Supplier Scheduling SystemsMin/Max and PODS

Suppliers

Greg SmileyCentral Supply Chain

Procurement Systems

Slide 2

Min/Max Supplier Training

Min/Max Concept Min/Max History Min/Max Web Screens in the Portal Order Policy - Min and Max Values Min/Max System Updates PODS – Purchase Order Discrete Scheduling system Instructions and Reference Supplier Scorecard Assistance

Slide 3

Min/Max Supplier Training - Concept

Simple system where minimum and maximum inventory quantity are set for each part number Vought inventory levels are then managed by the

supplier between the minimum and maximum levels Replenishment: The supplier action of ordering,

producing and shipping product to Vought Vought receiving parts up to the max qty, prior to the

inventory quantity going below the min qty

Slide 4

Min/Max Supplier Training - Concept

5

10

15

20

25

30

35

40

0

Inventory Quantity

Time

0 1 2 3 4 5 6 7 8 9 10 11 12 13 14

Consumption Consumption

Replenishment Replenishment

Minimum

Maximum

Consumption

Beginning Inventory = 25 pcs Monthly Demand = 2 pcs

Slide 5

Min/Max Supplier Training - History

Late 2001 Min/Max inventory management was identified as a process and system to replace APORs

In 2002 the first supplier began working to an early MM process (Excel spreadsheet)

In July 2009 we have 42 suppliers in MM and approximately 50% of all parts purchased by Vought are managed in the Min/Max system

2009 decision was announced to abandon APORs and move to Min/Max as much as possible

In August 2009 we moved most suppliers out of APORs and into Min/Max or PODS.

Slide 6

Min/Max Supplier Training - Portal

Slide 7

Min/Max Supplier Training - Portal

Slide 8

Min/Max Supplier Training - Portal

Part Number• Part Number as listed on Purchase Order• Only Part Numbers with open POs are listed

Slide 9

Min/Max Supplier Training - Portal

CH – Change Flag• An asterisk is shown when one of following conditions are

present: New Part Number, changed Min or Max value, new Purchase Order, or a new receipt is listed.

• The asterisk remains for 7 days

Slide 10

Min/Max Supplier Training - Portal

Site• Site that uses the part: STU, HAW, MSF, JSF, NAS,

MIL

Slide 11

Min/Max Supplier Training - Portal

Min Qty – Inv Qty – Max Qty• Min value that inventory is to be maintained above• Inventory Qty (updated nightly)• Max value that inventory is to be maintained below

Colors• Red = Under Min• Blue = Over Max• Green = Contact Buyer

Slide 12

Min/Max Supplier Training - Portal

Dir – Direction• Inventory vs Min or Max

– U = Under = Inventory < Minimum– O = Over = Inventory > Maximum– V = Vought = Contact Buyer

Slide 13

Min/Max Supplier Training - Portal

Priority Need Date (Initial sort of web screen)• If the Inv Qty does not support a manufacturing need date within

the next 30 days, a Priority Need Date is displayed• This is to help the supplier to identify critical PN requirements and

potential shortages

Slide 14

Min/Max Supplier Training - Portal

Metric Eff Date – Metric Effective Date (MED)• For purposes of measurement of seller’s performance to min/max inventory

management, the parties will agree to a metric effective date (MED) which shall be the date after which the seller agrees to manage the buyer’s inventory within the Min/Max range. If there is no date, the expectation is that the supplier is responsible for maintaining the inventory between the Min and the Max.

Slide 15

Min/Max Supplier Training - Portal

Behind Sch Demand – Behind Schedule Demand• If Vought’s manufacturing operation is behind schedule and did

not pull parts from inventory in a prior month, the qty of thoseparts is listed. These quantities will be consumed prior to consuming parts in the “current” month.

Slide 16

Min/Max Supplier Training - Portal

Monthly Demand / Planned Consumption• The web page displays 12 discrete months (rolling) of planned

consumption• Download file has 24 months of planned consumption• Suppliers may not have all the planned consumption on PO

Slide 17

Min/Max Supplier Training - Portal

Total Horizon Qty• Total quantity of parts loaded into Vought’s Master Schedule /

MRP System• Supplier may not have the Total Horizon Quantity on open POs

Slide 18

Min/Max Supplier Training - Portal

Lead Time Calendar Days• The supplier lead-time in calendar days for the specific PN

(includes raw material acquisition and fabrication time) • If these values are incorrect, please notify your Vought buyer that

your lead-times have changed

Slide 19

Min/Max Supplier Training - Portal

Program• The Vought program that the PN supports

Slide 20

Min/Max Supplier Training - Portal

PO Number – PO Item – Open Qty• A listing of all open POs, item numbers & the remaining open qty• For a PN to show in MM there needs to be at least one open PO• There can be more than one PO open for a PN

Slide 21

Min/Max Supplier Training - Portal

Total Open Qty• This represents the sum of all open PO quantities

Slide 22

Min/Max Supplier Training - Portal

Last Receipt Date – Last Receipt Qty• The date of the last receipt of this PN• The quantity of the last receipt of this PN• The download file lists the last 5 receipts

Slide 23

Min/Max Supplier Training - Portal

Colorization of Consumption Plan

Current Inv = 22 – (0 + 3 + 7) = 12 still above MinCurrent Inv = 22 – (0 + 3 + 7+ 7) = 5 < Min = YellowCurrent Inv = 22 – (0 + 3 + 7+ 7 + 7 ) < 0 = Red

Slide 24

Min/Max Supplier Training - Portal

Online Sort Capability• Underlined headings indicate a data field that can be

sorted

Slide 25

Min/Max Supplier Training – Download File

Sample Supplier

Slide 26

Min/Max Supplier Training – Download File

Text file, tab delimited that can be opened by MicroSoft Excel

(from within Excel).The same data as displayed on

the web, but includes 24 months of demand and 5 receipt dates

and quantities.

Slide 27

Min/Max Supplier Training – Order Policy

Monthly Ship Qty/ Ships$ Usage Min Max Span YearUnder $160 2 Mo 14 Mo 12 Mo 1

$161 to $300 1.5 Mo 7.5 Mo 6 Mo 2

$301 to $1K 1 Mo 5 Mo 4 Mo 3

$1K to $2K 0.5 Mo 2.5 Mo 2 Mo 6

Over $2K 0.5 Mo 1.5 Mo 1 Mo 12

Slide 28

Min/Max Supplier Training – System Updates

Real-time Updates (if input or changed by buyer)• Metric Effective Dates (MED)• Min Values• Max Values

Nightly updates to MM system• Inventory values• Purchase Orders• Receipt information

Weekly Updates to MM system• Demand data

Slide 29

Min/Max and PODS Supplier Training

Min/Max and PODS• APORs was replaced by Purchase Order Discrete Scheduling

System (PODS) – August 2009• Vought will have the ability to control by PN those parts that are in

Min/Max vs PODS– PODS candidate PNs – High dollar, out of production spares, etc.

• Some suppliers will have parts in both systems• Part delivery requirements/dates will be per the schedule on the

paper PO and will be reflected on the PODS screen• Nothing automated. If the delivery requirements/dates change,

supplier will receive a revised PO with the new dates

Slide 30

PODS Supplier Training

Slide 31

PODS Supplier Training

Slide 32

PODS Supplier Training

Slide 33

ABC MACHINE SHOP INC

PODS Supplier Training

Slide 34

Min/Max and PODS Supplier Training

Slide 35

Min/Max and PODS Supplier Training

Slide 36

Supplier Training – Supplier Scorecard

Slide 37

Supplier Training – Supplier Scorecard

PODS• Measures rolling twelve month average reflecting

percentage of shipments that were shipped on or before the contract negotiated ship date

Min/Max• Measures ratio of Part Numbers with:

– At least one open Purchase Order;– Inventory under Min – Without a Metric Effective Date

(MED) in the future;– Inventory over Max – Without a Metric Effective Date (MED)

in the future

Slide 38

Min/Max and PODS – Assistance

Scheduling Standard Note – S121• Nick Dyer• (972) 946-3285• [email protected]

Min or Max Values and MEDs• Contact your Vought Buyer

Portal, Min/Max or PODS Systems & Training• Greg Smiley• (972) 946-3181• [email protected]