Subways and light rail transit

Tokyo subway map (in Japanese)

INFORMATIONS ABOUT SUBWAY IN TOKYO

In addition to its extensive railroads, Japan has an impressive number of subway systems. The largest is

the Tokyo subway, where the network in 1989 consists of 211 kilometers of track serving 205 stations. Two

subway systems serve the capital: one run by the Tokyo Metro (named Teito Rapid Transit Authority until

2004), with nine lines (the oldest, Ginza line was built in 1927), and the other operated by the Tokyo

metropolitan government's Transportation Bureau (Toei), with four lines. Outlying and suburban areas are

served by seven private railroad companies, whose lines intersect at major stations with the subway

system. More than sixty additional kilometers of subway were under construction in 1990 by the two

companies.

~ 68 ~

Page 69: ukm - publick transport proposal

There are a number of other metro systems in other Japanese cities, including the Fukuoka City Subway,

Kobe Municipal Subway, Kyoto Municipal Subway, Osaka Municipal Subway, Nagoya Subway, Sapporo

Subway, Sendai Subway and Yokohama Subway.

While metro systems in Japanese cities are usually operated by the city government and therefore tend to

limit their networks within the city border, there are many cases of through services of subway trains onto

suburban railway lines and vice-versa. One of the reasons of this trend is the sharp increase of ridership on

the railways in the rapid growth of postwar economy that could not be handled by small original railway

terminals in the city center.

Automated guideway transit (rubber-tired motor cars running on concrete guideways) has also developed

in Japan. Cities with such intermediate capacity transit systems include Hiroshima, Kobe, Osaka, Saitama

and Tokyo.

Some cities operate streetcar systems, including Hiroshima, Matsuyama, Nagasaki, Tokyo (one line only)

and Toyohashi. All of these cities are also well served by public and private railroads; also, there are

private tramways not included above.

~ 69 ~

Page 70: ukm - publick transport proposal

GENERAL PROPOSALS

1- Provide a comprehensive and integrated transportation system that caters for the needs of

inter and intra city travel.

2- Optimise the road and rail transportation infrastructure so that it operates at its full capacity

and maximum efficiency;

3- Try to do that the overall configuration of land use is integrated with road and public

transportation networks to optimise the development of land.

4- Try to do that all areas within the City enjoy the same high quality and standard of provision

of public transport services.

5- Create a city that is highly accessible for all its occupants and users, in particular, one that is

pedestrian and handicapped friendly, and that is to enhance the city living environment and

government.

6-

7- Providing bus service efficient with excellent services and support with appropriate number.

8- Existing bus stations in the center of each (OUR AREAS)

9- Buses have to stop just in the main stations.

10- Provide more security within these stations to avoid problems, especially during peak hours.

11- Not allow to trucks to travel in these cities, especially leading to government departments, to

avoid traffic jams.

12- Increase number of bridges for pedestrians to avoid traffic jams in the active areas.

13- Design roads outside OUR AREAS , of an external procedure to alleviate congestion and

facilitate the movement of trucks and heavy machinery and passing through ths cities.

~ 70 ~

Page 71: ukm - publick transport proposal

POLICY AND PROPOSAL

GENERAL

a) Travel Demand Management

If current trends continue, motorised trips by car in 2014 are expected to be almost double those of 1997.

Increasing road capacity by constructing new roads and widening existing roads do not, in the long run,

resolve the situation but simply postpone the problem until more roads need to be built. Most areas in the

City, especially the City Centre, are now built up and land acquisition for road development is becoming

increasingly difficult and expensive.

Government is, therefore, moving towards a Travel Demand Management strategy that aims to redirect

movement patterns from private to public transport by integrating transport modes, extending and

promoting public transport and discouraging the use of private transport. The public transport system in the

City must be competitive, convenient, userfriendly and accessible to all income groups.

Policy:

1. Government shall determine Travel Demand Management measures to increase public transport usage

and liase with the relevant authorities to ensure that these measures are implemented.

2. Government shall implement a private vehicle restraint programme to improve traffic circulation in the

City Centre by discouraging car travel to and from the City Centre during peak hours and enforcing

measures to limit access to certain parts of the City.

b) Traffic Management System

In order to optimise the traffic management system now in place, the system needs to be upgraded to one

that can monitor and control all aspects of traffic movement in the City.

Policy:

Government shall enhance the traffic management system.

~ 71 ~

Page 72: ukm - publick transport proposal

c) Transit Oriented Development

A principal objective of the transportation sector is the integration of land use with transportation and the

development of a Transit Oriented Development Strategy. This strategy will promote intensified

development along the rail network. Any planned extension to the rail network must, therefore, complement

this policy by ensuring that rail stations serve designated urban centers.

Policy:

Government shall establish a Transit Planning Zone to facilitate intensification of transit oriented

residential, commercial and mixed-use development around rail stations.

. PUBLIC TRANSPORT

a) Public Transport Administration

The increased emphasis and capital expenditure on public transport requires complementary coordination

between government departments and other related agencies. Government shall take pro-active measures

in ensuring the implementation of government policy in relation to the public transport administration.

Policy:

Government shall assist to coordinate the planning, development and operation of public transport and

related private transport matters.

b) Public Transport Integration

Consistent with the government’s policy, emphasis will be on providing an integrated, flexible, wide ranging

and efficient public transport system orientated towards passenger accessibility and convenience. Central

to this approach is the integration of public transport modes with each other and with private transport so

that, with streamlined inter-modal transfer facilities and integrated ticketing, passenger trips become as

convenient and seamless as possible.

In order to avoid traffic congestion occurring on local streets, major bus and rail park-and-ride interchange

facilities will be located at the points of intersection of the rail stations and major roads.

~ 72 ~

Page 73: ukm - publick transport proposal

Policy:

Government shall assist in the implementation of a fully integrated transportation system in line with the

government’s policy.

c) Rail-Based Public Transport

The rail network is the most efficient means of providing high capacity rapid public transport. Medium and

long-term plans for the introduction of different types of rail systems such as tram and the expansion of the

rail network to outlying areas should be regularly examined in every 10 years for their feasibility. The major

growth areas in Kajang, Bangi, Bandar Seri Putra, Bukit Mahkota, Nilai 3 and Nilai, are now well linked to

the City Centre except those on the east-west axis.

Policy:

Government shall assist in the preparation of feasibility studies for future extensions to the rail network and

coordinate with the relevant authorities with regard to implementation.

d) Bus Services

Buses will remain the principal form of public transport especially outside the City Centre for the

foreseeable future. In order to encourage greater usage of bus services, it is essential that measures be

undertaken to improve their reliability, coverage, comfort and convenience.

Policy:

1- Government shall assist in determining measures to improve bus services with maximum penetration

into growth areas and all major employment and retail centers and coordinate with the relevant agencies

and operators.

2- Government shall implement a bus terminal network for inter-regional, intraregional and local bus

services.

e) Cars and Car Parking

By controlling the supply and distribution of car parking facilities in Kajang, Bangi, Bandar Seri Putra, Bukit

Mahkota, Nilai 3 and Nilai, government can help to reinforce public transport and Travel Demand

~ 73 ~

Page 74: ukm - publick transport proposal

Management objectives by making private transport a less attractive proposition than public transport,

especially within the City Centre. This can further be reinforced by controlling the cost of car parking in

different parts of the City.

Policy:

Government shall regulate the supply of parking facilities.

f) Taxis

In view of the vital role that taxis play in the business and commercial life of the City, it is important that

significant improvements are made to the levels of service and reliability. In achieving better overall public

transport services, taxis need to be expanded with innovative services into new markets.

Policy:

Government shall assist in improving the reliability and availability of taxi services in coordination with the

relevant agencies.

. PRIVATE TRANSPORTATION

a) Motorcycles

As Kajang, Bangi, Bandar Seri Putra, Bukit Mahkota, Nilai 3 and Nilai, looks to a cleaner and safer living

environment, the role of the motorcycle in transportation must be examined. A large percentage of

motorcycle users are those that would benefit from a more comprehensive public transportation system. In

a long term, measures to encourage motorcycle users to make greater use of public transport and limit

motorcycle usage in the City Centre to only essential users should be looked into. In the short and medium

term, measures to improve safety for motorcycle users shall be implemented and more rigorous

enforcement of existing regulations shall be exercised.

~ 74 ~

Page 75: ukm - publick transport proposal

Policy:

Government shall assist and coordinate with the relevant authorities in the improvement of road

infrastructure to enhance safety measures for motorcycle users.

. ROAD INFRASTRUCTURE

a) New Roads Development

The major road systems currently in place together with those which are under construction or committed

are considered sufficient to satisfy Kajang, Bangi, Bandar Seri Putra, Bukit Mahkota, Nilai 3 and Nilai ,

need to the year 2014. However, two new roads are proposed that are principally intended to improve

traffic flow in and out from the City Centre. In view of the difficulty of increasing existing road capacities in

the City Centre and the high cost associated with obtaining new corridors.

Policy:

1- Government shall determine a road development programme and coordinate with the relevant

authorities regarding implementation.

2- Government shall ensure that proposed and committed major roads are considered in the broader

context of public transport services, freight movement and impact upon the community and environment.

b) Improvements to the Existing Road Network

In order to complete the existing road network, increase its capacity and eradicate bottlenecks, a road

network improvement programme must be carried out to upgrade existing roads to arterial roads, build

missing linkages and improve interchanges.

Policy:

Government shall determine a road improvement programme and coordinate with the relevant authorities

regarding implementation.

~ 75 ~

Page 76: ukm - publick transport proposal

7- CONCLUSION

WE HOPE THAT THE GOVERNMENT UNDERSTAND AND REALIZE THE CAPITAL ROLE THAT

TRANSPORTATION SYSTEM AND DISTINGUISHING SYSTEM TRANSPORTATION ARE PLAYED ON

OF HUMANITY, THE CITY’S FUTURE TRANSPORT GOALS ARE DEVELOPING A PEOPLE AND

ENVIRONMENT-FRIENDLY COMPACT CITY. AS MALAYSIAN SOCIETY BECOMES

INCREASINGLY AGED WITH FEWER PEOPLE, REVITALIZING AND INCREASING THE

CONVENIENCE OF PUBLIC TRANSPORT WHILE DEVELOPING A PLEASANT

ENVIRONMENT NEAR PUBLIC TRANSPORT ROUTES WILL ALLOW MORE PEOPLE TO LIVE

IN SAFETY AND PEACE OF MIND.

~ 76 ~