Assembly and installation of TM0 Lab. F. Rossi. February 8th, 2012. MAGNETS & VACUUM TANKS. 4 DBQ (for 2 TM0) Installation on girders -> COMPLETED Alignment -> COMPLETED 2 VACUUM TANKS (for 2 TM0) Installation on girders -> COMPLETED. PETS UNITS. 2 PETS units (for 1st TM0) - PowerPoint PPT Presentation
Citation preview
1 Assembly and installation of T0 module Lab
Assembly and installation of TM0 Lab
F. Rossi
February 8th, 2012
2 Assembly and installation of T0 module Lab
MAGNETS & VACUUM TANKS4 DBQ (for 2 TM0)
• Installation on girders -> COMPLETED• Alignment -> COMPLETED
2 VACUUM TANKS (for 2 TM0)
• Installation on girders -> COMPLETED
3 Assembly and installation of T0 module Lab
PETS UNITS2 PETS units (for 1st TM0)
• Final brazing -> COMPLETED• Vacuum test -> COMPLETED• Fiducialisation -> COMPLETED• EBW -> COMPLETED• Vacuum test -> COMPLETED• Final dimensional control on Leitz -> COMPLETED• Installation on girders -> COMPLETED
STATUS: 100%
4 Assembly and installation of T0 module Lab
AS
# STEP1st TM0
1st half 2nd half
1st AS 2nd AS 3rd AS 4th AS 1st AS 2nd AS 3rd AS 4th AS
1 Delivery V V V V V V V V
2 Cleaning V V V V V V V V
3 Brazing WFM and disk stacks V V V V W07 W07 W07 W07
4 Machining WFM V V V V W08 W08 W08 W08
5 Cleaning WFM V V V V W08 W08 W08 W08
6 Cooling circuit test of disk stacks V V V V W09 W09 W09 W09
7 Brazing manifolds (1st) V V V V W10 W10 W10 W10
8 Brazing manifolds (2nd) V V V V W10 W10 W10 W10
9 Machining manifolds V V V V W11 W11 W11 W11
10 Brazing AS (1st) V V W07 W07 W12 W12 W12 W12
11 Brazing AS (2nd) V V W08 W08 W12 W12 W12 W12
12 Brazing small covers W07 W07 W08 W08 W12 W12 W12 W12
13 Vacuum test of AS W08 W08 W08 W08 W12 W12 W12 W12
14 Brazing super AS W09 W09 W13 W13
15 Brazing 1 stack W10 W14
16 Vacuum test of stacks W10 W14
17 Cooling circuit test of stacks W10 W14
18 Fiducialisation W11 W15
19 EBW 2 stacks W16
20 TIG welding vacuum flanges W16
21 Vacuum test of MB W16
22 Installation on girders W17
5 Assembly and installation of T0 module Lab
RF NETWORK & COMPACT LOAD2+2 RF networks (for 1 TM0)• Cleaning -> COMPLETED• 1st brazing -> COMPLETED• Intermediate machining -> COMPLETED• Cleaning -> COMPLETED• 2nd brazing -> COMPLETED• 3rd brazing -> IN PROGRESS• Vacuum test
STATUS: 80%
20 Compact loads (for 1 TM0)• Final brazing -> COMPLETED• Vacuum test -> COMPLETED
STATUS: 100%
Vacuum network (for 2 TM0)• Delivery to Lab -> COMPLETED
STATUS: 100%
6 Assembly and installation of T0 module Lab
SUMMARY
SUB-ASSEMBLY Q.TY STATUS
Magnets 2 100%
Vacuum tank 1 100%
PETS units 2 100%
AS 8 30%
Clamps for AS and PETS 100%
RF network 2+2 80%
Compact load 20 100%
Vacuum network 4 100%
Extremity flanges 1+1 100%
Supports for extremity flanges 2 100%
Cooling circuits under manufacturing
Gaskets, blank flanges, screws, swagelok under procurement
1st TM0
7 Assembly and installation of T0 module Lab
SUMMARY
SUB-ASSEMBLY Q.TY STATUS
Magnets 2 100%
Vacuum tank 1 100%
PETS units 2 30%
AS 8 under manufacturing
Clamps for AS and PETS 100%
RF network 2+2 70%
Compact load 20 70%
Vacuum network 4 100%
Extremity flanges 1+1 100%
Supports for extremity flanges 2 100%
Cooling circuits under manufacturing
Gaskets, blank flanges, screws, swagelok under procurement