Page 1: UCN 2014 Installation Overview/Logistics UCN Monthly Meeting Dec.18, 2013 (L.Lee)

UCN 2014 Installation Overview/Logistics

UCN Monthly Meeting

Dec.18, 2013(L.Lee)

Page 2: UCN 2014 Installation Overview/Logistics UCN Monthly Meeting Dec.18, 2013 (L.Lee)

UCN 2014 Installation: Schedule 2

UCN 2014 Installation folded into Shutdown Schedule• New schedule release today (SAS Committee)• UCN SASP0184,185,186,187 Start: January 2 ; Finish: ~ April 10 • Shield-Plug reconfiguration: starts in mid-March

• Work Requests (10) submitted; Not all approved yet.• Lift Plan (Jason), Alignment Plan (Dave P.), Dose Analysis (Cam RPG)• CNSC Approval of Shield Plug (“in the mail” “OK to proceed” Anne/Jeff)

Page 3: UCN 2014 Installation Overview/Logistics UCN Monthly Meeting Dec.18, 2013 (L.Lee)

UCN 2014 Installation: Personnel 3

.T-B/L (Beamlines)• Installation/Alignment of B/L Components• Consultation w/ TRIUMF Alignment Group (D.Preddy, B.Gasbarri, M.Vogel)• D.Pearce hired on contract direct UCN alignment efforts• Hexagon Metrology Engineer (R.Molari) services contract advisory

tracker specialist

.T-Mech (Mechanical) • General removal/assembly of components• M.Goyette hired on contract• T.Hessels (UCN Designer & .T-Mech) ~ 50% (?)• Require 1 more .T-Mech (TRIUMF) 50%

Crane Crew • At start of shutdown (Jan.2 – 17) remove/excavate shielding blocks• Intermittent (Jan.21 – Mar.26) removal/placing of components• Near end of shutdown (Mar.27 – Apr.10) restoring shielding+plug

Others• Contractors: Plumbing (Lockerbie), Electrical (Entech), Coring (West Coast)• Safety/RPG, Engineering (Civil, Electrical), Plant Group Intermittent• Diagnostics & Controls 1AM5 (best efforts)

Page 4: UCN 2014 Installation Overview/Logistics UCN Monthly Meeting Dec.18, 2013 (L.Lee)

UCN 2014 Installation: Alignment Plan 4

Alignment Plan & Logistics• Plan being developed in consultation w/ Alignment group & D.Pearce• Purchase Order for laser-tracker rental from Hexagon Metrology

Alignment Plan Overview • Fiducialize magnets, frames & other B/L components w/ Laser Tracker

- Shoot array of points (upstream/downstream) on each component

• Shoot Vault & 1A monuments w/ Laser Tracker & establish coord. system• Lay down grid of new monuments (Vault & 1A tunnel) & record

- Number/Locations of new monuments (consult Bruno/Mike)• Paint floor and/or lay down scribe lines

• Mark drill location (and angle) on Immovable-block for coring

• Install/Locate frames (Theodolite or Laser Tracker)

• Install/Align magnets/components according to schedule- Use Laser Tracker to position fiducialized points

Page 5: UCN 2014 Installation Overview/Logistics UCN Monthly Meeting Dec.18, 2013 (L.Lee)

Meson Hall Clean-up 5

M11 Cleanup Completed• Staging area for new Shielding

M13 Cleanup Completed• Staging area for “removed” blocks• Some blocks already moved to M13• Jason’s layout for temp. block storage• “Boot-box” area for 1A access M13

Cleanup above BL1A/1B • Almost completed (thanks to Ron K.)• 46 items removed; ~11 items left to move (this week & after beam OFF)• Catalogue of items removed:

https://ucn.triumf.ca/triumf/beamline/Catalog-MH-cleanup.pdf• Extra Blocks (6’ and smaller) stage to M13 “monolith”

Page 6: UCN 2014 Installation Overview/Logistics UCN Monthly Meeting Dec.18, 2013 (L.Lee)

Floor Plan (SW Meson Hall)

Total number of items: 9 (zone A) + 13 (zone B) + 30 (zone C) = 52

Gateway Zone C (slides 29-59)

Zone B (slides 15-28)

Zone A (slides 5-14)N S

E

W

(From Dec/2012)

Cleanup above BL1A/1B

Page 7: UCN 2014 Installation Overview/Logistics UCN Monthly Meeting Dec.18, 2013 (L.Lee)

Floor Plan (SW Meson Hall)

Total number of items: 9 (zone A) + 13 (zone B) + 30 (zone C) = 52

Gateway Zone C (slides 29-59)

Zone B (slides 15-28)

Zone A (slides 5-14)N S

E

W

(From Dec/2012)

Page 8: UCN 2014 Installation Overview/Logistics UCN Monthly Meeting Dec.18, 2013 (L.Lee)

Floor Plan (SW Meson Hall)

Total number of items: 1 (zone A) + 5 (zone B) + 3 (zone C) = 9 (43 objects cleared)

Gateway Zone C (slides 29-59)

Zone B (slides 15-28)

Zone A (slides 5-14)N S

E

W

(Dec/2013)

Objects rem.

Page 9: UCN 2014 Installation Overview/Logistics UCN Monthly Meeting Dec.18, 2013 (L.Lee)

Floor Plan (SW Meson Hall)

Total number of items: 1 (zone A) + 5 (zone B) + 3 (zone C) = 9 + 5 “New items”

Gateway Zone C (slides 29-59)

Zone B (slides 15-28)

Zone A (slides 5-14)N S

E

W

(Dec/2013)

Objects added

N1

N3 N2

N4

N5

Page 10: UCN 2014 Installation Overview/Logistics UCN Monthly Meeting Dec.18, 2013 (L.Lee)

Floor Plan (SW Meson Hall)

Total number of items: 1 (zone A) + 5 (zone B) + 3 (zone C) = 9 + 2 “New items”

Gateway Zone C (slides 29-59)

Zone B (slides 15-28)

Zone A (slides 5-14)N S

E

W(Dec/2013)

Objects added

(& removed)

N1

N3 N2

N4

N5

Page 11: UCN 2014 Installation Overview/Logistics UCN Monthly Meeting Dec.18, 2013 (L.Lee)

Remaining items to move

Page 12: UCN 2014 Installation Overview/Logistics UCN Monthly Meeting Dec.18, 2013 (L.Lee)

To M11:

To top of M9, M11, M20 blocks:

Beamlines R/H R/H UCN

To Storage “Barn”:

Beamlines

Remaining items to move this week

Detector Group

Page 13: UCN 2014 Installation Overview/Logistics UCN Monthly Meeting Dec.18, 2013 (L.Lee)

To Vault Roof:

T2K/SnolabBeamlinesPIENU

Outside M11:

EWB/Beamlines

Remaining items to move after beam OFF

Page 14: UCN 2014 Installation Overview/Logistics UCN Monthly Meeting Dec.18, 2013 (L.Lee)

FINIS

Page 15: UCN 2014 Installation Overview/Logistics UCN Monthly Meeting Dec.18, 2013 (L.Lee)

.T-Mech