Title: Town Cleansing Activity Report
1. Administrative Data
Name of Officer in Chargei. Mr. Din (Service Area Supervisor)
Date : April 24th, 2014Time : 8.30 am- 11.30 am
2. Technical Report
2.1 Activitiesi. Lawn Mowing (including scraping)ii. Drain cleansingiii. Road cleansing
2.2 Equipments neededi. Broom
1
[ ] ALAM FLORA
ii. Scraperiii. Mower (Grass cutter machines + Diesel + 2T oil)iv. Shovel
v. Plastic bagsvi. Bootsvii. Glovesviii. PPE (jacket, cap)ix. Wheeled dustbin
2.3 Procedures
STEP DESCRIPTION1 Morning Roll Call
Every locality are cleaned once in a month, regularly and stated in the schedule set by the supervisor. The supervisor will brief all movement on 7.00 am at the front of Alam Flora depoh.
2
[ ] ALAM FLORA
Every worker has to attend the roll call. Then they will proceed to start their job.
2 Work Progressi. Arriving at the locality mentioned by the supervisor, before
starting the job, they will wear PPE provided by the company according to their job-For lawn mowing: boots, goggle, cap, gloves, apron-For cleaning the drains: safety jacket, cap, boots-For sweeper: safety jacket, cap, gloves
ii. For each locality, one team consists of three (3) person, and they will specify each one’s job to increase effectiveness
3 Mowing the grassi. Each worker should cover 1600 to 1800 meters per day, from 1
meter distance from the roadside
ii. For machinery management, every machine will be turned off after 30 – 45 minutes of usage.
iii. One will do the sweeping job after mowing , and collect it in a plastic bag and thrown at the nearest public garbage drum
iv. Any problems or difficulties will be reported to the supervisorv. After finishing job, all apparatus and machines are cleaned and
kept in a storage room
3
[ ] ALAM FLORA
the whole mowing machine
The brand used by Alam Flora Sdn Bhd
The accessory- the cutter (plastic)
4 Drainage cleansingi. One team can be assigned at most of two (2) localityii. job classification ; scrap garbage in the drain, and collect in the
plastic bags
4
[ ] ALAM FLORA
iii. all garbage bags will be collected either by truck or by bringing it to the nearest garbage drum
vi. The standard is, the drain has to be clean from anything visible.
5
[ ] ALAM FLORA
BEFORE
AFTER
vii. Any problems or difficulties will be reported to the supervisorviii. After finishing job, all apparatus and machines are cleaned and
kept in a storage room
5 Road Cleansingi. For this job, usually for one locality, there is only one worker. The
area that should be covered is 3 km per day.ii. One wheeled garbage bin is provided for each worker.
6
[ ] ALAM FLORA
iii. The truck will come and pick up the garbage in the garbage binix. Any problems or difficulties will be reported to the supervisorx. After finishing job, all apparatus and machines are cleaned and
kept in a storage room
2.4 The worker’s welfarei. Each worker is provided with Corporate Medical Card, if there is any sickness
happen to the worker , they can always go to the Panel Clinicii. The supervisor will supervise each worker, every day. If there is any problem,
can be voiced out at the supervisor.
3. Legislation
i. Solid Waste Management and Town Cleansing Act 2007ii. Occupational Safety and Health Act (OSHA) 1994
4. Recommendation & Suggestion
i. The PPE are always supplied to the workers, and usually they do not wear them due to the excuse; not really comfortable. It is the company’s job to ensure the safety of the workers, thus, they have to make the PPE comfortable for the workers. Like for the reflecting jacket, the material can always be changed, to increase comfort.
7