23
1 Fulvio TESSAROTTO the new RICH beam pipe - pipe production, gluing and tests - measurement and removal of the old pipe - fixation system - installation of the new pipe - characteristics of the new pipe COMPASS TB meeting, CERN, 12/04/2012 Fulvio Tessarotto

the new RICH beam pipe

  • Upload
    janina

  • View
    71

  • Download
    0

Embed Size (px)

DESCRIPTION

the new RICH beam pipe. Fulvio Tessarotto. - pipe production, gluing and tests - measurement and removal of the old pipe - fixation system - installation of the new pipe - characteristics of the new pipe. Slide from the last TB:. Issue status - PowerPoint PPT Presentation

Citation preview

Page 1: the new RICH beam pipe

1Fulvio TESSAROTTO

the new RICH beam pipe

- pipe production, gluing and tests

- measurement and removal of the old pipe

- fixation system

- installation of the new pipe - characteristics of the new pipe

COMPASS TB meeting, CERN, 12/04/2012

Fulvio Tessarotto

Page 2: the new RICH beam pipe

2Fulvio TESSAROTTO COMPASS TB meeting, CERN, 02/02/2012

Slide from the last TB:Issue status

Removal of presently used pipe Extremely difficult behind the mirrors

Material for the thin pipe 5 layer aluminized Mylar, 0.6 ‰ X

Geometry 2 pipes 100 mm diam., 1570 mm long

Gas He, few l/h, 15 mbar overpressure

End caps alum. Mylar glued on Al microflanges

Fixation system Thin stainless steel wire ropes Extremely difficult behind the mirror wall: still to be defined

Page 3: the new RICH beam pipe

3Fulvio TESSAROTTO COMPASS TB meeting, CERN, 12/04/2012

tubes, microflanges, gluing tests

weight = 15 g

Page 4: the new RICH beam pipe

4Fulvio TESSAROTTO

Simulations for the new pipe

max = 0.1 Mpa,yield strength = 85 MPaCOMPASS TB meeting, CERN, 12/04/2012

Page 5: the new RICH beam pipe

5Fulvio TESSAROTTO COMPASS TB meeting, CERN, 12/04/2012

half-pipe He leak testsMeasured leak, including connections: 0.5 ml/h

Page 6: the new RICH beam pipe

6Fulvio TESSAROTTO

“Safety is the first of our priorities”

- RICH is a “confined space”: access is allowed to authorized persons only- Authorization requires a confined space formation course and a medical certification- New procedure: CERN asks for medical certification to be provided by the Institutes.

- Inside the RICH we needed a scaffolding: the old scaffolding is not complying to the rules.- The new scaffolding can only be mounted by authorized people.- The authorisation requires ….

1) a general CERN confined space course was organized and people sent to attend it 2) a medical check and certification protocol was defined, agreed upon and applied in Trieste 3) the activity inside the RICH was defined in detail and an access protocol was produced 4) the supervisor was changed 5) special exception to allow access for radioprotection experts, scaffolding responsible, etc. 6) a scaffolding was borrowed / built and certified by the responsible in Clean Area 7) authorization to mount the scaffolding by ourselves was obtained 8) authorization to use the scaffolding (after check) with a use protocol was provided 9) … 10) …All involved persons have been extremely collaborative!

Firenze, 22/03/2012

Page 7: the new RICH beam pipe

7Fulvio TESSAROTTO

RICH opening, old pipe removal1) Radiation level: < 0.2 μSv/h2) Surveying of the old pipe3) Large scaffolding installation4) Small scaffolding installation5) Removal of the old pipe4) Mirrors surveying

COMPASS TB meeting, CERN, 12/04/2012

Page 8: the new RICH beam pipe

8Fulvio TESSAROTTO

After the removal of the old pipe - We confirmed it is not possible to access the area downstream of the mirrors

- We decided to change the fixation system and the gas pipes to reduce the material

1) We prepared two beam pipes of 1.6 m and tested them: measured leak rate: 0.5 ml/h 2) We decided to produce a unique pipe by gluing two halves on 1.6 m 3) The vertical middle gluing needed a special microflange and a system for vertical operation 4) We continued to put pressure on Lamina, despite the denials, to try producing a 3.2 m tube 5) One 3.5 m long tube arrived in Trieste just in time. 6) The microflanges and the system for gluing were ready: the long pipe was glued and 7) Tested together with the “Tygon” pipes and plastic strips for gas connection: 0.6 ml/h 8) Both long pipes (single piece and two-halves shipped to CERN) 9) We checked that two suspensions are enough (pipe rigidity better than expected) Two fixation points are enough

COMPASS TB meeting, CERN, 12/04/2012

Page 9: the new RICH beam pipe

9Fulvio TESSAROTTO COMPASS TB meeting, CERN, 12/04/2012

gluing end-caps on the single pipe

Page 10: the new RICH beam pipe

10Fulvio TESSAROTTO COMPASS TB meeting, CERN, 12/04/2012

Careful packaging

Page 11: the new RICH beam pipe

11Fulvio TESSAROTTO COMPASS TB meeting, CERN, 12/04/2012

And transport

Page 12: the new RICH beam pipe

12Fulvio TESSAROTTO

Preparation for the new pipe10) Putting in place the top fixation systems was challenging but successful11) Dummy flanges positioned using a laser system12) Pipe introduced in the RICH and put in place13) Surveying to check the position found several millimeter offsets14) Position partially corrected and fixation system tensioned at 2 kg

COMPASS TB meeting, CERN, 12/04/2012

Page 13: the new RICH beam pipe

13Fulvio TESSAROTTO COMPASS TB meeting, CERN, 12/04/2012

Pre-alignment of pipe holders

Page 14: the new RICH beam pipe

14Fulvio TESSAROTTO COMPASS TB meeting, CERN, 12/04/2012

the new pipe inside the RICH

Page 15: the new RICH beam pipe

15Fulvio TESSAROTTO COMPASS TB meeting, CERN, 12/04/2012

The polycarbonate suspension ring

Page 16: the new RICH beam pipe

16Fulvio TESSAROTTO COMPASS TB meeting, CERN, 12/04/2012

Page 17: the new RICH beam pipe

17Fulvio TESSAROTTO COMPASS TB meeting, CERN, 12/04/2012

New fixation system and gas pipes

Page 18: the new RICH beam pipe

18Fulvio TESSAROTTO COMPASS TB meeting, CERN, 12/04/2012

Pipe specificationsInner diameter: 100.0 mm (+0.0-0.1)Thickness: 140 μm Length: 3140 mmMaterial: Mylar (PET) + 1 μm Al

Single pipe, front and rear window:same material: 140 μm Mylar + 1 μm AlMicroflanges: “F” shape Al, 0.5 mm thick

Upstream microflange acts as holder,Downstream holder at 80 cm from edge,Policarbonate 8mm x 8mm + 2 nylon screws

Fixation via stainless steel microwire ropes:4 ropes (90 degrees) per holder,1 x 7 wires 90 μm diam. (limit = 9 kg)+ 10 μm nylon coating, tensioning: 2 kg,thermal expansion +- 2 mm, equiv. 1 kg

Adjustement and tensioning microsystems placed out of the acceptance

Page 19: the new RICH beam pipe

19Fulvio TESSAROTTO COMPASS TB meeting, CERN, 12/04/2012

Upstream fixation and gas connections

Total amount of materialin the acceptance:

Fe (8 m microwire ropes): 5 gAl ( 2 m pipe + microfl.): 60 gMylar: 180 gPolycarbonate (fixation): 20 gEpoxy: 6 gCu: 0.5 gTygon: 5 gNylon: 4 g

Old gas pipes: 6x4 mm stainless steel tubes, new pipes: 6x5 mmAl pipes (10 times less X0)

Page 20: the new RICH beam pipe

20Fulvio TESSAROTTO COMPASS TB meeting, CERN, 12/04/2012

Measurement and adjustment

Page 21: the new RICH beam pipe

21Fulvio TESSAROTTO COMPASS TB meeting, CERN, 12/04/2012

position regulation and surveying

Page 22: the new RICH beam pipe

22Fulvio TESSAROTTO COMPASS TB meeting, CERN, 12/04/2012

Material budgetactual pipe material budget: (0.15 mm / 17.6 mm) 8.523 ‰ X0

goal for the material budget of the new pipe: 10% actual = 0.852 ‰ X0

5 layers of 27 μm thick Mylar : (0.135 mm / 287 mm) 0.470 ‰ X0

5 layers of 200 nm thick Al coating: (1.0 μm / 89 mm) 0.011 ‰ X0

4 layers of 6 μm thick Mylar glue: (24 μm / 280 mm) 0.086 ‰ X0

-----------------------------------------------------------------------------------------------------------total material budget for orthogonal crossing: 0.567 ‰ X0

total material budget for parallel crossing (r < 42 mm): 2.26 ‰ X0

parallel crossing (42 mm < r < 49 mm): 1.9 % X0

6 mrad particle crossing the pipe (old value = 1.4 X0) 9 % X0

The contribution from end caps, fixation rings, gas connections has been minimized

Page 23: the new RICH beam pipe

23Fulvio TESSAROTTO COMPASS TB meeting, CERN, 02/02/2012

time schedule

RICH opening February 21Scaffolding mounted February 24Old pipe measurement March 6Removal of the old pipe March 7Mirror measurement March 16Installation of the new pipe April 5He leak test April 17Scaffolding dismounting April 18RICH closing April 19 or April 25