Upload
edith-watts
View
215
Download
0
Tags:
Embed Size (px)
Citation preview
UCN 2014 Installation Overview/Logistics
UCN Monthly Meeting
Dec.18, 2013(L.Lee)
UCN 2014 Installation: Schedule 2
UCN 2014 Installation folded into Shutdown Schedule• New schedule release today (SAS Committee)• UCN SASP0184,185,186,187 Start: January 2 ; Finish: ~ April 10 • Shield-Plug reconfiguration: starts in mid-March
• Work Requests (10) submitted; Not all approved yet.• Lift Plan (Jason), Alignment Plan (Dave P.), Dose Analysis (Cam RPG)• CNSC Approval of Shield Plug (“in the mail” “OK to proceed” Anne/Jeff)
UCN 2014 Installation: Personnel 3
.T-B/L (Beamlines)• Installation/Alignment of B/L Components• Consultation w/ TRIUMF Alignment Group (D.Preddy, B.Gasbarri, M.Vogel)• D.Pearce hired on contract direct UCN alignment efforts• Hexagon Metrology Engineer (R.Molari) services contract advisory
tracker specialist
.T-Mech (Mechanical) • General removal/assembly of components• M.Goyette hired on contract• T.Hessels (UCN Designer & .T-Mech) ~ 50% (?)• Require 1 more .T-Mech (TRIUMF) 50%
Crane Crew • At start of shutdown (Jan.2 – 17) remove/excavate shielding blocks• Intermittent (Jan.21 – Mar.26) removal/placing of components• Near end of shutdown (Mar.27 – Apr.10) restoring shielding+plug
Others• Contractors: Plumbing (Lockerbie), Electrical (Entech), Coring (West Coast)• Safety/RPG, Engineering (Civil, Electrical), Plant Group Intermittent• Diagnostics & Controls 1AM5 (best efforts)
UCN 2014 Installation: Alignment Plan 4
Alignment Plan & Logistics• Plan being developed in consultation w/ Alignment group & D.Pearce• Purchase Order for laser-tracker rental from Hexagon Metrology
Alignment Plan Overview • Fiducialize magnets, frames & other B/L components w/ Laser Tracker
- Shoot array of points (upstream/downstream) on each component
• Shoot Vault & 1A monuments w/ Laser Tracker & establish coord. system• Lay down grid of new monuments (Vault & 1A tunnel) & record
- Number/Locations of new monuments (consult Bruno/Mike)• Paint floor and/or lay down scribe lines
• Mark drill location (and angle) on Immovable-block for coring
• Install/Locate frames (Theodolite or Laser Tracker)
• Install/Align magnets/components according to schedule- Use Laser Tracker to position fiducialized points
Meson Hall Clean-up 5
M11 Cleanup Completed• Staging area for new Shielding
M13 Cleanup Completed• Staging area for “removed” blocks• Some blocks already moved to M13• Jason’s layout for temp. block storage• “Boot-box” area for 1A access M13
Cleanup above BL1A/1B • Almost completed (thanks to Ron K.)• 46 items removed; ~11 items left to move (this week & after beam OFF)• Catalogue of items removed:
https://ucn.triumf.ca/triumf/beamline/Catalog-MH-cleanup.pdf• Extra Blocks (6’ and smaller) stage to M13 “monolith”
Floor Plan (SW Meson Hall)
Total number of items: 9 (zone A) + 13 (zone B) + 30 (zone C) = 52
Gateway Zone C (slides 29-59)
Zone B (slides 15-28)
Zone A (slides 5-14)N S
E
W
(From Dec/2012)
Cleanup above BL1A/1B
Floor Plan (SW Meson Hall)
Total number of items: 9 (zone A) + 13 (zone B) + 30 (zone C) = 52
Gateway Zone C (slides 29-59)
Zone B (slides 15-28)
Zone A (slides 5-14)N S
E
W
(From Dec/2012)
Floor Plan (SW Meson Hall)
Total number of items: 1 (zone A) + 5 (zone B) + 3 (zone C) = 9 (43 objects cleared)
Gateway Zone C (slides 29-59)
Zone B (slides 15-28)
Zone A (slides 5-14)N S
E
W
(Dec/2013)
Objects rem.
Floor Plan (SW Meson Hall)
Total number of items: 1 (zone A) + 5 (zone B) + 3 (zone C) = 9 + 5 “New items”
Gateway Zone C (slides 29-59)
Zone B (slides 15-28)
Zone A (slides 5-14)N S
E
W
(Dec/2013)
Objects added
N1
N3 N2
N4
N5
Floor Plan (SW Meson Hall)
Total number of items: 1 (zone A) + 5 (zone B) + 3 (zone C) = 9 + 2 “New items”
Gateway Zone C (slides 29-59)
Zone B (slides 15-28)
Zone A (slides 5-14)N S
E
W(Dec/2013)
Objects added
(& removed)
N1
N3 N2
N4
N5
Remaining items to move
To M11:
To top of M9, M11, M20 blocks:
Beamlines R/H R/H UCN
To Storage “Barn”:
Beamlines
Remaining items to move this week
Detector Group
To Vault Roof:
T2K/SnolabBeamlinesPIENU
Outside M11:
EWB/Beamlines
Remaining items to move after beam OFF
FINIS
.T-Mech