Upload
lytu
View
217
Download
4
Embed Size (px)
Citation preview
The Deepwater HorizonBlowout and Oil SpillBlowout and Oil Spill
T A&M U i itTexas A&M UniversityPETE Graduate Seminar
September 28, 2010
1Sources: Congressional testimony, Internet (theoildrum.com), Newspapers (WSJ), Magazines, TV, DOE, BP
Dynamically positioned
Size: 396 ft by 256 ft
Cost: US$ 560 million
2
The Deepwater Horizon semisubmersible in transitThe USS Cole – Yemen - Oct. 2000
The Deepwater Horizonp
5th G ti D t Ri5th Generation Deepwater Rig
Capable of operating in 10,000 ft of water
15,000 psi BOP Stack
Built in 2001
BP operating cost~ $1,000,000 per day
3
The BlowoutOn April 20, 2010, large quantities of hydrocarbons escaped from BP’s Macondo #1 well in the Gulf ofescaped from BP s Macondo #1 well in the Gulf of Mexico.
Multiple explosions and a fire resulted. 11 lives were lost and 17 others were injured.
The fire, continued for 36 hours until the rig sank.
Hydrocarbons continued to flow for 87 days causing millions of barrels of oil to spill into the Gulf.p
4
5The Deepwater Horizon on fire – April 21, 2010
Ri k ORig sank On April 22, 2010
View one oJune 20, 2010
6
Rotary drilling BASICS
In the openholeIn the openhole section
(no casing)
pmud > ppore
dand
pmud < pfracture} OPENHOLE
( p = pressure)} OPENHOLE SECTION
Well Casing
What is casing? Casingg
Steel pipe placed inside the wellbore
Wh i / t?
Cementinside the wellbore
Why run casing/cement?
• To prevent the hole from caving inTo prevent the hole from caving in
• To prevent vertical migration of fluids outside the casing
8
Halliburton d drecommended
21 centralizers
BP installed 6!!
9
Centralizer
Bow Spring type
10
11BP did not run a cement bond log
Casing Design OptionsRIG
DRILLINGRISER
STEP 1 STEP 2STEP 1 STEP 2
DRILLINGRISER
WELLHEAD
BOP STEP 1 STEP 2STEP 1 STEP 2
BOPWELLHEAD
12The Long String The Liner and Tieback
13
The Drilling Riser
14
Subsea BOP Stack Subsea BOP System
Operatedby
PressurizedPressurizedHydraulic
Fluid
1512’x12’x80’700,000 pounds
16
Ram Blowout Preventer
SHEAR / BLINDRAM ASSEMBLYRAM ASSEMBLY
17Ram Blowout Preventer - cont’d
ShearShear Rams
DrillPipe Only
Two Pipes?
18
Hydraulic fluid?
What Happened?
9 7/8”
SEAL
LEAK?
9 /8CASING
7” CASING
19
CEMENT
Circulate Bottoms up - N2 - Gas
What Happened?
SEAL? SEAL was set, but not locked down
LEAK?
9 7/8” CASINGPositive Pressure Test - OK
Negative pressure tests - ??
7” CASING
Negative pressure tests - ??
No Cement Plug was setPrior to displacing7 CASING Prior to displacing
mud with water
No Float Valve in Casing Shoe?
20
CEMENT THE WELL KICKED –BIG TIME
What is a KICK ?
An unscheduled entry
of formation fluidsof formation fluids
into the wellbore
What happens if a kick
is not caught early
and is not controlled properly?
21
What happens if a kickWhat happens if a kick is not controlled?
BLOWOUT !!!BLOWOUT !!!
22
The Macondo Well D t R dData Record
(last two hours)
FOUR independent kick indicators
• Mud flow into and out of the well
• Mud volume in the surface pits
• Hook load
• Bottom-hole pressureBottom hole pressure
Data recorded on the rig and ti l t t H t
23
continuously sent to Houston
Oil and Gas Flows
G
120,000,000 scf/dayOil Oil
Gasmethane +
Methane Dissolves
Hydrates Bio – degradation
Solubility ?
yd atesDissolve
Oil and Gas Methane
RISER
Dispersants Hydrate Formation
24
GAS: 90,000 bbl/dayBOP OIL: 40,000 bbl/day
Containment dome
~ 40’ height~ 40 height~ 100,000 pounds
Gas Hydrates
IncreasedIncreased Buoyancy
Pl iPlugging
Gas!
25
I ti T bInsertion TubeRISER INSERTION TUBE
26
The Top Kill
Acknowledgements.tifg
27
Top Hat
Acknowledgements.tifg
28
The New BOP that stopped the flowTotal Height = 30 ft ppgWeight = 165,000 lbs
29
Relief WellsThe ultimate solution!
Well #1 - Started May 2Reach near bottom inReach near bottom in
late July
Well #2Well #2Started May 22
Expert in charge had killed 40 blowouts!
30
(40 out of 40)
D th J l 5
31
Depth on July 5:17,725 ft
Possible Problems
Did not Circulate bottoms up prior to pumping cement
Installed 6 Centralizers on the Casing instead of 21
Used Long Casing String instead of Liner and Tieback
Did not Run Cement Bond Log
Did not Secure Seal at top of Casing
Performed questionable Negative Pressure Tests
Removed mud from the hole before setting cement plug
Did not pay close attention to KICK Indicators
Did not make sure BOP was thoroughly tested as needed
32
US OIL - Supply and Demand
20 millionbarrels/day
Imports Onshore
USProduction Deep Water
33
ProductionShallow Water
The BP Macondo Well:
Oil production ~ 40,000 barrels/day (rough estimate)
about 0.6% of total US oil production
Gas Production 120 000 000 standard cubicGas Production ~ 120,000,000 standard cubic feet of gas per day
The average US oil well produces ~ 10 barrels of oil per day. y
This is why we drill offshore in deep water!
34
This is why we drill offshore in deep water!
Saudi Arabia ~5,000 b/d
Oil Flow Rate
Estimated or Calculated flow rate:Estimated or Calculated flow rate:
From 1,000 barrels/day to 60,000 barrels/day
Captured and Measured flow rate:
/ /From 0 barrels/day to 25,000 barrels/day
Pl d C t C itPlanned Capture Capacity:
From 60,000 to 80,000 barrels/day
35Actual Oil Production Rate?
Calculating Flow Rate
Flow Velocity = 4 ft/sec
Flow Area (20” dia) ~ 2.2 sq. ft
Flow Rate = 8.8 cu.ft / sec ~ = 130,000 bbl / day
Assume gas/oil ratio (GOR) = 3,000 scf / bbl
S fl 150 t h ( pV = znRT )Seafloor pressure ~ = 150 atmospheres
GOR at seafloor = 3,000/150 * 0.68 * 500/530
= 13 cu.ft / bbl = 2.3 bbl of gas / bbl of oil
( pV = znRT )
g
Oil flow rate = 40 000 bbl/dayOil flow rate 40,000 bbl/day
Gas flow rate = 90,000 b/d (seafloor)
Now What?
On July 15 the well was closed in by closing the y y gvalves on the new BOP that was sitting on top of the old one.
On September 18, the relief well was used to finally plug the well by pumping lots of cement around the bottom of the well – the so-called “Bottom Kill.” Well declared dead on Sept. 19.
What is being done to prevent a similar occurrence in the future?
37
What is being done?
Learn as much as possible from the MacondoLearn as much as possible from the Macondo incident, determine what really did happen, and apply the lessons learnt to prevent future problems of this kind.
Four (five) major oil companies formed a consortium to develop better understanding, better methods, and
$equipment that is always ready and available. ($ 1 B!)
Not to be left out: Our government split the MMS into three separate units; pledged to provide more oversight, applied a DRILLING MORATORIUM !!
38
AcknowledgmentsAcknowledgments
Dr Alex Dessler Professor EmeritusDr. Alex Dessler - Professor Emeritus, atmospheric physics and astronomy, Rice U.
Dr. Ann Jochens - lawyer and oceanographer
They were very helpful in selecting and organizing the slides Without their help thisorganizing the slides. Without their help this presentation could have taken twice as long.
39
Any Questions?yDeepwater Horizon
Top HatRelief Wells
Th lti tThe ultimate solution!
Two wells
40