AFP-HPS 240 15/03/2011 1 D. D. INFN To/CERN PH UCM HPS240. Integration of Moving Beam Pipe and detector box. 1. Re-collection Layout of moving beam pipe on New connection Cryostat 2. Beam Vacuum requirements 3. FP420 Beam Pipe design 4. New single window Beam pipe for HPS 5. Beam Position monitor integration on BP 6. Si tracker package 7. Detector box 8. Bellows 9. Motorization 10.HPS Prototype Work Package Torino ( Mechanics)

HPS240. Integration of Moving Beam Pipe and detector box

  • Upload
    tayten

  • View
    105

  • Download
    3

Embed Size (px)

DESCRIPTION

HPS240. Integration of Moving Beam Pipe and detector box. Re-collection Layout of moving beam pipe on New connection Cryostat Beam Vacuum requirements FP420 Beam Pipe design New single window Beam pipe for HPS Beam Position monitor integration on BP Si tracker package Detector box - PowerPoint PPT Presentation

Citation preview

Page 1: HPS240. Integration of Moving Beam Pipe and detector box

AFP-HPS 240 15/03/2011 1D. D. INFN To/CERN PH UCM

HPS240. Integration of Moving Beam Pipe and detector box.

1. Re-collection Layout of moving beam pipe on New connection Cryostat

2. Beam Vacuum requirements3. FP420 Beam Pipe design 4. New single window Beam pipe for HPS5. Beam Position monitor integration on BP6. Si tracker package7. Detector box8. Bellows9. Motorization10. HPS Prototype Work Package Torino ( Mechanics)

Page 2: HPS240. Integration of Moving Beam Pipe and detector box

AFP-HPS 240 15/03/2011 2D. D. INFN To/CERN PH UCM

Layout

Page 3: HPS240. Integration of Moving Beam Pipe and detector box

AFP-HPS 240 15/03/2011 3D. D. INFN To/CERN PH UCM

Page 4: HPS240. Integration of Moving Beam Pipe and detector box

AFP-HPS 240 15/03/2011 4D. D. INFN To/CERN PH UCM

Page 5: HPS240. Integration of Moving Beam Pipe and detector box

AFP-HPS 240 15/03/2011 5D. D. INFN To/CERN PH UCM

FP420 Moveable Beam Pipe Integration in New connection Cryostat

Page 6: HPS240. Integration of Moving Beam Pipe and detector box

AFP-HPS 240 15/03/2011 6D. D. INFN To/CERN PH UCM

FP420 Moveable Beam Pipe on support table.

Page 7: HPS240. Integration of Moving Beam Pipe and detector box

AFP-HPS 240 15/03/2011 7D. D. INFN To/CERN PH UCM

BEAM VACUUM REQUIREMENTS

High conductivity copper internal coating, tapered

angle< 15.

Need close collaboration with CERN RF and AT/VAC experts

Mandatory discussion on material and design from very early stage of conception.

Page 8: HPS240. Integration of Moving Beam Pipe and detector box

AFP-HPS 240 15/03/2011 8D. D. INFN To/CERN PH UCM

Page 9: HPS240. Integration of Moving Beam Pipe and detector box

AFP-HPS 240 15/03/2011 9D. D. INFN To/CERN PH UCM

Coutesy of UC Louvain F.Benoit , K.Piotrzkowski

• Latest Prototype realized.

Two pockets are now laser welded.

FP 420 Beam Pipe (UC Louvain)

Page 10: HPS240. Integration of Moving Beam Pipe and detector box

AFP-HPS 240 15/03/2011 10D. D. INFN To/CERN PH UCM

HPS 240 Beam Pipe. Torino Proposal

• Single thin window. Length 450mm.• Machined by Wire Electro erosion from SS 316 LN solid bar.• Present design of thin windows similar (20x20mm) to FP420 BP.

Details to be discussed with CERN groups .• Beam Position Monitor integrated by laser welding.

STATUS: Material from CERN Store (following AT/VAC specification) already delivered in Torino mech. Workshop.Update design of thin windows, Flanges and BPM interface.FE Analysis.Validation .WEDM Machine available from mid April.

Page 11: HPS240. Integration of Moving Beam Pipe and detector box

AFP-HPS 240 15/03/2011 11D. D. INFN To/CERN PH UCM

HPS Beam pipe design –DRAFT-- 1

Page 12: HPS240. Integration of Moving Beam Pipe and detector box

AFP-HPS 240 15/03/2011 12D. D. INFN To/CERN PH UCM

HPS Beam pipe design –DRAFT-- 2

Page 13: HPS240. Integration of Moving Beam Pipe and detector box

AFP-HPS 240 15/03/2011 13D. D. INFN To/CERN PH UCM

HPS Beam pipe design –DRAFT-- 2 det.

Page 14: HPS240. Integration of Moving Beam Pipe and detector box

AFP-HPS 240 15/03/2011 14D. D. INFN To/CERN PH UCM

Courtesy Ray Thompson and Manchester Group.

Si detector package. Layout for FP420. Manchester group.

TO DO:Silicon board design to be defined.Design. To be adapted to HPS240.

Cooling still to be defined and integrated

Page 15: HPS240. Integration of Moving Beam Pipe and detector box

AFP-HPS 240 15/03/2011 15D. D. INFN To/CERN PH UCM

Silicon 3d mounting proposal (FP420)

Conical seat

Flat seat

V groove seat

Synthetics ruby balls

Carbon bearing system

Carbon blades support on cap and synthetics ruby balls fixed on detector frame.

Components act as reference system and thermal insulator.Cooling feedthroughs

Electrical feedthroughs

Page 16: HPS240. Integration of Moving Beam Pipe and detector box

AFP-HPS 240 15/03/2011 16D. D. INFN To/CERN PH UCM

Detector Box V2---DRAFT--This New Detector Box host Quartic or Gastof and Silicon Tracker.Internal dimensions are: 230 x 510 x 125 (mm)The enclosed volume is vacuum tight (secondary vacuum).Definition of detector dimension , required services and feed trough is to be defined.

Page 17: HPS240. Integration of Moving Beam Pipe and detector box

AFP-HPS 240 15/03/2011 17D. D. INFN To/CERN PH UCM

BELLOWS

Page 18: HPS240. Integration of Moving Beam Pipe and detector box

AFP-HPS 240 15/03/2011 18D. D. INFN To/CERN PH UCM

Specification:• Stainless steel AISI 316L or AISI 316Ti.• Vacuum tight.• Bake out to 250 C• Lateral offset +/- 31mm• Quantity 16 pcs.• Life cycle expectancy >>10.000 cycles

Bellows with intermediate tube allows extensive lateral movements minimizing stress.

In this studio diameter is over dimensioned, D=107,4mm, to allows integration of RF screen.

In case RF screen result not necessary, internal diameter can be reduced to 96mm; 93mm; or 85mm.

Bellows Studio. Witzenmann Standard corrugated tube. (CERN Supplier)

RF screen to shield the bellows from the beam?• Develop design in close collaboration

with AT/VAC.• Validate and finalize design and

manufacture to realize a prototype for tests.

INFN To

Page 19: HPS240. Integration of Moving Beam Pipe and detector box

AFP-HPS 240 15/03/2011 19D. D. INFN To/CERN PH UCM

Motor and controls hardware (lvdt, stops) are assumed to be the same of collimators.

Nevertheless some aspect are not yet clear. Auto retraction in garage position in case of hardware or control failure may require feature not compatible with the present layout.

A preliminary risk analysis is necessary to assess the validity of adopted solution.

Motorization and controls.

Page 20: HPS240. Integration of Moving Beam Pipe and detector box

AFP-HPS 240 15/03/2011 20D. D. INFN To/CERN PH UCM

Beam Position Monitor on Moveable Beam Pipe.The Beam Position Monitor on the Moveable Beam Pipe Station is now integrated on the Beam Pipe.In the figure a body of BPM used in LHC beam instrumentation is adapted. This body has been suggested as the most likely adaptable to our scope (FP420).Finalization of Beam Pipe design require also definition of this component. We need to re-establish contact in BE/AT group .

Page 21: HPS240. Integration of Moving Beam Pipe and detector box

AFP-HPS 240 15/03/2011 21D. D. INFN To/CERN PH UCM

INFN Torino Prototype WP’s Collaboration..

INFN Torino group is involved from the very preliminary (2005) R&D studies of feasibility on FP420.

We can offer collaboration on integration, engineering, design, manufacture, dimensional controls, assembly and installation of moving beam pipe and Si detector package. In particular concerning the realization of a complete prototype for HPS 240, we can take care to design and manufacture a new beam pipe with detector box, body of Beam position monitor, interfaces for motorization and supporting table.

Page 22: HPS240. Integration of Moving Beam Pipe and detector box

AFP-HPS 240 15/03/2011 22D. D. INFN To/CERN PH UCM

• Integration of various components still need effort to be effectively defined.

• Close collaboration with CERN group is mandatory and necessary to finalize the design.

• Collaboration with AFP would be very useful

• In Torino we can start production of aprototype beam pipe from April. Still many detail need to be agreed and finalized .

• Thanks.

Conclusion.

Page 23: HPS240. Integration of Moving Beam Pipe and detector box

AFP-HPS 240 15/03/2011 23D. D. INFN To/CERN PH UCM

Wire electrical discharge machining (WEDM)

Some of the advantages of EDM :Complex and high precision shapes that would otherwise be difficult to produce with conventional cutting toolsWire-cutting EDM is commonly used when low residual stresses are desired.There is no direct contact between tool and work piece. Therefore delicate sections and weak materials can be machined without any distortion.A good surface finish can be obtained.

This WEDM will be delivered in Torino Mech. Workshop by end of March.

Max. Workpiece dimension: 1050 x 500 x 600 (mm)

Page 24: HPS240. Integration of Moving Beam Pipe and detector box

AFP-HPS 240 15/03/2011 24D. D. INFN To/CERN PH UCM

Coordinate Measuring Machine (CMM)

Poli Galaxy Maxi CMMMaterial: Granite Construction Capacity (mm) : X 2300; Y 1200 ; Z 1000. Accuracy: 0.005 mmSoftware: DEA PC-DMIS ®

Mitutoyo CRT Apex C574Material: Granite Construction Capacity (mm) : X 505; Y 705 ; Z 405. Accuracy: 0.001 mmSoftware: DEA PC-DMIS ®

ZEISS Accura II (INFN PD)Material: Granite Construction Capacity (mm) : X 1200; Y 900 ; Z 700. Accuracy: 0.002 mmSoftware: Calypso

Equipped with Active Extension Stylus