TM0 components inventory and procurement schedule. In lab testing facility. Inventory layout. RF system Accelerating structure (x16) PETS structure (x8) RF distribution and loads Vacuum system BI and Vacuum systems BPM-DBQ chamber assembly Magnet system Cooling system Supporting system - PowerPoint PPT Presentation
Citation preview
A.Bartalesi
TM0 componentsinventory and procurement schedule
In lab testing facility
07/03/2011
Inventory layout
07/03/2011A.Bartalesi
RF system Accelerating structure (x16) PETS structure (x8) RF distribution and loads
Vacuum system BI and Vacuum systems
BPM-DBQ chamber assembly Magnet system Cooling system Supporting system Pre-alignment system
Components priority
07/03/2011A.Bartalesi
Priotity 0 -
30/11/2010
•Floor interface plate
•Floor interface plate
Priority 1 -
20/12/2010
•MB girders with V-shaped supports, cradles and actuators
•DB girders with V-shaped supports•Cradles•Actuators
Priority 2 -
31/01/2011
•Accelerating structures•Damping material
•Cooling interfaces
•RF flanges•Interconn. flanges
•Interconn. bellows
•PETS•Damping material
•Cooling interfaces
•RF flanges•Interconn. flanges
•DB QUADS•BPM•Vacuum chamber
•Support plate
•Interconn. bellows
Priority 3 -
15/02/2011
•Vacuum•Supports•Vacuum reservoir
•Interconn. bellows
Priority 4 -
28/02/2011
•RF distribution•Waveguides•RF components
•RF flanges•RF loads
Priority 5 -
10/03/2011
•Vacuum network
Priority 6 -
10/03/2011
•Cooling system
Priority 7 -
31/03/2011
•Heating device
•Transport device
Labels:3D
done2D
doneOrderedDelivere
d
A.Bartalesi
Accelerating structureoverview
07/03/2011
MB Unit (Assembly)Flange (VS)Compact load (RS)
Intermodule interconnection (VS)Cooling tubes (RS)
Manifold (RS)
Waveguides (RS)
07/03/2011A.Bartalesi
A.Bartalesi
RF systemAccelerating structure (1 of 5)
07/03/2011
Name Drawing #Quantit
y (2 TM0s)
Real or
Mock-
up?
StatusDeadline
for current status
FirmProcuremen
t Responsible
Comments
Last update in
this database
AS MOCK-UP - HOR. MANIFOLD WAVEGUIDE
TYPE 1
CLIATLAS0097 16 M Price inquiry
21/02/2011 ? Many A. French21/01/201
1
AS MOCK-UP - HOR. MANIFOLD WAVEGUIDE
TYPE 2
CLIATLAS0098 16 M Price inquiry
21/02/2011 ? Many A. French21/01/201
1
AS MOCK-UP - WAVEGUIDE DAMPING INTERFACE
HALF 1
CLIATLAS0100 64 M Price inquiry
21/02/2011 ? Many A. French21/01/201
1
AS MOCK-UP - WAVEGUIDE DAMPING INTERFACE
HALF 2
CLIATLAS0101 64 M Price inquiry
21/02/2011 ? Many A. French21/01/201
1
AS MOCK-UP - MANIFOLD DM INTERFACE CELL
CLIATLAS0110
128 M Price inquiry 21/02/2011 ? Many A. French
21/01/2011
AS MOCK-UP - MANIFOLD STANDARD CELL
CLIATLAS0111
1280+40 M Price inquiry
21/02/2011 ? Many A. French21/01/201
1
AS MOCK-UP - MANIFOLD WFM-CART INTERFACE
CLIATLAS0112 64 M Price inquiry
21/02/2011 ? Many A. French21/01/201
1
AS MOCK-UP - MANIFOLD EXTREMITY CELL
CLIATLAS0113 64 M Price inquiry
21/02/2011 ? Many A. French21/01/201
1
AS MOCK-UP - HOR. MANIFOLD WG TYPE 1
(MIRRORED)
CLIATLAS0120 16 M Price inquiry
21/02/2011 ? Many A. French21/01/201
1
AS MOCK-UP - HOR. MANIFOLD WG TYPE 2
(MIRRORED)
CLIATLAS0121 16 M Price inquiry
21/02/2011 ? Many A. French21/01/201
1
CLIC experimental
flange
CLIAVACU0184
64+8(+8 in PETS
+48 in RF dist.)
R
Prototypes received, control ongoing
15/03/2011
Kvis-gaar
dC. Garion
Ø 74Prototypes
to be manufactur
ed
17/2/2011
A.Bartalesi
RF systemAccelerating structure (2 of 5)
07/03/2011
Name Drawing #Quantit
y (2 TM0s)
Real or
Mock-
up?
StatusDeadline
for current status
FirmProcuremen
t Responsible
Comments
Last update in
this database
WFM WG bodyCLIATLAS003
1 64+8 M Price inquiry 21/02/2011 ? Many A. French
21/01/2011
WFM WG coverCLIATLAS003
0 64+8 M Price inquiry 21/02/2011 ? Many A. French
21/01/2011
AS cooling fitting adapter
CLIATLAS0053
128+32 R Price inquiry
21/02/2011 ? Many A. French21/01/201
1
MB-MB interconnection
bellow
CLIATLVS0004 4 R
Leak tested, to
be assembled
15/3/2011
COM-VAT C. Garion 17/2/2011
Intermediate piece
CLIATLAS0075 2 M Price inquiry
21/02/2011 ? Many A. French21/01/201
1
Intermediate piece 2
CLIATLAS0056 2 M Price inquiry
21/02/2011 ? Many A. French21/01/201
1
HOM Load (5x5, L=40)
CLIATLAS0004
64 MOrdered on 30/11/201
0
15/01/2011 M.P. A. French 13/12/201
0
Manifold small cover 2
CLIATLAS0065 64 M Price inquiry
21/02/2011 ? Many A. French21/01/201
1
PINCLIATLAS006
3 32 M Price inquiry 21/02/2011 ? Many A. French
21/01/2011
Manifold small cover 3 insert
CLIATLAS0090 32 M Price inquiry
21/02/2011 ? Many A. French21/01/201
1
AS MOCK-UP - STANDARD
CELL
CLIATLAS0099
320 M Price inquiry 21/02/2011 ? Many A. French 21/01/201
1
A.Bartalesi
RF systemAccelerating structure (3 of 5)
07/03/2011
Name Drawing #Quantit
y (2 TM0s)
Real or
Mock-
up?
StatusDeadline
for current status
FirmProcuremen
t Responsible
Comments
Last update in
this database
AS MOCK-UP - COOLING INTERFACE
CELL
CLIATLAS0103 32 M Price inquiry
21/02/2011 ? Many A. French21/01/201
1
AS MOCK-UP - ALIGNMENT
INTERFACE CELL
CLIATLAS0104 32 M Price inquiry
21/02/2011 ? Many A. French21/01/201
1
AS MOCK-UP - INPUT CELL
CLIATLAS0105 16 M Price inquiry
21/02/2011 ? Many A. French21/01/201
1
AS MOCK-UP - COUPLER A TYPE
1
CLIATLAS0106
14 M Price inquiry 21/02/2011 ? Many A. French 21/01/201
1
AS MOCK-UP - COUPLER B TYPE
1
CLIATLAS0107
16 M Price inquiry 21/02/2011 ? Many A. French 21/01/201
1
AS MOCK-UP - EXTREMITY CELL
CLIATLAS0108 14 M Price inquiry
21/02/2011 ? Many A. French21/01/201
1
AS MOCK-UP - COUPLER A TYPE
2
CLIATLAS0109
2 M Price inquiry 21/02/2011 ? Many A. French 21/01/201
1
AS MOCK-UP - EXTREMITY CELL
TYPE 3
CLIATLAS0116
2 M Price inquiry 21/02/2011 ? Many A. French 21/01/201
1
Manifold small cover 3 body
CLIATLAS0060 64 M Price inquiry
21/02/2011 ? Many A. French21/01/201
1
Wire d. 1 mm (St.)
Commercial3D:
ST029035232 M
Price inquiry launched on
01/11
12/11/2010 (any) A. French
1 cm long
metal wire
17/11/2010
UHV CF FIXED FLANGE Ø114-63-
60
STDVFUHV0092
16 (+8 in PETS)
ROrdered
27/10/10, to be machined
? CERN
C. Garion 26/11/2010
A.Bartalesi
RF systemAccelerating structure (4 of 5)
07/03/2011
Name Drawing #Quantit
y (2 TM0s)
Real or
Mock-
up?
StatusDeadline
for current status
FirmProcuremen
t Responsible
Comments
Last update in
this database
Vacuum tube P1
CLIATLAS0094 16 M Price inquiry
21/02/2011 ? Many A. French21/01/201
1
Vacuum tube Flange
CLIATLAS0095 16 M Price inquiry
21/02/2011 ? Many A. French21/01/201
1
Cover 2CLIATLAS006
7 16 M Price inquiry 21/02/2011 ? Many A. French
21/01/2011
MB interconnection
flange Ø155
CLIATLVS0006
4 R
Manufactured, leak tested, being
modified
25/2/2011
CERN
C. Garion 17/2/2011
Screw VacomMC-310 Commercial 96 R Vaco
m A. French17/11/201
0
12WDSDVG1.8_R05_SIC CORNER SUPPORT_001
CLIAAS120080
64+16 M Price inquiry
21/02/2011 ? Many A. French21/01/201
1
CoverCLIATLAS007
0 48 M Price inquiry 21/02/2011 ? Many A. French
21/01/2011
Damping material 12
CLIATLAS0072
64 + 2 R
Price offer received
17/11/2010? M.P. A. French On hold
13/12/2010
Cooling tubetype 1
CLIATLAS0080 8 M
In fabrication
?CER
N A. French21/01/201
1
MB ACCELERATING STRUCTURE -
COOLING TUBE U75
CLIATLAS0092 8 M
In fabrication
?CER
N A. French21/01/201
1
A.Bartalesi
RF systemAccelerating structure (5 of 5)
07/03/2011
Name Drawing #Quantit
y (2 TM0s)
Real or
Mock-
up?
StatusDeadline
for current status
FirmProcuremen
t Responsible
Comments
Last update in
this database
Cooling tubetype 3
CLIATLAS0082 8 M
In fabrication
?CER
N A. French21/01/201
1
Cooling tubetype 4
CLIATLAS0081 32 M
In fabrication
?CER
N A. French21/01/201
1
MB intermodule interconn.
Damping Mat.
CLIATLAS0086
4 ROrdered on 30/11/201
0
15/01/2011 M.P. A. French 13/12/201
0
Connector hoke 1
Commercial 4LMFS4BR TD
8mm112 R Swagel
ok A. French17/11/201
0
Connector hoke 2
Commercial 4COSBR TD
8mm16 R Swagel
ok A. French17/11/201
0
Screw Vacom MFA-412 Commercial 16 R Vaco
m A. French17/11/201
0
Target sphere holder 0.5”
Commercial Z04x06Ni-35
64 R Received HKCMH. Mainaud-
Durand
magnet Ø4,
length 6mm
10/01/2011
Spherical prism 0.5’’
CommercialBMR-.5-0.001
2 R ReceivedLeica/Hubb
s
H. Mainaud-Durand
(removable device)
10/01/2011
A.Bartalesi
PETS structureoverview
07/03/2011
DRIVE BEAM – PETS ASSEMBLY
Interconnection Flanges (Fixed)
PETS On-Off (Coupler)
PETS Mock-Up
Interconnection Flanges (Fixed)
Cooling tubes
Cooling fittings adapter
Cooling adapter
PETS Minitanks
07/03/2011A.Bartalesi
A.Bartalesi
RF systemPETS structure (1 of 3)
07/03/2011
Name Drawing #Quantit
y (2 TM0s)
Real or
Mock-
up?
StatusDeadline
for current status
FirmProcuremen
t Responsible
Comments
Last update in
this database
ON-OFF half 1CLIATLPE003
3 8 M Ordered 23/02/2011
14/03/2011
Lindenthal A. FrenchS.A.
reference person
04/03/2011
ON-OFF half 2CLIATLPE003
4 8 M Ordered 23/02/2011
14/03/2011
Lindenthal A. FrenchS.A.
reference person
04/03/2011
ON-OFF main body
CLIATLPE0029 8 M Raw material
sentCER
N A. FrenchS.A.
reference person
04/03/2011
CLIC experimental
flange
CLIAVACU0184
8(+72 in
AS +48 in RF dist.)
R
Prototypes received, control ongoing
15/03/2011
Kvis-gaar
dC. Garion
Ø 74Prototypes
to be manufactur
ed
17/2/2011
ON-OFF piston mock-up CLATLPE0028 8 M
Offers received
20/01/2011?
CERN A. French
J.M.G. reference
person
21/01/2011
ON-OFF plugCLIATLPE002
7 8 MOffers
received 20/01/2011
?CER
N A. FrenchJ.M.G.
reference person
21/01/2011
Parallel pin 5x20
CLIATLPE0049 32 R Ordered
23/02/201114/03/201
1 Chatel A. French
J.M.G. reference
person
04/03/2011
UHV CV fixed flange Ø202
CLIATLPE0017 4 R Ordered
23/02/201114/03/201
1 Lindenthal and Chatel A. French
J.M.G. reference
person
04/03/2011
PETS adapter disk 3
CLIATLPE0048 4 R
Offers received
20/01/2011?
CERN A. French
J.M.G. reference
person
21/01/2011
PETS adapter disk 2
CLIATLPE0020 4 R
Offers received
20/01/2011?
CERN A. French
J.M.G. reference
person
21/01/2011
PETS adapter disk 1
CLIATLPE0015 8 R
Offers received
20/01/2011?
CERN A. French
J.M.G. reference
person
21/01/2011
A.Bartalesi
RF systemPETS structure (2 of 3)
07/03/2011
Name Drawing #Quantit
y (2 TM0s)
Real or
Mock-
up?
StatusDeadline
for current status
FirmProcuremen
t Responsible
Comments
Last update in
this database
PETS beam pipe
CLIATLPE0021 4 R
Offers received
20/01/2011?
CERN A. French
J.M.G. reference
person
21/01/2011
DN 63 - UHV CF fixed flange
CLIATLPE0022 4 R To be
machinedDec 2010
CERN C. Garion Ø 114 26/11/201
0
PETS cooling adapter
CLIATLPE0030 16 R
Offers received
20/01/2011?
CERN A. French
J.M.G. reference
person
21/01/2011
Plug Ø14 CLIATLPE0043 16 R Ordered
23/02/201114/03/201
1 Chatel A. FrenchJ.M.G.
reference person
04/03/2011
PETS mock up bars
CLIATLPE0002 8 M Ordered Inflite A. French
04/03/2011
PETS damping block
CLIATLPE0007
64 MOrdered on 30/11/201
0
15/01/2011 M.P. A. French 13/12/201
0
PinCLIATLPE000
4 128 M Ordered Verejnoprospesne A. French
04/03/2011
Holder plateCLIATLPE000
3 64 MPrice inquiry
launched 28/10/2010
05/11/2010 B-S A. French
17/11/2010
VACOM MF-308 screw Commercial 128 R Vaco
m A. French17/11/201
0
Minitank tube CLIATLPE0009
4 RFabrication
to be launched
?CER
NA. French
J.M.G. reference
person
17/11/2010
Minitank tube (short)
CLIATLPE0051
4 RFabrication
to be launched
?CER
NA. French
J.M.G. reference
person
17/11/2010
A.Bartalesi
RF systemPETS structure (3 of 3)
07/03/2011
Name Drawing #Quantit
y (2 TM0s)
Real or
Mock-
up?
StatusDeadline
for current status
FirmProcuremen
t Responsible
Comments
Last update in
this database
Minitank flangeCLIATLPE001
0 16 ROffers
received 20/01/2011
05/11/2010
CERN A. French
Ø 120-124 J.M.G.
reference person
21/01/2011
TubeCLIATLPE001
1 8 R Ordered 23/02/2011
14/03/2011 Chatel A. French
J.M.G. reference
person
04/03/2011
UHV CF FIXED FLANGE Ø114-63-
60
STDVFUHV0092
8 (+16 in AS)
R To be machined
Dec 2010
CERN C. Garion
26/11/2010
PETS U-cooling tube
CLIATLPE0032
4 RFabrication
to be launched
05/11/2010
CERN
A. French 17/11/2010
Connector (Swagelok)
CommercialB-10M0-1-4RP
16 R Received Swagelok
A. French04/02/201
1
Copper gasket (Swagelok)
CommercialCU-4-RP-2
16 R Received Swagelok
A. French04/02/201
1
Target sphere holder 0.5”
CommercialBN223
32 R ReceivedBOSS-ARD
H. Mainaud-Durand
(Washer 8*16*2, glued on
pets)
10/01/2011
A.Bartalesi
RF distribution and loadsoverview
07/03/2011
Type 1 Type 2
Load Mock-up Load Mock-up
RF networks
A.Bartalesi 07/03/2011
A.Bartalesi 07/03/2011
A.Bartalesi
RF systemRF loads and distribution (1 of 3)
07/03/2011
Name Drawing #Quantit
y (2 TM0s)
Real or
Mock-
up?
StatusDeadline
for current status
FirmProcuremen
t Responsible
Comments
Last update in
this database
Nipple 1/4" CLIATLRF0026 80 ROrdered
01/02/2011
CERN/B.S./
Bodycote
A. FrenchCERN
contact person: A.
Costa
04/02/2011
Mock-up body CLIATLRF0028 40 MOrdered
01/02/2011
CERN/B.S./
Bodycote
A. FrenchCERN
contact person: A.
Costa
04/02/2011
Adapter 1 CLIATLRF0029 40 MOrdered
01/02/2011
CERN/B.S./
Bodycote
A. FrenchCERN
contact person: A.
Costa
04/02/2011
Adapter 2 CLIATLRF0030 40 MOrdered
01/02/2011
CERN/B.S./
Bodycote
A. FrenchCERN
contact person: A.
Costa
04/02/2011
Cooling case CLIATLRF0031 40 MOrdered
01/02/2011
CERN/B.S./
Bodycote
A. FrenchCERN
contact person: A.
Costa
04/02/2011
DN 40 - Fixed flange, tube 16/10
CLIATLRF0035 40 MOrdered
01/02/2011
CERN/B.S./
Bodycote
A. FrenchCERN
contact person: A.
Costa
04/02/2011
ConnectorCommercial
(B-8M0-1-4RP ) 40 M Received Swagelok
A. French04/02/201
1
ConnectorCommercial
(B-8M0-2-4PR ) 40 M Received Swagelok
A. French04/02/201
1
Copper gasketCommercial(CU-4-RP-2) 40 M Received Swagelo
kA. French
04/02/2011
CMF BELLOW - ASSEMBLY CLIATLRF0039 8 M 2D done A. French
04/02/2011
- WG_H90_BEND R11_01 CLIATLRF0040 8 M
Procuring launched
25/02/2011A. French
04/03/2011
A.Bartalesi
RF systemRF loads and distribution (2 of 3)
07/03/2011
Name Drawing #Quantit
y (2 TM0s)
Real or
Mock-
up?
StatusDeadline
for current status
FirmProcuremen
t Responsible
Comments
Last update in
this database
- WG_H90_BEND R11_02 CLIATLRF0041 8 M
Procuring launched
25/02/2011A. French
04/03/2011
RF NETWORK - HYBRID HALF 1 CLIATLRF0046 8 M
Procuring launched
25/02/2011A. French
04/03/2011
RF NETWORK - HYBRID HALF 2 CLIATLRF0047 8 M
Procuring launched
25/02/2011A. French
04/03/2011
RF NETWORK - SPLITTER BODY MOCK-
UPCLIATLRF0049 16 M
Procuring launched
25/02/2011A. French
04/03/2011
RF NETWORK - SPLITTER COVER CLIATLRF0057 16 M
Procuring launched
25/02/2011A. French
04/03/2011
RF NETWORK - WAVEGUIDE TYPE 1 HALF
1CLIATLRF0059 8 M
Procuring launched
25/02/2011A. French
04/03/2011
RF NETWORK - WAVEGUIDE TYPE 1 HALF
2CLIATLRF0060 8 M
Procuring launched
25/02/2011A. French
04/03/2011
RF NETWORK - WG REINFORCEMENT CLIATLRF0066 4 M
Procuring launched
25/02/2011A. French
04/03/2011
RF-NETWORK - WG TYPE 10
(BEND)CLIATLRF0069 32 M
Procuring launched
25/02/2011A. French 04/03/201
1
RF NETWORK - WG COOLING BAR TYPE
1CLIATLRF0070 4 M
Procuring launched
25/02/2011A. French 04/03/201
1
RF NETWORK - COOLING ADAPTER
CLIATLRF0071 16 MProcuring launched
25/02/2011A. French 04/03/201
1
RF NETWORK - WG COOLING BAR TYPE
2CLIATLRF0073 4 M
Procuring launched
25/02/2011A. French 04/03/201
1
A.Bartalesi
RF systemRF loads and distribution (3 of 3)
07/03/2011
Name Drawing #Quantit
y (2 TM0s)
Real or
Mock-
up?
StatusDeadline
for current status
FirmProcuremen
t Responsible
Comments
Last update in
this database
RF NETWORK - CMF (SINGLE PIECE) PART
1CLIATLRF0075 8 M
Procuring launched
25/02/2011A. French 04/03/201
1
RF NETWORK - CMF (SINGLE PIECE) PART
2CLIATLRF0076 8 M
Procuring launched
25/02/2011A. French 04/03/201
1
RF NETWORK - WG BENDING 1 CLIATLRF0077 4 M
Procuring launched
25/02/2011A. French
04/03/2011
RF NETWORK - WG BENDING 2 CLIATLRF0078 4 M
Procuring launched
25/02/2011A. French
04/03/2011
CLIC EXPERIMENTAL FLANGE CLIAVACU0185
48(+80 in
AS/PETS)R
Prototypes received, control ongoing
15/03/2011
Kvis-gaar
dC. Garion
Ø 74Prototypes
to be manufactur
ed
17/2/2011
A.Bartalesi
Vacuum systemoverview
07/03/2011
Type 1
Type 2
Central vacuum tank and pumps
Vacuum network
A.Bartalesi 07/03/2011
A.Bartalesi 07/03/2011
A.Bartalesi
Vacuum system (1 of 3)
07/03/2011
Name Drawing #Quantit
y (2 TM0s)
Real or
Mock-
up?
StatusDeadline
for current status
FirmProcuremen
t Responsible
Comments
Last update in
this database
Ion pumpCommercial
(Vaclon-plus75)
2 R On stock VARIAN C. Garion 19/01/2011
Cartridge pumpCommercial(SAES GP 500
MK5)4 R Received SAES C. Garion 19/01/201
1
CENTRAL VACUUM TANK BELLOW –
ASSEMBLY
CLIATLVS0031 24 R Ordered
Skodock C. Garion 17/2/2011
- DN 63 - UHV CF ROTAT. FLANGE HB
CLIATLVS0039 24 R
In fabrication
CERN C. Garion 17/2/2011
SCHCOCH END CAP 159,0 X 2.00
STANDARD(Acc. to DIN
28011)4 R
In fabrication C. Garion 17/2/2011
FIXED UHV FLANGE DIA. 70_FOR TUBE
DIA. 34/38
STDVFUHV0030 4 R
In fabrication
CERN C. Garion 17/2/2011
FIXED UHV FLANGE 152 - FOR TUBE
100/103
STDVFUHV0052 2 R
In fabrication
CERN C. Garion 17/2/2011
FIXED UHV FLANGE 114 - FOR TUBE
60/63
STDVFUHV0092 8 R
In fabrication
CERN C. Garion 17/2/2011
T0 CENTRAL VACUUM TANK - SPARE PUMPING
PORT TUBE
CLIATLVS0038 4 M
In fabrication
CERN C. Garion 17/2/2011
T0 CENTRAL VACUUM TANK -
RING TYPE 3
CLIATLVS0037 4 M
In fabrication
CERN C. Garion 17/2/2011
A.Bartalesi
Vacuum system (2 of 3)
07/03/2011
Name Drawing #Quantit
y (2 TM0s)
Real or
Mock-
up?
StatusDeadline
for current status
FirmProcuremen
t Responsible
Comments
Last update in
this database
T0 CENTRAL VACUUM TANK -
RING TYPE 2
CLIATLVS0036 2 M
In fabrication
CERN C. Garion 17/2/2011
T0 CENTRAL VACUUM TANK -
RING TYPE 1
CLIATLVS0034 8 M
In fabrication
CERN C. Garion 17/2/2011
CENTRAL VACUUM TANK - HOLDING
STRAP
CLIATLVS0033 8 M
In fabrication
CERN C. Garion 17/2/2011
T0 MODULE (LAB) VACUUM SYSTEM - CENTRAL VACUUM TANK EXTRUDED
TUBE
CLIATLVS0035 2 M
In fabrication
CERN C. Garion 17/2/2011
CLIC UHV RF gasket
CLIATLVS0005
80 R Ordered Jan 2010
GARL-OCK C. Garion
To be moved in RF
section, Ø 74
26/11/2010
“Helicoflex” Commercial 3 R OrderedJan
2010GARL-OCK C. Garion
26/11/2010
- MB INTERCONNECTION
BLANK FLANGE
CLIATLVS0032 2 M
CERN C. Garion
25/01/2011
UHV FLANGE_FIXED 202/150 SCEM 18.60.18.020.4
STDVFUHV0011 2 R
CERN C. Garion
25/01/2011
A.Bartalesi
Vacuum system (3 of 3)
07/03/2011
Name Drawing #Quantit
y (2 TM0s)
Real or
Mock-
up?
StatusDeadline
for current status
FirmProcuremen
t Responsible
Comments
Last update in
this database
VACUUM NETWORK - BELLOW
INTERFACE ASSY
CLIATLVS0026 16 M Ordered
Sko-dock C. Garion 17/2/2011
VACUUM NETWORK - DN 63 - ROTAT.
FLANGE 63.5/59.5
CLIATLVS0022 4 M To be
machinedMarch 2011
CERN C. Garion
03/02/2011
VACUUM NETWORK - TUBE
CLIATLVS0016 8 M In
fabricationApril 2011
CERN C. Garion
03/02/2011
VACUUM NETWORK - TUBE
CLIATLVS0017 8 M In
fabricationApril 2011
CERN C. Garion
03/02/2011
VACUUM NETWORK - COLLECTOR TUBE
STRAIGHT
CLIATLVS0018 2 M In
fabricationApril 2011
CERN C. Garion
03/02/2011
VACUUM NETWORK - COLLECTOR TUBE
- SECTION 1
CLIATLVS0019 2 M In
fabricationApril 2011
CERN C. Garion
03/02/2011
VACUUM NETWORK - COLLECTOR TUBE
- SECTION 2
CLIATLVS0020 2 M In
fabricationApril 2011
CERN C. Garion
03/02/2011
CAP DIAM. 64 mm
Commercial(FG INOX 2FB64)
4 R CERN
C. Garion 03/02/2011
A.Bartalesi
BI systemoverview
07/03/2011
Vacuum chamber
Rotating flange
BPM mockup
A.Bartalesi
BI System (1 of 2)(BPM-DBQ assembly)
07/03/2011
Name Drawing #Quantit
y (2 TM0s)
Real or
Mock-
up?
StatusDeadline
for current status
FirmProcuremen
t Responsible
Comments
Last update in
this database
UHV ROTATING FLANGE 114/63
insert
CLIATLVS0002
4 R
Raw ordered
(27/10/10), to be
machined
Dec 2010
CERN
C. Garion 26/11/2010
UHV flange ring 114/63
STDVFUHV0008 4 R Received
CERN C. Garion
26/11/2010
UHV ROTATING FLANGE
202/150 insert
CLIATLVS0001
4 R
Raw ordered
(27/10/10), to be
machined
Dec 2010
CERN
C. Garion 26/11/2010
UHV flange ring 202/150
CLIATLVS0003 4 R Received
CERN C. Garion
26/11/2010
Bellow(Ass.y
drawing) CLIATLBI0029
8 R Ordered Feb 2011
Sko-dock
C. Garion 17/02/2011
Welding fitting 1
(Ass.y drawing)
CLIATLBI00298 R Ordered
Feb 2011
Sko-dock C. Garion
Done by the
bellows manufactu
rer
17/02/2011
Welding fitting 2
(Ass.y drawing)
CLIATLBI00298 R Ordered
Feb 2011
Sko-dock C. Garion
Done by the
bellows manufactu
rer
17/02/2011
DB BEAM POSITION - MAGNET SYSTEM - BPM ALIGNMENT
FRAME
CLIATLBI0008 4 MProduction requested
15/02/2011
CERN (A.P.) L. Soby
20/01/2011
DB BPM ALIGNMENT - PIN
D4X10CLIATLBI0013 4 M
Production requested
15/02/2011
CERN (A.P.) L. Soby
20/01/2011
HEX SKT HD CAP Screw
M4x8
Commercial(VIS
CHC_M4x8)8 M Production
requested15/02/20
11CERN (A.P.) L. Soby 20/01/201
1
A.Bartalesi
BI System (2 of 2) (BPM-DBQ assembly)
07/03/2011
Name Drawing #Quantit
y (2 TM0s)
Real or
Mock-
up?
StatusDeadline
for current status
FirmProcuremen
t Responsible
Comments
Last update in
this database
DB BEAM POSITION - MAGNET SYSTEM -
DB BPM BODY MOCK-UP
CLIATLBI0024 4 MProductionrequested
15/02/2011
CERN (A.P.) L. Soby
20/01/2011
DB BPM MOCK-UP - INTERCONNECTION
INTERFACECLIATLBI0027 4 M
Productionrequested
15/02/2011
CERN (A.P.) L. Soby
20/01/2011
DB BPM MOCK-UP - DRIFT
TUBECLIATLBI0026 4 M Production
requested15/02/20
11CERN (A.P.) L. Soby 20/01/201
1
DB BPM MOCK-UP - DB BPM STRIPLINE
CLIATLBI0025 4 M Productionrequested
15/02/2011
CERN (A.P.) L. Soby 20/01/201
1
Target sphere holder 0.5”
Commercial Z04x06Ni-35
12 R Received HKCMH. Mainaud-
Durand
magnet Ø4,
length 6mm
10/01/2011
A.Bartalesi
Magnet systemoverview
07/03/2011
DBQ mock-up
A.Bartalesi
Magnet system (1 of 2)
07/03/2011
Name Drawing #Quantit
y (2 TM0s)
Real or
Mock-
up?
StatusDeadline
for current status
FirmProcuremen
t Responsible
Comments
Last update in
this database
DBQ magnet mock-up - yoke
CLIMQNBP0001 8+2 M
Mounting checked
CERN A. Bartalesi
01/03/2011
DBQ magnet mock-up - coil
mock-up
CLIMQNBP0002 32+8 M Mounting
checkedCER
NA. Bartalesi 01/03/201
1
DBQ magnet mock-up -
support angle
CLIMQNBP0003 4+1 M Mounting
checkedCER
NA. Bartalesi 01/03/201
1
DBQ magnet mock-up -
assembly shaft
CLIMQNBP0004 1 M Mounting
checkedCER
NA. Bartalesi 01/03/201
1
HEX SKT HD CAP SCREW
M8X65Commercial 64 R Mounting
checkedCER
NA. Bartalesi 01/03/201
1
HEX SKT HD CAP SCREW
M4X14Commercial 8 R Mounting
checkedCER
NA. Bartalesi 01/03/201
1
Normal PL washer 4X9 Commercial 8 R
Mounting checked
CERN A. Bartalesi
01/03/2011
HEX SKT HD CAP SCREW M10X100
Commercial 16 R Mounting checked
CERN
A. Bartalesi 01/03/2011
Normal PL washer 10X12 Commercial 32 R
Mounting checked
CERN A. Bartalesi
01/03/2011
HEX NUT STYLE1 GRADE
A M10Commercial 16 R Mounting
checkedCER
NA. Bartalesi 01/03/201
1
A.Bartalesi
Magnet system (2 of 2)
07/03/2011
Name Drawing #Quantit
y (2 TM0s)
Real or
Mock-
up?
StatusDeadline
for current status
FirmProcuremen
t Responsible
Comments
Last update in
this database
Target sphere holder 1.5”
glued on DBQ
Commercial1.5 SM-DN-3PS
24 R ReceivedLeica/Hubb
s
H. Mainaud-Durand
10/01/2011
Spherical prism 1.5’’
CommercialBMR-1.5-0.001
2 R ReceivedLeica/Hubb
s
H. Mainaud-Durand
10/01/2011
A.Bartalesi
Cooling system
07/03/2011
Name Drawing #Quantit
y (2 TM0s)
Real or
Mock-
up?
StatusDeadline
for current status
FirmProcuremen
t Responsible
Comments
Last update in
this database
Cooling system None 23D design
done ? Multiple A. French
29/10/2010
Rack commercial? ? ? ? ? A. French01/11/201
0
Acquisition commercial? ? ? ? ? A. French01/11/201
0
Cabling commercial? ? ? ? ? A. French01/11/201
0
A.Bartalesi
Supporting systemoverview
07/03/2011
DB(boostec)
MB(microcontrol
e)
Central vacuum tank support
A.Bartalesi 07/03/2011
A.Bartalesi
Supporting system (1 of 2)
07/03/2011
Name Drawing #Quantit
y (2 TM0s)
Real or
Mock-
up?
StatusDeadline
for current status
FirmProcuremen
t Responsible
Comments
Last update in
this database
DB girder withV-supports
CLIATLSS0005 2 R
Delivered &measured at
CERN
30/11/2010
Boostec N. Gazis
10/01/20110
DB cradle system
CLIGHGPA0001 3 R
2D drawings done, waiting
approval
15/11/2010
CERN N. Chritin
26/11/2010
MB girderCLIATLSS000
6 2 R
Delivered, measured &
assembled at CERN
3/12/2010
Micro-Control
eN. Gazis
10/12/2010
MB V-supportCLIATLSS000
6 10 R
Delivered, measured &
assembled at CERN
3/12/2010
Micro-control
eN. Gazis
10/12/2010
MB cradle system
CLIATLSS0006 3 R
Delivered, tested
& assembled at CERN
3/12/2010
Micro-Control
eN. Gazis
10/12/2010
U-clamps forV-support
CLIATLSS0011 44 R
Integration checked, FE
analysis finalized
17/12/2010
CERN N. Gazis
21/02/2011
DBQ supporting plate type 1
CLIATLSS0009 2 M Delivered 17/12/20
10CER
N N. Gazis03/02/201
1
DBQ supporting plate type 2
CLIATLSS0013 2 M Delivered 17/12/20
10CER
N N. Gazis03/02/201
1
- LEG CLIATLSS0015
4 RUnder price
inquiry
31/03/2011
CERN
N. Gazis 20/01/2011
- STIFFNESS RIB CLIATLSS0020
4 RUnder price
inquiry
31/03/2011
CERN
N. Gazis 20/01/2011
A.Bartalesi
Supporting system (2 of 2)
07/03/2011
Name Drawing #Quantit
y (2 TM0s)
Real or
Mock-
up?
StatusDeadline
for current status
FirmProcuremen
t Responsible
Comments
Last update in
this database
- STIFFNESS RIB CLIATLSS0016
12 RUnder price
inquiry
31/03/2011
CERN
N. Gazis 20/01/2011
- BOTTOM CLIATLSS0017
4 RUnder price
inquiry
31/03/2011
CERN
N. Gazis 20/01/2011
- CVT PLATE CLIATLSS0018
4 RUnder price
inquiry
31/03/2011
CERN
N. Gazis 20/01/2011
- SUPPORT CLIATLSS0019
4 RUnder price
inquiry
31/03/2011
CERN
N. Gazis 20/01/2011
THREADED ROD M20 X 160
Commercial 12 RUnder price
inquiry
31/03/2011
CERN
N. Gazis 20/01/2011
HEXAGON JAM NUT, M20; 0.5D
Commercial 36 RUnder price
inquiry
31/03/2011
CERN
N. Gazis 20/01/2011
FORME ‘D’ RONDELLE CONCAVE
Commercial 24 RUnder price
inquiry
31/03/2011
CERN
N. Gazis 20/01/2011
FORME ‘C’ RONDELLE CONCAVE
Commercial 24 RUnder price
inquiry
31/03/2011
CERN
N. Gazis 20/01/2011
NORMAL PL WASHER, 20 X
37Commercial 12 R
Under price
inquiry
31/03/2011
CERN
N. Gazis 20/01/2011
Metal V-supports for Epucret girder
with U-clamps integrated
12 RUnder Design
31/03/2011 NEW!
A.Bartalesi
Pre-alignment systemDB components only (1 of 2)
07/03/2011
Name Drawing #Quantit
y (2 TM0s)
Real or
Mock-
up?
StatusDeadline
for current status
FirmProcuremen
t Responsible
Comments
Last update in
this database
cWPS with 3D interface Commercial 5 R Ready F.N.
H. Mainaud-Durand
20/01/2011
cWPS interfaces Commercial 8 R Ready
M.S.N.
H. Mainaud-Durand
20/01/2011
oWPS Commercial 3 R Ready OSIH. Mainaud-
Durand20/01/201
1
oWPS interfaces Commercial 3 R Ready
H. Mainaud-Durand
20/01/2011
Inclinometer 1 axis
Commercial 3 RDelivered
(being tested)
Althen
H. Mainaud-Durand
20/01/2011
Temperature sensor
Commercial (PT100) 3 R Ready
H. Mainaud-Durand
20/01/2011
Linear actuator Commercial 9 R Received ZTSH. Mainaud-
Durand20/01/201
1
Base settlement interface
? 3 R Installed CERN
H. Mainaud-Durand
20/01/2011
Sensor plate ? 2 RDesign ready
30/11/2010
CERN
H. Mainaud-Durand
03/02/2011
Wire stretcher LHCGIWPS0189 2 R Ready
CERN
H. Mainaud-Durand
20/01/2011
Rack None 1 R ReadyCERN catalog
H. Mainaud-Durand
20/01/2011
A.Bartalesi
Pre-alignment systemDB components only (2 of 2)
07/03/2011
Name Drawing #Quantit
y (2 TM0s)
Real or
Mock-
up?
StatusDeadline
for current status
FirmProcuremen
t Responsible
Comments
Last update in
this database
Acquisition (SAS) None 1 R Ready
CERN
H. Mainaud-Durand
20/01/2011
MCA8 cable None 13 R ReadyCER
NH. Mainaud-
Durand20/01/201
1
Linear actuators cable None 5 R
Given to ZTS
CERN
H. Mainaud-Durand
20/01/2011
PC None 1 R ReadyCERN catalog
H. Mainaud-Durand
20/01/2011
Target sphere holder 1.5”
Commercial1.5 SM-DN-3PS
20 R ReceivedLeica/Hubb
s
H. Mainaud-Durand
Glued on DB girders
20/01/2011
Target sphere holder 1.5”
Commercial1.5 SMN-SS-25mm-6mm
10 R ReceivedLeica/Hubb
s
H. Mainaud-Durand
Fixed on DB girders
20/01/2011
A.Bartalesi
Pre-alignment systemMB components only (1 of 2)
07/03/2011
Name Drawing #Quantit
y (2 TM0s)
Real or
Mock-
up?
StatusDeadline
for current status
FirmProcuremen
t Responsible
Comments
Last update in
this database
cWPS with 3D interface Commercial 4 R Ready F.N.
H. Mainaud-Durand
20/01/2011
cWPS interfaces Commercial 7 R Ready
M.S.N.
H. Mainaud-Durand
20/01/2011
oWPS Commercial 3 R Ready OSIH. Mainaud-
Durand20/01/201
1
oWPS interfaces Commercial 3 R Ready
H. Mainaud-Durand
20/01/2011
Inclinometer 1 axis Commercial 3 R Received
Althen
H. Mainaud-Durand
20/01/2011
Temperature sensor
Commercial (PT100) 3 R Ready
H. Mainaud-Durand
20/01/2011
Sensor interface with
girderCERN 4 R Ready CER
NH. Mainaud-
Durand20/01/201
1
Base settlement interface
CERN 3 R Installed CERN
H. Mainaud-Durand
20/01/2011
Sensor plate CERN 2 R ReadyCER
NH. Mainaud-
Durand20/01/201
1
Wire stretcher LHCGIWPS0189 2 R Ready
CERN
H. Mainaud-Durand
20/01/2011
Rack None 1 R ReadyCERN catalog
H. Mainaud-Durand
20/01/2011
A.Bartalesi
Pre-alignment systemMB components only (2 of 2)
07/03/2011
Name Drawing #Quantit
y (2 TM0s)
Real or
Mock-
up?
StatusDeadline
for current status
FirmProcuremen
t Responsible
Comments
Last update in
this database
Acquisition (SAS) None 1 R Ready
CERN
H. Mainaud-Durand
20/01/2011
MCA8 cable None 13 R ReadyCER
NH. Mainaud-
Durand20/01/201
1
Target sphere holder 1.5”
Commercial1.5 SM-DN-3PS
14 R ReceivedLeica/Hubb
s
H. Mainaud-Durand
Glued on MB girders
20/01/2011
Target sphere holder 1.5”
Commercial1.5 SMN-SS-25mm-6mm
8 R ReceivedLeica/Hubb
s
H. Mainaud-Durand
Fixed on sensor
interface with
girders
20/01/2011
A.Bartalesi 07/03/2011
Thanks for you attention-and-
Thanks to all the procurement responsible people for their
precious help!