Upload
others
View
1
Download
0
Embed Size (px)
Citation preview
Staying Out of the TrenchContract Documents Address Unique
Trenchless Aspects
PRESENTER INTRODUCTION
• Joshua P. Farmer, PE• Corporate Tunneling and Drilling
Technology Leader
• Kyle E. Drumheller, PE, CCM• Trenchless Resident Engineer
Why is it Important to Understand the Unique Aspects of
Trenchless Construction?
1. Cost – Are we addressing the items that most impact project cost?
2. Schedule/Duration – Do we have enough information to reasonably
understand production?
3. Risk – Have we allowed for all appropriate/feasible methods? Have we
eliminated methods with low probability of success?
4. Stakeholder Impacts – Do we understand the true scale of known and
possible impacts to the Public, Traffic, or Environment?
5. Quality Assurance – Have we implemented contract measures and
appropriate scope to ensure construction and the final end product meets
expectations and operational needs?
Unique Aspects of Design and Oversight of Trenchless Construction
Higher Incident of Claims
Greater Production Variability; Production Drives Cost
Greater Importance of Geotech info
Method Constructability/Feasibility
Market Conditions and Equipment Availability
Stakeholder Impacts (Public/Traffic/Environmental)
Measurement and Payment (Front Loaded Costs & Float)
Monitoring
Contractor Qualifications
Construction Inspection and CA
Mitigations for the Potential Negative Impacts of these
Unique Aspects:
Approach
Scalable/Proportionate Risk Management Concepts
Contract
Claim Avoidance Strategies
Scope
Sufficient Information
Expertise in Trenchless Methods involved in the Design
Construction Admin & Inspection
Quality Assurance Program
Inspection Expertise
The Sweet Spot
Co
st
Risk Management
Risk
TransferredRisk is EliminatedScalable Risk
Management
Minimum Total
Project Cost
SECTION 3: ACT
Factors Influencing Cost - Claims
“Tunnel Construction involves the Highest Incident of Litigated and Mediated Differing Conditions Claims than Any Other Sector in Water and Wastewater Construction” • Construction Chart Book, fifth edition
• Differing Conditions Claims• Obstruction Claims• Production Delays• Annular Grout
Labor & Equipment
Rates
Production Rates
MaterialsConstruction
Cost
Cost: What Drives Trenchless Cost?
Production Rates
Project Risk
Cost Variability
Contract Risk
Ground Risk
Project Risk
Ground Conditions
Method Capability
Production Rates
Accurate Estimation of
Construction Cost
Geologic conditions
are as important as
any other factor 42%
Geotechnical Investigation
Ground Risk
Define Ground
Variability
Identify Obstructions
Understand Soil
Behavior
Geological Variability/ Complexity
For comparison:
Dallas Metroplex has 5
major soil/rock strata.
11
1
5
4
3
2
El Paso Metro Area
For comparison:
El Paso area contains…
23 different types of
geological strata groups…
showing the broad range
of subsurface conditions
that can be found when
constructing pipelines in
the area.
12
2
3 4 5
6
10
9
8
7
20
19
18
17
16
15
14
13
12
11
23
22
21
High-Risk Ground ConditionsHighly Variable
Practical Understanding of Soil Behavior
Competent
Rock
Weathered
Rock
Sand Silt Clay
Grain Size
USCS Classification
Typical Approach
FIRM
Example: hard, lean clay
SWELLING
Example: plastic clay
SQUEEZING
Example: soft to medium clay (under load)
BOULDERS
Size: Greater than 12”
COBBLES
Size: 3” – 12” (typical)
RUNNING
Example: dry sand
FLOWING
Example: saturated sand
RAVELING
Example: moist, dense sand
Practical Understanding of Soil Behavior
FIRM
Example: hard, lean clay
SWELLING
Example: plastic clay
SQUEEZING
Example: soft to medium clay (under load)
BOULDERS
Size: Greater than 12”
COBBLES
Size: 3” – 12” (typical)
RUNNING
Example: dry sand
FLOWING
Example: saturated sand
RAVELING
Example: moist, dense sand
Practical Understanding of Soil Behavior
Typical Approach
Competent Rock
Weathered Rock
Sand Silt Clay
Grain Size
USCS Classification
Competent Rock
Weathered Rock
Sand Silt Clay
Grain Size
USCS Classification
Boulders
Cobbles
Gravel
Running
Cohesive Running
Flowing(Fast Running)
Raveling
Swelling
Squeezing
Soil Behavior
Hazen’s Approach
Practical Understanding of Soil Behavior
All geotechnical
investigations
Typical Approach
PDR 30% 60% Finaldesign
Project Timeline
Hazen Approach
Desktop analysis• Geological maps
• Historical data
• < $1,000
Improved project
cost accuracyMinimum
soil borings
90%
Strategic
soil borings
(if needed)
Phasing Geotechnical Investigation
Alternatives to gathering soil borings only
River
River
Horizontal Directional Drill
(1000 ft)
Subsurface
Tool:
Electrical
Resistivity Scan
Subsurface
Tool:
Electrical
Resistivity Scan
Great Miami River
Great Miami River
Top View
Profile View
Force Main
Borings
Subsurface
Tool:
Electrical
Resistivity Scan
Top View
Profile View
Subsurface
Tool:
Electrical
Resistivity Scan
Top View
Profile View
Rerouted Force
Main
Understanding Your Tolerance for Risk
What is Risky Depends on Your… Point of View…
Risk TolerancePrioritization of Goals
Minimize
Impact to
Traffic
Protect Existing
Surface
Structures and
Infrastructure
Maintain
Abbreviated
Schedule
Reduce and
Control Costs
1 2 3 4
Method Feasibility – Starts with CapabilitiesWhat are the most important factors impacting Trenchless Constructability?
Jack & Bore/Auger Boring
(J&B)
Stand Up Time
This Graph shows Rock Mass Stability and the anticipated stand-up time for rock during tunnel excavation. However, for every subsurface condition that has cohesion, there is some stand up time
Dry Sand
Tun
nel
Exc
avat
ion
Sta
nd
up
Tim
e (
hrs
)
10-1 hrs
10-2 hrs
10 hrs
101 hrs
102 hrs
Soil Cohesion/Joint Spacing
Wet Sand
Silt Clay Gravel/Cobbles PWR Rock
UTILITY HAND TUNNELING
Pipe Jacking with Shield & Hand Mining
AUGER BORING
Jack and Bore & Pilot TubeOPEN FACE TBM
ExcavationOpen Face Technologies
Method Selection
Microtunneling(MTBM)
Utility Hand Tunneling
(UHT)
Jack & Bore/Auger Boring
(J&B)
HorizontalDirectional
Drilling(HDD)
Pipe Jacking with Shield
(PJ/S)
PilotTube Auger
Boring Methods(PTAB)
Tunnel Boring Machine
Tunneling(TBM)
Pipe Ramming
(PR)
Microtunneling(MTBM)
Utility Hand Tunneling
(UHT)
Jack & Bore/Auger Boring
(J&B)
HorizontalDirectional
Drilling(HDD)
Open Cut
Tunnel Boring Machine
Tunneling(TBM)
Pipe Ramming
(PR)
PilotTube Auger
Boring Methods(PTAB)
• Selection Criteria
Project Requirements
Site Conditions
Soil Behavior
Construction Risks
Microtunneling(MTBM)
Utility Hand Tunneling
(UHT)
Jack & Bore/Auger Boring
(J&B)
HorizontalDirectional
Drilling(HDD)
Pipe Jacking with Shield
(PJ/S)
PilotTube Auger
Boring Methods(PTAB)
Tunnel Boring Machine
Tunneling(TBM)
Pipe Ramming
(PR)
Microtunneling(MTBM)
Utility Hand Tunneling
(UHT)
Jack & Bore/Auger Boring
(J&B)
HorizontalDirectional
Drilling(HDD)
Open Cut
Tunnel Boring Machine
Tunneling(TBM)
Pipe Ramming
(PR)
PilotTube Auger
Boring Methods(PTAB)
Selecting the Right Method
Marsh Ln.220 LF 36”
~ 22 ft. Deep
54”
Project Conditions:
Culverts
Gravity Main
200’+ Segment
Length
Low Clearance Line & Grade Accuracy
Access Issues
Running Sand +
High Groundwater +
Worker Safety
Microtunneling(MTBM)
Utility Hand Tunneling
(UHT)
Jack & Bore/Auger Boring
(J&B)
HorizontalDirectional
Drilling(HDD)
Pipe Jacking with Shield
(PJ/S)
PilotTube Auger
Boring Methods(PTAB)
Tunnel Boring Machine
Tunneling(TBM)
Pipe Ramming
(PR)
Microtunneling(MTBM)
Utility Hand Tunneling
(UHT)
Jack & Bore/Auger Boring
(J&B)
HorizontalDirectional
Drilling(HDD)
Open Cut
Tunnel Boring Machine
Tunneling(TBM)
Pipe Ramming
(PR)
PilotTube Auger
Boring Methods(PTAB)
Selecting the Right Method
When you are a hammer…Risk should Influence Final Design
• So why would we ever:
• be prescriptive
• restrict means and methods, or
• limit the bidder pool?
MEASUREMENT AND PAYMENT
Consider Utilizing Additional Milestones with Liquidated Damages
• Project Dependent
• Monitor Float Use
• Accurate Progress Schedule Review
Basis of Payment Coordinate Contract
Concise Requirements
Cost-Loaded Schedule
Schedule of Values
MEASUREMENT AND PAYMENT
Mobilization and Refurbishment Costs of Tunneling Equipment Higher than Typical Construction
• Refurbishment of TBM to Benefit of Owner
• Implement Contract tools to address cost substantiation
MEASUREMENT AND PAYMENT
• Must Answer: What is the best way to achieve end goal?
• Critical infrastructure mandates allowable settlement through permitting
• Desired frequency of information collection
• Variety of Available Methods• PK Nail Grid
• Subsurface
• Multi-Point Borehole Extinsometers (MPBX)
Factors Influencing Quality Assurance – Settlement Monitoring
• Tunneling Project in Virginia• Several critical road crossings
• 6 lane divided private roadway
• Specifications Require PK Nail Grid
• Acceptable method of monitoring
• Contractor States Issue with Traffic and Area Construction
• Subsurface Monitors Implemented in lieu of PK Grid
Lessons Learned – Settlement Monitoring
Factors Influencing Quality Assurance – Contractor Qualifications
• Single biggest risk mitigation is QUALIFIED Contractor
• For high risk/exposure projects pre-qualification provides jump start to risk management
Contractor Qualification
• By Specification
• Advantage: Does Not Limit who can Submit a Bid
• Risk: Potential for Bid Protest
• Risk: Does not Allow Unpublicized Vetting
Contractor Prequalification
• By RFP
• Advantage: Advertises Project in Advance
• Advantage: Fully Vet – Financial & Experience
• Risk: Potential for Increased Bid Costs
• Risk: Increased Project Schedule & Design Cost
Contractor Experience can be Critical
Construction ContractContractor Qualifications vs Prequalification
Unclassified
Understand there is still a Limited Reliance on “Soils Info”
It is not a procedure to indemnify the Owner
Guaranteed Bore is in direct conflict with EJCDC
Geotechnical Baseline Report (GBR)
Risks are outlined in detail and borne by the Owner
All deviations to the baseline are paid with predetermined costs
Increased Risk to Owner is expected to be offset by Lower Bid Price
Baseline (Interpretive) Statements in Contract
Ensure there is no difference in interpretation of the range of conditions
No Warranty on Quantity or Location, only condition type
Balance Risk with Contingencies
Contractor’s Don’t Absorb Risk, They Price It!
1. Differences in Expectations of Ground Conditions = Differing Site Conditions Claims
2. If we Accept that the Risk is Monetized
3. How do we Best Handle Soils Information and the Construction Contract?
Construction Contract Managing Soils Information
Example: Obstructions
Definitions• What is an Obstruction?
• Stoppage of Tunneling Progress Procedures
Allowances • Obstruction Removal Standby Time
• Obstruction Removal Shaft
Construction Contract Remedy Clauses & Contingency Allowances
Obstruction Risk Tools
Allowances
Prevent paying for unrealized risk
Estimated Cost
without Risk
Bid Price
Risk Profit
What the Owner Sees
What the Contractor Plans
ProfitContractor Continues to Shed Risk:
Risk
Subcontractors
Work Packages/Subs
Claims Owner/Claims
To Avoid Paying For Unrealized Risks“Contractors Don’t Absorb Risk, They Price It”
To Avoid Paying For Unrealized Risks“Contractors Don’t Absorb Risk, They Price It”
Estimated Cost
without Risk
Bid Price
Risk Profit
What the Owner Sees
What the Contractor Plans
ProfitContractor Continues to Shed Risk:
Risk
Subcontractors
Work Packages/Subs
Claims Owner/Claims
Unrealized RiskUnrealized Risk = Profit
• Lack of Direct Observation• How can I know what I can’t see?
• Intuitive Understanding of Geotech
• Understanding Drive Specifics• Critical Document Packets
• Proactive Claim/Issue Resolution• Phase Specific Reporting• Graphical Tracking Tools• Defined Transitions Between Field Staff
Factors Influencing Quality Assurance – Inspection Philosophy
Lessons Learned – Inspection Philosophy
Proactive Graphical Tracking Tools
Raleigh, NC
Lessons Learned – Inspection Philosophy
Raleigh, NC
Proactive Graphical Tracking Tools
Lessons Learned – Inspection Philosophy
Raleigh, NC
Proactive Graphical Tracking Tools
Lessons Learned – Inspection Philosophy
Raleigh, NC
Proactive Graphical Tracking Tools
Require ALL Critical Submittals Prior to Launch
Work Sequencing
Minimize Risk
LESSONS LEARNED
• Avoid overspending/underspending during design and investigation
• SCALED approach to geotechnical investigation
• Risk strategies appropriate for Owner’s risk tolerance
• Ensure qualified Contractors are performing the Work
• Pre-Qualify when appropriate
CONCLUSIONS
CONCLUSIONS
• Ensure General Conditions are adequate for trenchless construction
• Definitions of Key Terms
• Contingency Allowances
• Work Hours
• Experienced field staff is essential• Proactive inspection
• Geotechnical working knowledge
• Effective issue resolution
BULLPEN SLIDES
INTRODUCTIONThree Main Categories of Unique Trenchless Characteristics
Cost• Higher Claim Rates
• Increased Production Variability
• Increased Reliance on Geotechnical Investigation
• Permitting
• Allowances
Impacts• Public vs Private
• Environmental
• Traffic
• Duration
• Footprint
• Constructability
• Feasibility
Quality Assurance• Contractor
Qualifications
• Settlement Monitoring
• Inspection Philosophy