Upload
vkumaran
View
62
Download
0
Embed Size (px)
Citation preview
04 JUNE 2007[Technology in Society] | 421-609
[Vigneswaran KUMARAN] | 277492
Aim
This essay is intended to provide a critical analysis on the aspired Bakun Dam construction in Malaysia. The significance of the technology and its impact on the indigenous society of Sarawak, and its environment is the main content of the analysis. The essay will attempt to address the following elements:
Technological need of rural society and the people of Malaysia, in particular of Sarawak
Energy requirement vis-à-vis state development
Chronological events of the dam construction and the political scenarios
The societal interaction, environmental needs and development requirement
Public participation and involvement in socio-environmental decision making
Coordinator: Dr. Lu AyeCivil and Environmental Department
THE BAKUN HYDROELECTRIC PROJECT: THE DAMNED DAM
THE BAKUN HYDROELECTRIC PROJECT IN MALAYSIA: THE DAMNED DAM
Other elements of threat or barriers in societal need for alternative technologies in favour of the dam construction
2 | P a g e
THE BAKUN HYDROELECTRIC PROJECT IN MALAYSIA: THE DAMNED DAM
Contents
Aim 3
1.0 Introduction 7
Conclusion 20
References and Notes 21
FiguresFigure 1 Industrial Fuel Intensity in Selected ASEAN Countries 1980-2000 13
3 | P a g e
THE BAKUN HYDROELECTRIC PROJECT IN MALAYSIA: THE DAMNED DAM
1.0 INTRODUCTION
The right to prosper in life beyond survivalism could be an ideal aim of every human being
and every nation on earth. Development in a society at a primary level, should address the
basic needs of the members of the society and it should be at the willingness of the society
to embrace the development, but not as an imposition due to external forces. The people of
Sarawak, a sovereign state of Malaysia is provided with the option of such development,
and it is important that the basis of such provision is critically reviewed and the implications
understood in its whole. Sarawak is the largest state in Malaysia being situated on the East
Malaysia, with massive tropical rainforest (though dwindling rapidly), and endowed with
large petroleum reserves [1]. It is one of the world’s largest exporters of tropical hardwood
timber [2], and the deforestation had depleted almost 90 % of the forested area.
The people of Sarawak, in particular the indigenous and locals along the Balui River of
Sarawak have been provided with the opportunity to develop to the standards considered in
par with other Malaysians. The opportunity came in the form of construction of a dam
which would consume a catchment area twenty times the size of Singapore and a reservoir
that would submerge Singapore in entirety [3]. This opportunity will displace the ten
thousand indigenous from their ancestral native land, their association with the
environment, and provide alternate source of income from the project. Their forced
relocation [4: www.rengah.c20.org] had undermined fundamental human rights in its basic
form, with threats of reduction in compensation, forced purchase of homes, and non-
transparent legal acquisition of native land.
The conception of Bakun Hydroelectric Project, in its feotal stage could be dated to the early
1960s, where the initial survey of hydroelectric potential in Sarawak was initiated under the
Colombo Plan aid programme. The survey was carried out by the Snowy Mountains Hydro-
Electric Authority of Australia. The late 1970s and early 1980s saw the detailed examination
of the Bakun site and preparation of development proposals. The feasibility study was
carried out by German-Swiss consultants and had involved an expenditure of US$ 15 million
4 | P a g e
THE BAKUN HYDROELECTRIC PROJECT IN MALAYSIA: THE DAMNED DAM
(1985). The construction of the 204m height dam and the power generation facility
(inclusive of eight power tunnels of 8.5m diameter) was estimated to extend over a period
of 12.5 years.
In 1986, although the nation was affected by recession, the government announced the
decision of proceeding with the Bakun project. The funds required for the project was
thought to be sourced from World Bank or Asian Development Bank (ADB). The general
public and the natives were infuriated by this uncouth action of the elected government.
However, in June 1990, the then Prime Minister of Malaysia (Tun Dato Seri (Dr.) Mahathir)
announced the cancellation of the project during an international conference on
conservation of tropical biodiversity, purportedly demonstrating Malaysia’s commitment to
conservation. However, this decision was more at the economic interest of the country,
rather than earnest environmental concern, which had been made obvious by the decrease
in electricity demand projection as an outcome of recession post 1985.
On September 9, 1993, the government of Malaysia had decided to revive the project of
building the dam. The reason could have been due to incessant lobbyist and strong political
push from the state government, as well in the rise of electricity demand. In January 1994,
the project was awarded to the Sarawak timber tycoon, Tan Sri Ting Phek Khiing under
Ekran Berhad, without formal protocol and bureaucracy associated with most government
linked project. This was a business entity without prior experience in dam construction or
power sector. In April 1995, Ekran (and the consortium formed) completed the EIA for the
project, however, the EIA was not released for public scrutiny.
The project with a capacity of 2400 MW is to cost US$ 2.5 billion and expected to be
completed by 2003. Additionally, a 670 km HVDC power transmission cable was to be laid
on the seabed to supply power from Sarawak to the West Malaysia. Ironically, Ekran
announced that the reports have been approved by Department of Environment (DOE),
which at the time, the reports have not been subjected to public scrutiny. This approval
reflected mismanagement at government level, whereby the jurisdiction of EIA at federal
level has been transferred to Sarawak state government by the Minister of Science, Energy
5 | P a g e
THE BAKUN HYDROELECTRIC PROJECT IN MALAYSIA: THE DAMNED DAM
and Technology and backdated to September 1, 2004. The state level EIA does not require
public feedback for the EIA approval. The EIA had been divided into four parts, defying the
purpose of EIA, and were to be approved in stages, while preliminary works at site such as
land clearing to proceed in order to meet the project milestones. The local society and
public were not provided the opportunity to voice their concerns, and humiliatingly the final
approved EIA was provided to the public four months later. This act by the government
reflects arrogance and complete disregard of public welfare, and EIA once again becomes a
piece of ineffective document, rather than a dynamic process for socio-environment
assessment. This preferential act also mirrors a socially corrupted political institution,
maximizing private profit against social welfare.
The EIA was later reviewed by a team of experts brought together by the International
Rivers Network (IRN) at the request of local society. The evaluation exposed some fallacies
and inadequacies in the project’s approved EIA, in which the project was reputed to supply
the nation with cheap, clean and reliable electricity. The team also concluded that the EIA’s
“usefulness is severely limited by basic methodological flaws”. The approved EIA had also
claimed that the dam would reduce loss of forests, whereas the site clearance would leave
hectares of land deforested. Apart from that, the EIA had not considered the no-project
alternative, long-term impact, and effect of water quality on fisheries. The IRN effectively
summed the EIA as not meeting the accepted international standards for environmental
assessments.
In 1997, during the Asian financial crisis, the project was halted. The government had
already made US$ 1.22 billion payment to the consortium on various completed works. The
resuscitation of the project for the third time took place in May 2000, via a government
owned company, Sarawak Hidro. However, numerous changes had taken place within the
past five years, in terms of the overall project development. In November 2007, a new
merger will allow Synergy Drive with a market capitalization of US$ 8 billion to takeover the
Bakun project, and the submarine HVDC cable to West Malaysia to be revived. The
projected time of completion is February 2008. Thus the actual cost of project estimated at
6 | P a g e
THE BAKUN HYDROELECTRIC PROJECT IN MALAYSIA: THE DAMNED DAM
US$ 2.5 billion in 1995 is now estimated to have overrun to US$ 4 billion, if it is completed at
the aforementioned date. Nevertheless, it should be noted that the World Commission on
Dams (WDC) states that the construction overrun cost for large dams are typically about 56
%, which could lead to a larger sum.
The social benefit cost analysis was not adequately undertaken by the Malaysian
government. Nonetheless an independent study by Hope and Morimoto (Cambridge) shows
that the project’s mean probability of Net Present Value (NPV) is negative throughout the
project life, assuming the facility’s life of 100 years. The 95 th percentile indicates the project
to have positive NPV only from the tenth to the thirtieth year, and subsequently lose its
economic value. This study and other similar propositions show that the Bakun was not a
project to maximize social economic welfare, but intended by a few in power for the benefit
of the elite few.
The energy requirement in West Malaysia and Sarawak as indicated in the Ninth Malaysia
Plan 2006-2010 has a reserve margin of 25.4% and 23.5%, respectively. The reserve margin
for Sarawak includes the power generation from Bakun, however this contribution is only at
400MW against a design capacity of 2400MW. The capacity being underutilised is an
economic loss, and even if the Bakun operates at 76% (as indicated in the Knowledge Base
of WCD) by 2008, the reserve margin would exceed by 60%. This extra margin is non-
consumable power, which ultimately reflects in the financial sheet of the project a huge
hole, and may eventually be covered with tax-payers money, as practiced in other
government linked operations. Arguably, the intention of the state and federal government
in carrying out such massive project with tax-payers money (the US$ 2.2 billion in payment
done) and blatant disregard of public concern has little to do with national development. As
shown by the number of attempts to revive the damned project, the societal need has least
importance in this short-term economic gain by the elite few.
Alternative sources of power generation have not been considered in replacement of this
project. To err is human, but to repeatedly err is ignorance, and the leaders of this
government have little thought or inclination to retract their failing acts. A massive project
7 | P a g e
THE BAKUN HYDROELECTRIC PROJECT IN MALAYSIA: THE DAMNED DAM
such as Bakun is becoming obsolete in developed countries such as Canada, Europe and
France, however developing countries such as Malaysia is willing to buy this obsolete yet
highly expensive technology to become an industrialised nation. A project which extends
over more than 12 years, had largely been exposed to severe economical constraints and
mismanagement should be reviewed conscientiously by good political governance. Sarawak
has large reserves of natural gas, and clean combined heat and power technology, and to
use latest state-of-the-art operations would have less capital requirement and
environmental impact, compared to submerging and deforesting a land that could
accommodate the whole nation of Singapore in its scarcity for land.
The Bakun project had taken away the indigenous people’s right by creating legislative rights
against their Native Customary Rights (NCR). The society had been displaced 50km from
their native land, with least compensation and against their preference. Development
against the need of the society is exploitation of the society for private profits, and such
development leads to social degradation more rapidly than if the society had been left
without development. The displaced Kenyah, Kayan, Ukit, Penan and Kajang ethnics have
been deprived of their ancestral land using the legislative interpretation by the state
government for the interest of a few in power. Until today, some of these people have not
even received their compensation, nor have their plights been consciously addressed.
In the name of development, these people are forced to strip their cultural inheritance,
their way of life and finally their identity as the indigenous who had been the rightful
owners of the Bakun. In the name of development, a society with rich traditional values,
worth more than any economic return is asked to sacrifice for the whole nation that lives in
cities and homes that knows not how much of fauna and flora of thousands of years
evolution is destroyed for the need of a few. It is disheartening that the plights of the
displaced people are yet to be attended. The following song (a ‘parap’ – offering in song and
rice wine) from a Kenyah indigenous aged women highlights the ill fated society’s plight:
“We are happy you came among us.For soon, we worry, we may drown
8 | P a g e
THE BAKUN HYDROELECTRIC PROJECT IN MALAYSIA: THE DAMNED DAM
Because of Bakun.We are mourning, due to our problems.Share your ideas with us, so we can have courage.Please help us, please tell yourFriends, and others in the world outside, That we have our problemsSo that you and they can help usOne way or the other.Please remember us and our plightWherever you go, wherever you may be.”
Technology is worth less than its economic value in a fading society, when the development
is imposed on the society, against their will and interest. The people of Balui River will be
forgotten as soon as the damned Bakun Hydroelectric generates power, but a technology
that displaces a culturally rich society, and diversified fauna and flora will leave a scar that
will remain in Malaysian history in pursuit for the title of developed nation.
9 | P a g e
THE BAKUN HYDROELECTRIC PROJECT IN MALAYSIA: THE DAMNED DAM
REFERENCES
1. MIEEIP, MEC
2. Achieving Industry Energy Efficiency in Malaysia, UNDP
3. The Ninth Malaysia Plan (RMK9), Economic Planning Unit, Malaysia
4. The Star Online, Friday, March 31, 2006
5. World Energy and Economic Outlook, International Energy Outlook 2006, Energy Information Administration, USA
6. A. Rahman Mohamed, K.T. Lee / Energy Policy 34 (2006) 2388–2397
7. Energy, The Eighth Malaysia Plan (RMK8), Economic Planning Unit, Malaysia
8. Concept Paper on EE Business Opportunity in Malaysia, R. Ponnudorai, PTM, Malaysia
9. Potential of Gas Fired CHP in the Manufacturing Sector in Malaysia, Malaysian-Danish Environmental Cooperation Programme, Ir. Phang Ah Chee, CHP Energy Services, Malaysia
10 | P a g e