TAYLOR Et Al on Stockton's Geothermal Installation

Embed Size (px)

Citation preview

  • 7/31/2019 TAYLOR Et Al on Stockton's Geothermal Installation

    1/17

    Technical Description of the Stockton College Geothermal HVAC Retrofit

    Harold E. Taylor*, Lynn F. Stiles and William Hemphill

    December 1997

    ABSTRACTThe need to replace old, worn out and obsolete Heating, Ventilating and Air Conditioning

    (HVAC) units led Stockton College to seek a study of current technologies which might be used.The study indicated that a ground coupled water source heat pump system would pay for its extrainitial costs in about 3 years. Hence, a new geothermal HVAC retrofit system was designed.It is a closed loop system of 400 wells each 425 feet deep with a U-tube of 11/4 inch high densitypolyethylene pipe inserted in each well. The entire well field is buried under a 4 acre parking lot.This well field is coupled through a primary supply loop and 5 separate secondary circulationloops to 61 roof mounted heat pumps to provide the heating and cooling for about 350,000square feet of the 440,000 square foot original academic complex of buildings. A newerbuilding of approximately 40,000 square feet with 58 smaller heat pumps was added to thesystem in 1996. Energy savings and cost estimates are summarized and the specifications of thenew geothermal HVAC system are presented.

    1. INTRODUCTION AND OVERVIEWStockton College is a public, undergraduate college of arts and sciences located in the PineLands of Southern New Jersey, 12 miles northwest of Atlantic City. The main academicbuilding complex consists of 14 wings connected by an enclosed gallery containingapproximately 440,000 square feet of floor space. The Arts & Sciences building with about40,000 square feet of additional space was added to the system in 1996. The college first openedin 1971 and in 5 years grew to its present size of over 5000 students and 200 faculty. Theoriginal buildings were designed and built prior to the energy shortages of the mid 1970s and

    thus are not as energy efficient as they might be. These buildings house the classrooms,laboratories, studios computing facilities and offices for faculty administration and staff. Inaddition they include a gym, library, pool, theater and cafeteria.

    The campus buildings were constructed in three stages: Phase 1 (wings A through D includingCC) was completed in 1971, Phase 2 (wings E through H) was completed in 1973 and Phase 3(wings I through M) was completed in 1975. By 1990, the Heating, Ventilating and AirConditioning (HVAC) units manufactured by Nesbitt and Lennox were reaching the end of their

  • 7/31/2019 TAYLOR Et Al on Stockton's Geothermal Installation

    2/17

    useful life. Nesbitt, the company who supplied the units in Phase 1, was no longer in businessand Lennox no longer manufactured the multi zone units. Changes were needed. Theengineering firm of Vinokur-Pace was retained to study the situation.

    The Vinokur-Pace study compared the costs and projected energy savings of both a directreplacement of the existing units and a replacement with ground-coupled water-source heat

    pumps. Their projections showed that a geothermal system would cost about $1.2 million moreto install, but that it would be expected to save $330,000 per year in energy costs. Thus, thesimple pay back of the extra costs of the geothermal system would be about 3.5 years.

    Furthermore, because the reduced peak electrical demand would reduce the need for AtlanticElectric Company to install new generators, the utility offered an $800/Ton rebate for installingthe geothermal system. On the 1600 ton system, this rebate would just cover the incrementalinitial costs of the geothermal system. With additional funding from the State of New Jerseyobtained in 1992, a contract was awarded for the retrofit and the geothermal system was installedin 1993. The new heat pumps were lifted to the rooftops and the old units removed in a day anda half by helicopter during the 1993 Christmas break and in mid-January 1994 when classes

    began, the new geothermal system was turned on.

    The Geothermal system consisted of replacement rooftop water source heat pump units coupledto a closed loop system of 400 wells each 425 feet deep located under a 4 acre parking lot.

    2. THE COLLEGE ACADEMIC BUILDINGSThe 14 wings of the academic complex are labeled alphabetically from A through M with a smallCC wing located opposite C-wing. These wings are connected by an enclosed, 2-level gallery.I-wing (the gym) and L-wing (the pool) are not cooled and M-wing (a 550 seat theater) has aseparate 175 ton Westinghouse chiller using 2 cooling towers. The wings all have two levels

    except E (the library) and F (housing many of the science labs) which have 3 levels. Typicallyeach level of each wing is conditioned by two multi zone roof mounted units.

    Energy usage for 1990 was 9,205,200 kWh of electricity and 40,543,000 cubic feet of gas.These translate into 106,780 million BTU of electricity and 41,759 million BTU of gas. Thecosts were $6.81/million BTU for electricity and $5.28 per million BTU for gas or an average of$6.38/million BTU for gas and electricity combined.

    3. PRE-RETROFIT EQUIPMENTThe original HVAC equipment consisted of multi-zone combination gas-fired heaters andelectric compressor type coolers. There were 70 units with a total cooling capacity of20,962,000 BTU/hr or 1,747 Tons. These units were mounted on the roofs of the wings theyserved. Table 1 is a summary of the total capacities/ratings for the original units by building.The 18 Phase 1 units have a total cooling capacity of 5,814,000 BTU/hr or 485 Tons. The 30Phase 2 units have a total cooling capacity of 10,451,000 BTU/hr or 871 Tons. The 22 Phase 3units had a total cooling capacity of 4,690,000 BTU/hr or 391 Tons. Detailed ratings ofindividual units are given in Appendix 1.

  • 7/31/2019 TAYLOR Et Al on Stockton's Geothermal Installation

    3/17

    Table 1: Original HVAC Units

    Building SupplyCFM

    FreshCFM

    FanskW

    CompressorskW

    Cooling106 BTU/hr

    Phase 1 137, 520 25,010 180 615 5.814

    Phase 2 239,115 62,530 405 1,122.8 10.451Phase 3 164,049 69,255 275 516.6 4.690Totals 540,684 156,795 860 2,254.4 20.955

    Table 2: Energy Consumption in1990

    EnergySource

    QuantityUsed

    Units Energy Used106 BTU

    Cost$

    Energy Cost$/106 BTU

    ElectricityGas

    9,205,200405,433

    kWhCCF

    106,78041,759

    727,211220,538

    6.815.28

    These units were installed between 1971 and 1975 and thus were nearing the end of their usefullifetime in the 1990s. Parts could no longer be obtained for these units and they were becoming

    increasingly difficult to keep in proper operating order. Thus in 1991, a study of possiblereplacement options was commissioned by the college. [Vin92]

    4. THE GEOTHERMAL RETROFITThe Vinokur-Pace engineering firm made cost savings and energy savings estimates for both adirect replacement of the existing units with current technology new units and with the water-source heat-pumps. Their estimates were based on 1990 energy use figures which are shown inTable 2.

    For this calculation an overall COP of 3.4 was assumed for the electrical usage so that 1 kWh of

    electricity yielded 11,600 BTU of useful energy. Also the energy content of the natural gas wasassumed to be 103,000 BTU/CCF.

    Projected energy usage and costs, based on rates in effect on in 1991 are shown in Table3.Projected installed cost of the direct replacement system was $3,567,493. For the geothermalsystem, the projected installed cost was $4,964,594 but the electric utility company offeredrebates of nominally $800 per installed ton which came to an actual rebate of $960,000 makingthe net installed cost of the geothermal system $4,004,594 or $437,101 more than the directreplacement system. Comparing the projected energy costs for the Geothermal system with theDirect Replacement system shows a savings of $126,047 per year. Thus the simple pay back

    time for the incremental cost of the geothermal system would be:437,101

    /126,047 3.5 years.

    Table 3: Projections of Energy Use and Cost

    Electrical Gas TotalSystem kWh Cost ($) Therms Cost ($) Cost ($)Existing 8,427,418 818,976 222,314 120,425 939,401Direct Replacement 7,112,911 665,675 160,919 87,461 753,136Geothermal 6,372,711 599,296 50,996 27,793 627,089

  • 7/31/2019 TAYLOR Et Al on Stockton's Geothermal Installation

    4/17

    Table 4: New HVAC Units: Building opened December 1996

    Supply Min Water Heat

    A & SBuilding

    SizeTons

    FlowGPM

    RejectBTU/hr

    AbsorbBTU/hr

    Fan/pumpkW

    Air 241.7 640.8 2,662,233 1,634,840 65.62Water 45.3 119. 448,537 284,893 10

    Totals 282. 760. 1,110,770 1,918,733 75.6

    4.1 ROOFTOP MULTI-ZONE HEAT PUMPS

    The geothermal HVAC system installed at Stockton is shown conceptually in Figure1. The heatpumps are mounted on the roof of the academic buildings and connected to the well field under alarge parking lot by piping.

    The specifications of the new (replacement) rooftop heat pumps are shown in Tables A, A and A.Note that the unit for the CC-wing (Unit No. RSZ 18) was not replaced and therefore does notappear in this table of new units.

    In Phase 1, (Table A) the 17 units have a total nominal size of 435~tons or 5,220,000 BTU/hr.

    In Phase 2 (Table A) there are 30 units with a total nominal size of 755 tons or 9,060,000BTU/hr.

    In Phase 3, the 8 old, heating-only units in the Gym (Wing-I; units 80-E, 80-F, 80-G & 80-H)and Pool (Wing-L; units 80-A, 80-B, 80-C & 80-D) were not replaced. The specifications of theunits replaced in Phase 3 are given in Table A. There are 14 units with a total nominal size of280 tons or 3,360,000 BTU/hr.

    Thus the total nominal size of the 61 replacement units is 1,470 tons or 17,640,000 BTU/hr or

    5.17 Megawatts. The system was designed to accommodate a new building in December 1996.The 57 units on this building added an additional 242 tons bringing the total load on the wellfield to 1712 tons (2.2 x 106 BTU/hr or 5.91 MW).

    4.2 THE WELL FIELD

    Once the heating and cooling load is determined, the size of the well field can be determined.The well field for the Stockton geothermal HVAC system was designed by Howard Alderson ofhis Alderson Associates engineering firm.

    The well field consists of 400 wells, each 425 feet deep as shown in Figure 2 with a U-tube if 1

    inch high density polyethylene pipe inserted in each well. The wells are grouted withbentonite to prevent water from one aquifer getting into another. Twenty wells are fed from one4-inch diameter lateral in a `reverse return' configuration to equalize the pressure drop (andpresumably the flow) through each of the 20 wells. The 20 4-inch laterals come together into a16-inch diameter manifold in a small cinder block building located on the east side of the wellfield. This manifold house is the only visible feature of this large well field since the wells andthe laterals are all buried under a 4 acre parking lot.

  • 7/31/2019 TAYLOR Et Al on Stockton's Geothermal Installation

    5/17

    The heat pumps are fed by a pair of 16-inch diameter pipes (the supply and return pipes) of themain loop coming out of the manifold house and going to the pumps in the F-wing of thebuildings on which the heat pumps are mounted. This primary loop provides a flow of up to4000 gallons per minute of water supply through the U-tubes in

    Figure 1: Conceptual view of the Stockton geothermal HVAC system. Also shown are the hydrogeological layers in which the well field is implanted.

  • 7/31/2019 TAYLOR Et Al on Stockton's Geothermal Installation

    6/17

    Figure 2: Diagram showing the layout of the well field with the monitoring wells. The wells areseparated by at least 15 feet.

  • 7/31/2019 TAYLOR Et Al on Stockton's Geothermal Installation

    7/17

    the wells. This is distributed to the heat pumps throughout the conditioned space in 5 separatesecondary loops.

    The wells go through three different aquifers and the intervening clay layers which confine themas shown schematically in Figure 3.

    The Upper Cohansey Aquifer begins near the surface and extends down to 80 feet. Then there isa 28 foot thick confining layer followed by the Lower Cohansey Aquifer from 108 to 160 feetdown. Transition layers surround a 12 foot thick confining bed from 160 to 315 feet in depth.Then there is the Rio Grande water bearing zone from 315 to 351 feet, below which there is athick confining bed to beyond the bottom of the wells. The water bearing layers are expected tohave a higher specific heat and a higher thermal conductivity. In addition the flow of the waterwill help in the heat transfer process.

    Four hundred wells each 425 feet deep gives 170,000 lineal feet of well for heat exchangepurposes. This translates into 106 feet per ton of cooling. The pipe for this closed loop system is

    actually twice as long since each well contains a U-tube. Furthermore the 4-inch laterals providean additional 19,200 feet of pipe in contact with the ground for additional heat exchange.Though this is only about 11% additional length, the 4-inch pipe has over three times the surfacearea of an equal length of 1 -inch pipe or about 1.5 times the area of the double 1 -inch pipeof the U-tubes in the wells. The heat exchange of the laterals thus adds about 15% to the heatexchange capacity of the well field. The designers expected this well field configuration tomaintain the temperature of the water supplied to the heat pumps between 40F and 90F underthe loads produced by the college buildings.

    5. CONCLUSIONSThis system was put into operation on January 19, 1994. During the first six months of operationthe pumps were running wide open, 24 hours a day. In June of 1994 the variable frequencydrives for the pumps were made operational and since then the pumping power has been onlywhat is needed for the daily load. In addition, a sophisticated energy management system (EMS)is being developed on site by the Trane Manufacturing Company to control the system. ThisEMS monitors over 2000 points - temperatures, flow rates (or pressures) valve or damperpositions etc. - and adjusts the system accordingly. As the EMS is completed and optimaloperating strategies are developed additional energy savings and conditioning comfort areanticipated.

    Also, a monitoring program has been set up to measure the performance of this system. It is tobe described in a forthcoming article. Some results were reported at the EPRI meeting inDecember 1995 [TEP +95]. Additional papers are being prepared for publication. Projectreports are available [SEP +94a], [SEP+94b] and [SEP +95] as is the EPRI meeting paper.

  • 7/31/2019 TAYLOR Et Al on Stockton's Geothermal Installation

    8/17

    Figure 3: Geologic layers that are penetrated by the 425 foot deep wells.

  • 7/31/2019 TAYLOR Et Al on Stockton's Geothermal Installation

    9/17

  • 7/31/2019 TAYLOR Et Al on Stockton's Geothermal Installation

    10/17

  • 7/31/2019 TAYLOR Et Al on Stockton's Geothermal Installation

    11/17

  • 7/31/2019 TAYLOR Et Al on Stockton's Geothermal Installation

    12/17

  • 7/31/2019 TAYLOR Et Al on Stockton's Geothermal Installation

    13/17

  • 7/31/2019 TAYLOR Et Al on Stockton's Geothermal Installation

    14/17

  • 7/31/2019 TAYLOR Et Al on Stockton's Geothermal Installation

    15/17

  • 7/31/2019 TAYLOR Et Al on Stockton's Geothermal Installation

    16/17

  • 7/31/2019 TAYLOR Et Al on Stockton's Geothermal Installation

    17/17

    REFERENCES

    [SEP+94a]Lynn Stiles, Claude Epstein, Sipra Pal, Louise Sowers, and Harold Taylor.Monitoring and analysis for the electrical demand, energy flow and well field

    parameters of the geothermal heat pump installation at the Richard Stockton Collegeof New Jersey. Technical report, The Richard Stockton College of New Jersey,Faculty of Natural Science and Math, Stockton College, Pomona, NJ 08240, Jun1994. Six Month Progress report to Atlantic Electric, Electric Power ResearchInstitute, Sandia National Laboratory and South Jersey Transportation Company.

    [SEP+94b]Lynn Stiles, Claude Epstein, Sipra Pal, Louise Sowers, Harold Taylor, WilliamHemphill, and Joseph Sowers. Monitoring and analysis for the electrical demand,energy flow and well field parameters of the geothermal heat pump installation at theRichard Stockton College of New Jersey. Technical report, The Richard Stockton

    College of New Jersey, Faculty of Natural Science and Math, Stockton College,Pomona, NJ 08240, Dec 1994. Annual 1994 Report to Atlantic Electric, ElectricPower Research Institute, Sandia National Laboratory and South JerseyTransportation Company.

    [SEP+95]Lynn Stiles, Claude Epstein, Sipra Pal, Louise Sowers, and Harold Taylor.Monitoring and analysis of the geothermal heat pump installation at Stockton College(NJ). Technical report, The Richard Stockton College of New Jersey, Faculty ofNatural Science and Math, Stockton College, Pomona, NJ 08240, Jul 1995. January -June 1995 report to Atlantic Electric, Electric Power Research Institute, SandiaNational Laboratory and South Jersey Transportation Company.

    [TEP+95]Harold Taylor, Claude Epstein, Sipra Pal, Louise Sowers, and Lynn Stiles.Monitoring and analysis for the electrical demand, energy flow and will fieldparameters of the geothermal heat pump installation at the Richard Stockton Collegeof New Jersey. In Proceedings of the 1995 Conference on Meeting Customer Needswith Heat Pumps, St. Louis, MO, December 1995. Electric Power Research Institute.

    [Vin92]Vinokur-Pace Engineering Services, Inc., 135 Old York Road, Jenkintown, PA 19046. Geothermal Energy System,March 1992. Report to Stockton College and the New Jersey Division of Building Control (DBC I0082).